HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
I PEKRJAAN LAPANGAN
1.1 Survey Pendahuluan Geolistrik Titik 5 2,000,000 10,000,000
1.2 Surat Ijin Pemboran (SIP) Ls - - -
1.3 Mob & Demob Peralatan Bor PP 2 1,000,000 2,000,000
1.4 Mob & Demob Personil Bor PP - - -
1.5 Persiapan Lokasi Ls 1 1,500,000 1,500,000
1.6 Basecamp Proyek Ls 1 2,000,000 2,000,000
JUMLAH I - - - 15,500,000
SATU MILYAR ENAM RATUS EMPAT JUTA DELAPAN PULUH LIMA RIBU RUPIAH
Dihitung Oleh
RENCANA ANGGARAN BIAYA ( RAB )
Pekerjaan : Rehabilitasi Sedang / Berat Gedung Kantor Kelurahan Sukahaji
Lokasi : Jalan Cipagalo Girang - Buah Batu Bandung
Tahun : 2011
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6
LANTAI I
I PEKERJAAN PERSIAPAN
1 Ijin Mendirikan Bangunan (IMB) m² 423.79 40,000.00 16,951,600.00
2 Pembuatan Direksikeet m² 9.00 #REF! #REF!
3 Biaya Pembuatan Sumur Bor + Pompa air Ls 1.00 12,000,000.00 12,000,000.00
4 Pas. Pagar Pengaman Proyek m' 63.45 #REF! #REF!
5 Pas. Bouwplank dan Pengukuran m' 59.45 #REF! #REF!
6 Pembuatan Papan Nama Proyek ls 1.00 350,000.00 350,000.00
7 Administrasi, Mobilisasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
Jumlah I #REF!
II PEKERJAAN GALIAN DAN URUGAN
1 Pek. Galian tanah u/ Pondasi StrauzPaal dia. 35 cm m' 336.00 40,000.00 13,440,000.00
2 Pek. Galian tanah u/ Pondasi Batu Kali m³ 83.39 #REF! #REF!
3 Pek. Galian tanah u/ Poer Plat m³ 18.72 #REF! #REF!
4 Pek. Galian tanah u/ Sloof m³ 5.21 #REF! #REF!
5 Pek. Urugan Tanah kembali m³ 57.80 #REF! #REF!
Jumlah II #REF!
III PEKERJAAN PONDASI DAN BETON
1 Pas. Pondasi Strauzpaal Ø 35 cm h. 8m m³ 30.96 #REF! #REF!
2 Pek. Urugan Pasir bawah pondasi t= 10cm m³ 10.42 #REF! #REF!
3 Pek. Aanstamping Batu Kali t=15 cm m³ 15.64 #REF! #REF!
4 Pas. Pondasi Batu Kali Menerus 1Pc : 5Psr (uk. 80.60.30) m³ 46.91 #REF! #REF!
5 Pas. Lantai Kerja 1 : 3 : 5 t= 15cm m³ 2.48 #REF! #REF!
6 Pas. Poer uk. 120.60.30 cm m³ 3.89 #REF! #REF!
7 Pas. Poer uk. 60.60.30 cm m³ 1.08 #REF! #REF!
8 Pas. Pondasi u/ Tangga Beton 80.80.40 m³ 0.26 #REF! #REF!
9 Pas. Sloof Beton 20/30 cm m³ 7.76 #REF! #REF!
10 Pas. Sloof Beton 15/20 cm m³ 1.39 #REF! #REF!
11 Pas. Kolom Beton 30/40 cm m³ 8.64 #REF! #REF!
12 Pas. Kolom Beton 30/30 cm m³ 4.86 #REF! #REF!
13 Pas. Kolom Beton 15/15 cm m³ 3.06 #REF! #REF!
14 Pas. Ring Balk Beton 15/15 cm m³ 1.35 #REF! #REF!
15 Pas. Balok Lintel 15/15 cm Diatas Kusen m³ 0.91 #REF! #REF!
16 Pas. Balok Lintel + Kolom 15/15 cm Pintu Utama (P2 B) m³ 0.11 #REF! #REF!
17 Pas. Plat Beton Kanopi Samping Kanan dan Kiri t = 8cm m³ 2.54 #REF! #REF!
18 Pas. Plat Tangga Beton + Bordes (Lantai 1 ke lantai 2) m³ 4.13 #REF! #REF!
Jumlah IV #REF!
V PEKERJAAN KUSEN DAN ALAT PENGGANTUNG
1 Pek. Pas. Kusen Pintu alumunium P1-A profil 4" (Warna) m¹ 6.82 #REF! #REF!
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6
2 Pek. Pas. Kusen Pintu alumunium P1-B profil 4" (Warna) m¹ 6.82 #REF! #REF!
3 Pek. Pas. Kusen Pintu alumunium P2-A profil 4" (Warna) m¹ 16.60 #REF! #REF!
4 Pek. Pas. Kusen alumunium PJ1 profil 4" (Warna) m¹ 20.96 #REF! #REF!
5 Pek. Pas. Kusen alumunium PJ2 profil 4" (Warna) m¹ 31.44 #REF! #REF!
6 Pek. Pas. Pintu Kaca Temperd t=12mm P2-B lengkap unit 1.00 12,500,000.00 12,500,000.00
7 Pek. Pas. Pintu PVC KM/WC P3-A Lengkap bh 2.00 375,000.00 750,000.00
8 Pek. Pas. Pintu PVC KM/WC P3-B Lengkap bh 2.00 375,000.00 750,000.00
9 Pek. Pas. Kusen Jendela alumunium J-1 profil 4" (Warna) m¹ 4.82 #REF! #REF!
10 Pek. Pas. Kusen Jendela alumunium J-2 profil 4" (Warna) m¹ 46.98 #REF! #REF!
11 Pek. Pas. Kusen Jendela alumunium J-3 profil 4" (Warna) m¹ 21.68 #REF! #REF!
12 Pek. Pas. Kusen alumunium BV-1 4" (Warna) m¹ 6.60 #REF! #REF!
13 Pek. Pas. Kusen alumunium BV-2 4" (Warna) m¹ 11.20 #REF! #REF!
14 Pek. Pas. Rangka Daun Pintu alumunium P1-A (Warna) m² 0.64 #REF! #REF!
15 Pek. Pas. Rangka Daun Pintu alumunium P1-B (Warna) m² 0.64 #REF! #REF!
16 Pek. Pas. Rangka Daun Pintu alumunium P2-A (Warna) m² 4.27 #REF! #REF!
17 Pek. Pas. Rangka Daun Pintu alumunium PJ-1 (Warna) m² 1.87 #REF! #REF!
18 Pek. Pas. Rangka Daun Pintu alumunium PJ-2 (Warna) m² 2.81 #REF! #REF!
19 Pek. Pas. Rangka Daun Jendela alumunium J-1 (Warna) m² 0.30 #REF! #REF!
20 Pek. Pas. Rangka Daun Jendela alumunium J-2 (Warna) m² 1.78 #REF! #REF!
21 Pek. Pas. Rangka Daun Jendela alumunium J-3 (Warna) m² 1.18 #REF! #REF!
22 Pek. Pas. Kaca Polos t= 5 mm m² 30.02 #REF! #REF!
23 Pek. Pas. Kaca Polos t= 12 mm m² 0.88 #REF! #REF!
24 Pek. Pas. Multiplek 9mm Lapis Teakwood m² 6.16 125,000.00 770,000.00
25 Pek. Pas. Glasblock bh 8.00 24,000.00 192,000.00
26 Pas. Rambucis Sek. Dekson bh 16.00 #REF! #REF!
27 Pas. Casement Sek. Dekson Psg 16.00 #REF! #REF!
28 Pas. Engsel Pintu Sek. Dekson Psg 17.00 #REF! #REF!
29 Pas. Lever Handle Sek. Dekson Psg 13.00 #REF! #REF!
30 Pas. Bodi Kunci + Cylinder Sek. Dekson Set 9.00 #REF! #REF!
31 Pas. Door Closer Sek. Dekson Psg 13.00 #REF! #REF!
Jumlah V #REF!
VI PEKERJAAN PLAFOND
1 Pas. Plafond Gypsum +Rangka Hollow m² 205.17 #REF! #REF!
2 Pas. Plafond MultiPlek + Rangka Hollow (KM/WC) m² 7.45 #REF! #REF!
3 Pas. List Plafond Gypsum m¹ 217.65 #REF! #REF!
Jumlah VI #REF!
VII PEKERJAAN LANTAI
1 Pek. Urugan pasir dibawah Lantai m³ 11.58 #REF! #REF!
2 Pek. Pas. Lantai Keramik 30 x 30 cm m² 231.52 #REF! #REF!
3 Pek. Pas. Keramik selasar 30 x 30 cm m² 6.08 #REF! #REF!
4 Pek. Pas. Keramik Tangga 30 x 30 cm m² 21.86 #REF! #REF!
5 Pek. Pas. Stepnozing Keramik u/ Tangga 5 x 30 cm m¹ 20.40 #REF! #REF!
6 Pek. Pas. Keramik KM/WC 20/20 cm (Anti Slip) m² 7.34 #REF! #REF!
7 Pek. Pas. Keramik Dinding KM/WC 20/25 cm m² 27.68 #REF! #REF!
8 Pekerjaan rabat beton (Floor) Pinggir Gedung m² 36.02 #REF! #REF!
9 Pek. Pas. Pavingblok t = 8cm Sek. Cisangkan m² 223.50 #REF! #REF!
Jumlah IX #REF!
X INSTALASI AIR BERSIH & AIR KOTOR
1 Instalasi Air Bersih
- Pipa PVC 1/2" m¹ 10.80 #REF! #REF!
- Pipa PVC 3/4" m¹ 48.64 #REF! #REF!
- Accsesories PVC ls 1.00 #REF! #REF!
Jumlah X #REF!
Sub Jumlah Lantai I #REF!
LANTAI II
I PEKERJAAN BETON
1 Pas. Balok Beton 25/60 cm m³ 12.60 #REF! #REF!
2 Pas. Balok Beton 20/40 cm m³ 7.99 #REF! #REF!
3 Pas. Balok Beton 20/30 cm m³ 1.40 #REF! #REF!
4 Pas. Plat Lantai Beton t = 12 cm m³ 25.81 #REF! #REF!
5 Pas. Kolom Beton 30/30 cm m³ 11.23 #REF! #REF!
6 Pas. Ringbalk Beton 20/30 cm m³ 5.21 #REF! #REF!
7 Pas. Ringbalk Beton 15/15 cm m³ 1.41 #REF! #REF!
8 Pas. Balok Lintel 15/15 cm Diatas Kusen m³ 0.75 #REF! #REF!
9 Pas. Plat Beton Kanopi Samping Kanan dan Kiri t = 8cm m³ 2.54 #REF! #REF!
10 Pas. Plat Dak Beton Atap Tangga m³ 3.23 #REF! #REF!
Jumlah I #REF!
II PEKERJAAN PASANGAN DINDING
1 Pek. Pasangan dinding 1/2 bata ad. 1 : 5 m² 217.78 #REF! #REF!
2 Pek. Plesteran dinding + acian ad.1 : 5 m² 435.56 #REF! #REF!
3 Pek. Pasangan Roaster Keramik bh 12.00 45,000.00 540,000.00
Jumlah II #REF!
III PEKERJAAN KUSEN DAN ALAT PENGGANTUNG
1 Pek. Pas. Kusen Pintu alumunium P2-A profil 4" (Warna) m¹ 8.30 #REF! #REF!
2 Pek. Pas. Kusen Jendela alumunium J-4 profil 4" (Warna) m¹ 23.00 #REF! #REF!
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6
3 Pek. Pas. Kusen Jendela alumunium J-5 profil 4" (Warna) m¹ 16.40 #REF! #REF!
4 Pek. Pas. Kusen alumunium BV-2 4" (Warna) m¹ 33.60 #REF! #REF!
5 Pek. Pas. Rangka Daun Pintu alumunium P2-A (Warna) m² 2.14 #REF! #REF!
6 Pek. Pas. Rangka Daun Jendela alumunium J-4 (Warna) m² 1.02 #REF! #REF!
7 Pek. Pas. Kaca Polos t= 5 mm m² 26.20 #REF! #REF!
8 Pek. Pas. Multiplek 9mm Lapis Teakwood m² 1.00 125,000.00 125,000.00
9 Pas. Rambucis Sek. Dekson bh 20.00 #REF! #REF!
10 Pas. Casement Sek. Dekson Psg 20.00 #REF! #REF!
11 Pas. Engsel Pintu Sek. Dekson Psg 3.00 #REF! #REF!
12 Pas. Lever Handle Sek. Dekson Psg 2.00 #REF! #REF!
13 Pas. Bodi Kunci + Cylinder Sek. Dekson Set 1.00 #REF! #REF!
14 Pas. Door Closer Sek. Dekson Psg 2.00 #REF! #REF!
Jumlah IV #REF!
V PEKERJAAN PLAFOND
1 Pas. Plafond Gypsum +Rangka Hollow m² 256.06 #REF! #REF!
2 Pas. Plafond Calsiboard +Rangka Hollow m² 89.70 #REF! #REF!
3 Pas. List Plafond Gypsum m¹ 629.10 #REF! #REF!
Jumlah V #REF!
VI PEKERJAAN LANTAI
1 Pek. Urugan pasir dibawah Lantai m³ 9.92 #REF! #REF!
2 Pek. Pas. Lantai Keramik 30 x 30 cm m² 198.40 #REF! #REF!
Jumlah VI #REF!
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Sek. "SANLEX" m² 492.18 #REF! #REF!
2 Pek, Pengecatan Plafond gypsum Sek. "SANLEX" m² 345.76 #REF! #REF!
3 Pek, Melamik daun Pintu Multiplek P2A m² 1.80 75,000.00 135,000.00
4 Pek. Plint cat sek. "SEIV" m² 9.92 #REF! #REF!
Jumlah IX #REF!
X PEKERJAAN LAIN-LAIN
1 Pasangan Huruf timbul Stainless tinggi = 15cm
- "PEMERINTAH KOTA BANDUNG KELURAHAN MARGASARI" cm 585.00 7,500.00 4,387,500.00
Pasangan Logo 1x1m & Huruf Timbul tinggi 5 cm
- "GEMAH RIPAH WIBAWA MUKTI" ls 1.00 12,500,000.00 12,500,000.00
2 Pembersihan & Buangan Sisa-sisa pekerjaan ls 1.00 1,500,000.00 1,500,000.00
Jumlah X 18,387,500.00
Sub Jumlah Lantai II #REF!
DAFTAR HARGA SATUAN PEKERJAAN
BERDASARKAN SNI EDISI 2007
#REF!
DINAS TATA RUANG DAN CIPTA KARYA
KOTA BANDUNG
Jumlah Harga
No. Uraian Jenis Pekerjaan Sat. Bahan + Upah
Rp.
1 2 3 4
A ANALISA BIAYA KONSTRUKSI PEKERJAAN PERSIAPAN
5 PAS. BOUWPLANK & PENGUKURAN M' #REF!
B ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH
2 GALIAN TANAH BIASA KEDALAMAN 1 M' M² #REF!
3 GALIAN TANAH BIASA KEDALAMAN 2 M' M² #REF!
4 GALIAN TANAH BIASA KEDALAMAN 3 M' M² #REF!
10 URUGAN TANAH KEMBALI M² #REF!
12 URUGAN TANAH PENINGGIAN LANTAI M² #REF!
13 URUGAN PASIR M² #REF!
14 PASANGAN LAPISAN IJUK M² #REF!
C ANALISA BIAYA KONSTRUKSI PEKERJAAN PONDASI BATU KALI
1 PASANGAN BATU KOSONG / AANSTAMPING M³ #REF!
4 PASANGAN PONDASI BATU KALI, 1 PC. : 5 PS. M³ #REF!
8 PASANGAN PONDASI SUMURAN, DIAMETER 100 CM M³ #REF!
D ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON
1 BETON MUTU F¹C = 7,4 MPa (K 100) SLUMP (12 + 2) cm, w/c = 0,87 M³ #REF!
33 PLAT PENUTUP SEPTICTANK BETON BERTULANG (75 Kg besi + bekisting) M³ #REF!
E ANALISA BIAYA KONSTRUKSI PEKERJAAN DINDING
7 PAS. DINDING BATA MERAH UK. (5x11x22) cm TEBAL ½ BATA, CAMPURAN 1 PC. : 3 PS. M² #REF!
9 PAS. DINDING BATA MERAH UK. (5x11x22) cm TEBAL ½ BATA, CAMPURAN 1 PC. : 5 PS. M² #REF!
F ANALISA BIAYA KONSTRUKSI PEKERJAAN PLESTERAN
3 PLESTERAN DINDING 1 PC. : 3 PS; TEBAL 15 MM M² #REF!
5 PLESTERAN DINDING 1 PC. : 5 PS; TEBAL 15 MM M² #REF!
21 PLESTERAN CIPRAT, 1PC. : 2 PS, M² #REF!
25 PASANGAN ACIAN M² #REF!
G ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU
51 PASANG LISTPLANK 3 x 20 CM, KAYU KAMPER M¹ #REF!
H ANALISA BIAYA KONSTRUKSI PEKERJAAN PENUTUP LANTAI
24 PASANGAN LANTAI KERAMIK , UK. 30 x 30 CM PUTIH POLOS M² #REF!
26 PASANGAN LANTAI KERAMIK , UK. 20 x 20 CM M² #REF!
28 PASANGAN PLINT KERAMIK , UK. 10 x 20 CM M¹ #REF!
43 PASANGAN DINDING KERAMIK , UK. 20 x 25 CM CORAK / WARNA M² #REF!
55 PASANGAN PAVINGBLOCK WARNA TEBAL 6 Cm M² #REF!
57 PASANGAN PAVINGBLOCK NATURAL TEBAL 6 Cm M² #REF!
I ANALISA BIAYA KONSTRUKSI PEKERJAAN LANGIT - LANGIT
14 LANGIT - LANGIT GYPSUM BOARD UK. 120x240 CM TEBAL 9 MM M² #REF!
19 LIST LANGIT - LANGIT KAYU PROFIL M¹ #REF!
20 LANGIT - LANGIT ASBES ( 1 x 1 ) M, T = 3,2 MM + RANGKA KAYU BORNEO M² #REF!
1 2 3 4
J ANALISA BIAYA KONSTRUKSI PEKERJAAN PENUTUP ATAP
3 PASANG ATAP GENTENG PALENTONG SUPER M² #REF!
6 PASANG GENTENG BUBUNG PALENTONG SUPER M² #REF!
7 PASANG ROOF LIGHT FIBREGLASS, 90 X 180 CM M² #REF!
8 PASANG ATAP ASBES GELOMBANG, 92 x 250 x 0.5 CM M² #REF!
20 PASANG BUBUNG STEL GELOMBANG, 0.92 M M¹ #REF!
22 PEKERJAAN BONDEX M² #REF!
29 PASANG ATAP GENTENG BETON M¹ #REF!
30 PASANG ATAP GENTENG METAL M² #REF!
32 PASANG NOK GENTENG BETON M¹ #REF!
33 PASANG NOK GENTENG METAL M¹ #REF!
40 PASANG TALANG DATAR, SENG BJLS 30 M¹ #REF!
41 PASANG TALANG MIRING, SENG BJLS 30 M¹ #REF!
K ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALUMINIUM
1 PASANG RANGKA ATAP BAJA Kg #REF!
2 PASANG RANGKA BESI KANAL C. 150.65.20.3,2 Kg #REF!
3 PASANG RANGKA BESI SIKU MACAM-MACAM UKURAN Kg #REF!
10 PASANG PINTU SUNSCREEN ALLUMUNIUM M² #REF!
12 PASANG KUSEN PINTU ALUMUNIUM M¹ #REF!
13 PASANG PINTU ALLUMINIUM STRIP LEBAR 8 CM M² #REF!
14 PASANG PINTU KACA RANGKA ALLUMINIUM M² #REF!
L ANALISA BIAYA KONSTRUKSI PEKERJAAN SANITASI
#REF!
