RENCANA ANGGARAN PELAKSANAAN

PROYEK : RUKO TYPE 100


PEKERJAAN : PEKERJAAN RUKO 2 LANTAI
LOKASI : LOBAR

HARGA TOTAL JUMLAH


No. JENIS PEKERJAAN SAT VOLUME SATUAN HARGA TOTAL
(Rp) (Rp) (Rp)
1 2 3 4 6 7 8

I PEKERJAAN PENDAHULUAN 832.134,00


1 Pasang Uitzet dan Bouwplank m 30,00 27.738 832.134,00

II PEKERJAAN TANAH, PASIR 6.812.775,47


1 Galian pondasi m3 17,01 66.400 1.129.171,84
2 Urugan tanah peninggian lantai m3 12,00 91.250 1.095.000,00
3 Urugan Pasir m3 6,00 168.750 1.012.500,00
4 Timbunan Kembali m3 5,67 45.625 258.626,83
4 Galian Tanah Pondasi Footplate m3 49,96 66.400 3.317.476,80

III PEKERJAAN PASANGAN 87.812.934,25


Lantai 1
1 Pasangan batu kali m3 7,22 378.321 2.729.702,60
2 Pas. Dinding Bata m2 64,35 91.304 5.875.613,08
3 Plesteran Dinding Eksterior m2 64,35 32.321 2.079.964,84
4 Plesteran Dinding Interior m2 64,35 32.321 2.079.964,84
5 Acian Dinding Interior m2 64,35 24.800 1.595.942,00
6 Acian Dinding Eksterior m2 64,35 24.800 1.595.942,00
7 Cat Dinding Interior m2 64,35 28.975 1.864.613,69
8 Cat Dinding Eksterior m2 64,35 29.570 1.902.903,43
9 Keramik Lantai 30x30 m2 46,17 167.643 7.739.668,37
10 Keramik Lantai 30x30 Teras m2 10,68 167.643 1.790.425,71
11 Finishing Void m2 1,59 27.391 43.442,69
12 Sponengan m 39,20 23.750 931.000,00
13 Finishing Beton m2 75,18 61.557 4.627.835,22
14 Finishing Pondasi m2 26,63 16.714 445.034,57
15 Cat Plafond m2 45,45 33.292 1.513.131,19
16 Skrit Dak m2 3,17 36.976 117.360,92
17 Water proof m2 3,17 42.440 134.704,56

Lantai 2
18 Pas. Dinding Bata m2 104,72 91.304 9.561.693,48
19 Plesteran Dinding Eksterior m2 104,72 32.321 3.384.835,93
20 Plesteran Dinding Interior m2 104,72 32.321 3.384.835,93
21 Acian Dinding Interior m2 104,72 24.800 2.597.160,16
22 Acian Dinding Eksterior m2 104,72 24.800 2.597.160,16
23 Cat Dinding Interior m2 104,72 28.975 3.034.383,70
24 Cat Dinding Eksterior m2 104,72 29.570 3.096.694,59
25 Keramik Lantai 30x30 m2 40,58 152.943 6.205.763,49
26 Keramik Lantai WC 30x30 m2 5,55 152.943 848.190,50
27 Keramik Dinding WC 30x30 m2 13,91 152.943 2.126.884,55
28 Finishing Void m2 2,83 27.391 77.627,11
29 Sponengan m 68,40 23.750 1.624.500,00
30 Finishing Beton m2 32,84 61.557 2.021.407,30
31 Cat Plafond m2 44,22 33.292 1.472.261,51
32 Roster m2 0,40 397.970 159.187,80
33 Skrit Dak m2 56,17 36.976 2.077.073,77
34 Water proof m2 56,17 42.440 2.384.024,56
35 ACP m2 6,82 600.000 4.092.000,00

