I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 22.00 m1 22,264.00 489,808.00
2 Pembersihan Lapangan dan Perataan 28.00 m2 11,825.00 331,100.00 820,908.00
II PEKERJAAN TANAH
1 Penggalian Tanah Biasa Sedalam 0.6m 17.10 m3 74,500.00 1,273,950.00
2 Pengurugan Kembali Galian Tanah 8.89 m3 52,525.00 467,052.30
3 Pengurugan tanah peninggian lantai 16.80 m3 85,602.00 1,438,113.60 3,179,115.90
V PEKERJAAN PASANGAN
1 Pasang Bata merah, camp. 1PC : 4PS 38.00 m2 125,071.10 4,752,701.80
2 Plesteran + Aci 76.00 m2 59,065.38 4,488,968.88
9,241,670.68
VI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Lantai Keramik uk. 40 x 40 cm glossy 29.20 m2 222,525.00 6,497,730.00
2 Bata ekspose tempel 6.78 m2 235,521.00 1,596,832.38
3 Ornamen Gunungan 2.00 bh 1,500,000.00 3,000,000.00 11,094,562.38
IX PEKERJAAN PENGECATAN
1 Cat weathershield 41.91 m2 32,356.00 1,356,039.96
2 Cat plafon interior 40.00 m2 22,339.71 893,588.24 2,249,628.20
1 2 3 4 5 6
XI PEKERJAAN ELEKTRIKAL
1 Pasang stop kontak 2.00 ttk 211,585.00 423,170.00
2 pasang lampu LED panel 18W 4.00 bh 221,485.00 885,940.00
3 pasang saklar 2.00 bh 196,185.00 392,370.00
4 pasang MCB 4 phase 1.00 set 1,100,000.00 1,100,000.00 2,801,480.00
TOTAL 66,467,796.46
DIBULATKAN 66,400,000.00