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
I PEKRJAAN LAPANGAN
1.1 Survey Pendahuluan Geolistrik Titik 5 2,000,000 10,000,000
1.2 Surat Ijin Pemboran (SIP) Ls - - -
1.3 Mob & Demob Peralatan Bor PP 2 1,000,000 2,000,000
1.4 Mob & Demob Personil Bor PP - - -
1.5 Persiapan Lokasi Ls 1 1,500,000 1,500,000
1.6 Basecamp Proyek Ls 1 2,000,000 2,000,000
JUMLAH I - - - 15,500,000
JUMLAH IV - - - 1,500,000
JUMLAH V - - - 12,750,000
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
JUMLAH VI - - - 2,000,000
TERBILANG : # DUA RATUS TUJUH PULUH DELAPAN JUTA TIGA RATUS ENAM PULUH RIBU RUPIAH #
RYANTHONY
DIREKTUR
Jl. Cihanjuang No. 5 Cibaligo Kec. Parongpong Kab. Bandung Barat
Telp. ( 022 ) 663 4222
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
I PEKERJAAN PERSIAPAN
1.1 Survey Pendahuluan Geolistrik Titik 5 5,000,000 25,000,000
1.2 Surat Ijin Pemboran (SIP) Ls 1 30,000,000 30,000,000
1.3 Mob & Demob Peralatan Bor PP 2 2,000,000 4,000,000
1.4 Mob & Demob Personil Bor PP - - -
1.5 Persiapan Lokasi Ls 1 2,500,000 2,500,000
1.6 Basecamp Proyek 2 x 4 M Ls 1 4,000,000 4,000,000
JUMLAH I - - 65,500,000
II PEKERJAAN PENGEBORAN
2.1 Pemboran awal (Pilot hole) dengan menggunakan diameter 6/8"
termasuk pengadaan air pemboran, lumpur pemboran (bentonit),
pengambilan sampel batuan, dll. meter 125 750,000 93,750,000
JUMLAH IV - - - 2,500,000
JUMLAH V - - - 13,095,000
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
TERBILANG : # TIGA RATUS ENAM PULUH TUJUH JUTA SERATUS SEMBILAN PULUH RIBU RUPIAH #
TERBILANG : # DUA RATUS SEMBILAN BELAS JUTA DUA RATUS TIGA PULUH DUA RIBU RUPIAH #
RYANTHONY
DIREKTUR
Jl. Cihanjuang No. 5 Cibaligo Kec. Parongpong Kab. Bandung Barat
Telp. ( 022 ) 663 4222
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
I PEKERJAAN PERSIAPAN
1.1 Survey Pendahuluan Geolistrik Titik 5 5,625,000 28,125,000
1.2 Surat Ijin Pemboran (SIP) Ls 1 33,750,000 33,750,000
1.3 Mob & Demob Peralatan Bor PP 2 2,250,000 4,500,000
1.4 Mob & Demob Personil Bor PP - - -
1.5 Persiapan Lokasi Ls 1 2,812,500 2,812,500
1.6 Basecamp Proyek 2 x 4 M Ls 1 4,500,000 4,500,000
JUMLAH I - - 73,687,500
II PEKERJAAN PENGEBORAN
2.1 Pemboran awal (Pilot hole) dengan menggunakan diameter 6/8"
termasuk pengadaan air pemboran, lumpur pemboran (bentonit),
pengambilan sampel batuan, dll. meter 125 843,750 105,468,750
JUMLAH IV - - - 2,812,500
JUMLAH V - - - 14,731,875
HARGA
JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN
( 1 titik Bor )
(Rp.)
VI PEKERJAAN PEMASANGAN SUMERSIBLE
6.1 Pekerjaan Pemasangan Pompa Sumersible (Permanen) ls 1 3,375,000 3,375,000
JUMLAH VI - - - 3,375,000
VII PENGADAAN BAHAN & MATERIAL
7.1 Pengadaan Pipa PVC Paralon AW diameter 6" Rucika meter 95 264,375 25,115,625
7.2 Pengadaan Pipa Saringan/Screen PVC Paralon AW 6" Rucika meter 30 393,750 11,812,500
7.3 Pengadaan Gravel Pack (Batu Saringan) m³ 8 270,000 2,160,000
7.4 Semen (untuk Grouting) zak 20 84,375 1,687,500
7.5 Pengadaan Pipa Naik Galvanis diameter 2" meter 110 84,375 9,281,250
7.6 Pengadaan Pompa Sumersible 3 PK merk Franklin unit 1 39,375,000 39,375,000
7.7 Pengadaan Panel Pompa Sumersible 3 PK unit 1 4,500,000 4,500,000
7.8 Pengadaan Kabel Pompa meter 125 28,125 3,515,625
7.9 Pengadaan Kabel Elektroda meter 125 11,250 1,406,250
7.10 Pengadaan elektroda buah 8 84,375 675,000
JUMLAH VII - - - 99,528,750
TOTAL KESELURUHAN ( I s/d VIII ) 413,088,750
PEMBULATAN 413,088,000
TERBILANG : # EMPAT RATUS TIGA BELAS JUTA DELAPAN PULUH DELAPAN RIBU RUPIAH #
TERBILANG : # DUA RATUS EMPAT PULUH EMPAT JUTA TUJUH RATUS DELAPAN BELAS RIBU RUPIAH #
RYANTHONY
DIREKTUR
GAMBAR KONTRUKSI SUMUR DALAM
GAMBAR KONTRUKSI SUMUR DALAM
GAMBAR KONTRUKSI BAK PENAMPUNGAN
6M
3M
Plat Besi
Pipa keluar Pipa Masuk
dia 2" dia 2"
Tangga
7M stainless
dinding beton
tebal 20 cm
Sloof Gantung
Pondasi Sumuran Lantai kerja
dia 60 cm tebal 5 cm
Pembesian Ø 12 - 200 double
Jl. Cihanjuang No. 5 Cibaligo Kec. Parongpong Kab. Bandung Barat
Telp. ( 022 ) 663 4222
HARGA
JUMLAH
NO URAIAN SAT VOL SATUAN
Murni 25% Murni 25%
RYANTHONY
DIREKTUR
ANALISA HARGA SATUAN
TAHUN ANGGARAN 2012
Harga Jumlah Harga Jumlah Harga
No Uraian Sat. Koeff Satuan Bahan Upah Bahan + Upah
(Rp) (Rp) (Rp) (Rp)
1 1 M2 Pembuatan Papan Nama Proyek
Bahan :
Kayu Borneo m3 0.1300 1,500,000.00 195,000.00
Seng Plat BJLS 25 lbr 0.6787 48,500.00 32,916.95
Paku 5 - 7 cm kg 0.2500 11,640.00 2,910.00
Cat Minyak lbr 1.0000 11,640.00 11,640.00
Penulisan ls 1.0000 50,000.00 50,000.00
Ongkos Pasang ls 1.0000 25,000.00 25,000.00
Jumlah 317,466.95 317,466.95
Keuntungan Maksimal 10% 31,746.70
Jumlah Total 349,213.65
2 1 M1 Pasang Pipa PVC Type AW diameter 6"
BAHAN
Pipa PVC AW diameter 6" Rucika m1 1.2000 221,875.00 266,250.00
Perlengkapan ls 1.0000 250,000.00 144,000.00
TENAGA
Pekerja org 0.0360 50,000.00 1,800.00
Tukang batu org 0.0600 55,000.00 3,300.00
Kepala tukang org 0.0060 60,000.00 360.00
Mandor org 0.0018 75,000.00 135.00
Jumlah 410,250.00 5,595.00
Keuntungan 10% 41,025.00 559.50
Jumlah Total 451,275.00 6,154.50 457,429.50
3 1 M' Pemboran Pilot Hole dia 8"
Kedalaman 0 - 75 m
Alat
Sewa Alat 1 unit Hari 0.1050 1,000,000.00 105,000.00
Bahan
Solar Liter 15.7890 4,500.00 71,050.50
Olie Kg 0.2110 19,400.00 4,093.40
Grease Kg 0.1050 22,500.00 2,362.50
Karet Piston Psng 0.1050 60,000.00 6,300.00
Bentonite Zak 0.2140 150,000.00 32,100.00
Mata Bor Bh 0.0070 500,000.00 3,500.00
Tenaga
Juru Bor Oh 0.1050 60,000.00 6,300.00
Ass. Juru Bor Oh 0.1050 55,000.00 5,775.00
Mekanik Oh 0.1050 50,000.00 5,250.00
Pekerja Oh 0.3160 50,000.00 15,800.00
Jumlah 224,406.40 33,125.00 257,531.40
Keuntungan 10% 25,753.14
Jumlah Total 283,284.54
4 1 M Pemboran Pilot Hole dia 8"
Keadalaman 75 -150 m
Alat
Sewa Alat 1 Unit Hari 0.1670 1,000,000.00 167,000.00
Bahan
Solar Liter 17.6570 4,500.00 79,456.50
olie Kg 0.3330 19,400.00 6,460.20
grease Kg 0.1670 22,500.00 3,757.50
Karet Piston Psng 0.1670 60,000.00 10,020.00
Bentonite Zak 0.3330 150,000.00 49,950.00
Mata Bor Bh 0.0070 500,000.00 3,500.00
Tenaga
Juru Bor Oh 0.0830 60,000.00 4,980.00
Ass. Juru Bor Oh 0.0830 55,000.00 4,565.00
Mekanik Oh 0.0830 50,000.00 4,150.00
Pekerja Oh 0.2500 50,000.00 12,500.00
Jumlah 320,144.20 26,195.00 346,339.20
Keuntungan 10% 34,633.92
Jumlah Total 380,973.12
5 1 M Pembesaran Lubang Bor dia 10"
Kedalaman 0 - 75 m
Alat
Sewa Alat 1 Unit Hari 0.0560 1,000,000.00 56,000.00
Bahan
Solar Liter 8.3330 4,500.00 37,498.50
olie Kg 0.1110 19,400.00 2,153.40
grease Kg 0.0560 22,500.00 1,260.00
Karet Piston Psng 0.0560 60,000.00 3,360.00
Bentonite Zak 0.1110 150,000.00 16,650.00
Mata Bor Bh 0.0060 500,000.00 3,000.00
Tenaga
Juru Bor Oh 0.0560 60,000.00 3,360.00
Ass. Juru Bor Oh 0.0560 55,000.00 3,080.00
Mekanik Oh 0.0560 50,000.00 2,800.00
Pekerja Oh 0.1670 50,000.00 8,350.00
Jumlah 119,921.90 17,590.00 137,511.90
Keuntungan 10% 13,751.19
Jumlah Total 151,263.09
6 1 M Pembesaran Lubang Bor dia 10"
Keadalaman 75 -150 m
Alat
Sewa Alat 1 Unit Hari 0.0630 1,000,000.00 63,000.00
Bahan
Solar Liter 9.3750 4,500.00 42,187.50
olie Kg 0.1250 19,400.00 2,425.00
grease Kg 0.0630 22,500.00 1,417.50
Karet Piston Psng 0.0630 60,000.00 3,780.00
Bentonite Zak 0.1250 150,000.00 18,750.00
Mata Bor Bh 0.0070 500,000.00 3,500.00
Tenaga
Juru Bor Oh 0.0630 60,000.00 3,780.00
Ass. Juru Bor Oh 0.0630 55,000.00 3,465.00
Mekanik Oh 0.0630 50,000.00 3,150.00
Pekerja Oh 0.1880 50,000.00 9,400.00
Jumlah 135,060.00 19,795.00 154,855.00
Jumlah 157,310.00 39,590.00 196,900.00
Keuntungan 10% 19,690.00
Jumlah Total 216,590.00
7 Memasang 1 M' pipa Galvanis diameter 2"
Bahan
Pipa Galvanis M' 1.2000 50,000.00 50,001.20
Perlengkapan Ls 0.3500 17,500.00 17,500.35
Tenaga
Pekerja Oh 0.1080
Tukang batu Oh 0.1800
Kepala tukang batu Oh 0.0180
Mandor Oh 0.0054
Jumlah 67,501.55 - 67,501.55
Keuntungan 10% 6,750.16
Jumlah Total 74,251.71
ANALISA HARGA SATUAN PEKERJAAN
KOTA CIMAHI
TAHUN ANGGARAN 2012
1 2 3 4 5 6=(3x5)
Jumlah 61,115.10
Keuntungan Max. 6,111.51
Jumlah 67,226.61
Dibulatkan 67,220.00
Jumlah 30,465.00
Keuntungan Max. 3,046.50
Jumlah 33,511.50
Dibulatkan 33,510.00
Jumlah #N/A
Dibulatkan #N/A
B016 1 m2 Pembuatan jalan sementara, tebal 25 cm
Dibulatkan 573,440.00
C011 1 m Pas. pondasi batu belah, 1/4 PC : 1 KP : 4 PP
3
C013 1 m3 Pas. pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah
C016 1 M' Pembuatan tiang pancang (35 x 35) Cm, beton bertulang
Pasir Urug 0.0160 M3 67,500.00 1,080.00
Pasir Beton 0.0800 M 3
250,000.00 20,000.00
Koral Beton 0.1250 M3 127,000.00 15,875.00
Semen PC Tiga Roda / 50 kg 0.9800 Zak 66,000.00 64,680.00
Besi Beton U-24 Rata - Rata ( Polos ) 34.5000 Kg 9,000.00 310,500.00
Kawat Beton 0.7000 Kg 16,625.00 11,637.50
Kayu Balok Borneo Super 0.0270 M3 4,500,000.00 121,500.00
Paku 4 cm s/d 7 cm 0.1200 Kg 15,000.00 1,800.00
Plus Oil 0.0900 Lt 21,000.00 1,890.00
Plamir Tembok Sanlex 0.2000 Kg 15,000.00 3,000.00
Pekerja 0.8000 Oh 53,400.00 42,720.00
Tukang batu 0.5000 Oh 62,700.00 31,350.00
Kepala tukang 0.0500 Oh 68,900.00 3,445.00
Mandor 0.0400 Oh 75,300.00 3,012.00
Jumlah 632,489.50
Keuntungan Max. 63,248.95
Jumlah 695,738.45
Dibulatkan 695,730.00
D002 1M1 m3
Lebih
2zak Beton
dari=30
PC
Pasangan memerlukan
50m'
bata 40 liter=atebal
kg: =merah ………….
= 0.04 m3 (bb)
:1 Upah
bata, ……………..kg
= Pekerja
11/25
PC : 2Setempat
m3 PP (Hasil Perhitungan
( rupiah ) )
maka setiap jarak : (1 / (275 L / ( L: +Jarak
75 )))angkut
/25 x adalam m1
(bb)
Bata kg besi
Merah beton
Bakar Rp. I……………………………………………..
