Th.Anggaran : 2022
JUMLAH
NO URAIAN PEKERJAAN
(Rp.)
I LOKASI I
A PEKERJAAN SUMUR BOR DANGKAL 38,109,585.20
B PEKERJAAN TOWER RESERVOIR DAN LISTRIK 33,140,414.80
SUB JUMLAH 71,250,000.00
II LOKASI II
A PEKERJAAN SUMUR BOR DANGKAL 38,109,585.20
B PEKERJAAN TOWER RESERVOIR DAN LISTRIK 33,140,414.80
SUB JUMLAH 71,250,000.00
III JUMLAH TOTAL PEKERJAAN 142,500,000.00
Terbilang : Seratus empat puluh dua juta lima ratus ribu rupiah
Mengetahui
Pejabat Pelaksana Teknis Kegiatan Pejabat Pembuat Komitmen
II LOKASI II
A PEKERJAAN SUMUR BOR
1 Biaya Pengeboran Diameter 6 60.00 m 300,000.00 18,000,000.00
2 Tes Geolistrik 1.00 ls 2,500,000.00 2,500,000.00
3 Pompa Submersible 1.00 unit 3,500,000.00 3,500,000.00
4 Panel control 1.00 unit 3,500,000.00 3,500,000.00
5 Kabel NYY 2x1,5 mm 45.00 m 21,500.00 967,500.00
6 Kabel NYY 4x2,5 mm 45.00 m 45,000.00 2,025,000.00
7 Tambang 60.00 m 7,500.00 450,000.00
8 Pipa Hisap Ø 1,5 " PVC AW 12.00 batang 90,000.00 1,080,000.00
9 Pipa Chasing PVC Ø 5 " AW 8.00 batang 625,000.00 5,000,000.00
10 Sock drat dalam Ø 1,5'' PVC 3.00 bh 10,000.00 30,000.00
11 Sock drat luar Ø 1,5'' PVC 3.00 bh 10,000.00 30,000.00
12 Flange Penutup Sumur Ø 1,5 " 1.00 bh 10,000.00 10,000.00
13 Pumping Test 48.00 jam 21,189.28 1,017,085.20
SUB JUMLAH A 38,109,585.20
B PEKERJAAN RESERVOIR DAN LISTRIK
1 PEKERJAAN GALIAN DAN PASANGAN
a Galian tanah 17.00 m3 56,250.00 956,250.00
b Pasangan Pondasi Batu Belah 1 SP : 4 PP 2.70 m3 685,225.00 1,850,107.50
SUB JUMLAH 1 2,806,357.50
2 PEKERJAAN BETON BERTULANG
a Pondasi Fooplate 0.77 m3 997,719.46 763,255.39
Pembesian Sloof 35.84 kg 13,757.50 493,013.77
b Sloof 25/30 cm, beton K 200 0.60 m3 997,719.46 598,631.67
Pembesian Sloof 51.13 kg 13,757.50 703,466.83
Bekisting sloof 0.75 m2 108,475.00 81,356.25
c Kolom 30/30 cm, beton K 200 0.94 m3 997,719.46 933,865.41
Pembesian Kolom 63.97 kg 13,757.50 880,039.76
Bekisting Kolom 1.87 m2 175,475.00 328,489.20
d Balok Beton 25/30, beton K 200 0.60 m3 997,719.46 598,631.67
Pembesian Balok 51.13 kg 13,757.50 703,466.83
Harga Satuan Jumlah Harga
No. Uraian Volume Satuan
(Rp) (Rp)
Bekisting Balok 0.90 m2 198,300.00 178,470.00
e Plat Lantai tebal 12 cm, Beton K 200 1.35 m3 997,719.46 1,343,628.79
Pembesian 92.77 kg 13,757.50 1,276,319.96
Bekisting 11.22 m2 198,300.00 2,225,421.75
SUB JUMLAH 2 11,108,057.30
Harga Satuan Jumlah Harga
No. Uraian Volume Satuan
(Rp) (Rp)
3 PEKERJAAN PIPA
a Pipa Jaringan PVC D 1,5" 320.00 m 15,000.00 4,800,000.00
b Pipa PVC D Outlet 2" 4.00 m 20,000.00 80,000.00
