PROYEK

LINGKUP PEKERJAAN

LOKASI

SPK OPNAME MANDOR

TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS


NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

B PEKERJAAN LINGKUNGAN

B.I PEKERJAAN SALURAN DAN PAGAR LINGKUNGAN

1 Pengukuran & bouwplank m1 473.50 7,700 3,645,950

2 Galian tanah m3 263.73 55,000 14,505,337

3 Angkut tanah ex. galian m3 158.24 150,000 23,736,006

4 Urug kembali tanah dan dipadatkan m3 105.49 27,500 2,901,067

5 Urug sirtu bawah pondasi & dipadatkan, t = 10 cm m3 60.40 13,200 797,298

6 Pondasi batu kali pagar depan (1:5) m3 230.87 73,700 17,014,871

7 Pasangan batu kali untuk saluran keliling m3 129.84 73,700 9,569,383

8 Kolom stump uk. 40x40cm besi 4Ø8 & Ø6-200mm, stek 4Ø10mm, H = 120 cm Unit 208.00 85,000 17,680,000 besi, begesting, cor

9 Kolom pagar precast beton tinggi 3.20 m Ttk 208.00 -

10 Pagar precast beton tinggi 2.40 m (uk. 2.40x0.40 m / lbr, 6 susun) m1 463.50 -

11 Besi siku 40x40x4 mm, P = 0.80 m (untuk kawat duri) Bh 208.00 11,000 2,288,000

12 Kawat duri 5 jalur / meter m1 460.00 6,050 2,783,000

13 Finish plester permukaan saluran batu kali 5 cm m2 796.66 24,200 19,279,092

14 Finish aci permukaan saluran batu kali m2 796.66 8,800 7,010,579

15 Decker beton tutup saluran, t = 20cm -

a. Beton ready mix K-300 m3 6.50 30,800 200,200

b. Besi beton kg 933.67 1,210 1,129,735

c. Cakar ayam 32,5 x 1,5 Bh 49.00 825 40,425

d. Decking beton 32,5 x 1,5 Bh 49.00 825 40,425

e. Begisting m2 33.50 30,250 1,013,375

16 Stek besi beton Ø10-300 mm, jarak 500 mm (batu kali - saluran) Bh 938.00 2,000 1,876,000

e. Jidar, perataan, gosok + alur jalan m2 26.00 2,750 71,500

f. Pengukuran & bouwplank m1 13.00 7,700 100,100

file:///conversion/tmp/scratch/428377260.xls 1/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

g. Galian tanah m3 17.16 55,000 943,800

h. Angkut tanah ex. galian m3 10.30 150,000 1,544,400

i. Urug kembali tanah dan dipadatkan m3 6.86 27,500 188,760

j. Sirtu dibawah pondasi & dipadatkan, t = 20 cm m3 5.72 13,200 75,504

k. Pasangan pondasi batu kali (1: 5) m3 10.97 73,700 808,397

l. Stek besi beton Ø10-300 mm, jarak 500 mm (batu kali - decker) Bh 54.00 2,000 108,000

m. Pipa Sulingan PVC Ø 2'' D + ijuk, Rata'' p = 1.00 m Bh 465.00 5,500 2,557,500

17 Pagar jalusi hollow uk. 2200x1200 mm (JA-1) Unit 1.00 -

18 Pagar jalusi hollow uk. 2300x1200 mm (JA-2) Unit 7.00 -

Sub Total B.I 131,908,705

B.II PEKERJAAN PINTU GERBANG UTAMA & JALAN LINGKUNGAN

1 Pengukuran & bowplank m1 10.00 7,700 77,000

2 Pekerjaan galian tanah m3 4.09 55,000 225,033

3 Urug kembali tanah dipadatkan m3 1.64 150,000 245,490

4 Buang tanah ex. Galian m3 2.45 27,500 67,510

5 Sirtu dipadatkan di bawah pondasi, t = 10cm m3 0.33 13,200 4,343

6 Lantai kerja t = 5cm, bawah pondasi ( camp. 1:3:5 ) m2 3.20 8,250 26,400

7 Pondasi setempat dan kolom pedestal -

a. Beton Ready Mix K – 300 m3 1.01 66,000 66,875

b. Besi beton kg 154.11 1,210 186,471

c. Decking beton 7,49 x 1,5 Bh 11.00 825 9,075

d. Begisting m2 7.49 30,250 226,573

8 Pintu gerbang double swing besar Unit 1.00 -

9 Pintu gerbang single swing kecil Unit 1.00 -

10 Pekerjaan jalan lingkungan :

a. Beton Ready Mix K – 300 m3 476.00 30,800 14,660,800

b. Perataan/leveling u/persiapan cor m2 2,380.00 1,650 3,927,000

c. Wiremesh M6 - 1 lapis m2 2,380.00 1,815 4,319,700

d. Cakar ayam 2380 x 1,5 Bh 3,570.00 825 2,945,250

e. Jidar, perataan, gosok + alur jalan m2 2,380.00 2,750 6,545,000

f. Plastik cor m2 2,380.00 550 1,309,000

file:///conversion/tmp/scratch/428377260.xls 2/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

g Stop cor m1 723.50 3,520 2,546,720

h. Dilatasi joint sealent m1 723.50 -

j. Potong + pasang besi dowel D16-300 Bh 1,451.00 2,000 2,902,000

k. Potong + pasang pipa PVC 3/4" u/besi dowel Bh 1,451.00 2,000 2,902,000

11 Sirtu dibawah lantai & dipadatkan, t = 30 cm m3 864.90 13,200 11,416,680

12 Pemasangan paving blok t=8cm m2 385.00 16,500 6,352,500

13 Pasang Grating saluran m1 60.00 5,000 300,000

Sub Total B.II 54,608,918

B.IV PEKERJAAN BONGKARAN BANGUNAN EXISTING

1 Bongkar atap+rangka kayu m2 1,378.30 - SDH DIKERJAKAN

2 Bongkar dinding+kp+bp m2 1,470.70 - SDH DIKERJAKAN

3 Bongkar pagar+pondasi pagar m1 467.00 35,000 16,345,000

4 Buang puing sekitar lokasi 6org x 20hr x 55000 hr 120.00 55,000 6,600,000

Sub Total B.IV 22,945,000

TOTAL B

C PEKERJAAN BANGUNAN GUDANG UTAMA

C.I PEKERJAAN PONDASI & STRUKTUR BETON

1 Pengukuran & bouwplank m1 438.54 7,700 3,376,720

2 Pekerjaan mini pile 200x200, L = 12 m Ttk 120.00 -

3 Bobok kepala tiang mini pile Ttk 120.00 18,700 2,244,000

4 Pek. Galian tanah m3 1,337.00 55,000 73,535,000

5 Angkut tanah ex. Galian m3 802.20 150,000 120,330,000

6 Urug kembali tanah dan dipadatkan m3 535.00 27,500 14,712,500

7 Urug sirtu bawah pondasi & dipadatkan, t = 10 cm m3 72.79 13,200 960,828

8 Urug sirtu bawah lantai & dipadatkan, t = 30 cm (termasuk kantor adm) m3 1,900.80 13,200 25,090,560

9 Lantai kerja bawah pondasi tapak & balok tarik, t = 5 cm m2 247.40 8,250 2,041,050

10 Pasangan pondasi batu kali (1:5) m3 215.49 73,700 15,881,613

11 Pondasi umpak batu kali (1:5) m3 3.51 73,700 258,687

12 Stek besi beton dia. 10 - 500 mm, p = 30 cm (batu kali-sloof & umpak) Bh 914.00 1,500 1,371,000

13 Pondasi tapak -

a. Beton Ready mix K-250 m3 16.72 66,000 1,103,256

file:///conversion/tmp/scratch/428377260.xls 3/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