Kelas k : Harga angkutan per m3 a 140.0000
= Upah Pekerja
Bh Setempat (rupiah )
600.00 84,000.00
L = 10 m1 = ( Termasuk xharga bahan
0,01236 a L dan= peralatan
Jarak angkut: bambu,
angkut dalam dll)
m1
Semen
L PC
= Tiga50Roda
m1 / 50 = kg 0,01818 x a k = 0.8700 Zak
Harga angkutan per m3 66,000.00 57,420.00
kL = =a /275 100( m1
L + = 75 ) 0,02545 x a (termasuk harga bahan dan peralatan angkut, bambu, dll)
Pasir
L Pasang
= 200 m1 = 0,04000 x a 0.0800 M 3
185,000.00 14,800.00
L
Pekerja = 300 m1 = 0,05454 x a 0.6000 Oh 53,400.00 32,040.00
Tukang
Ket. : Batu
L = Jarak angkut dalam m1 0.2000 Oh 62,700.00 12,540.00
a = Upah pekerja setempat ( Rupiah )
Kepala tukang 0.0200 Oh 68,900.00 1,378.00
Mandor 0.0300 Oh 75,300.00 2,259.00
Jumlah 204,437.00
Keuntungan Max. 20,443.70
Jumlah 224,880.70
Dibulatkan 224,880.00
Concrete Block Regular Full (390x190x90) 10.01 ex. 12.5000 Bh #N/A #N/A
Semen PC Tiga Roda / 50 kg 0.3032 Zak 66,000.00 20,011.20
Pasir Pasang 0.3640 M3 185,000.00 67,340.00
Besi Beton U-24 Rata - Rata ( Polos ) 0.2800 Kg 9,000.00 2,520.00
Pekerja 0.3000 Oh 53,400.00 16,020.00
Tukang Batu 0.1000 Oh 62,700.00 6,270.00
Kepala tukang 0.0100 Oh 68,900.00 689.00
Mandor 0.0150 Oh 75,300.00 1,129.50
Jumlah #N/A
Keuntungan Max. #N/A
Jumlah #N/A
Dibulatkan #N/A
D023 1 M Pasangan dinding HB/CB 10, 1 PC : 4 PP
2
Concrete Block Regular Full (390x190x90) 10.01 ex. 12.5000 Bh #N/A #N/A
Semen PC Tiga Roda / 50 kg 0.2426 Zak 66,000.00 16,011.60
Pasir Pasang 0.3880 M3 185,000.00 71,780.00
Besi Beton U-24 Rata - Rata ( Polos ) 0.2800 Kg 9,000.00 2,520.00
Pekerja 0.3000 Oh 53,400.00 16,020.00
Tukang Batu 0.1000 Oh 62,700.00 6,270.00
Kepala tukang 0.0100 Oh 68,900.00 689.00
Mandor 0.0150 Oh 75,300.00 1,129.50
Jumlah #N/A
Keuntungan Max. #N/A
Jumlah #N/A
Dibulatkan #N/A
D024 1 M2 Pasangan dinding conblock (CB. 20)
Jumlah #N/A
Keuntungan Max. #N/A
Jumlah #N/A
Dibulatkan #N/A
Dibulatkan 46,310.00
E004 1 M Plesteran 1 PC : 4 PP, tebal 15 mm
2
Jumlah 73,378.80
Dibulatkan 73,370.00
E025 1 M2 Plesteran 1 PC : 3 PP, tebal 30 mm
Semen PC Tiga Roda / 50 kg 0.2830 Zak 66,000.00 18,678.00
Pasir pasang 0.0390 M3
185,000.00 7,215.00
Pekerja 0.3200 Oh 53,400.00 17,088.00
Tukang Batu 0.2500 Oh 62,700.00 15,675.00
Kepala tukang 0.0250 Oh 68,900.00 1,722.50
Mandor 0.0150 Oh 75,300.00 1,129.50
Jumlah 61,508.00
Keuntungan Max. 6,150.80
Jumlah 67,658.80
Dibulatkan 67,650.00
E027 1 M Plesteran 1 PC : 4 PP, tebal 30 mm
2
Jumlah 12,543,295.00
Keuntungan Max. 1,254,329.50
Jumlah 13,797,624.50
Dibulatkan 13,797,620.00
F002 1 M Pasang kusen pintu dan jendela kayu kamper (kayu kelas II atau III)
3
Jumlah 433,251.39
Dibulatkan 433,250.00
F006 1 M2 Pasang pintu klamp standar kayu borneo (kayu kelas II)
Kayu Papan Borneo Super 0.0400 M3 5,500,000.00 220,000.00
Paku 4 cm s/d 7 cm 0.0500 Kg 15,000.00 750.00
Pekerja 0.3500 Oh 53,400.00 18,690.00
Tukang kayu 1.0500 Oh 62,700.00 65,835.00
Kepala tukang 0.1050 Oh 68,900.00 7,234.50
Mandor 0.0180 Oh 75,300.00 1,355.40
Jumlah 313,864.90
Keuntungan Max. 31,386.49
Jumlah 345,251.39
Dibulatkan 345,250.00
F007 1 M Pasang pintu klamp sederhana, kayu albasiah untuk gudang sementara
2
F010 1 M Pasang pintu dan jendela kaca kayu jati (kayu kelas I atau II)
2
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F014 1 M Pasang pintu dan jendela jalusi kayu kamper (kayu kelas I atau II)
2
F018 1 M2 Pasang jalusi kusen kayu jati (kayu kelas I atau II)
Kayu Jati Jabar dia. 40 cm keatas 0.0600 M3 Err:509 Err:509
Paku 1 cm s/d 3 cm 0.1500 Kg Err:509 Err:509
Pekerja 0.6700 Oh 53,400.00 35,778.00
Tukang kayu 2.0000 Oh 62,700.00 125,400.00
Kepala tukang 0.2000 Oh 68,900.00 13,780.00
Mandor 0.3350 Oh 75,300.00 25,225.50
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F019 1 M Pasang jalusi kusen kayu kamper (kayu kelas I atau II)
2
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F023 1 M2 Pasang pintu plywood rangkap & formika, rangka kayu jati
Kayu Jati Jabar dia. 40 cm keatas 0.0196 M3 Err:509 Err:509
Paku 1 cm s/d 3 cm 0.3000 Kg Err:509 Err:509
Lem kayu 0.8000 Kg Err:509 Err:509
Triplek 4 mm Ukuran Pintu 1.0000 Lbr Err:509 Err:509
Formika Ukuran Pintu 0.5000 Lbr Err:509 Err:509
Pekerja 0.8000 Oh 53,400.00 42,720.00
Tukang kayu 2.5000 Oh 62,700.00 156,750.00
Kepala tukang 0.2500 Oh 68,900.00 17,225.00
Mandor 0.0400 Oh 75,300.00 3,012.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F024 1 M2 Pasang pintu plywood rangkap & formika, rangka kayu kamper
Kayu Papan Kamper Banjar 0.0196 M3 Err:509 Err:509
Paku 1 cm s/d 3 cm 0.3000 Kg Err:509 Err:509
Lem kayu 0.8000 Lt Err:509 Err:509
Triplek 4 mm Ukuran Pintu 1.0000 Lbr Err:509 Err:509
Formika Ukuran Pintu 0.5000 Lbr Err:509 Err:509
Pekerja 0.8000 Oh 53,400.00 42,720.00
Tukang kayu 2.5000 Oh 62,700.00 156,750.00
Kepala tukang 0.2500 Oh 68,900.00 17,225.00
Mandor 0.0400 Oh 75,300.00 3,012.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F025 1 M2 Pasang pintu teakwood rangkap lapis formika, rangka expose kayu kamper (kayu kelas II)
Kayu Papan Kamper Banjar 0.0250 M3 Err:509 Err:509
Paku 1 cm s/d 3 cm 0.0300 Kg Err:509 Err:509
Lem kayu 0.8000 Kg Err:509 Err:509
Teak Wood 4 mm 120 x 240 0.6875 Lbr Err:509 Err:509
Formika Ukuran Pintu 0.5000 Lbr Err:509 Err:509
Pekerja 0.8500 Oh 53,400.00 45,390.00
Tukang kayu 2.5500 Oh 62,700.00 159,885.00
Kepala tukang 0.2550 Oh 68,900.00 17,569.50
Mandor 0.0430 Oh 75,300.00 3,237.90
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F026 1 M2 pasang pintu teakwood & formika, rangka kayu kamper (divernis)
Kayu Papan Kamper Banjar 0.0196 M3 Err:509 Err:509
Paku 1 cm s/d 3 cm 0.3000 Kg Err:509 Err:509
Lem kayu 0.8000 Kg Err:509 Err:509
Teak Wood 4 mm 120 x 240 0.3438 Lbr Err:509 Err:509
Vernis 0.5000 Lt Err:509 Err:509
Formika Ukuran Pintu 0.5000 Lbr Err:509 Err:509
Pekerja 0.8000 Oh 53,400.00 42,720.00
Tukang kayu 2.5000 Oh 62,700.00 156,750.00
Kepala tukang 0.2500 Oh 68,900.00 17,225.00
Mandor 0.0400 Oh 75,300.00 3,012.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F027 1 M2 Pasang pintu formika double, rangka kayu jati
F029 1 M Pasang konstruksi kuda-kuda konvensional, kayu jati (kayu kelas I, II dan III) bentang 6 m
3
F030 1 M Pasang konstruksi kuda-kuda konvensional, kayu kamper (kayu kelas I, II dan III) bentang 6 m
3
F031 1 M Pasang konstruksi kuda-kuda konvensional, kayu borneo (kayu kelas I, II dan III) bentang 6 m
3
F032 1 M Pasang konstruksi kuda-kuda konvensional, kayu kamper m/kruing (kayu kelas I, II dan III) bentang 6 m
3
F035 1 M2 Pasang rangka atap (kaso + reng) genteng keramik, kayu kamper (kayu kelas II)
Kayu Balok Kamper Banjar 0.0176 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.2500 Kg Err:509 Err:509
Pekerja 0.1000 Oh 53,400.00 5,340.00
Tukang kayu 0.1000 Oh 62,700.00 6,270.00
Kepala tukang 0.0100 Oh 68,900.00 689.00
Mandor 0.0050 Oh 75,300.00 376.50
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F036 1 M Pasang rangka atap (kaso + reng) genteng keramik, kayu borneo (kayu kelas II)
2
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F037 1 M Pasang rangka atap (kaso + reng) genteng monier, kayu jati
2
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F041 1 M Pasang rangka atap (kaso + reng) sirap, kayu borneo (kayu kelas II)
2
F046 1 M2 Pasang rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Kaso-kaso 5/7 (Balok) Kayu (Kelas II atau III) 0.0163 M3 Err:509 Err:509
Paku 8 cm s/d 12 cm 0.2500 Kg Err:509 Err:509
Pekerja 0.2000 Oh 53,400.00 10,680.00
Tukang kayu 0.3000 Oh 62,700.00 18,810.00
Kepala tukang 0.0300 Oh 68,900.00 2,067.00
Mandor 0.0100 Oh 75,300.00 753.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F049 1 M2 Pasang lisplang ukuran (3 x 20) cm, Kayu jati (kayu kelas I atau II)
Kayu Jati Jabar dia. 40 cm keatas 0.0108 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.1000 Kg Err:509 Err:509
Pekerja 0.1000 Oh 53,400.00 5,340.00
Tukang kayu 0.2000 Oh 62,700.00 12,540.00
Kepala tukang 0.0200 Oh 68,900.00 1,378.00
F050 1 M2 Pasang lisplang ukuran (3 x 20) cm, Kayu kamper (kayu kelas I atau II)
Kayu Papan Kamper Banjar 0.0072 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.0500 Kg Err:509 Err:509
Pekerja 0.1000 Oh 53,400.00 5,340.00
Tukang kayu 0.2000 Oh 62,700.00 12,540.00
Kepala tukang 0.0250 Oh 68,900.00 1,722.50
Mandor 0.0050 Oh 75,300.00 376.50
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F051 1 M Pasang lisplang ukuran (3 x 30) cm, Kayu jati (kayu kelas I atau II)
2
F058 1 M2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper (kayu kelas II)
Kayu Balok Kamper Banjar 0.0280 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.1500 Kg Err:509 Err:509
Teak Wood 4 mm 120 x 240 0.8600 Lbr Err:509 Err:509
Lem kayu 0.5600 Kg Err:509 Err:509
Pekerja 0.1500 Oh 53,400.00 8,010.00
Tukang kayu 0.4500 Oh 62,700.00 28,215.00
Kepala tukang 0.0450 Oh 68,900.00 3,100.50
Mandor 0.0080 Oh 75,300.00 602.40
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F059 1 M2 Pasang dinding pemisah plywood rangkap, rangka kayu kamper (kayu kelas II)
Kayu Balok Kamper Banjar 0.0280 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.1500 Kg Err:509 Err:509
Triplek 4 mm 120 x 240 0.8600 Lbr Err:509 Err:509
Lem kayu 0.5600 Kg Err:509 Err:509
Pekerja 0.2000 Oh 53,400.00 10,680.00
Tukang kayu 0.6000 Oh 62,700.00 37,620.00
Kepala tukang 0.0600 Oh 68,900.00 4,134.00
Mandor 0.0100 Oh 75,300.00 753.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F060 1 M2 Pasang dinding lambriziring dari papan jati (kayu kelas I)
Kayu Jati Jabar dia. 40 cm keatas 0.0070 M3 Err:509 Err:509
Paku 4 cm s/d 7 cm 0.1000 Kg Err:509 Err:509
Paku Sekrup 0.1500 Kg Err:509 Err:509
Pekerja 0.6000 Oh 53,400.00 32,040.00
Tukang kayu 1.8000 Oh 62,700.00 112,860.00
Kepala tukang 0.1800 Oh 68,900.00 12,402.00
Mandor 0.0300 Oh 75,300.00 2,259.00
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
F061 1 M Pasang dinding lambriziring dari plywood ukuran (120 x 240) cm
2
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
Jumlah Err:509
Keuntungan Max. Err:509
Jumlah Err:509
Dibulatkan Err:509
Jumlah 6,069.36
Dibulatkan 6,060.00
G020 1 M' Memasang PVC Waterstop lebar 200 mm
Waterstop lebar 200 mm 1.0500 M' -
Pekerja 0.0700 Oh 53,400.00 3,738.00
Tukang batu 0.0350 Oh 62,700.00 2,194.50
Kepala tukang 0.0040 Oh 68,900.00 275.60
Mandor 0.0040 Oh 75,300.00 301.20
Jumlah 6,509.30
Keuntungan Max. 650.93
Jumlah 7,160.23
Dibulatkan 7,160.00
G021 1 M' Memasang PVC Waterstop lebar 230 mm
Waterstop lebar 230 mm 1.0500 M' -
Pekerja 0.0800 Oh 53,400.00 4,272.00
Tukang batu 0.0400 Oh 62,700.00 2,508.00
Kepala Tukang 0.0040 Oh 68,900.00 275.60
Mandor 0.0040 Oh 75,300.00 301.20
Jumlah 7,356.80
Keuntungan Max. 735.68
Jumlah 8,092.48
Dibulatkan 8,090.00
G022 1 M' Memasang PVC Waterstop lebar 250 mm
Waterstop lebar 250 mm 1.0500 M' -
Pekerja 0.0800 Oh 53,400.00 4,272.00
Tukang batu 0.0400 Oh 62,700.00 2,508.00
Kepala Tukang 0.0040 Oh 68,900.00 275.60
Mandor 0.0040 Oh 75,300.00 301.20
Jumlah 7,356.80
Keuntungan Max. 735.68
Jumlah 8,092.48
Dibulatkan 8,090.00
G023 1 M' Memasang PVC Waterstop lebar 300 mm
Waterstop lebar 300 mm 1.0500 M' -
Pekerja 0.0800 Oh 53,400.00 4,272.00
Tukang batu 0.0400 Oh 62,700.00 2,508.00
Kepala Tukang 0.0040 Oh 68,900.00 275.60
Mandor 0.0040 Oh 75,300.00 301.20
Jumlah 7,356.80
Keuntungan Max. 735.68
Jumlah 8,092.48
Dibulatkan 8,090.00
Atap Fiber Glass Tebal 80 x 180 (gelombang) 0.6000 Lbr 70,000.00 42,000.00
Paku 1 cm s/d 3 cm 0.0500 Kg 19,300.00 965.00
Pekerja 0.1400 Oh 53,400.00 7,476.00
Tukang kayu 0.0670 Oh 62,700.00 4,200.90
Kepala tukang 0.0070 Oh 68,900.00 482.30
Mandor 0.0070 Oh 75,300.00 527.10
Jumlah 55,651.30
Keuntungan Max. 5,565.13
Jumlah 61,216.43
Dibulatkan 61,210.00
H008 1 M2 Pasang atap asbes gelombang (2,50x0,92 m) x 5 mm
Jumlah 59,545.31
Dibulatkan 59,540.00
H010 1 M2 Pasang atap asbes gelombang (2,00x0,92 m) x 5 mm
Asbes gelombang 0.6000 Lbr 60,000.00 36,000.00
Paku pancing 60x230 0.1200 Kg 40,000.00 4,800.00
Pekerja 0.1400 Oh 53,400.00 7,476.00
Tukang kayu 0.0700 Oh 62,700.00 4,389.00
Kepala tukang 0.0070 Oh 68,900.00 482.30
Mandor 0.0070 Oh 75,300.00 527.10
Jumlah 53,674.40
Keuntungan Max. 5,367.44
Jumlah 59,041.84
Dibulatkan 59,040.00
H011 1 M Pasang atap asbes gelombang (1,80x0,92 m) x 5 mm
2
Atap Asbes Gel. Besar 5 mm 105 x 180 0.7500 Lbr 60,000.00 45,000.00
Paku pancing 60x230 0.1200 Kg 40,000.00 4,800.00
Pekerja 0.1400 Oh 53,400.00 7,476.00
Tukang kayu 0.0700 Oh 62,700.00 4,389.00
Kepala tukang 0.0070 Oh 68,900.00 482.30
Mandor 0.0070 Oh 75,300.00 527.10
Jumlah 62,674.40
Keuntungan Max. 6,267.44
Jumlah 68,941.84
Dibulatkan 68,940.00
H012 1 M2 Pasang atap asbes gelombang (3,00x1,05 m) x 4 mm
Asbes gelombang 0.3500 Lbr 60,000.00 21,000.00
Paku pancing 0.1200 Kg 40,000.00 4,800.00
Pekerja 0.1400 Oh 53,400.00 7,476.00
Tukang kayu 0.0700 Oh 62,700.00 4,389.00
Kepala tukang 0.0070 Oh 68,900.00 482.30
Mandor 0.0070 Oh 75,300.00 527.10
Jumlah 38,674.40
Keuntungan Max. 3,867.44
Jumlah 42,541.84
Dibulatkan 42,540.00
H013 1 M Pasang atap asbes gelombang (2,70x1,05 m) x 4 mm
2
Jumlah 133,520.00
Keuntungan Max. 13,352.00
Jumlah 146,872.00
Dibulatkan 146,870.00
Jumlah 60,814.50
Keuntungan Max. 6,081.45
Jumlah 66,895.95
Dibulatkan 66,890.00
I009 1 M Langit-langit tripleks ukuran (120x240) cm, tebal 3 mm, 4 mm, dan 6 mm
2
Jumlah 59,759.70
Dibulatkan 59,750.00