c Pipa PVC D Inlet 1,5" 8.00 m 15,000.00 120,000.00
d Gate Valve 1,5" 2.00 bh 90,000.00 180,000.00
e Knee 2" 3.00 bh 10,000.00 30,000.00
f Knee 1,5" 2.00 bh 8,000.00 16,000.00
g Tangga Besi 1.00 unit 500,000.00 500,000.00
SUB JUMLAH 3 5,726,000.00
4 PEKERJAAN INSTALASI LISTRIK
a Penyambungan Listrik PLN 2200 watt 1.00 ls 3,000,000.00 3,000,000.00
b Penambahan Kabel Jaringan Listrik 100.00 m 20,000.00 2,000,000.00
SUB JUMLAH 4 5,000,000.00
5 TAMPUNGAN 5 m3
a Toren 5.000 lt 1.00 unit 8,500,000.00 8,500,000.00
SUB JUMLAH 5 8,500,000.00
SUB JUMLAH B 33,140,414.80
II LOKASI II
A PEKERJAAN SUMUR BOR
1 Biaya Pengeboran Diameter 6 60.00 m 300,000.00 18,000,000.00
2 Tes Geolistrik 1.00 ls 2,500,000.00 2,500,000.00
3 Pompa Submersible 1.00 unit 3,500,000.00 3,500,000.00
4 Panel control 1.00 unit 3,500,000.00 3,500,000.00
5 Kabel NYY 2x1,5 mm 45.00 m 21,500.00 967,500.00
6 Kabel NYY 4x2,5 mm 45.00 m 45,000.00 2,025,000.00
7 Tambang 60.00 m 7,500.00 450,000.00
8 Pipa Hisap Ø 1,5 " PVC AW 12.00 batang 90,000.00 1,080,000.00
9 Pipa Chasing PVC Ø 5 " AW 8.00 batang 625,000.00 5,000,000.00
10 Sock drat dalam Ø 1,5'' PVC 3.00 bh 10,000.00 30,000.00
11 Sock drat luar Ø 1,5'' PVC 3.00 bh 10,000.00 30,000.00
12 Flange Penutup Sumur Ø 1,5 " 1.00 bh 10,000.00 10,000.00
13 Pumping Test - jam 21,189.28 -
SUB JUMLAH A 37,092,500.00
B PEKERJAAN RESERVOIR DAN LISTRIK
1 PEKERJAAN GALIAN DAN PASANGAN
a Galian tanah 17.00 m3 56,250.00 956,250.00
b Pasangan Pondasi Batu Belah 1 SP : 4 PP 2.70 m3 685,225.00 1,850,107.50
SUB JUMLAH 1 2,806,357.50
2 PEKERJAAN BETON BERTULANG
a Pondasi Fooplate 0.77 m3 997,719.46 763,255.39
Pembesian Sloof 35.84 kg 13,757.50 493,013.77
b Sloof 25/30 cm, beton K 200 0.60 m3 997,719.46 598,631.67
Pembesian Sloof 51.13 kg 13,757.50 703,466.83
Bekisting sloof 0.75 m2 108,475.00 81,356.25
c Kolom 30/30 cm, beton K 200 0.94 m3 997,719.46 933,865.41
Pembesian Kolom 63.97 kg 13,757.50 880,039.76
Bekisting Kolom 1.87 m2 175,475.00 328,489.20
d Balok Beton 25/30, beton K 200 0.60 m3 997,719.46 598,631.67
Harga Satuan Jumlah Harga
No. Uraian Volume Satuan
(Rp) (Rp)
Pembesian Balok 51.13 kg 13,757.50 703,466.83
Bekisting Balok 0.90 m2 198,300.00 178,470.00
e Plat Lantai tebal 12 cm, Beton K 200 1.35 m3 997,719.46 1,343,628.79
Pembesian 92.77 kg 13,757.50 1,276,319.96
Bekisting 11.22 m2 198,300.00 2,225,421.75
f Rabat Beton tebal 5 cm, beton K-100 0.21 m3 854,102.09 177,085.20
SUB JUMLAH 2 11,285,142.50
Harga Satuan Jumlah Harga