b. Besi beton kg 2,355.08 1,210 2,849,643

c. Bekisting batako m2 88.92 16,500 1,467,180

14 Pedestal -

a. Beton Ready mix K-250 m3 25.75 66,000 1,699,583

b. Besi beton kg 4,440.81 1,210 5,373,378

c. Decking beton 303,51 x 1,5 Bh 455.00 825 375,375

d. Bekisting pedestal m2 303.51 30,250 9,181,178

15 Sloof 15x20 cm -

a. Beton Ready mix K-250 m3 11.00 66,000 725,739

b. Besi beton kg 2,206.74 1,210 2,670,150

c. Decking beton 146,61 x 1,5 Bh 220.00 825 181,500

d. Bekisting sloof m2 146.61 16,500 2,419,131

16 Balok tarik 20x30 cm -

a. Beton Ready mix K-250 m3 21.12 66,000 1,393,920

b. Besi beton kg 5,418.91 1,210 6,556,877

c. Decking beton 216 x 1,5 Bh 324.00 825 267,300

d. Bekisting batako m2 216.00 16,500 3,564,000

17 Plat lantai, t = 15 cm (termasuk kantor ADM) -

a. Beton Ready mix K-300 m3 950.40 30,800 29,272,320

b. Perataan/leveling u/persiapan cor m2 6,336.00 1,650 10,454,400

c. BRC wiremesh M-6 (1-lps) m2 6,336.00 1,815 11,499,840

d. Cakar ayam 6336 x 1,5 Bh 9,504.00 825 7,840,800

e. Lembaran plastik diatas sirtu untuk pengecoran lantai m2 6,336.00 550 3,484,800

f. Bekisting stop cor m1 1,764.00 3,520 6,209,280

g. Floor hardener non metalic 5 kg/m2 warna natural m2 6,336.00 -

h. Dilatasi joint sealent m1 1,404.00 -

18 Kolom dan balok opening roll door utama 25x30 cm -

a. Beton site mix K-250 m3 0.93 73,700 68,541

b. Besi beton kg 143.22 1,210 173,299

c. Decking beton 13,64 x 1,5 Bh 20.00 825 16,500

d. Bekisting kolom & balok m2 13.64 30,250 412,610

file:///conversion/tmp/scratch/428377260.xls 4/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

19 Tangga rollage bata teras depan kantor -

a. Pondasi rollage bata m2 3.00 33,000 99,000

b. Beton site Mix K - 250 m3 0.45 73,700 33,165

20 Grouting base kolom Ttk 98.00 35,000 3,430,000

21 Perapihan + cat pondasi batu kali keliling bangunan m2 140.40 -

22 Perapihan + cat sloof sisi luar bangunan m2 62.40 -

23 Perapihan + cat pedestal m2 131.61 -

24 Perapihan + cat kolom dan balok pintu rolling door m2 13.64 -

ITEM TAMBAHAN -

25 Plester loading dock sisi samping m2 38.40 12,100 464,640

26 Acian loading dock sisi samping m2 38.40 8,800 337,920

Sub Total C.I 373,427,282

C.IV PEKERJAAN ARSITEKTUR / FINISHING

1 Pasangan bata merah (1:5) m2 1,000.00 16,500 16,500,000

2 Plesteran pada dinding bata t = 2,0 cm (1:5) m2 2,000.00 12,100 24,200,000

3 Acian pada dinding bata m2 2,000.00 8,800 17,600,000

4 Cat dinding dalam m2 1,000.00 -

5 Cat dinding luar m2 1,000.00 -

6 Kolom praktis 15x15 cm m1 151.56 19,250 2,917,530

7 Ring balok praktis 12x15 cm m1 382.78 21,450 8,210,631

8 Finish sudutan, plester aci top dinding m1 324.00 15,400 4,989,600

9 Kolom praktis sisi kolom baja m1 328.00 19,250 6,314,000

10 Stek besi beton Ø10 - 400 mm di las di kolom baja, p = 30 cm Bh 656.00 2,500 1,640,000

11 Cat list dinding 20 cm m1 582.00 -

11 Pintu Rolling door 3600x4100 mm Unit 1.00 -

Sub Total C.IV 82,371,761

Sub Total C 455,799,043

D PEKERJAAN LOADING DOCK DAN RAMP

D.I PEKERJAAN PONDASI & STRUKTUR BETON LOADING DOCK

1 Pengukuran dan bouwplank m1 60.00 7,700 462,000

2 Pek. Galian tanah m3 52.80 55,000 2,904,000

file:///conversion/tmp/scratch/428377260.xls 5/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