I015 1 M2 Langit-langit lat kayu kamper
Kayu Papan Kamper Banjar 0.0240 M3 7,250,000.00 174,000.00
Paku 4 cm s/d 7 cm 0.0100 Kg 14,000.00 140.00
Paku Sekrup 0.0500 Kg 20,000.00 1,000.00
Pekerja 0.2000 Oh 53,400.00 10,680.00
Tukang kayu 0.6000 Oh 62,700.00 37,620.00
Kepala tukang 0.0600 Oh 68,900.00 4,134.00
Mandor 0.0100 Oh 75,300.00 753.00
Jumlah 228,327.00
Keuntungan Max. 22,832.70
Jumlah 251,159.70
Dibulatkan 251,150.00
I016 1 M2 Langit-langit soft board
Soft board 4'x8'x4 mm 0.3500 Lbr -
Paku 4 cm s/d 7 cm 0.0300 Kg 14,000.00 420.00
Pekerja 0.6000 Oh 53,400.00 32,040.00
Tukang kayu 0.1000 Oh 62,700.00 6,270.00
Kepala tukang 0.0100 Oh 68,900.00 689.00
Mandor 0.0030 Oh 75,300.00 225.90
Jumlah 39,644.90
Keuntungan Max. 3,964.49
Jumlah 43,609.39
Dibulatkan 43,600.00
I017 1 M Langit-langit akustik ukuran (60 x 120) cm + rangka allumunium
2
Jumlah 396,269.50
Keuntungan Max. 39,626.95
Jumlah 435,896.45
Dibulatkan 435,890.00
J003 Memasang 1 buah kloset jongkok teraso
Kloset jongkok teraso 1.0000 bh -
Bata Merah Bakar Kelas II 7.0000 bh 500.00 3,500.00
Semen PC Tiga Roda / 50 kg 0.1200 Zak 60,000.00 7,200.00
Pasir pasang 0.0100 m3 122,150.00 1,221.50
Pekerja 1.0000 oh 53,400.00 53,400.00
Tukang batu 1.5000 oh 62,700.00 94,050.00
Kepala tukang 0.3000 oh 68,900.00 20,670.00
Mandor 0.1100 oh 75,300.00 8,283.00
Jumlah 188,324.50
Keuntungan Max. 18,832.45
Jumlah 207,156.95
Dibulatkan 207,150.00
J004 Memasang 1 buah urinoir
Urinoar Lengkap TOTO Warna Standard lengkap 1.0000 bh 900,000.00 900,000.00
Perlengkapan 0.0300 lot 900,000.00 27,000.00
Semen PC Tiga Roda / 50 kg 0.1200 Zak 60,000.00 7,200.00
Pasir pasang 0.0100 m3 122,150.00 1,221.50
Pekerja 1.0000 oh 53,400.00 53,400.00
Tukang Batu 1.0000 oh 62,700.00 62,700.00
Kepala tukang 0.1000 oh 68,900.00 6,890.00
Mandor 0.1000 oh 75,300.00 7,530.00
Jumlah 1,065,941.50
Keuntungan Max. 106,594.15
Jumlah 1,172,535.65
Dibulatkan 1,172,530.00
J005 Memasang 1 buah wastafel
Wastafel Lengkap INA 1.0000 bh 500,000.00 500,000.00
Perlengkapan 0.1200 lot 500,000.00 60,000.00
Semen PC Tiga Roda / 50 kg 0.1200 Zak 60,000.00 7,200.00
Pasir Pasang 0.0100 m3 122,150.00 1,221.50
Pekerja 1.2000 oh 53,400.00 64,080.00
Tukang batu 1.4500 oh 62,700.00 90,915.00
Kepala tukang 0.1500 oh 68,900.00 10,335.00
Mandor 0.1000 oh 75,300.00 7,530.00
Jumlah 741,281.50
Keuntungan Max. 74,128.15
Jumlah 815,409.65
Dibulatkan 815,400.00
J006 Memasang 1 buah bak mandi teraso volume 0,30 m 3
Jumlah #N/A
Keuntungan Max. #N/A
Jumlah #N/A
Dibulatkan #N/A
J018 Memasang 1 buah bak kontrol pasangan batu bata ukuran (60x60) cm tinggi 65 cm
Bata Merah Bakar Kelas II 0.3710 m3 500.00 185.50
Semen PC Tiga Roda / 50 kg 2.2800 Zak 60,000.00 136,800.00
Pasir pasang 0.1840 m3 122,150.00 22,475.60
Batu Pecah Mesin 2/3 0.0330 m3 175,000.00 5,775.00
Besi Beton U-24 Rata - Rata ( Polos ) 4.8500 kg 8,500.00 41,225.00
Pasir Beton 0.1200 m3 #N/A #N/A
Pekerja 2.1600 oh 53,400.00 115,344.00
Tukang batu 0.7200 oh 62,700.00 45,144.00
Kepala tukang 0.0720 oh 68,900.00 4,960.80
Mandor 0.1080 oh 75,300.00 8,132.40
Tukang gali 0.1000 oh 62,700.00 6,270.00
Jumlah #N/A
Keuntungan Max. #N/A
Jumlah #N/A
Dibulatkan #N/A
J019 Memasang 1 m' pipa galvanis diameter ½"
Pipa GIP Medium A Ø 1/2" ( 6 m1 ) 1.2000 m' 125,000.00 150,000.00
Perlengkapan 0.3300 lot 150,000.00 49,500.00
Pekerja 0.0540 oh 53,400.00 2,883.60
Tukang batu 0.0900 oh 62,700.00 5,643.00
Kepala tukang 0.0090 oh 68,900.00 620.10
Mandor 0.0270 oh 75,300.00 2,033.10
Jumlah 210,679.80
Keuntungan Max. 21,067.98
Jumlah 231,747.78
Dibulatkan 231,740.00
J020 Memasang 1 m' pipa galvanis diameter ¾"
Jumlah 404,029.80
Keuntungan Max. 40,402.98
Jumlah 444,432.78
Dibulatkan 444,430.00
J022 Memasang 1 m' pipa galvanis diameter 1 ½"
Pipa PVC MASPION ABU Ø 1/2" (AW) 1.2000 m' 20,850.00 25,020.00
Perlengkapan 0.3500 lot 25,020.00 8,757.00
Pekerja 0.0360 oh 53,400.00 1,922.40
Tukang batu 0.0600 oh 62,700.00 3,762.00
Kepala tukang 0.0060 oh 68,900.00 413.40
Mandor 0.0018 oh 75,300.00 135.54
Jumlah 40,010.34
Keuntungan Max. 4,001.03
Jumlah 44,011.37
Dibulatkan 44,010.00
J026 Memasang 1 m' pipa PVC tipe AW diameter ¾"
Pipa PVC MASPION ABU Ø 3/4" (AW) 1.2000 m' 24,850.00 29,820.00
Perlengkapan 0.3500 lot 29,820.00 10,437.00
Pekerja 0.0360 oh 53,400.00 1,922.40
Tukang batu 0.0600 oh 62,700.00 3,762.00
Kepala tukang 0.0060 oh 68,900.00 413.40
Mandor 0.0018 oh 75,300.00 135.54
Jumlah 46,490.34
Keuntungan Max. 4,649.03
Jumlah 51,139.37
Dibulatkan 51,130.00
J027 Memasang 1 m' pipa PVC tipe AW diameter 1"
Pipa PVC MASPION ABU Ø 1" (AW) 1.2000 m' 30,900.00 37,080.00
Perlengkapan 0.3500 lot 37,080.00 12,978.00
Pekerja 0.0360 oh 53,400.00 1,922.40
Tukang batu 0.0600 oh 62,700.00 3,762.00
Kepala tukang 0.0060 oh 68,900.00 413.40
Mandor 0.0018 oh 75,300.00 135.54
Jumlah 56,291.34
Keuntungan Max. 5,629.13
Jumlah 61,920.47
Dibulatkan 61,920.00
J028 Memasang 1 m' pipa PVC tipe AW diameter 1½"
Pipa PVC MASPION ABU Ø 1 1/2" (AW) 1.2000 m' 55,100.00 66,120.00
Perlengkapan 0.3500 lot 66,120.00 23,142.00
Pekerja 0.0360 oh 53,400.00 1,922.40
Tukang batu 0.0600 oh 62,700.00 3,762.00
Kepala tukang 0.0060 oh 68,900.00 413.40
Mandor 0.0018 oh 75,300.00 135.54
Jumlah 95,495.34
Keuntungan Max. 9,549.53
Jumlah 105,044.87
Dibulatkan 105,040.00
J029 Memasang 1 m' pipa PVC tipe AW diameter 2"
Pipa PVC Rucika ABU Ø 2" (D) 1.2000 m' 68,750.00 82,500.00
Perlengkapan 0.3500 lot 82,500.00 28,875.00
Pekerja 0.0540 oh 53,400.00 2,883.60
Tukang batu 0.0900 oh 62,700.00 5,643.00
Kepala tukang 0.0090 oh 68,900.00 620.10
Mandor 0.0027 oh 75,300.00 203.31
Jumlah 120,725.01
Keuntungan Max. 12,072.50
Jumlah 132,797.51
Dibulatkan 132,790.00
J030 Memasang 1 m' pipa PVC tipe AW diameter 2½"
Pipa PVC MASPION ABU Ø 2 1/2" (AW) 1.2000 m' 105,000.00 126,000.00
Perlengkapan 0.3500 lot 126,000.00 44,100.00
Pekerja 0.0360 oh 53,400.00 1,922.40
Tukang batu 0.0600 oh 62,700.00 3,762.00
Kepala tukang 0.0060 oh 68,900.00 413.40
Pipa PVC MASPION ABU Ø 3" (AW) 1.2000 m' 150,000.00 180,000.00
Perlengkapan 0.3500 lot 180,000.00 63,000.00
Pekerja 0.0810 oh 53,400.00 4,325.40
Tukang batu 0.1350 oh 62,700.00 8,464.50
Kepala tukang 0.0135 oh 68,900.00 930.15
Mandor 0.0041 oh 75,300.00 308.73
Jumlah 257,028.78
Keuntungan Max. 25,702.88
Jumlah 282,731.66
Dibulatkan 282,730.00
J032 Memasang 1 m' pipa PVC tipe AW diameter 4"
Pipa PVC MASPION ABU Ø 4" (AW) 1.2000 m' 218,500.00 262,200.00
Perlengkapan 0.3500 lot 262,200.00 91,770.00
Pekerja 0.0810 oh 53,400.00 4,325.40
Tukang batu 0.1350 oh 62,700.00 8,464.50
Kepala tukang 0.0350 oh 68,900.00 2,411.50
Mandor 0.0041 oh 75,300.00 308.73
Jumlah 369,480.13
Keuntungan Max. 36,948.01
Jumlah 406,428.14
Dibulatkan 406,420.00
J033 Memasang 1 bh bak cuci piring stainles steel
Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) 1.0000 m' 175,000.00 175,000.00
Water drain + asesories 1.0000 set -
Pekerja 0.0300 oh 53,400.00 1,602.00
Tukang batu 0.3000 oh 62,700.00 18,810.00
Kepala tukang 0.0300 oh 68,900.00 2,067.00
Mandor 0.0015 oh 75,300.00 112.95
Jumlah 197,591.95
Keuntungan Max. 19,759.20
Jumlah 217,351.15
Dibulatkan 217,350.00
J034 Memasang 1 bh bak cuci piring teraso
Bak cuci teraso 1.0000 bh -
Water drain + asesories 1.0000 bh -
Semen PC Tiga Roda / 50 kg 0.4000 Zak 60,000.00 24,000.00
Pasir Pasang 0.0500 m3 122,150.00 6,107.50
Pekerja 0.0500 oh 53,400.00 2,670.00
Tukang batu 0.5000 oh 62,700.00 31,350.00
Kepala tukang 0.0500 oh 68,900.00 3,445.00
Mandor 0.0025 oh 75,300.00 188.25
Jumlah 67,760.75
Keuntungan Max. 6,776.08
Jumlah 74,536.83
Dibulatkan 74,530.00
J035 Memasang 1 bh kran diameter ¾"atau ½"
Jumlah 55,772.20
Keuntungan Max. 5,577.22
Jumlah 61,349.42
Dibulatkan 61,340.00
Seng BJLS 30 lebar 90cm (1 rol 50 m' ) 1.0500 M' 35,000.00 36,750.00
Paku 1 cm s/d 3 cm 0.0150 Kg 19,300.00 289.50
Kayu Papan Borneo Super 0.0190 M 3
4,520,000.00 85,880.00
Pekerja 0.2000 Oh 53,400.00 10,680.00
Tukang kayu 0.4000 Oh 62,700.00 25,080.00
Kepala tukang 0.0250 Oh 68,900.00 1,722.50
Mandor 0.0100 Oh 75,300.00 753.00
Jumlah 161,155.00
Keuntungan Max. 16,115.50
Jumlah 177,270.50
Dibulatkan 177,270.00
K028 1 M' Pasang talang 1/2 lingkaran D-15 cm, seng bjls 30 lebar 45 cm
Seng Plat BJLS 30 dia. 40 cm ( 100 m1 ) 1.0500 M' 650,000.00 682,500.00
Paku 1 cm s/d 3 cm 0.0100 Kg 19,300.00 193.00
Plat Besi 2 mm s/d 5 mm 0.5000 Kg 129,000.00 64,500.00
Pekerja 0.1500 Oh 53,400.00 8,010.00
Tukang kayu 0.3000 Oh 62,700.00 18,810.00
Dibulatkan 95,860.00
L004 1 Buah Pasang kunci silinder
Jumlah 12,425.57
Dibulatkan 12,420.00
L009 1 Buah Pasang kait angin
Jumlah 110,295.98
Keuntungan Max. 11,029.60
Jumlah 121,325.57
Dibulatkan 121,320.00
Jumlah 45,546.99
Dibulatkan 45,540.00
M003 1 M2 Pasang lantai ubin PC abu-abu ukuran 20x20 cm
Ubin abu-abu 20x20 cm 26.5000 Bh -
Semen PC Tiga Roda / 50 kg 0.2080 Zak 60,000.00 12,480.00
Pasir pasang 0.0450 M3 122,150.00 5,496.75
Pekerja 0.2700 Oh 53,400.00 14,418.00
Tukang batu 0.1350 Oh 62,700.00 8,464.50
Kepala tukang 0.0140 Oh 68,900.00 964.60
Mandor 0.0140 Oh 75,300.00 1,054.20
Jumlah 42,878.05
Keuntungan Max. 4,287.81
Jumlah 47,165.86
Dibulatkan 47,160.00
M004 1 M2 Pasang lantai ubin warna ukuran 40x40 cm
Ubin warna 40x40 cm 6.6300 Bh -
Semen PC Tiga Roda / 50 kg 0.1960 Zak 60,000.00 11,760.00
Pasir pasang 0.0450 M3 122,150.00 5,496.75
Semen warna 1.3000 Kg 7,500.00 9,750.00
Pekerja 0.2500 Oh 53,400.00 13,350.00
Tukang batu 0.1250 Oh 62,700.00 7,837.50
Kepala tukang 0.0130 Oh 68,900.00 895.70
Mandor 0.0130 Oh 75,300.00 978.90
Jumlah 50,068.85
Keuntungan Max. 5,006.89
Jumlah 55,075.74
Dibulatkan 55,070.00
M005 1 M Pasang lantai ubin warna ukuran 30x30 cm
2
Jumlah 55,028.05
Keuntungan Max. 5,502.81
Jumlah 60,530.86
Dibulatkan 60,530.00
Jumlah 678,552.15
Keuntungan Max. 67,855.22
Jumlah 746,407.37
Dibulatkan 746,400.00
Jumlah 54,661.95
Keuntungan Max. 5,466.20
Jumlah 60,128.15
Dibulatkan 60,120.00
Keramik 33 x 33 cm 1.0500 M2 -
Semen PC Tiga Roda / 50 kg 0.1638 Zak 60,000.00 9,828.00
Pasir pasang 0.0450 M3 122,150.00 5,496.75
Semen warna 1.6200 Kg 7,500.00 12,150.00
Pekerja 0.7000 Oh 53,400.00 37,380.00
Tukang batu 0.3500 Oh 62,700.00 21,945.00
Kepala tukang 0.0350 Oh 68,900.00 2,411.50
Mandor 0.0350 Oh 75,300.00 2,635.50
Jumlah 91,846.75
Keuntungan Max. 9,184.68
Jumlah 101,031.43
Dibulatkan 101,030.00
Jumlah 30,723.40
Keuntungan Max. 3,072.34
Jumlah 33,795.74
Dibulatkan 33,790.00
Sabun 0.0500 Kg -
Pekerja 0.1500 Oh 53,400.00 8,010.00
Mandor 0.0025 Oh 75,300.00 188.25
Jumlah 8,198.25
Keuntungan Max. 819.83
Jumlah 9,018.08
Dibulatkan 9,010.00
N003 1 M Mengerok karat cat lama permukaan baja dengan cara manual
2
Sabun 0.0500 Kg -
Pekerja 0.1500 Oh 53,400.00 8,010.00
Mandor 0.0025 Oh 75,300.00 188.25
Jumlah 8,198.25
Keuntungan Max. 819.83
Jumlah 9,018.08
Dibulatkan 9,010.00
N009 1 M Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
2
N014 1 M2 Pengecatan tembok baru ex. ICI (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
plamir 0.1000 Kg 14,000.00 1,400.00
Cat Dasar ICI 0.3600 Kg 26,080.00 9,388.80
Pekerja 0.0200 Oh 53,400.00 1,068.00
Tukang Cat / Pelitur 0.0630 Oh 62,700.00 3,950.10
Kepala tukang 0.0063 Oh 68,900.00 434.07
Mandor 0.0025 Oh 75,300.00 188.25
Jumlah 16,429.22
Keuntungan Max. 1,642.92
Jumlah 18,072.14
Dibulatkan 18,070.00
N015 1 M Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
2
N022 1 M2 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 1 lapis cat mutakhir dengan tebal 200 um
Cat Besi Sieve 0.3000 Kg 41,800.00 12,540.00
Pekerja 0.0060 Oh 53,400.00 320.40
Tukang Cat / Pelitur 0.0600 Oh 62,700.00 3,762.00
Kepala tukang 0.0120 Oh 68,900.00 826.80
Mandor 0.0060 Oh 75,300.00 451.80
Jumlah 17,901.00
Keuntungan Max. 1,790.10
Jumlah 19,691.10
Dibulatkan 19,690.00
N023 1 M Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 3 lapis cat mutakhir dengan tebal 200 um
2
1 Kolom K1 : 30x50
- Beton K-350 5.40 M3 949,118.75 5,125,241
- Besi beton 1,480.56 Kg 11,337.50 16,785,861
- Bekisting 57.60 M2 50,645.89 2,917,203
2 Kolom K2 : 30x50
- Beton K-350 21.60 M3 949,118.75 20,500,965
- Besi beton 5,922.24 Kg 11,337.50 67,143,444
- Bekisting 230.40 M2 50,645.89 11,668,814
3 Balok G1 dim.30x45, L = 6 m
- Beton K-350 18.55 M3 949,118.75 17,603,495
- Besi beton 2,693.78 Kg 11,337.50 30,540,752
- Bekisting 231.84 M2 50,645.89 11,741,744
4 Balok G2 dim.30x45, L = 4.5 m
- Beton K-350 7.92 M3 949,118.75 7,517,021
- Besi beton 1,165.41 Kg 11,337.50 13,212,880
- Bekisting 99.00 M2 50,645.89 5,013,943
5 Balok G3 dim.30x45, L = 2.3 m
- Beton K-350 2.84 M3 949,118.75 2,690,752
- Besi beton 501.70 Kg 11,337.50 5,687,977
- Bekisting 32.40 M2 50,645.89 1,640,927
6 Balok G4 dim.30x45, L = 6 m
- Beton K-350 11.62 M3 949,118.75 11,024,963
- Besi beton 2,580.26 Kg 11,337.50 29,253,697
- Bekisting 145.20 M2 50,645.89 7,353,784
7 Balok GS1 dim.30x45, L = 4.5 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
8 Balok GS1 dim.30x45, L = 6 m
- Beton K-350 2.30 M3 949,118.75 2,186,770
- Besi beton 268.17 Kg 11,337.50 3,040,394
- Bekisting 28.80 M2 50,645.89 1,458,602
9 Balok CG dim.30x45, L = 1.25 m
- Beton K-350 0.94 M3 949,118.75 888,375
- Besi beton 266.27 Kg 11,337.50 3,018,783
- Bekisting 12.48 M2 50,645.89 632,061
10 Balok BA dim.30x45, L = 6 m
- Beton K-350 0.96 M3 949,118.75 911,154
- Besi beton 145.83 Kg 11,337.50 1,653,400
- Bekisting 13.80 M2 50,645.89 698,913