IV PEKERJAAN BEKISTING BETON BERTULANG 123.127.829,08


Lantai 1
1 Rabat Beton Lt.1 m2 50,00 34.893 1.744.642,86
2 Pondasi Foot Plate FP (150x150) bh 6,00 2.256.618 13.539.707,05
3 Kolom Pedestal (45x45) Type A m 4,80 606.350 2.910.481,76
4 Kolom Pedestal (45x45) Type B m 2,40 606.350 1.455.240,88
5 Sloof struktur (20x30) m 22,75 243.770 5.545.757,98
6 Kolom K1 Lt.1 (45x45) Type A m 12,80 488.656 6.254.799,42
RENCANA ANGGARAN PELAKSANAAN

PROYEK : RUKO TYPE 100


PEKERJAAN : PEKERJAAN RUKO 2 LANTAI
LOKASI : LOBAR

HARGA TOTAL JUMLAH


No. JENIS PEKERJAAN SAT VOLUME SATUAN HARGA TOTAL
(Rp) (Rp) (Rp)
1 2 3 4 6 7 8
7 Kolom K1 Lt.1 (45x45) Type B m 6,40 488.656 3.127.399,71
8 Balok Bodres (15x30) m 2,00 217.928 435.855,72
9 Balok Anak elv.3,2m (15x20) m 2,23 287.822 641.843,72
11 Balok B1 elv.3,2m (35x45) Type A m 13,65 389.124 5.311.537,68
12 Balok B1 elv.3,2m (35x45) Type B m 18,20 387.897 7.059.722,49
12 Plat Sunshading t=10cm m2 3,17 257.347 816.819,99

Lantai 2
13 Kolom K2 Lt.2 (30x30) Type A m 9,75 327.057 3.188.803,84
14 Kolom K2 Lt.2 (30x30) Type B m 9,75 327.057 3.188.803,84
14 Kolom KP Lt.2 (15x15) m 12,73 157.539 2.005.465,37
10 Balok Anak elv.6,18m (15x20) m 4,00 287.822 1.151.289,19
11 Balok B2 elv.6,8m (25/35) Type A m 16,64 277.226 4.613.032,97
12 Balok B2 elv.6,8m (25/35) Type B m 17,39 283.123 4.923.505,62
13 Plat Dak t=10cm m2 47,00 407.288 19.142.538,11
14 Plat Tangga t=14cm m2 8,00 618.641 4.949.126,81
15 Plat Lantai 2 t = 12 cm m2 47,50 622.681 29.577.370,91
16 Plat Sunshading t=10cm m2 6,00 257.347 1.544.083,16

V PEKERJAAN PLUMBING 3.849.572,05


1 Kloset Duduk set 1,00 800.000 800.000,00
2 Pipa 3" m 20,00 35.365 707.308,84
3 Pipa 4" m 20,00 45.244 904.879,88
4 Pipa 3/4 m 20,00 25.973 519.466,67
5 Pipa 2 m 20,00 21.361 427.216,67
6 Floordrain bh 1,00 50.700 50.700,00
7 Buis D80 bh 4,00 90.000 360.000,00
8 Tutup Buis D80 bh 1,00 80.000 80.000,00

VI PEKERJAAN ELEKTRIKAL 4.080.000,00


1 Lantai 1 titik 22,00 120.000 2.640.000,00
2 Lantai 2 titik 12,00 120.000 1.440.000,00

VII PEKERJAAN KUSEN & RAILING 14.232.400,00


1 Railing Balkon m2 4,08 400.000 1.632.400,00
2 Railing Tangga m 10,00 250.000 2.500.000,00
3 Kusen Alumunium ls 1,00 8.000.000 8.000.000,00
4 Daun Pintu Balkon bh 1,00 1.500.000 1.500.000,00
5 Daun Pintu WC bh 1,00 600.000 600.000,00

VIII PEKERJAAN PLAFOND 9.157.672,78


1 Plafond Lt.1 m2 45,5 102.122 4.641.520,13
2 Plafond Lt.2 m2 44,22 102.122 4.516.152,65

TOTAL 249.905.317,63
JUMLAH TOTAL DIBULATKAN 250.000.000,00
LUAS BANGUNAN 100,00
HARGA/M2 2.500.000,00