3 Angkut tanah ex. Galian m3 31.68 150,000 4,752,000

4 Urug kembali tanah dan dipadatkan m3 21.12 27,500 580,800

5 Urug sirtu bawah lantai dipadatkan, (t = 30 cm) m3 86.40 13,200 1,140,480

6 Pasangan pondasi batu kali (1:6) m3 31.05 73,700 2,288,385

7 Stek besi beton dia. 10 - 500 mm, p = 300 mm (batu kali-sloof) Bh 121.00 1,500 181,500

8 Lantai beton Ready mix K-300, t = 15 cm m3 43.20 30,800 1,330,560

9 BRC wiremesh M-6 (1-lps) m2 288.00 1,815 522,720

10 Lembaran plastik diatas sirtu untuk pengecoran lantai m2 288.00 550 158,400

11 Bekisting stop cor m1 78.00 3,520 274,560

12 Floor hardener non metalic 5 kg/m2 warna natural m2 288.00 -

13 Dilatasi joint sealent m1 18.00 -

14 Perapihan + cat pondasi batu kali m2 27.00 -

15 Corner L 60x60x6 + angkur + finish m1 85.00 20,000 1,700,000

16 Urug sirtu bawah pondasi dipadatkan (t = 10 cm) m3 4.80 13,200 63,360

17 Sloof 15x20 cm -

a. Beton Ready Mix K – 250 m3 1.80 66,000 118,800

b. Besi beton Kg 381.94 1,210 462,147

c. Decking beton 24 x 1,5 Bh 36.00 825 29,700

d. Bekisting sloof m2 24.00 16,500 396,000

Sub Total D.I 17,365,412

D.III PEKERJAAN RAMP BETON

1 Pengukuran dan bouwplank m1 13.00 7,700 100,100

2 Pek. Galian tanah m3 7.30 55,000 401,500

3 Angkut tanah ex. Galian m3 4.38 150,000 657,000

4 Urug kembali tanah dan dipadatkan m3 2.92 27,500 80,300

5 Urug sirtu bawah lantai dipadatkan, (t = 30 cm) m3 3.00 13,200 39,600

6 Pasangan pondasi batu kali (1:6) m3 3.47 73,700 255,739

7 Stek besi beton dia. 10 - 500 mm, p = 300 mm (batu kali-sloof) Bh 28.00 1,500 42,000

8 Perataan/leveling persiapan cor m2 10.00 1,650 16,500

9 Lantai beton Ready mix K-300, t = 15 cm m3 1.50 30,800 46,200

10 BRC wiremesh M-6 (1-lps) m2 10.00 1,815 18,150

file:///conversion/tmp/scratch/428377260.xls 6/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

11 Lembaran plastik diatas sirtu untuk pengecoran lantai m2 10.00 550 5,500

12 Bekisting stop cor m1 6.50 3,520 22,880

13 Floor hardener non metalic 5 kg/m2 warna natural m2 10.00 -

14 Garis ramp m2 10.00 20,000 200,000

15 Perapihan + cat pondasi batu kali m2 4.00 -

16 Corner L 60x60x6 + angkur + finish m1 8.00 20,000 160,000

17 Urug sirtu bawah pondasi dipadatkan (t = 10 cm) m3 0.94 13,200 12,408

Sub Total D.III 2,057,877

Sub Total D 19,423,289

E PEKERJAAN KANTOR ADM.

E.I PEK. PONDASI & BETON

1 Tangga beton kantor administrasi & Tangga Mess

a. Beton ready mix K-300 m3 2.65 66,000 174,879

b. Besi beton kg 473.03 1,210 572,365

c. Bekisting tangga m2 16.05 30,250 485,513

d. Decking beton 16 x 1.5 Bh 24.00 825 19,800

e. Railing pipa Stainless steel 1.5'' + accesoris m1 10.00 -

f. perapihan sisi bawah m2 11.00 8,800 96,800

g. Step nozing m1 34.10 14,300 487,630

h. Pek. Galian tanah m1 0.55 55,000 30,250

i. Angkut tanah ex. Galian m2 0.33 150,000 49,500

j. Urug kembali tanah dan dipadatkan m1 0.22 27,500 6,050

k. Urug sirtu bawah pondasi & dipadatkan, t = 20 cm m1 0.20 13,200 2,640

l. Lantai kerja t = 5 cm, bwh pondasi tapak m2 0.05 8,250 413

2 Dinding brankas -

a. Beton ready mix K-300 m3 1.72 66,000 113,652

b. Besi beton kg 238.17 1,210 288,181

c. Decking beton 25,45 x 1,5 Bh 38.00 825 31,350

d. Bekisting dinding m2 25.45 30,250 769,711

e. Stek besi beton Ø 10mm - 200mm ( Double ) Bh 74.00 1,500 111,000

f. Finis aci permukaan beton dinding brangkas m2 25.45 8,800 223,916

file:///conversion/tmp/scratch/428377260.xls 7/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

3 Plat lantai mezanin t = 12 cm -

a. Beton ready mix K-300 m3 42.40 33,880 1,436,427

b. BRC wiremesh M-6 (1-lps) m2 353.31 1,815 641,262

c. Cakar ayam 353,31 x 1,5 Bh 530.00 825 437,250

d. Bekisting stop cor m1 150.00 1,815 272,250

e. Pelat bondek "Smart Deck" tension 5500 m2 353.31 -

f. Shear connector Bh 1,020.00 2,000 2,040,000

4 Bangku beton lapis keramik (R. kasir) 1.60x0.40 m Bh 1.00 150,000 150,000

5 Meja Locket Beton Finish Keramik L = 40 cm t = 15 cm m1 3.95 65,000 256,750

6 Septictank Beton 2,0x3,0x1,5 Unit 1.00 -

a. Pek. Galian tanah uk. 2m x 3m x 1,5m m3 9.00 55,000 495,000

b. Angkut tanah ex. Galian m3 9.00 150,000 1,350,000

c. Bekisting (9m x 2m)+(1,5mx2mx2m) m2 24.00 30,250 726,000

d. Decking beton 24 x 1.5 Bh 36.00 825 29,700

e. Dinding beton site mix + pembesian (9m x 2m x 0,1m)+(2mx1,5mx0,1m) m3 2.10 70,000 147,000

f. Tutup septicktank beton site mix + pembesian (3m x 1,5m x 0,12) m3 0.54 70,000 37,800

g. Begesting tutup septicktank (3m x 1,5m) m2 4.50 30,250 136,125

h. Cakar ayam 4,5 x 1.5 Bh 7.00 825 5,775

7 Sewa Concrete pump Unit 1.00 -

Sub Total E.I 11,624,989

E.II LANTAI - 01 + PARTISI

1 Pekerjaan dinding :

a. Pasang dinding bata m2 339.71 16,500 5,605,215

b. Plester dinding bata m2 679.42 12,100 8,220,982

c. Aci dinding bata m2 679.42 8,800 5,978,896

d. Kolom praktis 15x15cm m3 1.80 19,250 34,650

e. Ring balok praktis 15x15cm m3 1.28 21,450 27,461

f. Kolom + ringbalok praktis 12x12cm pintu jendela m1 41.67 20,000 833,400

g. Finish opening pintu jendela m1 41.67 15,400 641,718

h. Cat dinding dalam m2 462.79 -

i. Cat dinding luar m2 216.63 -

file:///conversion/tmp/scratch/428377260.xls 8/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

j. Kolom praktis sisi kolom baja m1 55.00 19,250 1,058,750

k. Stek besi beton Ø10 - 400 mm di las di kolom baja, p = 30 cm Bh 121.00 2,500 302,500

l. Keramik dinding 25x50 cm, area Toilet m2 19.53 34,100 665,973 Material SBO

m. Composite kolom baja m1 30.00 150,000 4,500,000

n. Composite balok baja m1 132.00 150,000 19,800,000

o. Topi, Beton Finish Plester Aci L = 20 cm t = 10 cm m1 17.35 25,000 433,750

2 Pekerjaan Finishing Lantai : -

a. Keramik ruangan 40x40 cm m2 124.69 22,000 2,743,070 Material SBO

b. Keramik lantai area toilet 25x50 cm m2 3.23 22,000 70,950 Material SBO

c. Plint keramik 10x40 cm m1 70.38 14,300 1,006,363 Material SBO

3 Pekerjaan Plafond : -

a. Pasang plafond gypsum t = 9 mm + cat + rangka hollow galvanis + support CNP m2 78.19 -