11 Balok BA dim.30x45, L = 4.5 m
- Beton K-350 0.36 M3 949,118.75 341,683
- Besi beton 63.13 Kg 11,337.50 715,705
- Bekisting 1.73 M2 50,645.89 87,364
12 Plat lantai t = 13 cm
- Beton K-350 89.28 M3 949,118.75 84,736,183
- Besi beton 9,230.19 Kg 11,337.50 104,647,266
- Bekisting 686.76 M2 50,645.89 34,781,574
13 Plat lantai t = 10 cm
- Beton K-350 14.62 M3 949,118.75 13,878,963
- Besi beton 1,196.15 Kg 11,337.50 13,561,335
- Bekisting 146.23 M2 50,645.89 7,405,949
14 Plat lantai Canopy t = 10 cm
- Beton K-350 3.55 M3 949,118.75 3,373,263
- Besi beton 230.90 Kg 11,337.50 2,617,786
- Bekisting 32.40 M2 50,645.89 1,640,699
15 Tangga type-1 (tengah)
- Beton K-350 3.72 M3 949,118.75 3,530,722
- Besi beton 503.57 Kg 11,337.50 5,709,255
- Bekisting 7.20 M2 50,645.89 364,650
16 Tangga type-2 (2 unit)
- Beton K-350 5.14 M3 949,118.75 4,879,230
- Besi beton 594.23 Kg 11,337.50 6,737,077
- Bekisting 9.36 M2 50,645.89 474,046
17 Shear Wall t=20 cm
- Beton K-350 19.79 M3 949,118.75 18,781,162
- Besi beton 3,071.41 Kg 11,337.50 34,822,165
- Bekisting 232.80 M2 50,645.89 11,790,364
1 Kolom K3 : 30x50
- Beton K-350 21.60 M3 949,118.75 20,500,965
- Besi beton 4,535.53 Kg 11,337.50 51,421,599
- Bekisting 230.40 M2 50,645.89 11,668,814
2 Kolom K4 : 30x50
- Beton K-350 5.40 M3 949,118.75 5,125,241
- Besi beton 1,972.71 Kg 11,337.50 22,365,576
- Bekisting 57.60 M2 50,645.89 2,917,203
3 Balok G1 dim.30x45, L = 6 m
- Beton K-350 17.74 M3 949,118.75 16,838,126
- Besi beton 2,576.66 Kg 11,337.50 29,212,893
- Bekisting 221.76 M2 50,645.89 11,231,233
4 Balok G2 dim.30x45, L = 4.5 m
- Beton K-350 5.28 M3 949,118.75 5,011,347
- Besi beton 776.94 Kg 11,337.50 8,808,587
- Bekisting 66.00 M2 50,645.89 3,342,629
5 Balok G3 dim.30x45, L = 2.3 m
- Beton K-350 2.84 M3 949,118.75 2,690,752
- Besi beton 501.70 Kg 11,337.50 5,687,977
- Bekisting 32.40 M2 50,645.89 1,640,927
6 Balok G4 dim.30x45, L = 6 m
- Beton K-350 12.67 M3 949,118.75 12,027,233
- Besi beton 2,814.83 Kg 11,337.50 31,913,125
- Bekisting 158.40 M2 50,645.89 8,022,310
7 Balok GS1 dim.30x45, L = 4.5 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
8 Balok GS1 dim.30x45, L = 6 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
9 Balok CG dim.30x45, L = 1.25 m
- Beton K-350 1.87 M3 949,118.75 1,776,750
- Besi beton 532.53 Kg 11,337.50 6,037,565
- Bekisting 24.96 M2 50,645.89 1,264,121
10 Balok BA dim.30x45, L = 6 m
- Beton K-350 0.96 M3 949,118.75 911,154
- Besi beton 145.83 Kg 11,337.50 1,653,400
- Bekisting 13.80 M2 50,645.89 698,913
11 Balok BA dim.30x45, L = 4.5 m
- Beton K-350 0.36 M3 949,118.75 341,683
- Besi beton 63.13 Kg 11,337.50 715,705
- Bekisting 1.73 M2 50,645.89 87,364
12 Plat lantai t = 13 cm
- Beton K-350 89.28 M3 949,118.75 84,736,183
- Besi beton 9,230.19 Kg 11,337.50 104,647,266
- Bekisting 686.76 M2 50,645.89 34,781,574
13 Plat lantai t = 10 cm
- Beton K-350 14.62 M3 949,118.75 13,878,963
- Besi beton 1,196.15 Kg 11,337.50 13,561,335
- Bekisting 146.23 M2 50,645.89 7,405,949
14 Plat lantai Canopy t = 10 cm
- Beton K-350 3.59 M3 949,118.75 3,408,855
- Besi beton 233.25 Kg 11,337.50 2,644,499
- Bekisting 32.40 M2 50,645.89 1,640,699
15 Tangga type-1 (tengah)
- Beton K-350 3.72 M3 949,118.75 3,530,722
- Besi beton 503.57 Kg 11,337.50 5,709,255
- Bekisting 7.20 M2 50,645.89 364,650
16 Tangga type-2 (2 unit)
- Beton K-350 5.14 M3 949,118.75 4,879,230
- Besi beton 594.23 Kg 11,337.50 6,737,077
- Bekisting 9.36 M2 50,645.89 474,046
17 Shear Wall t=20 cm
- Beton K-350 19.79 M3 949,118.75 18,781,162
- Besi beton 3,071.41 Kg 11,337.50 34,822,165
- Bekisting 232.80 M2 50,645.89 11,790,364
1 Kolom K3 : 30x50
- Beton K-350 21.60 M3 949,118.75 20,500,965
- Besi beton 4,535.53 Kg 11,337.50 51,421,599
- Bekisting 230.40 M2 50,645.89 11,668,814
2 Kolom K4 : 30x50
- Beton K-350 5.40 M3 949,118.75 5,125,241
- Besi beton 1,972.71 Kg 11,337.50 22,365,576
- Bekisting 57.60 M2 50,645.89 2,917,203
3 Balok G1 dim.30x45, L = 6 m
- Beton K-350 17.74 M3 949,118.75 16,838,126
- Besi beton 2,576.66 Kg 11,337.50 29,212,893
- Bekisting 221.76 M2 50,645.89 11,231,233
4 Balok G2 dim.30x45, L = 4.5 m
- Beton K-350 5.28 M3 949,118.75 5,011,347
- Besi beton 776.94 Kg 11,337.50 8,808,587
- Bekisting 66.00 M2 50,645.89 3,342,629
5 Balok G3 dim.30x45, L = 2.3 m
- Beton K-350 2.84 M3 949,118.75 2,690,752
- Besi beton 501.70 Kg 11,337.50 5,687,977
- Bekisting 32.40 M2 50,645.89 1,640,927
6 Balok G4 dim.30x45, L = 6 m
- Beton K-350 12.67 M3 949,118.75 12,027,233
- Besi beton 2,814.83 Kg 11,337.50 31,913,125
- Bekisting 158.40 M2 50,645.89 8,022,310
7 Balok GS1 dim.30x45, L = 4.5 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
8 Balok GS1 dim.30x45, L = 6 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
9 Balok CG dim.30x45, L = 1.25 m
- Beton K-350 1.87 M3 949,118.75 1,776,750
- Besi beton 532.53 Kg 11,337.50 6,037,565
- Bekisting 24.96 M2 50,645.89 1,264,121
10 Balok BA dim.30x45, L = 6 m
- Beton K-350 0.96 M3 949,118.75 911,154
- Besi beton 145.83 Kg 11,337.50 1,653,400
- Bekisting 13.80 M2 50,645.89 698,913
11 Balok BA dim.30x45, L = 4.5 m
- Beton K-350 0.36 M3 949,118.75 341,683
- Besi beton 63.13 Kg 11,337.50 715,705
- Bekisting 1.73 M2 50,645.89 87,364
12 Plat lantai t = 13 cm
- Beton K-350 89.28 M3 949,118.75 84,736,183
- Besi beton 9,230.19 Kg 11,337.50 104,647,266
- Bekisting 686.76 M2 50,645.89 34,781,574
13 Plat lantai t = 10 cm
- Beton K-350 14.62 M3 949,118.75 13,878,963
- Besi beton 1,196.15 Kg 11,337.50 13,561,335
- Bekisting 146.23 M2 50,645.89 7,405,949
14 Plat lantai Canopy t = 10 cm
- Beton K-350 3.59 M3 949,118.75 3,408,855
- Besi beton 233.25 Kg 11,337.50 2,644,499
- Bekisting 32.40 M2 50,645.89 1,640,699
15 Tangga type-1 (tengah)
- Beton K-350 3.72 M3 949,118.75 3,530,722
- Besi beton 503.57 Kg 11,337.50 5,709,255
- Bekisting 7.20 M2 50,645.89 364,650
16 Tangga type-2 (2 unit)
- Beton K-350 5.14 M3 949,118.75 4,879,230
- Besi beton 594.23 Kg 11,337.50 6,737,077
- Bekisting 9.36 M2 50,645.89 474,046
17 Shear Wall t=20 cm
- Beton K-350 19.79 M3 949,118.75 18,781,162
- Besi beton 3,071.41 Kg 11,337.50 34,822,165
- Bekisting 232.80 M2 50,645.89 11,790,364
1 Kolom K3 : 30x50
- Beton K-350 21.60 M3 949,118.75 20,500,965
- Besi beton 4,535.53 Kg 11,337.50 51,421,599
- Bekisting 230.40 M2 50,645.89 11,668,814
2 Kolom K4 : 30x50
- Beton K-350 5.40 M3 949,118.75 5,125,241
- Besi beton 1,972.71 Kg 11,337.50 22,365,576
- Bekisting 57.60 M2 50,645.89 2,917,203
3 Balok G1 dim.30x45, L = 6 m
- Beton K-350 17.74 M3 949,118.75 16,838,126
- Besi beton 2,576.66 Kg 11,337.50 29,212,893
- Bekisting 221.76 M2 50,645.89 11,231,233
4 Balok G2 dim.30x45, L = 4.5 m
- Beton K-350 5.28 M3 949,118.75 5,011,347
- Besi beton 776.94 Kg 11,337.50 8,808,587
- Bekisting 66.00 M2 50,645.89 3,342,629
5 Balok G3 dim.30x45, L = 2.3 m
- Beton K-350 2.84 M3 949,118.75 2,690,752
- Besi beton 501.70 Kg 11,337.50 5,687,977
- Bekisting 32.40 M2 50,645.89 1,640,927
6 Balok G4 dim.30x45, L = 6 m
- Beton K-350 12.67 M3 949,118.75 12,027,233
- Besi beton 2,814.83 Kg 11,337.50 31,913,125
- Bekisting 158.40 M2 50,645.89 8,022,310
7 Balok GS1 dim.30x45, L = 4.5 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
8 Balok GS1 dim.30x45, L = 6 m
- Beton K-350 1.73 M3 949,118.75 1,640,077
- Besi beton 208.79 Kg 11,337.50 2,367,153
- Bekisting 21.60 M2 50,645.89 1,093,951
9 Balok CG dim.30x45, L = 1.25 m
- Beton K-350 1.87 M3 949,118.75 1,776,750
- Besi beton 532.53 Kg 11,337.50 6,037,565
- Bekisting 24.96 M2 50,645.89 1,264,121
10 Balok BA dim.30x45, L = 6 m
- Beton K-350 0.96 M3 949,118.75 911,154
- Besi beton 145.83 Kg 11,337.50 1,653,400
- Bekisting 13.80 M2 50,645.89 698,913
11 Balok BA dim.30x45, L = 4.5 m
- Beton K-350 0.36 M3 949,118.75 341,683
- Besi beton 63.13 Kg 11,337.50 715,705
- Bekisting 1.73 M2 50,645.89 87,364
12 Plat lantai t = 13 cm
- Beton K-350 89.28 M3 949,118.75 84,736,183
- Besi beton 9,230.19 Kg 11,337.50 104,647,266
- Bekisting 686.76 M2 50,645.89 34,781,574
13 Plat lantai t = 10 cm
- Beton K-350 14.62 M3 949,118.75 13,878,963
- Besi beton 1,196.15 Kg 11,337.50 13,561,335
- Bekisting 146.23 M2 50,645.89 7,405,949
14 Plat lantai Canopy t = 10 cm
- Beton K-350 3.59 M3 949,118.75 3,408,855
- Besi beton 233.25 Kg 11,337.50 2,644,499
- Bekisting 32.40 M2 50,645.89 1,640,699
15 Tangga type-1 (tengah)
- Beton K-350 3.72 M3 949,118.75 3,530,722
- Besi beton 503.57 Kg 11,337.50 5,709,255
- Bekisting 7.20 M2 50,645.89 364,650
16 Tangga type-2 (2 unit)
- Beton K-350 5.14 M3 949,118.75 4,879,230
- Besi beton 594.23 Kg 11,337.50 6,737,077
- Bekisting 9.36 M2 50,645.89 474,046
17 Shear Wall t=20 cm
- Beton K-350 19.79 M3 949,118.75 18,781,162
- Besi beton 3,071.41 Kg 11,337.50 34,822,165
- Bekisting 232.80 M2 50,645.89 11,790,364
1 Kolom K4 : 30x50
- Beton K-350 1.08 M3 949,118.75 1,025,048
- Besi beton 487.71 Kg 11,337.50 5,529,455
- Bekisting 43.20 M2 50,645.89 2,187,903
2 Kolom K5 : 30x30
- Beton K-350 3.67 M3 949,118.75 3,485,164
- Besi beton 1,416.89 Kg 11,337.50 16,063,999
- Bekisting 47.00 M2 50,645.89 2,380,438
3 Balok RB1 dim.25x45, L = 4.5 m
- Beton K-350 25.20 M3 949,118.75 23,917,793
- Besi beton 4,083.37 Kg 11,337.50 46,295,190
- Bekisting 386.40 M2 50,645.89 19,569,573
4 Balok RB2 dim.25x45, L = 6 m
- Beton K-350 10.13 M3 949,118.75 9,609,827
- Besi beton 1,701.43 Kg 11,337.50 19,289,942
- Bekisting 155.25 M2 50,645.89 7,862,775
5 Balok RB3 dim.25x45, L = 2.3 m
- Beton K-350 2.59 M3 949,118.75 2,455,845
- Besi beton 478.10 Kg 11,337.50 5,420,436
- Bekisting 39.68 M2 50,645.89 2,009,376
6 Balok BA dim.25x45, L = 6 m
- Beton K-350 7.68 M3 949,118.75 7,289,232
- Besi beton 1,166.68 Kg 11,337.50 13,227,197
- Bekisting 110.40 M2 50,645.89 5,591,307
7 Balok BA dim.25x45, L = 4.5 m
- Beton K-350 0.72 M3 949,118.75 683,366
- Besi beton 126.25 Kg 11,337.50 1,431,410
- Bekisting 10.35 M2 50,645.89 524,185
8 Balok BA dim.25x45, L = 1.5 m
- Beton K-350 0.96 M3 949,118.75 911,154
- Besi beton 180.87 Kg 11,337.50 2,050,570
- Bekisting 13.80 M2 50,645.89 698,913
9 Plat lantai t = 13 cm
- Beton K-350 4.13 M3 949,118.75 3,920,810
- Besi beton 384.34 Kg 11,337.50 4,357,487
- Bekisting 27.54 M2 50,645.89 1,394,788
10 Plat lantai Canopy t = 10 cm
- Beton K-350 14.62 M3 949,118.75 13,878,963
- Besi beton 1,196.15 Kg 11,337.50 13,561,335
- Bekisting 146.23 M2 50,645.89 7,405,949
1 Tiang pancang selesai terpasang uk. 25 x 25 cm, pjg. 22 M : 22 titik 150.00 M' 206,700.00 31,005,000
2 Pile Cap PC - 1 = 10 unit
- Beton K-350 3.38 M3 949,118.75 3,203,276
- Besi beton 1,174.22 Kg 11,337.50 13,312,683
- Bekisting 18.00 M2 50,645.89 911,626
3 Tie Beam / Sloof TB 25X45 L = 2.05 m, unit : 8 bh
- Beton K-350 1.31 M3 949,118.75 1,238,600
- Besi beton 324.28 Kg 11,337.50 3,676,484
- Bekisting 46.10 M2 50,645.89 2,334,776
4 Tie Beam / Sloof TB 25X45 L = 1 m, unit : 4 bh
- Beton K-350 0.18 M3 949,118.75 170,841
- Besi beton 72.02 Kg 11,337.50 816,564
- Bekisting 22.00 M2 50,645.89 1,114,210
5 Galian tanah
Galian tanah STP 22.77 M3 31,215.00 710,766
Galian Tanah Pile Cap PC-1 4.22 M3 31,215.00 131,688
Galian Tanah Tie Beam L = 2.05 m 1.46 M3 31,215.00 45,476
Galian Tanah Tie Beam L = 1 m 0.32 M3 31,215.00 9,833
6 Urug tanah ruang pompa 25.00 M3 241,480.00 6,037,000
7 Urug pasir dibawah Pile Cap t=10 cm
Urugan pasir ruang pompa STP 1.44 M3 241,480.00 347,731
Urugan Pasir Pile Cap PC-1 0.56 M3 241,480.00 135,833
Urugan Pasir Tie Beam L = 2.05 m 0.21 M3 241,480.00 50,122
Urugan Pasir Tie Beam L = 1 m 0.09 M3 241,480.00 21,733
8 Lantai kerja t=5 cm
Lantai Kerja ruang pompa STP 0.72 M3 756,920.00 544,982
Lantai Kerja Pile Cap PC-1 0.28 M3 756,920.00 212,884
Lantai Kerja Tie Beam L = 2.05 m 0.23 M3 756,920.00 174,565
Lantai Kerja Tie Beam L = 1 m 0.10 M3 756,920.00 75,692
5 Dudukan Septic Tank Biotech t = 20 cm ( bawah )
- Beton K-350 3.600 M3 949,118.75 3,416,828
- Besi 525.464 kg 11,337.50 5,957,446
- Bekisting Pelat 1.440 m2 50,645.89 72,930
6 Penutup Septic Tank Biotech t = 12 cm ( atas )
- Beton K-350 1.728 M3 949,118.75 1,640,077
- Besi 92.550 kg 11,337.50 1,049,290
- Bekisting Pelat 14.400 m2 50,645.89 729,301
Urugan tanah kembali 26.46 M3 241,480.00 6,389,697
Pasangan bata Bak Kontrol Septic Tank Biotech 1.000 Unit 500,000.00 500,000
Pipa PVC + galian (terpasang) 2.000 M 350,000.00 700,000
Rumah Blower uk 120 x 120 cm (lengkap terpasang) 1.000 Unit 750,000.00 750,000
HARGA BAHAN / MATERIAL TERTINGGI
TAHUN ANGGARAN 2013
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
2
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
100 Kanstien Beton uk. 390 x 90 x 200 cm ex. Cisangkan bh 24,956
101 Kanstien Beton uk. 600 x 150 x 300 cm ex. Cisangkan bh 75,625
102 Kanstien Beton uk. 800 x 150 x 210 cm ex. Cisangkan bh 81,675
103 Kanstien uk. 28 x 60 Nanjung bh 28,875
104 Kanstien uk. 40 x 60 Nanjung bh 37,813
105 Kanstien uk. 9 x 40 Nanjung bh 13,750
106 Kanstien Jalan Beton uk. 18 x 40 x 60 bh 35,000
107 Kanstien Jalan Beton uk. 18 x 28 x 40 bh 31,250
108 Kanstien Taman bh 23,125
109 Kaanstien Paving Blok 8 x 15 x 40 bh 43,750
110 Kaanstien Paving Blok 8 x 15 x 20 bh 37,500
111 Kanstin Jalan Ukuran Besar ( Bina Marga ) 1 bh = 60 cm ( 15 x 40 x 60 ) bh 47,500
112 Semen PC Tiga Roda / 50 kg zak 82,500
113 Semen Gresik zak 81,250
114 Semen Holcin zak 81,250
115 Semen Putih zak 112,500
116 Semen Warna bk 13,125
