V PEKERJAAN DINDING
1 Pasangan 1/2 Bata Merah 386.20 m2 125,000 48,275,000 11.24
2 Pasangan 1/4 Bata Merah (Penebalan depan) 6.97 m2 125,000 871,250 0.20
3 Pasang Cover Kolom 68.40 m2 125,000 8,550,000 1.99
4 Acian 461.57 m2 20,000 9,231,400 2.15
5 Tali air / Skoneng 32.00 m1 20,000 640,000 0.15
6 Waterproofing KM/WC 19.00 m2 98,000 1,862,000 0.43
7 Waterproofing Roof Lt.3 63.00 m2 98,000 6,174,000 1.44
8 Rolag bata teras / Sloof beton 11.00 m1 26,000 286,000 0.07
Sub Total 75,889,650 17.67
X PEKERJAAN PENGECATAN
1 Pengecatan Plafond dgn Cat Catylax 90.00 m2 25,500 2,295,000 0.53
2 Pengecatan Pintu dgn Cat Melamik 55.44 m2 37,000 2,051,280 0.48
3 Pengecatan List Plafond Cat Kayu m1 12,000 - 0.00
4 Cat kusen dgn Melamik 5.60 m2 37,000 207,200 0.05
5 Cat daun pintu & jendela dgn Melamik 30.00 m2 37,000 1,110,000 0.26
6 Cat Batu bata + Coating 461.57 m2 40,000 18,462,800 4.30
Sub Total 24,126,280 5.62
XI PEKERJAAN KUSEN
Kusen Pintu Balkon Jati+Daun Pintu + Assesories
1 1.00 set 3,500,000 3,500,000 0.82
Kusen Pintu K.Tidur ,Belakang Jati+Daun Pintu +
2 3.00 set 2,000,000 6,000,000 1.40
Assesories
3 Kusen Jendela Kayu jati + Kaca + Assesories 6.00 set 930,000 5,580,000 1.30
4 Kusen + Pintu PVC Kamar Mandi (KM) 2.00 set 800,000 1,600,000 0.37
Railling Balkon & Tangga (Besi Holo 4x4cm, 2x4cm,
5 16.68 m2 300,000 5,004,000 1.17
tebal 1.4mm) Finishing Cat Besi
6 Drill / Jelosi Tampak Depan (Besi Hollo) m2 300,000 - 0.00
7 Roster Kayu 12.00 Unit 75,000 900,000 0.21
8 Glassblock 6.00 Bh 25,000 150,000 0.03
Sub Total 22,734,000 5.29
REKAPITULASI BIAYA
RUKO T.137 / 105 M2
Bobot
No. URAIAN PEKERJAAN JML HARGA
%
I PEKERJAAN PERSIAPAN 4,865,000 1.13
II PEKERJAAN TANAH & PONDASI 4,325,150 1.01
III PEKERJAAN STRUKTUR BETON 70,112,000 16.33
IV KONSTRUKSI BAJA 141,644,660 32.98
V PEKERJAAN DINDING 75,889,650 17.67
VI PEKERJAAN RANGKA & PENUTUP PLAFON 15,725,000 3.66
VII PEKERJAAN LANTAI 19,015,000 4.43
VIII PEKERJAAN INSTALASI LISTRIK 9,398,000 2.19
IX PEKERJAAN SANITASI & INSTALASI AIR 12,120,500 2.82
X PEKERJAAN PENGECATAN 24,126,280 5.62
XI PEKERJAAN KUSEN 22,734,000 5.29
XI PEKERJAAN LAIN-LAIN 29,475,000 6.86
TOTAL 429,430,240 100.00
HARGA PER METER PERSEGI 137 m2 3,134,527