b. Pasang list plafond U Alumunium m1 89.80 -

4 Pekerjaan Pintu dan Jendela : -

a. Pintu Jendela TG – 01 Unit 1.00 -

b. Pintu Jendela TG – 02 Unit 1.00 -

c. Pintu Jendela TG – 03 Unit 1.00 -

d. Pintu AD - 01 Unit 2.00 -

e. Pintu PVC Unit 1.00 -

f. Jendela AW – 02 L Unit 1.00 -

g. Jendela AW – 03 L Unit 1.00 -

h. BV – 02 Unit 2.00 -

i. SD – 1 Unit 1.00 -

j. Meja beton lapis keramik uk.400x1110 mm Unit 1.00 75,000 75,000

k. LV – 01 Unit 1.00 -

5 Pekerjaan sanitary : -

a. Closet duduk type Toto CW 420 J / SW 516 Bh 1.00 55,000 55,000

file:///conversion/tmp/scratch/428377260.xls 9/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

b. Kran dinding Toto T23 B13 Bh 1.00 4,400 4,400

c. Floor drain TX 1 AN Toto Bh 1.00 15,000 15,000

d. Fixed shower ex.Toto Bh 1.00 11,500 11,500

e. Jet spray TX 403 SPIV Bh 1.00 11,500 11,500

f. Wastafel type LW 24O CJ Unit 1.00 49,500 49,500

g. Cermin ukuran 60x80 Unit 1.00 50,000 50,000

Sub Total E.II 52,195,578

E.III LANTAI - 02

1 Pekerjaan dinding :

a. Pasang dinding bata m2 439.04 16,500 7,244,201

b. Plester dinding bata m2 878.08 12,100 10,624,768

c. Aci dinding bata m2 878.08 8,800 7,727,104

d. Kolom praktis 15x15cm m3 3.31 19,250 63,669

e. Ring balok praktis 15x15cm m3 4.41 21,450 94,643

f. Finish sudutan, plester aci top dinding m1 196.00 15,400 3,018,400

g. Kolom + ringbalok praktis 12x12cm pintu jendela m1 268.06 20,000 5,361,200

h. Finish opening pintu jendela m1 268.06 15,400 4,128,124

i. Cat dinding dalam m2 724.83 -

j. Cat dinding luar m2 120.50 -

k. Kolom praktis sisi kolom baja m1 84.00 19,250 1,617,000

m. Stek besi beton Ø10 - 400 mm di las di kolom baja, p = 30 cm Bh 196.00 2,500 490,000

n. Keramik dinding 25x50 cm, area Toilet m2 32.76 34,100 1,117,116 Material SBO

o. Composite kolom baja m1 39.00 150,000 5,850,000

p. Topi, Beton Finish Plester Aci & cat L = 20 cm t = 10 cm m1 118.50 25,000 2,962,500

2 Pekerjaan Finishing Lantai : -

a. Keramik ruangan 25x50 cm m2 348.06 22,000 7,657,375 Material SBO

b. Keramik lantai area toilet 25x50 cm m2 5.25 22,000 115,500 Material SBO

c. Plint keramik 10x40 cm m1 218.50 14,300 3,124,550 Material SBO

d. Water proofing (area toilet) bitumen sheet 3mm m2 5.25 -

file:///conversion/tmp/scratch/428377260.xls 10/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

3 Pekerjaan Plafond : -

a. Pasang plafond gypsum t = 9 mm + cat + rangka hollow galvanis + support CNP m2 360.00 -

b. Pasang list plafond U Alumunium m1 242.40 -

4 Pekerjaan Pintu dan Jendela : -

a. Pintu AD – 01 Unit 5.00 -

b. Pintu AD – 02 Unit 1.00 -

c. Pintu PVC Unit 2.00 -

d. Jendela AW – 01 Unit 3.00 -

e. Jendela AW – 04A Unit 1.00 -

f. Jendela AW – 07 Unit 9.00 -

g. Jendela AW -07A Unit 10.00 -

h. BV – 01A Unit 2.00 -

i. Jendela AW – 08 Unit 2.00 -

5 Pekerjaan sanitary : -

a. Closet duduk type Toto CW 421 J Unit 2.00 55,000 110,000

b. Kran dinding Toto T23 B13 Unit 3.00 4,400 13,200

c. Floor drain TX 1 AN Toto Unit 3.00 15,000 45,000

d. Fixed shower ex.Toto Unit 2.00 11,500 23,000

e. Jet spray TX 403 SPIV Unit 2.00 11,500 23,000

f. Wastafel type LW 24O CJ Unit 2.00 49,500 99,000

g. Cermin ukuran Unit 2.00 50,000 100,000

h. Meja dapur + lapis keramik uk. 800x4500 mm Unit 1.00 600,000 600,000

i. Kitchen zinc 1 lubang + kran angsa Unit 1.00 47,000 47,000

Sub Total E.III 62,256,350

TOTAL E 126,076,917

F PEKERJAAN AREA BANGUNAN GUDANG

F.I PEKERJAAN KANTOR GUDANG

a. PEK. PASANGAN BATA

1 Pasangan bata merah (1:5) m2 91.00 16,500 1,501,500

file:///conversion/tmp/scratch/428377260.xls 11/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

2 Plesteran pada dinding bata t = 2,0 cm (1:5) m2 182.00 12,100 2,202,200

3 Acian t = 3 mm m2 182.00 8,800 1,601,600

4 Cat dinding dalam m2 98.00 -

5 Cat dinding luar m2 61.00 -

6 Cat list dinding 20 cm m1 10.00 -

7 Kolom praktis 15x15 cm m3 0.90 19,250 17,325

8 Ring balok praktis 15x20 cm m3 0.45 21,450 9,653

9 Kolom & balok praktis opening pintu jendela 11x11 cm m1 23.97 20,000 479,400

10 Finish opening pintu jendela m1 23.97 15,400 369,138

11 Kolom praktis sisi kolom baja m1 20.00 19,250 385,000

12 Stek besi beton Ø10mm - 400 mm di las di kolom baja, p = 30 cm Bh 40.00 2,500 100,000

13 Keramik dinding area Toilet 25x50 cm, h = 2.5 m m2 - - BATAL

Sub Total - a. 6,665,816

b. PEK. LANTAI

1 Keramik lantai area kantor 25x50 cm m2 24.00 22,000 528,000 Material SBO

2 Keramik lantai area toilet 25x50 cm m2 - - BATAL

3 Plint keramik 10 cm m1 19.00 14,300 271,700 Material SBO

Sub Total - b. 799,700

c. PEK. PLAFOND

1 Pasang plafond gypsumboard t = 9 mm + cat + rangka hollow ga;vanis + support CNP m2 24.00 -

2 Pasang list plafond U Alumunium m1 20.00 -

3 Gantungan CNP 150.50.20.2,3 Kg 119.04 -

4 Plafond GRC 4,5mm + rangka ( Tutup Atas ) m2 24.00 -

Sub Total - c. -

d. PEK. PINTU & JENDELA

1 Pintu AD - 1 Unit 1.00 -

2 Pintu PVC Unit - - BATAL

3 Jendela AW – 01L Unit 1.00 -

4 Jendela AW – 05 Unit 1.00 -

5 Jendela AW – 06 Unit 1.00 -

6 BV – 1 Unit - - BATAL

file:///conversion/tmp/scratch/428377260.xls 12/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