117 Tanah Pilihan m³ 81,250
118 Tanah Urug m³ 75,000
119 Tanah Merah m³ 87,500
120 Tanah Lembang m³ 83,750
121 Readymix Beton K 500, tanpa pompa ( selang ) m³ 1,268,750
122 Readymix Beton K 450, tanpa pompa ( selang ) m³ 1,212,500
123 Readymix Beton K 425, tanpa pompa ( selang ) m³ 1,156,250
124 Readymix Beton K 400, tanpa pompa ( selang ) m³ 1,097,500
125 Readymix Beton K 375, tanpa pompa ( selang) m³ 1,087,500
126 Readymix Beton K 350, tanpa pompa ( selang) m³ 1,035,000
127 Readymix Beton K 325, tanpa pompa ( selang ) m³ 1,043,750
128 Readymix Beton K 300, tanpa pompa ( selang ) m³ 985,000
129 Readymix Beton K 275, tanpa pompa ( selang ) m³ 962,500
130 Readymix Beton K 250, tanpa pompa ( selang ) m³ 922,500
131 Readymix Beton K 225, tanpa pompa ( selang ) m³ 918,750
132 Readymix Beton K 175, tanpa pompa ( selang ) m³ 860,000
133 Readymix Beton K 150, tanpa pompa ( selang ) m³ 843,750
134 Readymix Beton K 125, tanpa pompa ( selang ) m³ 812,500
135 Readymix Beton K 100, tanpa pompa ( selang ) m³ 787,500
136 Readymix Beton B0/K50, tanpa pompa ( selang ) m³ 750,000
137 Material Agregat Kelas A ( Halus ) LPA m³ 177,500
138 Material Agregat Kelas B ( Kasar ) LPA m³ 168,750
139 Base Course Kelas A (LPB) m3 110,000
140 Base Course Kelas B (LPB) m3 103,125
141 Base Course Kelas C (LPB) m3 123,750
142 Tanah Liat m³ 45,000
143 Bentonit zak 150,000
144 Screen/ Melubangi Pipa PVC n btg 136,250
168 Barangkal m³ 87,500
-
B. BAHAN FINISHING : -
LABURAN, PENGISI, DAN ALATNYA -
169 Plamir Tembok Sanlex kg 18,750
170 Plamir Tembok RJ kg 11,875
171 Plamir Tembok BSA kg 31,250
3
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
172 Plamir Tembok Dulux Interior kg 31,250
173 Plamir Tembok Dulux Exterior kg 33,750
174 Cat Tembok ICI Eksterior Mowilex kg 75,000
175 Cat Tembok ICI Interior Mowilex kg 50,000
176 Cat Tembok Vinilex kg 23,750
177 Cat Dasar ICI kg 87,500
178 Cat Tembok Sanlex kg 25,000
179 Cat Tembok DULUX untuk interior kg 93,750
180 Cat Tembok DULUX untuk eksterior kg 118,750
181 Cat Tembok Catylac untuk interior kg 24,750
182 Cat Tembok Catylac untuk eksterior kg 26,250
183 Cat Tahan Asam kg 116,875
184 Pelapis Alkali ICI ( Cat Dasar Beton Eksterior ) lt 97,500
185 Cat Marka / Spotlight kg 59,375
186 Cat Marka kg 68,750
187 Sealant tube 12,500
188 Sealant Dow Corning btl 43,750
189 Water Profing Emulsion kg 56,250
190 Water Profing Membrance 1x1.5 m2 116,875
191 Kapur Pasang/ kapur tembok m³ 15,625
192 Kapur Sirih kg 6,250
193 Rool Cat Tembok bh 31,250
194 Kape Tembok 4' bh 15,625
195 Kape Kayu 2' bh 50,000
196 Soligneum 1 blek 5 lt 56,250
197 Plincote kg 50,000
198 Pengawetan Kayu m³ 34,375
199 Pengopenan Kayu m³ 529,375
200 Kwas 3" bh 12,500
201 Oker kg 37,500
202 Oyan bks 18,750
203 Oten ( Pewarna Plitur ) bks 15,000
204 Spirtus lt 12,500
205 Bahan Plitur Kripik ( Sirlak India ) kg 437,500
206 Plitur kg 56,250
207 Plitur Vog kg 56,250
208 Plitur Pinoguard kg 58,750
209 Dempul Lilin kg 12,500
210 Dempul Plitur Kayu kg 32,500
211 Dempul Halus / Imfra ( Wood Filler ) kg 37,500
212 Terpentin lt 18,750
213 Tiner A lt 18,750
214 Tiner B lt 22,500
215 Kumpon kg 43,750
216 Melamik kg 66,250
217 Dempul Plastik Classy kg 65,000
218 Dempul Plastik Sanpolac kg 43,750
219 Dempul Duco kg 50,000
220 Ampelas lbr 3,750
221 Dempul Kayu Cap Kucing kg 31,875
222 Meni Besi kg 38,750
223 Meni Kayu kg 31,250
4
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
224 Sincromat kg 56,250
225 Cat Kayu Sieve kg 56,250
226 Cat Besi Sieve kg 57,500
227 Cat Besi Duco Danaglos/ICI kg 68,750
228 Cat Bron kg 118,750
233 Cat Besi (Green Vespa 199 (NIPPE)) kg 68,750
234 Cat Kayu Avian kg 56,250
235 Cat Besi Avian kg 56,250
236 Flinkur/flinkote Seiv kg 40,625
237 Thinner lt 25,000
238 Thinner CH lt 28,125
239 Dempul Gipsum (Compound) zak 112,500
240 Dempul Gipsum (Compound) UB.88 zak 93,750
241 Lem Kayu kg 18,750
242 Vernis batu ltr 81,250
243 Plastik Membran m2 65,000
-
C. BAHAN KAYU BERIKUT BAHAN JADINYA -
243 Bambu Ø 5 s.d 7 bt 18,750
244 Bambu Ø 7 s.d 10 bt 12,500
245 Bambu Gombong bt 37,500
246 Kayu Kamper Singkil / Kapur ( K. Samarinda Klas II ) m³ 11,875,000
247 Kayu Balok Borneo Super m³ 5,625,000
248 Kayu Papan Borneo Super m³ 6,875,000
249 Kayu Balok Kamper Medan (kruing) m³ 8,125,000
250 Kayu Papan Kamper Medan (Kruing) m³ 8,750,000
251 Kayu Balok Kamper Banjar m³ 8,125,000
252 Kayu Papan Kamper Banjar m³ 9,375,000
253 Kayu Balok Kamper Samarinda m³ 11,250,000
254 Kayu Papan Kamper Samarinda m³ 11,875,000
255 Kayu Balok Rasamala m³ 3,500,000
256 Kayu Jati Jatim Tua dia. 40 cm m³ 43,106,250
257 Kayu Jati Jateng Tua dia. 80 cm keatas m³ 39,022,500
258 Kayu Jati Jabar Tua dia. 80 cm keatas m³ 23,443,750
259 Kayu Jati Jabar dia. 40 cm keatas m³ 12,100,000
260 Kayu Hutan Kelas I ( Segeng, Mahoni, Laban ) m³ 3,437,500
261 Kayu Albasia m³ 1,187,500
262 Dolken 5 s/d 7 bt 21,875
263 Dolken 7 s/d 10 bt 37,500
264 List profil kamper 1 cm m1 21,875
265 List profil kamper 2 cm m1 18,750
266 List profil kamper 4 cm m1 21,250
267 List profil kamper 5 cm m1 25,000
268 List profil kamper 10 cm m1 37,500
269 Pegangan Tangga profil Jati m1 169,125
270 Pegangan Tangga profil Kamper m1 56,250
271 Kayu Reng 2/3 Borneo Super bt 17,500
272 Kayu Reng 2/3 Kamper Banjar bt 15,625
273 Kayu Reng 3/4 Kamper Banjar bt 37,500
274 Kayu Kaso 5/7 Borneo Super m³ 5,802,500
275 Kayu 5/10 Borneo Super m³ 7,142,500
-
5
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
D. BAHAN PENUTUP RANGKA PLAFOND -
275 Bahan plafond hardpleks 3 mm m² 43,750
276 Bahan plafond Asbes Semen 5 mm m² 31,250
277 Gypsum 120 x 240 t = 9 mm ex DN lbr 73,750
278 Gypsum 120 x 240 t = 9 mm ex Luar lbr 75,000
279 GRC lbr 71,250
280 Acustik Amstrong 60 x 120 lbr 122,500
281 Plafon PVC ( SILAHKAN CARI HARGA lbr -
-
E. BAHAN KAYU LAPIS -
281 Triplek 3 mm 120 x 240 lbr 60,000
282 Triplek 4 mm 120 x 240 lbr 72,500
283 Triplek 4 mm Ukuran Pintu lbr 57,500
284 Triplek 6 mm 120 x 240 lbr 106,250
285 Triplek 9 mm 120 x 240 lbr 156,250
286 Jabar Wood 4 mm lbr 122,500
287 Bilik Bambu ( tanpa kulit ) lbr 31,250
288 Bilik Bambu ( dengan kulit ) lbr 43,750
289 Bilik Bambu Hitam Variasi lbr 187,500
290 Wall Paper ( kls menengah ) m² 112,500
291 Multiplek 9 mm 120 x 240 lbr 156,250
292 Multiplek 12 mm 120 x 240 lbr 181,250
293 Multiplek 18 mm 120 x 240 lbr 300,000
294 Ply Wood 18 mm 120 x 240 lbr 287,500
295 Teak Wood 3 mm 120 x 240 lbr 125,000
296 Teak Wood 4 mm 120 x 240 lbr 131,250
297 Teak Wood 3 mm 120 x 240 Ukuran Pintu lbr 93,750
298 Teak Wood ukuran Pintu 4 mm lbr 93,750
299 Tacon ( tahan bakar ) m² 81,250
300 Supercon m' 37,500
301 Melamin 4 mm 120 x 240 lbr 108,750
302 Melamin 3mm 120 x 240 doff lbr 118,750
303 Melamin 3mm 120 x 240 glossy lbr 106,250
304 Melamin TOK 3 mm m² 93,750
305 Formika 120 x 240 lbr 137,500
306 Formika motif kayu jati lbr 123,750
307 Formika Polos Besar lbr 123,750
308 Formika Polos Kecil lbr 103,125
309 Formika Ukuran Pintu lbr 100,000
310 Tacon lbr 143,750
-
F. BAHAN LANTAI DAN PELAPIS DINDING -
310 Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos m² 58,750
311 Keramik 10 x 20 KW I DN Corak / Warna / Anti Slip m² 56,250
312 Keramik 20 x 20 (KM) KW I DN Corak / Warna / Anti Slip m² 60,000
313 Keramik 20 x 20 (KM) KWI DN Putih Polos m² 58,750
314 Keramik 20 x 25 Dinding KM KWI DN Polos m² 62,500
315 Keramik 20 x 25 Dinding KM KWI DN Corak m² 65,000
316 Keramik 30 x 30 KW I DN putih polos m² 52,500
317 Keramik 30 x 30 KW I DN Warna/Corak ( ANTI SLIP ) m² 66,250
318 Plint Keramik 10 x 30 KW1 DN Putih/Polos m² 43,750
319 Vinyl Lantai Standar m² 31,250
6
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
322 Stepnosing keramik 10x30 KW1 DN bh 24,063
323 Stepnosing keramik 8x40 KW1 DN bh 20,625
324 Stairnosing keramik 10/20 bh 17,188
325 Stairnosing fiber m' 11,250
326 Taraso Kerang 30 x 30 m² 56,250
327 Plin Taraso 10 x 30 bh 18,750
328 Granit Alam LN Ukuran Besar m² 2,125,000
329 Granit Alam LN Ukuran Kecil m² 1,750,000
330 Granit Alam DN Ukuran Besar m² 1,437,500
331 Granit Alam DN Ukuran Kecil m² 1,312,500
332 Granito Tile Essenza Ukuran 40 x 40 Polis m² 203,500
333 Granito Tile Essenza Ukuran 40 x 40 Unpolis m² 185,625
334 Marmer Alam Lampung Ukuran Besar ( 60 x 90 cm ) m² 525,000
335 Marmer Alam Lampung Ukuran Kecil ( 60 x 60 cm ) m² 425,000
336 Marmer Alam Citatah Ukuran Besar ( 60 x 90 cm) m² 375,000
337 Marmer Alam Citatah Ukuran Kecil ( 60 x 60 cm ) m² 268,750
338 Marmer Sintetis m² 137,500
339 Granito Tile Essenza 60 x 60 Polis m² 144,375
340 Granito Tile Essenza 60 x 60 Unpolis m² 312,500
341 Granito Tile 60 x 60 ex. Roman Polished m² 187,500
342 Bata Karawang bh 8,125
343 Rooster 12 x 11 x 24 bh 8,125
344 Campuran untuk Kedap Air (AM) bh 35,000
345 Batu Candi 20 x 20 m² 212,500
346 Batu Basalto flame 20 x 20 m² 387,500
347 Batu Basalto flame 20 x 30 m² 350,000
348 Batu Basalto fancy 20 x 30 m² 262,500
349 Batu Sikat Hitam m² 393,750
350 Batu Sikat Natural ex. Cisangkan m² 237,500
351 Batu Sikat Hitam/MB/HJ ex. Cisangkan m² 312,500
352 Batu Pelindung Kabel TM/TR bh 362,500
353 Batu sikat merah/marun m² 362,500
354 Batu sikat putih m² 262,500
355 Batu koral/ceper hitam m² 262,500
356 Batu Andesit 15x30,20x20 m² 262,500
357 Batu Andesit 20x30,30x30 m² 262,500
358 Batu Andesit 30x60 m² 262,500
359 Batu Tempel Tekstur Garis m² 150,000
-
G. BAHAN SALURAN AIR KOTOR/BERSIH -
359 Grafel U 20 cm' bh 34,375
360 Grafel U 30 cm' bh 43,750
361 Grafel U 40 cm bh 56,250
362 Grafel U 50 cm' bh 68,750
363 Grafel U 60 cm' bh 87,500
364 Grafel U 80 cm' bh 112,500
365 Grafel U 20 cm' ex. Cisangkan bh 49,500
366 Grafel U 30 cm' ex. Cisangkan bh 70,125
367 Grafel U 40 cm' ex. Cisangkan bh 99,000
368 Grafel U 20 cm' ex. NANJUNG bh 23,438
369 Grafel U 30 cm' ex. NANJUNG bh 32,813
370 Grafel U 40 cm' ex. NANJUNG bh 39,063
7
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
371 Grafel U 50 cm' ex. NANJUNG bh 53,125
372 Grafel U 60 cm' ex. NANJUNG bh 84,375
373 Buis Beton Ø 20 cm ( 1 m' ) bh 75,000
374 Buis Beton Ø 30 cm ( 1 m' ) bh 87,500
375 Buis Beton Ø 40 cm ( 1 m' ) bh 87,500
376 Buis Beton Ø 50 cm ( 1 m' ) bh 99,000
377 Buis Beton Ø 60 cm ( 1 m' ) bh 123,750
378 Buis Beton Ø 80 cm ( 1 m' ) bh 276,719
379 Buis Beton Ø 100 cm ( 1 m' ) bh 233,750
380 Buis Beton Ø 50 cm ( 0.5m' ) bh 46,406
381 Buis Beton Ø 80 cm ( 0.5 m' ) bh 171,875
382 Buis Beton Ø 100 cm ( 0.5m' ) bh 116,875
383 Buis Beton Ø 20 cm ( 1 m' ) ex. Cisangkan bh 82,500
384 Buis Beton Ø 30 cm ( 1 m' ) ex. Cisangkan bh 116,875
385 Buis Beton Ø 40 cm ( 1 m' ) ex. Cisangkan bh 165,000
386 Buis Beton Ø 50 cm ( 1 m' ) ex. Cisangkan bh 275,000
387 Buis Beton Ø 60 cm ( 1 m' ) ex. Cisangkan bh 412,500
388 Buis Beton Ø 80 cm ( 1 m' ) ex. Cisangkan bh 577,500
389 Buis Beton Ø 100 cm ( 1 m' ) ex. Cisangkan bh 660,000
390 Buis Beton Ø 50 cm ( 0.5m' ) ex. Cisangkan bh 165,000
391 Buis Beton Ø 80 cm ( 0.5 m' ) ex. Cisangkan bh 346,500
392 Buis Beton Ø 100 cm ( 0.5m' ) ex. Cisangkan bh 396,000
393 Buis Beton Ø 20 cm ( 1 m' ) ex. NANJUNG bh 46,875
394 Buis Beton Ø 30 cm ( 1 m' ) ex. NANJUNG bh 65,625
395 Buis Beton Ø 40 cm ( 1 m' ) ex. NANJUNG bh 78,125
396 Buis Beton Ø 50 cm ( 1 m' ) ex. NANJUNG bh 106,250
397 Buis Beton Ø 60 cm ( 1 m' ) ex. NANJUNG bh 168,750
398 Buis Beton Ø 80 cm ( 1 m' ) ex. NANJUNG bh -
399 Buis Beton Ø 100 cm ( 1 m' ) ex. NANJUNG bh -
400 Buis Beton Ø 50 cm ( 0.5m' ) ex. NANJUNG bh -
401 Buis Beton Ø 80 cm ( 0.5 m' ) ex. NANJUNG bh 168,750
402 Buis Beton Ø 100 cm ( 0.5m' ) ex. NANJUNG bh -
403 Injuk kg 6,250
404 Buis Beton Ø 80 cm ( 1/2 m' ) bh 225,000
405 Buis Beton Ø 1 m ( 1/2 m' ) bh 258,750
406 U Ditch 600 x 600 x 1200 bh 996,125
407 U Ditch 600 x 700 x 1200 bh 1,140,875
408 U Ditch 600 x 800 x 1200 bh 1,247,375
409 U Ditch 800 x 800 x 1200 bh 1,475,625
410 U Ditch 800 x 900 x 1200 bh 1,583,125
411 U Ditch 800 x 1000 x 1200 bh 1,695,250
412 U Ditch 1000 x 1000 x 1200 bh 2,104,125
413 U Ditch 1200 x 1200 x 1200 bh 3,212,125
414 U Ditch 1400 x 1400 x 1200 bh 4,993,750
415 Box Culvert 800 x 800 x 1200 bh 3,239,500
416 Box Culvert 1000 x 1000 x 1200 bh 4,433,500
417 Box Culvert 1200 x 1200 x 1200 bh 6,053,375
418 Box Culvert 1500 x 1500 x 1200 bh 10,606,625
419 Box Culvert 2000 x 2000 x 1200 bh 15,969,125
420 Pipa RJ Dia. 300 R - Class2 bh 543,125
421 Pipa RJ Dia. 400 R - Class2 bh 751,000
422 Pipa RJ Dia. 500 R - Class2 bh 1,363,750
8
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
423 Pipa RJ Dia. 600 R - Class2 bh 1,732,375
424 Pipa RJ Dia. 700 R - Class2 bh 2,173,250
425 Pipa RJ Dia. 800 R - Class2 bh 2,939,125
426 Pipa RJ Dia. 900 R - Class2 bh 3,436,375
427 Pipa RJ Dia. 1000 R - Class2 bh 4,957,750
428 Pipa RJ Dia. 1100 R - Class2 bh 5,893,000
429 Pipa RJ Dia. 1200 R - Class2 bh 6,384,250
430 Pipa RJ Dia. 1500 R - Class2 bh 9,996,375
431 Pipa RJ Dia. 1650 R - Class2 bh 11,716,625
432 Pipa RJ Dia. 1800 R - Class2 bh 14,537,125
433 Pipa RJ Dia. 2000 R - Class2 bh 18,274,625
434 Penutup U Ditch bh -
-
H. BAHAN LOGAM DAN BAHAN JADINYA -
434 Besi Beton U-24 Rata - Rata ( Polos ) kg 11,250
435 Besi Beton U-32 Rata - Rata ( Ulir ) kg 11,875
436 Besi Beton U-39 ( Ulir ) kg 12,500
437 Pagar BRC Lengkap Tiang ( Tanpa Pondasi ) T 90 cm X240 m² 193,750
438 Pagar BRC Lengkap Tiang ( Tanpa Pondasi ) T 120 cmX240 m² 243,750
439 Bondek m² 165,000
440 IWF Ex DN SII kg 17,188
