RENCANA ANGGARAN BIAYA

PEKERJAAN : RUMAH TYPE 27


LOKASI : KALIWUNGU - KENDAL
TH. ANGGARAN : 2014

Harga Jumlah
NO URAIAN PEKERJAAN Volume Sat
Satuan (Rp) Satuan (Rp)
1 2 3 4 5 6

A RUMAH TYPE 27
I PEKERJAAN PERSIAPAN

1 Pembuatan Gudang penyimpanan Semen 1.00 Ls 500,000.00 500,000.00


2 Pembersihan Lokasi & Pemerataan 35.00 m2 8,500.00 297,500.00
3 Pengukuran/Uitzet bowplank 42.13 m' 59,090.00 2,489,461.70
4 Bongkaran Dinding Lama 1.91 m3 335,660.00 639,432.30
5 Bongkaran Atap Lama 1.00 Ls 500,000.00 500,000.00
Sub Jumlah I 4,426,394.00

II PEKERJAAN TANAH

1 Galian tanah pondasi lajur 33.70 m3 39,250.00 1,322,882.00


2 Urugan tanah kembali bekas galian 11.23 m3 13,083.33 146,986.89
3 Urugan sirtu bawah pondasi t:5 cm 1.69 m3 159,450.00 268,705.14
4 Urugan pasir bawah lantai t:10 cm 1.63 m3 134,500.00 218,697.00
Sub Jumlah II 1,957,271.03

III PEKERJAAN PASANGAN

1 Pasangan Batu Belah 1pc : 8 pp 10.70 m3 490,562.75 5,249,070.48


2 Pasangan Batu Kosong 4.76 m3 275,901.00 1,312,074.80
3 Pasangan Dinding 1/2 bata 1pc : 6pp 147.42 m2 78,574.60 11,583,388.96
4 Plesteran 1pc : 5pp Tebal 15 mm 294.84 m2 45,282.72 13,351,066.60
5 Acian 294.84 m2 21,894.06 6,455,201.60
6 Pasangan Keramik 40 x 40 39.41 m2 146,302.64 5,765,786.94
7 Pasangan Keramik Lantai 20x20 (KM/ WC) 1.50 m2 139,311.00 208,966.50
8 Pasangan Keramik Dinding 20x25 (KM/WC) 6.52 m2 152,720.63 995,433.03
9 Pasangan Plint keramik 10 x 20 dinding KM / WC 4.22 m' 67,912.83 286,592.12
10 Skoning 94.14 m' 33,613.63 3,164,386.66
11 Pasangan Batu Alam 2.92 m2 185,434.69 540,912.98
Sub Jumlah III 48,912,880.67

IV PEKERJAAN BETON

1 Sloof 15/20
Beton K200 1.26 m3 937,125.50 1,184,432.92
Besi 189.59 kg 13,243.40 2,510,749.99
Bekisting 16.85 m2 143,047.00 2,410,628.04
2 Kolom 12/12
Beton K200 0.95 m3 937,125.50 891,453.75
Besi 142.69 kg 13,243.40 1,889,695.45
Bekisting 19.82 m2 312,576.00 6,194,631.17

3 Ring Balk 12/20


Beton K200 1.62 m3 937,125.50 1,514,319.84
Besi 242.39 kg 13,243.40 3,210,041.24
Bekisting 20.20 m2 328,746.00 6,640,340.45

4 Balok Lateu 12/20


Beton K200 0.30 m3 937,125.50 280,013.10
Besi 44.82 kg 13,243.40 593,569.19
Bekisting 3.74 m2 328,746.00 1,227,866.31
5 Plat Leufel t = 10 cm
Beton K200 0.75 m3 937,125.50 706,592.63
Besi 113.10 kg 13,243.40 1,497,828.54
Bekisting 7.54 m2 391,776.00 2,953,991.04
6 Kuda-kuda Beton
Beton K200 0.38 m3 937,125.50 355,639.13
Besi 56.93 kg 13,243.40 753,880.55
Bekisting 0.45 0.45 328,746.00 148,593.19

Sub Jumlah IV 34,964,266.52

V PEKERJAAN KAYU KUSEN DAN ATAP

1 Kusen pintu dan jendela Kayu Kamper 0.35 m3 8,843,325.00 3,091,909.41


2 Daun Pintu Panil Kayu Kamper 1.89 m2 543,755.00 1,027,696.95
3 Daun Pintu Panil Tekwod 3.36 m2 444,338.00 1,492,975.68
4 Daun Jendela Rangka Kayu Kamper 3.75 m2 383,810.00 1,439,287.50
5 Gording Kayu Bengkirai 6 / 12 cm 0.31 m3 7,543,090.00 2,367,926.81
6 Rangka Atap Asbes 52.61 m2 144,505.00 7,602,408.05
7 Atap Asbes 52.61 m2 39,600.00 2,083,356.00
Sub Jumlah V 19,105,560.40

VI PEKERJAAN BESI DAN PLAFOND

1 Plafond Gypsum 45.76 m2 36,230.60 1,657,912.26


2 Rangka Hollow 40x40 & 20x20 45.76 m2 57,607.00 2,636,096.32
3 List tepi plafond 59.56 m' 32,697.00 1,947,433.32
Sub Jumlah VI 6,241,441.90

VII PEKERJAAN SANITAIR

1 Kran 1/2 " 2.00 bh 26,782.00 53,564.00


2 Tempat Sabun (Terpasang) 1.00 bh 35,200.00 35,200.00
3 Floor Drain 1.00 bh 37,870.00 37,870.00
4 Closed Duduk 1.00 bh 416,577.50 416,577.50
5 Pipa PVC AW Abu-abu 1/2 " Pemasukan 8.15 m' 14,939.25 121,754.89
6 Pipa PVC AW Abu-abu 3 " Floor Drain 3.50 m' 48,997.33 171,490.67
7 Pipa PVC AW Abu-abu 4 " Buangan Closed 2.90 m' 51,839.00 150,333.10
Sub Jumlah VII 986,790.15

VIII PEKERJAAN KUNCI DAN PENGAGGANTUNG

1 Pas. Engsel Pintu 9.00 bh 29,030.00 261,270.00


2 Pas. Handle Pintu 3.00 bh 99,000.00 297,000.00
3 Sloot Tanam 2 x Putar Setara Yale 3.00 bh 29,610.00 88,830.00
4 Pas. Engsel Jendela 10.00 bh 25,220.00 252,200.00
5 Pas. Kait Angin 10.00 bh 27,457.50 274,575.00
6 Grendel Tanam 5.00 bh 20,000.00 100,000.00
7 Pas.Handle Jendela 5.00 bh 15,000.00 75,000.00
Sub Jumlah VIII 1,348,875.00

IX PEKERJAAN INSTALASI LISTRIK

1 Pas. Titik Listrik 18.00 bh 150,000.00 2,700,000.00


2 Pas. Stop Kontak 6.00 bh 25,000.00 150,000.00
3 Pas. Saklar Tunggal&Ganda 7.00 bh 25,000.00 175,000.00
4 Pas. Lampu SL 18 Watt 7.00 bh 40,000.00 280,000.00
5 Pas. Lampu PL 8 Watt 4.00 bh 25,000.00 100,000.00
6 Pas. Fitting 18.00 bh 17,000.00 306,000.00
Sub Jumlah IX 3,711,000.00

X PEKERJAAN CAT

1 Cat tembok 294.84 m2 15,307.10 4,513,114.75


2 Cat Plafond 45.76 m2 15,307.10 700,452.90
3 Cat kayu 4.85 m2 33,061.00 160,279.73
Sub Jumlah X 5,373,847.37