7 Meja beton lapis keramik p=2.30 m Unit 1.00 190,000 190,000

Sub Total - d. 190,000

Sub Total F.I 7,655,516

F.II PEKERJAAN GUDANG PROMO DAN ARSIP

a. PEK. PASANGAN BATA

1 Pasangan bata merah (1:5) m2 183.48 16,500 3,027,379

2 Plesteran dan acian pada dinding bata t = 2,0 cm (1:5) m2 366.96 12,100 4,440,156

3 Acian t = 3 mm m2 366.96 8,800 3,229,204

4 Cat dinding dalam m2 201.48 -

5 Cat dinding luar m2 165.48 -

6 Cat list dinding 20 cm m1 68.85 -

7 Kolom praktis 15x15 cm m3 0.81 19,250 15,593

8 Ring balok praktis 15x20 cm m3 1.98 21,450 42,471

9 Finish sudutan, plester aci top dinding m1 66.00 15,400 1,016,400

10 Kolom & balok praktis opening jendela 11x11 cm m1 58.68 20,000 1,173,600

11 Finish opening pintu jendela m1 58.68 15,400 903,672

12 Kolom praktis sisi kolom baja m1 33.00 19,250 635,250

13 Stek besi beton Ø10mm - 400 mm di las di kolom baja, p = 30 cm (u/ikatan bata) Bh 77.00 2,500 192,500

Sub Total - a. 14,676,224

b. PEK. PLAFOND

1 Plafond gypsum m2 144.00 -

2 List plafond U alumunium m1 72.00 -

3 Plafond grc 4,5mm + rangka ( Tutup Atas ) m2 144.00 -

4 Gantungan CNP 150.50.20.2,3 Kg 13,946.40 -

Sub Total - b. -

c. PEK.PINTU & JENDELA

1 Pintu rolling door manual uk. (2,15x2,15) Unit 1.00 -

2 Pintu AD - 1 Unit 1.00 -

3 Jendela BV - 2A Unit 10.00 -

Sub Total - c. -

Sub Total F.II 14,676,224

file:///conversion/tmp/scratch/428377260.xls 13/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

TOTAL F 22,331,739

G PEKERJAAN FASILITAS PENUNJANG

G.I PEKERJAAN POS JAGA

a. Pekerjaan Pondasi dan Beton


1 Pengukuran & bowplank m1 13.00 7,700 100,100

2 Galian tanah m3 6.71 55,000 368,775

3 Angkut tanah ex. galian m3 4.02 150,000 603,450

4 Urug kembali tanah dan dipadatkan m3 2.68 27,500 73,755

5 Sirtu dipadatkan untuk lantai, t=20cm m3 3.00 13,200 39,600

6 Pekerjaan pondasi : -

a. Pasangan batu kali untuk pondasi (1:5) m3 4.21 73,700 310,093

b. Pasangan rollag bata untuk teras m1 10.50 33,000 346,500

c. Stek besi Ø10-500 L=300 mm (pondasi - sloof) Bh 34.00 1,500 51,000

d. Lantai kerja tapak & sloof dalam, t = 50 mm m2 9.00 8,250 74,250

e. Sirtu dipadatkan untuk pondasi tapak, t = 10cm m3 0.32 13,200 4,277

7 Sloof 150x200 mm : -

a. Beton site mix K-250 m3 0.50 66,000 32,670

b. Besi beton Kg 79.72 1,210 96,467

c. Decking beton 6,6 x 1,5 Bh 10.00 825 8,250

c. Bekisting sloof m2 6.60 16,500 108,900

8 Kolom 25x15 cm : -

a. Beton site mix K-250 m3 0.64 66,000 42,240

b. Besi beton Kg 150.52 1,210 182,125

c. Decking beton 12,8 x 1,5 Bh 19.00 825 15,675

d. Bekisting kolom m2 12.80 30,250 387,200

e. Perapihan kolom (pester + aci) m2 12.80 20,900 267,520

9 Ring balok 15x20 cm : -

a. Beton ready mix K-250 m3 0.71 66,000 46,530

b. Besi beton Kg 176.86 1,210 214,003

c. Decking beton 12,9 x 1,5 Bh 19.00 825 15,675

d. Bekisting m2 12.93 30,250 390,981

file:///conversion/tmp/scratch/428377260.xls 14/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

e. Perapihan Ring balok beton expose m2 9.40 8,800 82,720

10 Pelat lantai dasar t = 10 cm : -

a. Beton Ready mix K-300 m3 1.80 30,800 55,440

b. Perataan/leveling u/persiapan cor m2 18.00 1,650 29,700

c. BRC wiremesh M-6 (1 lapis) m2 18.00 1,815 32,670

d. Cakar ayam 18 x 1,5 Bh 27.00 825 22,275

e. Plastik cor di atas sirtu m2 18.00 550 9,900

e. Bekisting stop cor m1 17.00 3,520 59,840

11 Dak beton t = 10 cm -

a. Beton Ready mix K-300 m3 2.25 66,000 148,500

b. Besi beton Kg 217.76 1,815 395,229

c. Cakar ayam 22,5 x 1,5 Bh 34.00 825 28,050

d. Bekisting m2 22.50 30,250 680,625

e. Water Proofing Membrane + Screed m2 22.50 -

f. Roof Drain Bh 2.00 16,200 32,400

g. Down Pipe PVC D 4 " ( Klem + Accesorry ) m1 10.00 7,200 72,000

h. Perapihan dak expose m2 22.50 9,000 202,500

12 Pondasi tapak 1000x1000 mm -

a. Beton Ready mix K-250 m3 0.39 66,000 25,872

b. Besi beton Kg 77.93 1,210 94,299

c. Decking beton 2.24 x 1.5 Bh 4.00 825 3,300

d. Bekisting m2 2.24 16,500 36,960

13 Lisplank Atap 10/50 -

a. Beton Ready mix K-250 m3 1.14 66,000 75,240

b. Besi beton Kg 173.19 1,210 209,559

c. Decking beton 24 x 1.5 Bh 36.00 825 29,700

d. Bekisting m2 24.70 30,250 747,175

Sub Total - a. 6,853,989

b. Pekerjaan Arsitektur / Finishing


1 Pekerjaan dinding :

a. Pasangan bata merah (1:5) m2 39.50 16,500 651,750

file:///conversion/tmp/scratch/428377260.xls 15/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