441 IWF Ex Jepang kg 18,750
442 Besi Profil DN SII kg 13,750
443 Besi Profil Ex LN kg 13,750
444 Besi Profil UNP 10 btg 468,750
445 Besi Profil UNP 6,5 btg 287,500
446 Besi Profil UNP 5 btg 218,750
447 Besi C Lip Chanel kg 13,750
448 Besi C ex. DN. SII kg 13,125
449 Ongkos Galfanis Besi kg 15,625
450 Kawat Beton kg 20,781
451 Kawat Duri Kecil kg 75,938
452 Kawat Duri Besar kg 92,500
453 Kawat Pengikat kg 25,000
454 Kawat Bronjong 4 mm kg 36,094
455 Kawat Tembaga kg 151,250
456 Ram Nyamuk Hijau m² 22,500
457 Ram Kawat 1 x 1 cm m² 15,625
458 Ram Ayam m² 18,750
459 Kawat Kasa 1 x 1 cm ( Putih ) m² 22,500
460 Kawat Harmonika 4 cm m² 28,750
461 Kawat Harmonika 2 cm m² 27,500
462 Kawat Las Listrik kg 28,750
463 Wiremesh M10 2 x 5 m lbr 1,100,000
464 Wiremesh M8 2 x 5 m lbr 837,500
465 Wiremesh M7 2 x 5 m lbr 587,500
466 Wiremesh M6 2 x 5 m lbr 468,750
467 Wiremesh M5 2 x 5 m lbr 300,000
468 Timah kg 45,000
469 Timah Hitam kg 55,000
470 Ram Nyamuk Alumunium m² 26,250
471 Plat Strip Ø 2 x 30 mm ( 6 m1 ) bt 45,000
9
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
472 Plat Strip Ø 3 x 30 mm ( 6 m1 ) bt 57,500
473 Plat Alumunium 0.2 mm m² 25,000
474 Plat Alumunium 0.3 mm m² 35,000
475 Plat Alumunium 0.4 mm m² 45,000
476 Plat Alumunium 0.5 mm m² 56,250
477 Plat Alumunium 0.6 mm m² 80,000
478 Plat Alumunium 1.0 mm m² 120,000
479 Kusen Alumunium Natural 1.3 mm t=1,3 mm ( 4 " ) m1 88,750
480 Kusen Alumunium Warna 1.3 mm t=1,3 mm ( 4 " ) m1 122,500
481 Daun Jendela Alumunium Natural ( Tanpa Kaca dan Accessories ) m² 75,000
482 Daun Jendela Alumunium Warna ( Tanpa Kaca dan Accessories ) m² 92,500
483 Daun Pintu Alumunium Natural ( Tanpa Kaca dan Accessories ) m² 92,500
484 Daun Pintu Alumunium Warna ( Tanpa Kaca dan Accessories ) m² 111,250
485 Handle Alumunium ( Tarikan Pintu Alumunium ) bh 101,250
486 Kait Angin Alumunium ps 72,500
487 Alumunium ½ x ½ m1 18,125
488 Alumunium 5/8 x 5/8 m1 21,875
489 Alumunium 3/4 x 3/4 m1 26,250
490 Alumunium 1 x 1 m1 43,750
491 Alumunium 1¼ x 1¼ m1 46,250
492 Alumunium 1½ x 1½ m1 57,500
493 Alumunium 2 x 2 m1 75,000
494 Karet Asisoris Kusen / Pintu Alumunium m1 5,000
495 List Alumunium / Profil m1 32,500
496 Seng Plat BJLS 30 dia. 40 cm ( 100 m1 ) rol 875,000
497 Seng Plat BJLS 30 dia. 60 cm ( 100 m1 ) rol 1,500,000
498 Seng Plat BJLS 30 dia. 90 cm ( 100 m1 ) rol 1,562,500
499 Seng Plat BJLS 30 dia. 90 cm Gelombang lbr 81,250
500 Plat Besi Tipis 1 mm lbr 81,250
501 Plat Besi Tipis 0.5 mm lbr 343,750
502 Plat Besi 2 mm s/d 5 mm lbr 177,375
503 Plat Besi 6 mm s/d 10 mm lbr 1,993,750
504 Plat Besi 10 mm Ke atas kg 13,750
508 Hollow 4 x 4 TBL btg 106,250
509 Hollow 4 x 4 BSA btg 103,125
511 Hollow 2 x 4 TBL btg 125,000
512 Hollow 2 x 4 BSA btg 93,750
515 Besi Siku 30 x 30 x 3 bt 87,500
516 Besi Siku 40 x 40 x 4 bt 125,000
517 Besi Siku 50 x50 x 2.5 bt 156,250
518 Besi Siku 50 x50 x 5 kg 225,000
521 Stainless Steel 10 x 10 bt 137,500
522 Stainless Steel 15 x15 bt 171,875
523 Stainless Steel 20 x20 bt 206,250
524 Stainless Steel 25 x25 bt 240,625
525 Stainless Steel 30 x 30 bt 275,000
526 Stainless Steel 40 x 40 bt 378,125
527 Stainless Steel 50 x 50 bt 536,250
528 Stainless Steel 60 x 60 bt 750,000
529 Stainless Steel 25 x 50 bt 425,000
530 Stainless Steel 20 x 40 bt 275,000
531 Stainless Steel 15 x 30 bt 247,500
10
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
532 Stainless Steel 10 x 20 bt 171,875
533 Stainless Steel Bulat ½" bt 89,375
534 Stainless Steel Bulat 5/8" bt 89,375
535 Stainless Steel Bulat 3/4" bt 85,250
536 Stainless Steel Bulat 1" bt 116,875
537 Stainless Steel Bulat 1¼" bt 151,250
538 Stainless Steel Bulat 1½" bt 213,125
539 Stainless Steel Bulat 2" bt 240,625
543 Pagar BRC T= 90 cm m1 218,750
545 Pagar BRC T= 120 cm m1 243,750
546 Roda Besi Bawah BCM kwalitas baik bh 40,625
547 Roda Besi Bawah BCM kwalitas sedang bh 50,000
548 Lem Kuning (aibond) kg 43,750
549 Lem Fox kg 43,750
550 Sling 8mm kg 21,875
-
I. BAHAN KACA -
550 Kaca Polos 2 mm ( ASAHI ) m² 81,250
551 Kaca Polos 3 mm ( ASAHI ) m² 106,250
552 Kaca Polos 5 mm ( ASAHI ) m² 118,750
553 Kaca Rayband 5 mm ( ASAHI ) m² 118,750
554 Kaca Rayband 8 mm ( ASAHI ) m² 106,250
555 Kaca Rayband 12 mm ( ASAHI ) m² 412,500
556 Kaca Patri Lokal Terpasang ( ASAHI ) m² 1,000,000
557 Kaca Patri EX Luar negeri terpasang m² 2,500,000
558 Kaca 8 mm Gravver m² 1,406,250
559 Glass Block DN 20 x 20 ( Kedawung ) bh 23,750
560 Glass Block DN 20 x 20 (Mulia) bh 21,875
561 Glass Block DN 20 x 20 Ex LN bh 150,000
562 Cermin 3mm m² 175,000
563 Cermin 5 mm m² 175,000
-
J. BAHAN PAKU DAN MUR BAUT -
563 Paku 1 cm s/d 3 cm kg 21,875
564 Paku 4 cm s/d 7 cm kg 18,750
565 Paku 8 cm s/d 12 cm kg 18,750
566 Paku Beton 2 cm s/d 5 cm bh 625
567 Paku Beton 8 cm bh 1,000
568 Paku Kait Lengkap bh 2,063
569 Paku Cacing kg 81,250
570 Paku Sekrup kg 23,125
571 Sekrup fisher lsn 12,500
572 Fisher lsn 10,000
573 Besi Beugel kuda - kuda kg 18,750
574 Duk Angker bh 14,375
575 Angker Mur Baut dia.19 / panjang 60 cm bh 53,750
576 Mur Baut dia. 10 (3 cm) bh 2,063
577 Mur Baut HTB dia. 19 s/d 16 (6 cm) bh 11,250
578 Mur Baut besi 3/4 x 30 mm bh 2,063
579 Mur Baut besi 1/2x 30 mm bh 1,500
580 Mur Baut Biasa dia.19 s/d 16 (5 cm) bh 6,000
581 Piser dia. 12 s/d 20 cm bh 6,875
11
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
582 Paku 4, 5, 7 dan 10 Kg 15,625
583 Ramset ttk 3,125
-
K. BAHAN PERPIPAAN 1.² -
583 Besi Pipa untuk Hydrant BSP Ø 1" bt 193,750
584 Besi Pipa untuk Hydrant BSP Ø 1,25" bt 218,750
585 Besi Pipa untuk Hydrant BSP Ø 1,5" bt 250,000
586 Besi Pipa untuk Hydrant BSP Ø 2" bt 356,250
587 Besi Pipa untuk Hydrant BSP Ø 2,5" bt 512,500
588 Besi Pipa untuk Hydrant BSP Ø 3" bt 687,500
589 Besi Pipa untuk Hydrant BSP Ø 4" bt 937,500
590 Besi Pipa untuk Hydrant BSP Ø 6" bt 1,500,000
591 Besi Pipa Hitam Ø 1" t=2 mm bt 137,500
592 Besi Pipa Hitam Ø 1 1/2" t=2 mm bt 200,000
593 Besi Pipa Hitam Ø 2" t=2 mm bt 275,000
594 Besi Pipa Hitam Ø 3" t=2 mm bt 446,875
595 Besi Pipa Hitam Ø 4" t=2 mm bt 481,250
596 Besi Pipa Hitam Ø 6" t=2 mm bt 1,787,500
597 Pipa GIP Medium A Ø 1/2" ( 6 m1 ) bt 171,875
598 Pipa GIP Medium A Ø 3/4" ( 6 m1 ) bt 220,000
599 Pipa GIP Medium A Ø 1" ( 6 m1 ) bt 318,750
600 Pipa GIP Medium A Ø 1 1/4" ( 6 m1 ) bt 350,000
601 Pipa GIP Medium A Ø 1 1/2" ( 6 m1 ) bt 406,250
602 Pipa GIP Medium A Ø 1 3/4"( 6 m1 ) bt 450,000
603 Pipa GIP Medium A Ø 2" ( 6 m1 ) bt 562,500
604 Pipa GIP Medium A Ø 2 1/2" ( 6 m1 ) bt 783,750
605 Pipa GIP Medium A Ø 3" ( 6 m1 ) bt 1,031,250
606 Pipa GIP Medium A Ø 4" ( 6 m1 ) bt 1,500,000
607 Pipa GIP Medium B Ø 2" ( 6 m1 ) bt 312,500
608 Pipa GIP Medium B Ø 2 1/2" ( 6 m1 ) bt 406,250
609 Pipa GIP Medium B Ø 3" ( 6 m1 ) bt 493,750
610 Pipa GIP Medium B Ø 4" ( 6 m1 ) bt 643,750
611 Macam2 Sambungan GIP Ø 1/2" bh 2,500
612 Macam2 Sambungan GIP Ø 3/4" bh 3,125
613 Macam2 Sambungan GIP Ø 1" bh 3,750
614 Macam2 Sambungan GIP Ø 1 1/4" bh 4,375
615 Macam2 Sambungan GIP Ø 1 1/2" bh 5,000
616 Macam2 Sambungan GIP Ø 1 3/4" bh 5,625
617 Macam2 Sambungan GIP Ø 2" bh 2,500
618 Macam2 Sambungan GIP Ø 2 1/2" bh 3,750
619 Macam2 Sambungan GIP Ø 3" bh 5,000
620 Macam2 Sambungan GIP Ø 4" bh 7,500
621 Pipa PVC RUCIKA type AW Ø 1/2" bt 31,250
622 Pipa PVC RUCIKA type AW Ø 3/4" bt 34,375
623 Pipa PVC RUCIKA type AW Ø 1" bt 40,625
624 Pipa PVC RUCIKA type AW Ø 1 1/4" bt 46,875
625 Pipa PVC RUCIKA type AW Ø 1 1/2" bt 56,250
626 Pipa PVC RUCIKA type AW Ø 2" bt 68,750
627 Pipa PVC RUCIKA type AW Ø 2 1/2" bt 93,750
628 Pipa PVC RUCIKA type AW Ø 3" bt 156,250
629 Pipa PVC RUCIKA type AW Ø 4" bt 250,000
630 Pipa PVC RUCIKA type AW Ø 6" bt 937,500
12
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
631 Pipa PVC RUCIKA type AW Ø 8" bt 1,325,000
632 Pipa PVC MASPION ABU Ø 1/2" (AW) bt 28,125
633 Pipa PVC MASPION ABU Ø 3/4" (AW) bt 33,750
634 Pipa PVC MASPION ABU Ø 1" (AW) bt 42,500
635 Pipa PVC MASPION ABU Ø 1 1/4" (AW) bt 59,375
636 Pipa PVC MASPION ABU Ø 1 1/2" (AW) bt 78,125
637 Pipa PVC MASPION ABU Ø 2" (AW) bt 116,250
638 Pipa PVC MASPION ABU Ø 2 1/2" (AW) bt 150,000
639 Pipa PVC MASPION ABU Ø 3" (AW) bt 212,500
640 Pipa PVC MASPION ABU Ø 4" (AW) bt 312,500
641 Pipa PVC MASPION ABU Ø 6" (AW) bt 650,000
642 Pipa PVC MASPION ABU Ø 1 1/4" (D) bt 43,750
643 Pipa PVC MASPION ABU Ø 2" (D) bt 106,250
644 Pipa PVC MASPION ABU Ø 4" (D) bt 168,750
645 Pipa PVC MASPION ABU Ø 6" (D) bt 337,500
646 Pipa PVC MASPION PUTIH Ø 2" (D) bt 81,250
647 Pipa PVC MASPION PUTIH Ø 1 1/4" (D) bt 50,000
648 Pipa PVC MASPION PUTIH Ø 4" (D) bt 125,000
649 Pipa PVC MASPION PUTIH Ø 6" (D) bt 262,500
650 Macam2 Sambungan Pipa PVC Ø 1/2" bh 2,500
651 Macam2 Sambungan Pipa PVC Ø 3/4" bh 3,750
652 Macam2 Sambungan Pipa PVC Ø 1" bh 4,375
653 Macam2 Sambungan Pipa PVC Ø 1 1/4" bh 5,000
654 Macam2 Sambungan Pipa PVC Ø 1 1/2" bh 6,250
655 Macam2 Sambungan Pipa PVC Ø 1 3/4" bh 4,375
656 Macam2 Sambungan Pipa PVC Ø 2" bh 8,750
657 Macam2 Samb. Pipa PVC Ø 2 1/2" bh 10,625
658 Macam2 Samb. Pipa PVC Ø 3" bh 11,250
659 Macam2 Samb. Pipa PVC Ø 4" bh 13,750
660 Sambungan Pipa PVC Jenis AW 4 " TY bh 48,125
661 Lem Paralon tb 8,750
662 Seal tape gl 2,500
663 Pipa PVC 4" berlobang jenis AW m1 67,031
664 Pipa PVC Pralon Ø 1/2" AW Putih bt 15,000
665 Pipa PVC Pralon Ø 3/4" AW Putih bt 20,000
666 Pipa PVC Pralon Ø 1" AW Putih bt 28,750
667 Pipa PVC Pralon Ø 2" AW Putih bt 67,500
668 Pipa PVC Pralon Ø 2.5" AW Putih bt 93,750
669 Pipa PVC Pralon Ø 3" AW Putih bt 131,250
670 Pipa PVC Pralon Ø 4" AW Putih bt 218,750
671 Keni Ø 1/2" Rucika bh 3,125
672 Keni Ø 3/4" Rucika bh 3,750
673 Keni Ø 1" Rucika bh 4,375
674 Keni Ø 1 1/2" Rucika bh 6,250
675 Keni Ø 2" Rucika bh 11,875
676 Keni Ø 2 1/2" Rucika bh 14,375
677 Keni Ø 3" Rucika bh 27,500
678 Keni Ø 4" Rucika bh 27,500
-
L. BAHAN SANITAIR -
678 Stop Kran 3/4 " KITZ bh 112,500
679 Stop Kran 3/4 " ONDA bh 75,000
13
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
680 Stop Kran 1 " KITZ bh 171,875
681 Stop Kran 1 " ONDA bh 100,000
682 Stop Kran 1 1/2 " KITZ bh 306,250
683 Stop Kran 1 1/2 " ONDA bh 240,625
684 Stop Kran 2 " KITZ bh 437,500
685 Stop Kran 2 " ONDA bh 309,375
686 Stop Kran 2 1/2" KITZ bh 1,031,250
687 Stop Kran 2 1/2" ONDA bh 618,750
688 Stop Kran 3 " KITZ bh 1,718,750
689 Stop Kran 3 " ONDA bh 825,000
690 Check Valve 1/2 " PVC bh 9,375
691 Check Valve 1/2 " onda bh 58,438
692 Check Valve 2" bh 440,000
693 Double Neple 1/2 " PVC bh 5,000
694 Double Neple 1/2 " besi bh 68,750
695 Water Mur 1/2 " BESI bh 18,750
696 Water Mur 1/2 " PVC bh 12,500
697 Gate Valve 1/2 " KITZ bh 61,875
698 Gate Valve 1/2 " ONDA bh 61,875
699 Gate Valve 2" ONDA bh 378,125
700 Knee BESI Ø 2" bh 22,500
701 Knee BESI Ø 2 1/2" bh 55,000
702 Knee BESI Ø 3" bh 75,625
703 Knee BESI Ø 4" bh 130,625
704 Saringan Air Lt KM Stainless Steel bh 87,500
705 Pressure Gauge bh 103,125
706 Soket langsung bh 20,625
707 Apooer Bath Tube bh 9,375
708 Kran stain less Lokal Kait bh 36,678
709 Shower Dengan Tiang bh 468,750
710 Shower Tanpa Tiang bh 62,500
711 Shower Dengan Tiang bh 18,750
712 Shower Tanpa Tiang bh 378,125
713 Kran Tembok San Ei dia. 1/2 " bh 31,250
714 Kran Tembok TOTO dia. 1/2 " bh 206,250
715 Kran Bebek San Ei 1/2 " bh 288,750
716 Kran Bebek TOTO 1/2 " bh 231,250
717 Kran Panas Dingin San Ei Standard bh 206,250
718 Bath Cape Washteren unit 1,512,500
719 Tempat Sabun Porslin bh 31,250
720 Tempat Sabun Keramik bh 43,750
721 Wastafel Lengkap TOTO unit 2,197,250
722 Wastafel Lengkap INA unit 500,000
723 Closet Jongkok KERAMIK warna INA unit 150,000
724 Closet Jongkok Standard Putih KERAMIK INA unit 137,500
725 Closet Duduk Warna Standard TOTO C 421 Lengkap unit 2,145,000
726 Wastafel Bulat Warna Standard Lengkap unit 412,500
727 Closet Duduk Warna Standard lengkap INA bh 1,312,500
728 Urinoar Lengkap TOTO Warna Standard lengkap unit 1,237,500
729 Penyekat Poslin Urinoar TOTO lbr 412,500
730 Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) bh 218,750
731 Kithchen Zink Stainless Non Standard Franke ( 1 Lobang ) bh 240,625
14
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
732 Kitchen Zink Stainless Non Standard Franke ( 2 Lobang ) bh 687,500
733 Closet Jongkok Lengkap Sistem Jet TOTO unit 1,312,500
734 Kran San Ei (Poilet) bh 343,750
735 Kran Wastapel TOTO bh 343,750
736 Kran Closset bh 59,375
737 Fleksible 30 Cm bh 46,875
738 Fleksible 30 Cm San Ei (Keras) bh 21,875
739 Fleksible 30 Cm San Ei bh 178,750
740 Wastafel TOTO unit 350,625
741 Radar Otomatis unit 206,250
742 Radar unit 62,500
-
M. BAHAN PENUTUP ATAP -
742 Atap Plastik Gelombang 80 x 180 lbr 56,500
743 Atap Fiber Glass Tipis 80 x 180 (gelombang) lbr 54,688
744 Atap Fiber Glass Tebal 80 x 180 (gelombang) lbr 84,375
745 Atap Alumunium Natural USR 26 ( JAINDO ) m² 150,000
746 Atap Alumunium Warna USR 26 ( JAINDO ) m² 175,000
747 Atap Asbes Gel. Kecil 4 mm 80 x 180 lbr 40,625
748 Atap Asbes Gel. Besar 5 mm 105 x 180 lbr 62,500
749 Atap Tegola Kubota, lengkap m² 525,000
750 Atap Tegola Kwalitas Sedang m² 281,250
751 Atap Tenda m² 837,500
752 Alumunium foile m² 8,750
753 Atap Genteng Plentong pres Bakar KW 1 bh 2,250
754 Atap Genteng Plentong pres Molen Oven KW1 bh 1,813
755 Atap Genteng Flam pres Molen Oven Jatiwangi bh 2,063
756 Atap Baja Ringan ex. Pryda m² 1,875
757 Bubung Genteng pres Bulat Ex Jatiwangi bh 7,500