No. Uraian Volume Satuan
(Rp) (Rp)
3 PEKERJAAN PIPA
a Pipa Jaringan PVC D 1,5" 376.00 m 15,000.00 5,640,000.00
b Pipa PVC D Outlet 2" 4.00 m 20,000.00 80,000.00
c Pipa PVC D Inlet 1,5" 8.00 m 15,000.00 120,000.00
d Gate Valve 1,5" 2.00 bh 90,000.00 180,000.00
e Knee 2" 3.00 bh 10,000.00 30,000.00
f Knee 1,5" 2.00 bh 8,000.00 16,000.00
g Tangga Besi 1.00 unit 500,000.00 500,000.00
SUB JUMLAH 3 6,566,000.00
4 PEKERJAAN INSTALASI LISTRIK
a Penyambungan Listrik PLN 2200 watt 1.00 ls 3,000,000.00 3,000,000.00
b Penambahan Kabel Jaringan Listrik 100.00 m 20,000.00 2,000,000.00
SUB JUMLAH 4 5,000,000.00
5 TAMPUNGAN 5 m3
a Toren 5.000 lt 1.00 unit 8,500,000.00 8,500,000.00
SUB JUMLAH 5 8,500,000.00
SUB JUMLAH B 34,157,500.00
Harga
No Jenis Satuan
(Rp)
A UPAH
1 Pekerja OH 75,000.00
2 Tukang Batu OH 85,000.00
B BAHAN
1 Batu belah putih kg 125,000.00
2 Kawat beton kg 20,000.00
3 Besi beton kg 11,750.00
4 Bataco bh 2,500.00
5 Bambu btg 10,000.00
6 Kayu Bekisting m3 1,950,000.00
7 Triplek 9 mm lbr 120,000.00
8 Minyak Bekisting ltr 10,000.00
9 Kayu balok m3 4,250,000.00
10 Plamur kg 10,000.00
11 Cat Tembok kg 35,000.00
12 Alkali kg 15,000.00
16 Pasir m' 275,000.00
17 Semen/PC 40 Kg zak 53,000.00
18 Kabel NYA 1x2,5 mm m' 2,500.00
19 Pipa Prolon 5/8 btg 8,000.00
20 Saklar Ganda bh 20,000.00
21 Indoos bh 2,300.00
22 Stop kontak bh 13,500.00
23 Fitting bh 5,000.00
24 Roset bh 1,000.00
25 Lampu 18 watt bh 37,400.00
26 Box MCB tanam bh 50,000.00
27 MCB 10 A bh 50,000.00
28 Isolasi bh 3,900.00
29 Keprus m3 125,000.00
30 Koral beton hari 295,000.00
31 Pasir Urug m3 150,000.00
A PEKERJAAN RESEVOIR
I PERSIAPAN
1 Pek ukur & bouwplang 2.50 2.50 5.00
2 Pembersian Lapangan 2.50 2.50 6.25
3 Steger bambu 3.50
4 Gudang material 1
II PEK TANAH
1 Galian tanah 10 1 1.7 17
17
2 Urugan Tanah Kembali 4.25
4.25
3 Pemadatan 2.5 2.5 0.25 1.56
1.56
4 urugan pasir bwh pondasi 10 1 0.05 0.50
0.50
5 bawah lantai 2.5 2.5 0.05 0.31
0.31
6 Urugan Peninggian Lantai 2.5 2.5 0.9 5.63
5.63
92.77 kg
Bekisting 3.35 3.35 1 11.22 m2
5 Pondasi Footplate 1.7 1 0.45 4 0.77 m3
0.77 m3
Pembesian Tulangan 10 mm 1.7 8.5 4 0.62 35.84 kg
35.84 kg
IV PEK. PASANGAN
1 Pas. Pondasi Batu Belah camp. 1:4 10 0.45 0.6 2.70
2.70
Gunungkidul, 2022
Mengetahui, Diperiksa Dibuat
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Pendamping teknis Kelompok Tani Sekar Wangi
Gunungkidul, 2022
Mengetahui, Diperiksa Dibuat
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan Pendamping teknis Kelompok Tani Sekar Wangi