b. Plesteran dan acian pada dinding bata t = 2,0 cm (1:5) m2 79.00 12,100 955,900

c. Acian t = 3 mm m2 79.00 8,800 695,200

d. Kolom praktis 15x15 cm m3 0.27 19,250 5,198

e. Ring balok praktis 15x15 cm m3 0.37 21,450 7,963

f. Kolom dan balok praktis opening jendela,pintu(11x11 cm) m1 31.40 20,000 628,000

g. Finish opening pintu jendela m1 31.40 15,400 483,560

h. Cat dinding dalam m2 50.00 -

i. Cat dinding luar m2 32.50 -

j. Cat list dinding 20 cm m1 26.50 -

k. Meja beton lapis keramik lebar 40 cm m1 4.00 65,000 260,000

2 Pekerjaan finishing lantai : -

a. Keramik 25x50 cm untuk lantai m2 18.00 22,000 396,000 Material SBO

b. Plint keramik 100 mm m1 26.50 14,300 378,950 Material SBO

3 Pekerjaan pintu & jendela : -

a. Pintu AD-1 (engsel nylon, kunci alfa, handele al.plate,door closer dorma) Unit 1.00 -

b. Jendela AW - 1 Unit 1.00 -

c. Jendela AW – 2 Unit 1.00 -

d. Jendela AW - 1L Unit 1.00 -

e. BV - 1A Unit 2.00 -

f. Batu alam m2 13.00 45,000 585,000

Sub Total - b. 5,047,521


Sub Total G.I 11,901,509
G.II PEKERJAAN FASUM DAN GUDANG BS

a. Pekerjaan Pondasi dan Beton

1 Pengukuran & bowplank m1 40.00 7,700 308,000

2 Galian tanah m3 35.48 55,000 1,951,400

3 Angkut tanah ex. galian m3 21.29 150,000 3,193,200

4 Urug kembali tanah dan dipadatkan m3 14.19 27,500 390,280

5 Sirtu dipadatkan untuk pondasi tapak, t = 10cm m3 4.02 13,200 53,064

6 Sirtu dipadatkan untuk lantai teras, t=30cm m3 2.70 13,200 35,640

7 Sirtu dipadatkan untuk lantai fasum t=30cm m3 21.60 13,200 285,120

file:///conversion/tmp/scratch/428377260.xls 16/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

8 Pekerjaan pondasi : -

a. Pasangan batu kali untuk pondasi (1:5) m3 10.13 33,000 334,125

b. Pasangan rollag bata untuk teras m1 9.00 33,000 297,000

c. Stek besi Ø10-500 L=300 mm (pondasi - sloof) Bh 62.00 1,500 93,000

d. Lantai kerja tapak & sloof dalam, t = 5 cm m3 0.30 8,250 2,500

9 Pondasi tapak 1200x700 mm -

a. Beton Ready mix K-250 m3 1.51 66,000 99,792

b. Besi beton Kg 207.67 1,210 251,279

c. Decking beton 0.84 x 1.5 Bh 2.00 825 1,650

d. Bekisting pondasi tapak m2 6.84 16,500 112,860

10 Pedestal 300x450 mm : -

a. Beton Ready mix K-250 m3 1.66 66,000 109,593

b. Besi beton Kg 271.35 1,210 328,330

c. Decking beton 18,45 x 1.5 Bh 28.00 825 23,100

c. Bekisting pedestal m2 18.45 30,250 558,113

11 Sloof dalam 200x300 mm : -

a. Beton Ready mix K-250 m3 0.84 66,000 55,440

b. Besi beton Kg 166.49 1,210 201,451

c. Decking beton 8,4 x 1.5 Bh 13.00 825 10,725

d. Bekisting sloof m2 8.40 16,500 138,600

12 Sloof 150x200 mm : -

a. Beton Ready mix K-250 m3 0.90 66,000 59,400

b. Besi beton Kg 198.60 1,210 240,311

c. Decking beton 12 x 1.5 Bh 18.00 825 14,850

c. Bekisting sloof m2 12.00 16,500 198,000

13 Pelat lantai dasar t = 15 cm : -

a. Beton Ready mix K-300 m3 12.15 30,800 374,220

b. BRC wiremesh M-5 (1 lapis) m2 81.00 1,815 147,015

c. Cakar ayam 81 x 1.5 Bh 122.00 825 100,650

d. Perataan/leveling u/persiapan cor m2 81.00 1,650 133,650

e. Plastik cor di atas sirtu m2 81.00 550 44,550

file:///conversion/tmp/scratch/428377260.xls 17/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

f. Bekisting stop cor m1 45.00 3,520 158,400

g. Floor hardener non metalic 5 kg/m2 warna natural m2 81.00 -

h. Dilatasi joint sealent m1 6.00 -

14 Perapihan + cat sloof sisi luar bangunan m2 7.80 -

15 Perapihan + cat pedestal expose m2 9.00 -

16 Pekerjaan mini pile 200x200, L = 9 m Ttk 12.00 -

17 Bobok kepala tiang mini pile Ttk 12.00 18,700 224,400

18 Pondasi umpak batu kali (1:6) m3 0.23 55,000 12,375

19 Grouting base kolom Ttk 6.00 35,000 210,000

Sub Total - a. 10,752,082


d. PEK. FINISHING KERAMIK LANTAI DAN DINDING

1 Keramik lantai 40x40 cm m2 66.00 22,000 1,452,000 Material SBO

2 Keramik lantai area tempat cuci 40x40 cm m2 6.00 22,000 132,000 Material SBO

3 Keramik dinding tempat cuci 40x40 cm m2 24.40 34,100 832,040 Material SBO

4 Keramik dinding dalam gudang repack & BS 40x40 cm m2 96.18 34,100 3,279,653 Material SBO

5 Keramik lantai toilet m2 7.68 22,000 168,960 Material SBO

6 Keramik dinding toilet m2 50.82 34,100 1,732,962 Material SBO

7 Plint keramik 10 cm m1 41.60 14,300 594,809 Material SBO

Sub Total – d. 8,192,423

g. PEKERJAAN SANITARY

1 Tanggulan bata lapis keramik 15x40 cm m1 6.20 75,000 465,000

2 Floor drain Toto TX 1 AN Unit 6.00 18,150 108,900

3 Kran dinding Toto T23 B13 N Unit 10.00 5,500 55,000

4 Pipa PVC dia. 2" AW Wavin, p = 25 cm Unit 4.00 5,500 22,000

5 Pipa PVC dia. 3'' + acesories m1 36.00 7,150 257,400

6 Dop pvc dia. 2" Unit 3.00 3,000 9,000

7 Ball valve pvc dia.3/4" (stop kran air dari dalam) Unit 10.00 9,350 93,500

8 Closet jongkok Unit 2.00 55,000 110,000

9 Septictank uk.1.50x1.50x1.50m & rembesan uk.1.50x1.50x1.50m -

a. Pek. Galian tanah uk. 1,5m x 1,5m x 1,5m m3 3.38 55,000 185,900

b. Angkut tanah ex. Galian m3 3.38 150,000 507,000

file:///conversion/tmp/scratch/428377260.xls 18/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

