RENCANA ANGGARAN BIAYA

PEKERJAAN : PEKERJAAN PANGGUNG PERMANEN SMP N 1 JETIS


TAHUN : 2023
LOKASI : SMP N 1 JETIS
SATUAN JUMLAH JUMLAH
NO NAMA PEKERJAAN VOLUME HARGA HARGA TOTAL
Rp Rp Rp
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 22.00 m1 22,264.00 489,808.00
2 Pembersihan Lapangan dan Perataan 28.00 m2 11,825.00 331,100.00 820,908.00

II PEKERJAAN TANAH
1 Penggalian Tanah Biasa Sedalam 0.6m 17.10 m3 74,500.00 1,273,950.00
2 Pengurugan Kembali Galian Tanah 8.89 m3 52,525.00 467,052.30
3 Pengurugan tanah peninggian lantai 16.80 m3 85,602.00 1,438,113.60 3,179,115.90

III PEKERJAAN PONDASI


1 Pondasi batu Belah Campuran 1Pc : 4Pp 8.21 m3 684,096.50 5,615,064.07
5,615,064.07
IV PEKERJAAN BETON
1 Membuat Beton Rabat 2.80 m3 1,133,594.00 3,174,063.20
4 Kolom 15x15 0.63 m3 6,237,909.09 3,929,882.73
5 Sloof beton bertulang 15 x 20 0.75 m3 3,942,213.91 2,956,660.43
6 Balok ring beton bertulang 15 x 20 0.75 m3 3,942,213.91 2,956,660.43 13,017,266.79

V PEKERJAAN PASANGAN
1 Pasang Bata merah, camp. 1PC : 4PS 38.00 m2 125,071.10 4,752,701.80
2 Plesteran + Aci 76.00 m2 59,065.38 4,488,968.88
9,241,670.68
VI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Lantai Keramik uk. 40 x 40 cm glossy 29.20 m2 222,525.00 6,497,730.00
2 Bata ekspose tempel 6.78 m2 235,521.00 1,596,832.38
3 Ornamen Gunungan 2.00 bh 1,500,000.00 3,000,000.00 11,094,562.38

VII PEKERJAAN LANGIT - LANGIT


1 Pemasangan rangka hollow dan plafon gypsum 42.50 m2 126,830.00 5,390,275.00
5,390,275.00
VIII PEKERJAAN PENUTUP ATAP
1 Rangka atap baja ringan 40.00 m2 112,000.00 4,480,000.00
2 Atap galvalum 52.28 m2 95,000.00 4,966,600.00
3 Listplank GRC finishing cat 26.00 m1 63,659.44 1,655,145.44
4 Bubungan genteng 19.96 m1 98,000.00 1,956,080.00 13,057,825.44

IX PEKERJAAN PENGECATAN
1 Cat weathershield 41.91 m2 32,356.00 1,356,039.96
2 Cat plafon interior 40.00 m2 22,339.71 893,588.24 2,249,628.20
1 2 3 4 5 6
XI PEKERJAAN ELEKTRIKAL
1 Pasang stop kontak 2.00 ttk 211,585.00 423,170.00
2 pasang lampu LED panel 18W 4.00 bh 221,485.00 885,940.00
3 pasang saklar 2.00 bh 196,185.00 392,370.00
4 pasang MCB 4 phase 1.00 set 1,100,000.00 1,100,000.00 2,801,480.00

TOTAL 66,467,796.46
DIBULATKAN 66,400,000.00

PEKERJAAN : PEKERJAAN PERKERASAN PARKIRAN


TAHUN : 2023
LOKASI : SMP N 1 JETIS
I PEKERJAAN PERKERASAN PARKIRAN
1 Pekerjaan persiapan 210.00 m2 7,500.00 1,575,000.00
2 Membuat Beton Rabat 5cm 10.50 m3 550,000.00 5,775,000.00
TOTAL 7,350,000.00
DIBULATKAN 7,300,000.00