SUMMARY PROJECT

PEMBANGUNAN PONDASI SUTET


TITIK 86
NO URAIAN PEKERJAAN SATUAN VOL HARGA SATUAN JUMLAH
RENCANA ANGGARAN BIAYA KONTRAK
1 BIAYA PEKERJAAN PONDASI SUTET 1.00 M3 Rp 2,900,000
( BESI DISEDIAKAN OLEH OWNER PROJECT )
2 BIAYA PEKERJAAN BORE PILE 1.00 ML Rp 620,000

RENCANA ANGGARAN PELAKSANAAN


1 BIAYA LANGSIR MATERIAL 1.00 LS Rp 2,000,000 Rp 2,000,000
2 GALIAN TAPAK PONDASI ( 4 Tapak ) 144.00 M3 Rp 55,000 Rp 7,920,000
3 PENGURUGAN KEMBALI 144.00 M3 Rp 14,000 Rp 2,016,000
4 PEMBESIAN BASE PLANTE 191.18 M3 Rp 4,000 Rp 764,720
5 BIAYA BEKISTING DAN KELENGKAPAN 1.00 LS Rp 6,708,000 Rp 6,708,000
6 BIAYA MATERIAL PENDUKUNG TAK TERDUGA 4.00 TITIK Rp 2,000,000 Rp 8,000,000
7 BIAYA BETON TERPASANG K-225 MANUAL 35.55 M3 Rp 850,000 Rp 30,217,500
8 BIAYA BORE PILE 278.40 M Rp 350,000 Rp 97,440,000
9 BIAYA BESI BORE PILE 1,121.98 KG Rp 9,500 Rp 10,658,810
10 BIAYA TAK TERDUGA 10 % LS Rp 16,572,500
TOTAL Rp 182,297,530
NILAI KONTRAK Rp 235,664,640
RAP PELAKSANAAN Rp 182,297,530
Rp 53,367,110
FEE INTERNAL MAINCONT 10% Rp 5,336,711
Rp 48,030,399