c. Bekisting (1,5mx1,5mx4m) m2 9.00 30,250 272,250

d. Decking beton 9 x 1.5 Bh 14.00 825 11,550

e. Dinding beton site mix + pembesian (1,5mx6mx0,1m) m3 0.90 70,000 63,000

f. Tutup septicktank beton site mix + pembesian (1,5m x 1,5m x 0,12) m3 0.27 70,000 18,900

g. Begesting tutup septicktank (1,5m x 1,5m) m2 2.25 30,250 68,063

h. Cakar ayam 2,25 x 1.5 Bh 4.00 825 3,300

10 Rembesan uk.1.50x1.50x1.50m

a. Pek. Galian tanah uk. 1,5m x 1,5m x 1,5m m3 3.38 55,000 185,900

b. Pasang ijuk, batu koral, urug pasir, urug tanah Unit 1.00 100,000 100,000

Sub Total – g. 1,120,800

h. Pekerjaan Finishing

1 Pasangan bata merah (1:5) m2 257.83 16,500 4,254,224

2 Plesteran dan acian pada dinding bata t = 2,0 cm (1:5) m2 515.66 12,100 6,239,528

Acian pada dinding t=3mm m2 515.66 8,800 4,537,839

3 Ventilated block m2 5.04 22,000 110,880

4 Kolom praktis 15x15 cm m1 139.56 19,250 2,686,530

5 Ring balok praktis 15x15 cm m1 104.44 21,450 2,240,238

6 Kolom + balok praktis opening pintu jendela 11x11 cm m1 55.37 20,000 1,107,400

Finish opening pintu jendela m1 55.37 15,400 852,698

7 Cat dinding dalam m2 222.72 -

8 Cat dinding luar m2 172.37 -

9 Cat list dinding 20 cm m1 36.00 -

10 Composite kolom baja uk. 20 x 30 cm, t = 3,00 m m1 18.00 150,000 2,700,000

11 Composite balok baja uk. 20 x 30 cm m1 49.26 150,000 7,389,000

12 Tanggulan bata finish keramik, h = 30 cm m1 6.20 40,000 248,000

13 Bangku beton lapis keramik lebar 40 cm m1 13.00 35,000 455,000

14 Grouting base kolom pedestal Bh 6.00 35,000 210,000

Sub Total – h. 33,031,337

Sub Total G.II #REF!

G.III PEKERJAAN PARKIRAN MOBIL

a. PEKERJAAN STRUKTUR PONDASI DAN BETON

file:///conversion/tmp/scratch/428377260.xls 19/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

1 Pengukuran & bouwplank m1 40.00 7,700 308,000

2 Galian tanah m3 6.26 55,000 344,520

3 Urug kembali tanah dan dipadatkan m3 3.76 27,500 103,356

4 Angkut tanah ex. Galian m3 2.51 150,000 375,840

5 Sirtu t = 10 cm, bwh pondasi m3 0.43 13,200 5,702

6 Lantai kerja t = 5 cm, bwh pondasi m2 4.40 8,250 36,300

7 Pondasi tapak dan pedestal -

a. Beton Ready mix K-250 m3 1.22 66,000 80,190

b. Besi beton Kg 162.57 1,210 196,708

c. Decking beton 8,64 x 1,5 Bh 13.00 825 10,725

d. Bekisting m2 8.64 30,250 261,360

8 Sloof 150x200 mm : -

a. Beton Ready mix K-250 m3 0.30 66,000 19,800

b. Besi beton Kg 59.58 1,210 72,094

c. Decking beton 4 x 1.5 Bh 6.00 825 4,950

c. Bekisting sloof m2 4.00 30,250 121,000

9 Car stopper Bh 8.00 40,000 320,000

Sub Total - a. 2,260,546

Sub Total G.III 2,260,546

G.V RUANGAN GENERATOR SET

a. PEKERJAAN PONDASI & STRUKTUR BETON

1 Pengukuran & bowplank m1 21.00 7,700 161,700

2 Pekerjaan tanah : -

a. Galian tanah m3 8.32 55,000 457,600

b. Angkut tanah ex. galian m3 4.99 150,000 748,800

c. Urug kembali tanah dan dipadatkan m3 3.33 27,500 91,520

d. Sirtu dipadatkan untuk pondasi m3 1.04 13,200 13,728

e. Sirtu dipadatkan untuk lantai m3 1.05 13,200 13,860

3 Pekerjaan pondasi : -

a. Pasangan batu kali untuk pondasi (1:5) m3 4.68 73,700 344,916

b. Stek besi Ø10-500 L=300 mm (pondasi - sloof) Bh 26.00 1,500 39,000

file:///conversion/tmp/scratch/428377260.xls 20/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

c. Pondasi mesin genset t = 200 mm : -

- Beton Ready mix K-300 m3 1.75 66,000 115,500

- BRC wiremesh M-6 (2 lapis) m2 8.75 1,815 15,881

- Cakar ayam 8,75 x 1.5 Bh 14.00 825 11,550

- Plastik cor di atas sirtu m2 8.75 550 4,813

- Bekisting stop cor m1 12.00 3,520 42,240

- Dilatasi bitumen m1 12.00 -

4 Pekerjaan struktur beton : -

a. Sloof 150x200 mm : -

- Beton site mix mix K-250 m3 0.39 73,700 28,743

- Besi beton Kg 41.48 1,210 50,195

- Decking beton 5.3 x 1.5 Bh 8.00 825 6,600

- Bekisting m2 5.20 30,250 157,300

b. Rabat beton t = 100 mm : -

- Beton Ready mix K-250 m2 3.00 8,250 24,750

- Perataan/leveling u/persiapan cor m2 3.00 1,650 4,950

- Plastik cor di atas sirtu m2 3.00 550 1,650

c. Kolom 200x200 mm : -

- Beton site mix mix K-250 m3 0.53 73,700 38,914

- Besi beton Kg 52.88 1,210 63,979

- Decking beton 9,12 x 1.5 Bh 14.00 825 11,550

- Bekisting m2 9.12 30,250 275,880

- Perapihan (plester aci + cat) m2 9.12 20,900 190,608

d. Ring balok 150x300 mm : -

- Beton site mix mix K-250 m3 0.87 73,700 64,340

- Besi beton Kg 40.85 1,210 49,431

- Decking beton 11,64 x 1.5 Bh 18.00 825 14,850

- Bekisting m2 11.64 30,250 352,110

- Perapihan (plester aci + cat) m2 11.64 20,900 243,276

e. Pelat lantai dak t = 100 mm : -

- Beton Ready mix K-250 m3 2.35 30,800 72,257

file:///conversion/tmp/scratch/428377260.xls 21/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

- Besi beton Kg 227.29 1,210 275,023

- Decking beton 23,46 x 1.5 Bh 35.00 825 28,875

- Bekisting m2 23.46 30,250 709,665

- Waterproofing Bitumen sheet t = 3 mm + screed m2 23.46 -

Sub Total - a. 4,726,053

b. PEKERJAAN ARSITEKTUR / FINISHING

1 Pekerjaan dinding :

a. Pasangan bata merah (1:5) m2 34.04 16,500 561,619

b. Plesteran dan acian pada dinding bata t = 20 mm (1:5) m2 68.08 20,900 1,422,768

c. Cat dinding bata - dalam m2 34.04 -

d. Cat dinding bata - luar m2 34.04 -

e. Kolom praktis 15x15 cm m1 26.22 19,250 504,735

2 Pekerjaan pintu & jendela : -

a. Perforated rolling door 2150x2150 mm Unit 1.00 -

b. Tralis BRC M6 rangka siku 50 Unit 1.00 -

c. Louver alumunium Unit 1.00 -

3 Plasteran & acian pada pondasi batu kali & sloof (1:5) m2 5.20 33,000 171,600

4 Floor hardener 5 kg/m2 natural non metalic m2 10.50 -

5 Cat lantai dak expose sisi bawah m2 10.50 -

Sub Total - b. 2,660,721

G.VII PENANGKAL PETIR

1 Pekerjaan tanah :

a. Galian tanah m3 3.34 55,000 183,968

b. Angkut tanah ex. galian m3 1.34 150,000 200,693

c. Urug kembali tanah dan dipadatkan m3 2.01 27,500 55,191

2 Pekerjaan pondasi & struktur beton : -

a. Strauss pile Ø300 mm L = 3000 mm m1 3.00 71,500 214,500

b. Pondasi tapak / kepala tiang : -

- Lantai kerja (beton K-125) t = 50 mm m3 0.07 8,250 578

- Beton site mix mix K-250 m3 0.20 73,700 14,740

- Besi beton Kg 23.84 1,210 28,846

file:///conversion/tmp/scratch/428377260.xls 22/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

- Bekisting pondasi tapak m2 0.80 16,500 13,200

c. Pedestal : -

- Beton ready mix K-250 m3 0.19 66,000 12,540

- Besi beton Kg 19.09 1,210 23,099

- Decking beton 1,71 x 1.5 Bh 3.00 825 2,475

- Bekisting m2 1.71 30,250 51,728

- Perapihan Pedestal Plester Aci m2 1.04 20,900 21,736

3 Bak kontrol & tutup Unit 1.00 15,000 15,000

4 Penangkal petir R-150/KURN/t=20 m + izin Unit 1.00 -

Sub Total G.VII 838,293

G.VIII TIANG BENDERA

1 Pekerjaan tanah :

a. Galian tanah m3 3.14 55,000 172,480

b. Angkut tanah ex. galian m3 1.25 150,000 188,160

c. Urug kembali tanah dan dipadatkan m3 1.25 27,500 34,496

2 Pekerjaan pondasi & struktur beton : -

a. Pondasi : -

- Lantai kerja (beton K-125) t = 50 mm m3 0.20 8,250 1,617

- Beton site mix mix K-250 m3 0.80 73,700 59,236

- Besi beton Kg 71.68 1,210 86,733

- Decking beton 4.2 x 1.5 Bh 6.00 825 4,950

- Bekisting pondasi m2 4.20 30,250 127,050

3 Pekerjaan tiang bendera Unit 2.00 -

Sub Total G.VIII 674,723

G.IX TIANG PJU

1 Pekerjaan tanah :

a. Galian tanah m3 2.11 55,000 116,160

b. Angkut tanah ex. galian m3 0.84 150,000 126,720

c. Urug kembali tanah dan dipadatkan m3 1.27 27,500 34,848

2 Pekerjaan pondasi & struktur beton : -

a. Strauss pile Ø300 mm L = 1500 mm m1 1.50 71,500 107,250

file:///conversion/tmp/scratch/428377260.xls 23/48
TOTAL HARGA PROGRESS MINGGU PROGRESS PROGRESS
NO. DESKRIPSI PEKERJAAN SAT. VOLUME HARGA SAT.
( Rp ) LALU MINGGU INI KESELURUHAN

b. Pondasi : -

- Beton lantai kerja t = 50 mm m3 0.87 8,250 7,153

- Beton site mix ( Camp. 1:1,5:2,5 ) m3 0.74 73,700 54,170

- Besi beton Kg 131.88 1,210 159,576

- Decking beton 6 x 1.5 Bh 9.00 825 7,425

- Bekisting pondasi m2 6.00 30,250 181,500

3 Pekerjaan tiang PJU Unit 2.00 -

Sub Total G.IX 794,801

TOTAL G #REF!

H PEKERJAAN PLUMBING

H.I INSTALASI AIR BERSIH

1 Pompa jet pump grundfos JDF 7 Unit 1.00 96,250 96,250

2 Tangki air silinder 2 m3 (plastik) Unit 1.00 184,800 184,800

3 Sumur bor 40 m m1 40.00 71,500 2,860,000

4 Water level kontrol Set 1.00 96,250 96,250

5 Pipa PVC AW 1/2" m1 12.00 4,510 54,120

6 Pipa PVC AW 3/4" m1 32.00 4,510 144,320

7 Pipa PVC AW 1" m1 96.00 5,280 506,880

8 Pipa PVC AW 1 1/2" m1 204.00 5,280 1,077,120

10 Ball valve dia.3/4" Bh 2.00 9,350 18,700

11 Ball valve dia.1 1/2" Bh 4.00 9,350 37,400

Sub Total H.I 5,075,840

H.II INSTALASI AIR BEKAS & KOTOR

1 Pipa PVC D 4" m1 184.00 7,150 1,315,600

2 Pipa PVC D 3" m1 172.00 7,150 1,229,800

3 Pipa PVC D 2" m1 24.00 5,500 132,000

Sub Total H.II 2,677,400

TOTAL H 7,753,240

GRAND TOTAL #REF!

file:///conversion/tmp/scratch/428377260.xls 24/48
KETERANGAN

ON PROGRESS

SUBCONT/ON PROGRESS

SUBCONT/ON PROGRESS

file:///conversion/tmp/scratch/428377260.xls 25/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 26/48
KETERANGAN

SDH DIKERJAKAN

SDH DIKERJAKAN

file:///conversion/tmp/scratch/428377260.xls 27/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 28/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 29/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 30/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 31/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 32/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 33/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 34/48
KETERANGAN

SUBCONT

SUBCONT

file:///conversion/tmp/scratch/428377260.xls 35/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 36/48
KETERANGAN

SUBCONT

SUBCONT

SUBCONT

file:///conversion/tmp/scratch/428377260.xls 37/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 38/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 39/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 40/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 41/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 42/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 43/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 44/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 45/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 46/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 47/48
KETERANGAN

file:///conversion/tmp/scratch/428377260.xls 48/48