758 Genteng Bubungan Ex Jatiwangi Segi Tiga bh 4,375
759 Genteng Bubungan Beton bh 13,000
760 Genteng Metal ( Rainbow Roof ) m² 225,000
761 Genteng Type. Victoria Slate/Multiline/Vine/Classic Warna Standard ex. Cisangkan bh 13,613
762 Genteng Type. Victoria Slate/Multiline/Vine/Classic Warna Khusus ex. Cisangkan bh 13,613
763 Genteng Gelombang Excellent/ Majestic/Oriental/New Royal warna standard ex. Cisangkan bh 11,798
764 Genteng Gelombang Excellent/ Majestic/Oriental/New Royal warna khusus ex. Cisangkan bh 11,798
765 Genteng Metal Hana m² 168,750
766 Nok Atas Metal ( Rainbow Roof ) m1 152,500
767 Nok Atas Metal Hana m1 81,250
768 Nok Atas Warna Standard Ex. Cisangkan bh 18,125
769 Nok Atas Warna Khusus Ex. Cisangkan bh 20,625
770 Nok Bawah Warna Standard Ex. Cisangkan bh 18,125
771 Nok Bawah Warna Khusus Ex. Cisangkan bh 20,625
772 Nok Samping Warna Standar Ex. Cisangkan bh 20,000
773 Nok Samping Warna Khusus Ex. Cisangkan bh 20,625
774 Nok Siku Warna Standard Ex. Cisangkan bh 31,250
775 Nok Siku Warna Khusus Ex. Cisangkan bh 31,250
776 Nok Ujung Warna Standard Ex. Cisangkan bh 2,750
777 Nok Ujung Warna Khusus Ex. Cisangkan bh 31,250
778 Nok Samping Ujung Warna Standard Ex. Cisangkan bh 27,500
779 Nok Samping Ujung Warna Khusus Ex. Cisangkan bh 31,250
780 Nok Pinggir Metal ( Rainbow Roof ) m1 107,500
15
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
781 Nok Pinggir Hana m1 87,500
782 Genteng Kodok Natural Pleret bh 3,125
783 Genteng Kodok Glazur Pleret bh 3,750
784 Genteng Plentong Natural Pleret bh 1,875
785 Genteng Plentong Glazur Pleret bh 3,125
786 Genteng Turbo Natural Pleret bh 2,500
787 Genteng Turbo Glazur Pleret bh 3,375
788 Genteng Kanmuri Natural Pleret bh 10,625
789 Genteng Kanmuri Glazur Pleret bh 17,500
790 Genteng Beton Plat Natural Pleret bh 6,250
791 Genteng Beton Plat Glazur Pleret bh 8,750
792 Genteng Centerion Natural Pleret bh 6,875
793 Genteng Centerion Glazur Pleret bh 7,500
794 Genteng Morando Natural Pleret bh 2,625
795 Genteng Morando Glazur Pleret bh 4,375
796 Metal Roof Bahan m2 118,750
797 Metal Roof Terpasang m2 143,750
798 Ceramik Deck CB 10 bh 6,875
799 Ceramik Deck CB 12 bh 8,125
800 Ceramik Deck CB Terpasang m2 562,500
801 Baja Ringan Terpasang Zingalume m2 162,500
802 Nok Beton Natural bh 12,500
803 Nok Beton Warna bh 18,750
804 Nok Bulat Natural bh 6,250
805 Nok Bulat Warna bh 12,500
806 Nok Segi 3 Natural bh 5,000
807 Nok Segi 3 Warna bh 10,000
808 Starter Warna Standard Ex. Cisangkan bh 2,750
809 Starter Warna Khusus Ex. Cisangkan bh 31,250
810 Starter Siku Warna Standard Ex. Cisangkan bh 2,750
811 Starter Siku Warna Khusus Ex. Cisangkan bh 31,250
812 Apex Warna Standard Ex. Cisangkan bh 27,500
813 Apex Warna Khusus Ex. Cisangkan bh 31,250
814 Tepi Kiri/Kanan, Oriental Warna Standard Ex. Cisangkan bh 27,500
815 Tepi Kiri/Kanan, Oriental Warna Khusus Ex. Cisangkan bh 31,250
816 Genteng Kiri/Kanan, Oriental/Majectic Warna Standard Ex. Cisangkan bh 27,500
817 Genteng Kiri/Kanan, Oriental/Majectic Warna Khusus Ex. Cisangkan bh 31,250
818 Genteng Sudut Kiri/Kanan, Oriental Warna Standard Ex. Cisangkan bh 27,500
819 Genteng Sudut Kiri/Kanan, Oriental Warna Khusus Ex. Cisangkan bh 31,250
820 Genteng Bawah O/RR Warna Standard Ex. Cisangkan bh 46,250
821 Genteng Bawah O/RR Warna Khusus Ex. Cisangkan bh 50,000
822 Apex O Warna Standard Ex. Cisangkan bh 62,500
823 Apex O Warna Khusus Ex. Cisangkan bh 67,500
824 Genteng Kaca Ex. Cisangkan bh 93,750
825 Wall Flashing Hana m1 80,000
826 Atap Genteng Beton Warna 14,5 / m2 m² 108,750
827 Genteng Beton Natural m² 105,000
828 Genteng Cisangkan warna Standard m² 125,000
829 Sirap Kelas I ( 80 / m2 ) bh 1,750
830 Genteng Keramik Natural Intan 14,5 / m2 m² 106,250
831 Genteng Keramik Glasur Standard 14,5 / m2 m² 90,000
832 Genteng Keramik Glasur Special 14,5 / m2 m² 125,000
16
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
833 Genteng Keramik Glasur Premium 14,5 / m2 m² 137,500
834 Genteng Murando Natural 1m2 = 20 bh bh 4,375
835 Genteng Murando Glasur 1m2 = 20 bh bh 5,625
836 Bubung Murando Natural bh 7,500
837 Bubung Murando Glasur bh 10,625
838 Bubungan Genteng Keramik bh 9,375
839 Bubung Cisangkan bh 19,965
840 Seng Talang m² 62,563
841 Seng Gelombang BJLS 28 lbr 56,250
842 Seng BJLS 30 lebar 60cm (1 rol 50 m' ) m 37,500
843 Seng BJLS 30 lebar 90cm (1 rol 50 m' ) m 47,500
844 Poly Carbonat Carboron 2.1 x 11 roll 2,337,500
845 Canopy Star Polly (Solartuff) 80x240 m² 247,500
846 Policarbonate (Twinlite) 2.1 x 11 m² 2,812,500
847 Genteng Plentong Jatiwangi bh 2,500
-
N. BAHAN MEKANIKAL -
847 Jockey Pump kap. 80 gln / menit 100 m1 ( 18,6 kW ) unit 65,000,000
848 Electrical Pump kap. 750 gln / menit 120 m1 ( 90 kW ) unit 218,750,000
849 Diesel Pump kap. 750 gln / menit 120 m1 ( 105 kW ) unit 45,000,000
850 Presure Tank kap. 500 liter lengkap unit 31,250,000
851 Hydran Box dalam Gedung (lengkap) unit 6,000,000
852 Fire House 1.5 x 30 m + nose unit 4,625,000
853 Exhouse Fan H 360 W 60 x 60 cm unit 1,625,000
854 Exhouse Fan H 380 W CFM 55 x 55 cm unit 1,100,000
855 Exhouse Fan H 100 W 40 x 40 cm unit 812,500
856 AC Split 3 PK Setara TOSHIBA unit 14,375,000
857 AC Split 2 PK Setara TOSHIBA unit 9,125,000
858 AC Split 1 PK Setara TOSHIBA unit 4,875,000
859 AC Split 4 PK Setara TOSHIBA unit -
-
O. BAHAN ELEKTRIKAL 1.5 -
859 Kabel NYA 1x 1.5 Prima (1 rol = 50 m') ROLL 437,500
860 Kabel NYA 1x 2.5 Prima (1 rol = 50 m') ROLL 437,500
861 Kabel NYM 2 x 1.5 Prima (1 rol = 50 m') m1 293,750
862 Kabel NYM 3 x 1.5 Prima (1 rol = 50 m') m1 381,250
863 Kabel NYM 2 x 2.5 Prima (1 rol = 50 m') m1 468,750
864 Kabel NYM 3 x 2.5 Prima (1 rol = 50 m') m1 606,250
865 Kabel NYM 4 x 2.5 Prima (1 rol = 50 m') m1 25,000
866 Kabel NYM 2 x 4 Prima (1 rol = 50 m') m1 15,125
867 Kabel NYM 3 x 4 Prima (1 rol = 50 m') m1 18,750
868 Kabel NYM 4 x 4 Prima (1 rol = 50 m') m1 23,750
869 Kabel NYM 2 x 6 Supreme (1 rol = 50 m') m1 21,250
870 Kabel NYM 3 x 6 Supreme (1 rol = 50 m') m1 23,375
871 Kabel NYM 4 x 6 Supreme (1 rol = 50 m') m1 30,000
872 Kabel NYM 2 x 10 Supreme (1 rol = 50 m') m1 17,500
873 Kabel NYM 3 x 10 Supreme (1 rol = 50 m') m1 40,000
874 Kabel NYM 4 x 10 Supreme (1 rol = 50 m') m 1
43,750
875 Kabel NYM 4 x 16 Supreme (1 rol = 50 m') m1 61,250
876 Kabel NYY 2 x 4 Supreme (1 rol = 50 m') m1 13,750
877 Kabel NYY 3 x 4 Supreme (1 rol = 50 m') m 1
23,750
878 Kabel NYY 4 x 4 Supreme (1 rol = 50 m') m1 28,750
17
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
879 Kabel NYY 2 x 6 Supreme (1 rol = 50 m') m1 17,500
880 Kabel NYY 3 x 6 Supreme (1 rol = 50 m') m1 30,000
881 Kabel NYY 4 x 6 Supreme (1 rol = 50 m') m1 32,500
882 Kabel NYY 2 x 10 Supreme (1 rol = 50 m') m1 32,500
883 Kabel NYY 3 x 10 Supreme (1 rol = 50 m') m1 55,000
884 Kabel NYY 4 x 10 Supreme (1 rol = 50 m') m1 66,250
885 Kabel NYY 4 x 16 Supreme (1 rol = 50 m') m1 98,750
886 Kabel NYY 1.5 m 1
63,750
887 Kabel NYY 2.5 m1 92,500
888 Kabel TM NA2XEYBY 20 KV/XLPE 3 X 240 sqmm m1 92,500
889 Kabel TR NYFGBY 220 V/380 V 4 x 240 sqmm m1 92,500
890 Kabel Pompa Submersible m1 32,500
891 Kabel Elektroda m1 10,625
892 Elektroda m1 32,500
893 Kabel Power m1 21,250
894 Kabel Single core D1 x 25 sqmm m1 3,125
895 Elektroda Automatic m1 55,000
896 NSFB FUJI EA - 100 A bh 937,500
897 NSFB FUJI EA - 150 A bh 2,375,000
898 Rumah Panel 30 x 60 cm (kosong) unt 162,500
899 Rumah Panel 40 x 60 cm (kosong) unt 312,500
900 Skring Kas 2 grop Biasa unt 6,875
901 Skring Kas 3 grop Biasa unt 31,250
902 Skring Kas 5 grop Biasa unt 43,750
903 MCB 1 PHASA bh 18,750
904 MCB 3 PHASA bh 20,625
905 Tahanan 50 A Merk Fuji bh 550,000
906 Saklar Broko Tunggal Standard ( 1 Phase ) bh 16,250
907 Saklar Broko Seri Standard ( 1 Phase ) bh 18,750
908 Stop Kontak Broko Standard ( 1 Phase ) bh 16,250
909 Stop Kontak Broko 3 Phase ( Out Bow ) bh 21,875
910 Stop Kontak Broko 3 Phase ( In Bow ) bh 21,875
911 Stop Kontak Handle 3 Phase bh 66,250
912 Stop Kontak Nasional bh 17,500
913 Saklar Tunggal Nasional bh 15,000
914 Saklar Double Nasional bh 23,750
915 Saklar 3 Nasional bh 22,500
916 Kabel Tray Telephone bh 50,000
917 Instalasi Titik Lampu / Stop Kontak ( Upah dan Alat ) ttk 200,000
918 Lampu PLC bh 12,500
919 Lampu pijar 25 Watt s/d 100 Watt bh 153,750
920 Lampu Neon TL Philip 18 W bh 43,750
921 Lampu Neon TL Philip 20 W bh 43,750
922 Lampu Neon TL Philip 36 W bh 50,000
923 Lampu Neon TL Philip 40 W bh 50,000
924 Lampu Neon TL Philip 80 W bh 50,000
925 Trapo TL 20 W ( Philip ) bh 37,500
926 Trapo TL 40 W ( Philip ) bh 42,500
927 Trapo TL 20 W ( Sinar ) bh 42,500
928 Trapo TL 40 W ( Sinar ) bh 56,250
929 Trafo 3 ph, 20 KV/400 V, 630 KVA bh 25,000
930 Stater Neon Philip bh 6,250
18
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
931 Stater Neon Biasa bh 2,250
932 Rumah TL In Bow / Out Bow 2 x 20 W ( Kosongan ) bh 48,750
933 Down Light + SL 25 W bh 125,000
934 Lampu SL Philip 25 W bh 21,875
935 Lampu Sirkel TL 20 W Lengkap bh 72,500
936 Lampu Mercuri 80 W bh 300,000
937 Lampu Taman + Tiang + Lampu 1 Buah bh 218,750
938 Lampu Baret 30 cm + Neon bh 167,500
939 Lampu Neon Arcrilik 2 x 40 W lengkap bh 387,500
940 Jarum Penangkal Petir 16 bh 37,500
941 Kawat BC ( Tembaga ) kg 118,750
942 Pentanahan Penangkal Petir ttk 406,250
943 Pentanahan Panel ttk 537,500
944 Panel Kontrol 225,000
945 Lampu Halogen 500 W bh 2,062,500
946 Lampu Armatur Halogen 500 W bh 1,687,500
947 HPI PLUS 250 W bh 5,875,000
948 Lampu NAVE 70 W bh 3,125,000
949 Lampu PAR 38 EC Plood 30 - 120 W bh 925,000
950 Lampu BTA 18 W bh 1,437,500
-
P. BAHAN ALAT PENGANTUNG DAN KUNCI -
951 Kunci Silinder ALFA untuk Pintu Alumunium bh 43,750
952 Tarikan Pintu Alumunium bh 112,500
953 Tarikan Laci bh 12,500
954 Kunci 2 Slaag ROYAL bh 43,750
955 Rel Henderson Lengkap m' 231,250
956 Rel Maraton I Pintu m' 137,500
957 Kunci 2 Slaag Silinder SEIS Asli type 210 s/d type 226 bh 437,500
958 Kunci 2 Slaag Ancor Asli bh 187,500
959 Kunci 2 Slaag ISO bh 218,750
960 Kunci KM Bulat Kualitas Biasa bh 33,750
961 Kunci KM Bulat ALFA bh 68,750
962 Kunci 2 Slaag Silinder Utama Standard bh 125,000
963 Kunci Gembok Besar bh 12,500
964 Kunci 2 Slaag Kuda Terbang bh 110,000
965 Espangolet ps 58,750
966 Grendel 15 cm bh 25,000
967 Grendel 5 cm bh 7,500
968 Hak Angin Kait Jendela Biasa ps 18,750
969 Hak Angin Jendela Antik ps 15,000
970 Hak Angin Sendok Stainless / Kuningan bh 25,000
971 Nako Lengkap Tralis 1 Daun dn 92,500
972 Sloot Pintu berikut Rantai bh 43,750
973 Sloot Jendela Tunggal bh 8,125
974 Engsel Pintu Unilon Standard besar 5" ps 15,000
975 Engsel Jendela Unilon ps 12,500
976 Engsel Patrun ps 8,125
977 Engsel Harmonika m1 31,250
978 Door Closer Kelas Standard ( Kelas Sedang ) unt 150,000
979 Door Closer Kelas Standard ( Kelas Baik ) unt 225,000
980 Door Closer Kelas Rendah unt 112,500
19
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
981 Tarikan Almari Rata - rata bh 11,250
982 Kunci Pintu Kayu ex. SES bh 37,500
983 Kunci Pintu Besar ex. ALPHA unit 125,000
984 Kunci Pintu Kecil ex. ALPHA unit 100,000
985 Sloot Pintu Sedang untuk Jendela bh 9,375
986 Engsel Stainless ps 31,250
987 Door Closer Pintu Otomatis Buka Tutup unit 412,500
988 Dudukan gembok uk. Besar bh 12,500
-
Q. BAHAN PENGIKAT UNTUK KONTRUKSI JALAN -
989 Hotmix Jadi berikut alat dan bahan bakar ( T = 5 cm => 9 m2 ) ton 1,450,000
990 Aspal ( ESO ) 1 Drum 150 Kg kg 11,694
991 Aspal Curah kg 11,694
992 Aspal RC 70 ( Cilacap ) kg 11,694
993 Emulsi kg 13,045
994 ATB ton 1,175,000
995 AC-WC ton 1,312,500
996 AC-BC ton 1,275,000
997 AC-BASE ton 1,237,500
998 HRS ton 1,437,500
999 Prime Coat lt 11,875
1000 Tack Coat lt 11,875
-
R. BAHAN PENGHISAP AIR SUMUR DALAM -
1000 Pompa Kodok unit 225,000
1001 Pompa Dragon Tegal unit 368,750
1002 Pompa Dragon Asli unit 637,500
1003 Mesin Pompa Air 100 W - Sanyo unit 875,000
1004 Mesin Pompa Air 125 W - Sanyo unit 4,437,500
1005 Mesin Pompa Air 150 W - Sanyo unit 1,312,500
1006 Pompa Zet pump 250 W - Sanyo unit 5,062,500
1007 Pompa Zet pump 250 W - Simitsu unit 1,687,500
1008 Pompa Zet pump 375W - Simitsu unit 2,031,250
1009 Pompa Zet pump 450 W - Sanyo unit 7,875,000
1010 Pompa Submersible kap. 150 liter/menit 3 kW ex. Grunfos unit 33,750,000
1011 Pompa Submersible 5 HP - SP 8 A - 25 ex. Grunfos unit 31,250,000
1012 Pompa Submersible 7,5 HP - SP 8 A - 30 ex. Grunfos unit 43,750,000
1013 Gear Pump kap. 60 liter/menit unit 18,750,000
1014 Hand Oil Pump unit 5,875,000
1015 Deep Well dengan kelengkapannya kap. 150 liter/menit unit 26,250,000
1016 Pompa Air 250 W - Grundfos unit 3,500,000
1017 Mesin 5 HP4KW unit 30,625,000
1018 Mesin 5 HP4KW unit 37,500,000
1019 Sentripugal EBARA unit 14,062,500
-
S. BAHAN PENAMPUNG AIR -
1020 Tangki Air Fiber Glass 0.5 m3 ( Excel ) bh 812,500
1021 Tangki Air Fiber Glass 1 m3 ( Excel ) bh 1,437,500
1022 Tangki Air Fiber Glass 2 m3 ( Excel ) bh 2,625,000
1023 Tangki Air Pinguin 1500 Ltr bh 3,437,500
1024 Tangki Air Pinguin 2000 Ltr bh 4,062,500
1025 Tangki Air Pinguin 5000 Ltr bh 8,750,000
20
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
1026 Torn 3000 lt bh 5,000,000
1027 Torn 2000 lt bh 2,593,750
1028 Torn 1500 lt bh 1,937,500
1029 Torn 1000 lt bh 1,375,000
1030 Bak KM Fiber 60 x 60 bh 156,250
1031 Bak Taraso WC 40 x 40 bh 175,000
1032 Bak KM Taraso 60 x 60 bh 225,000
1033 Tangki Hidropoore 1 M3 bh 20,625,000
1034 Tangki Hidropoore ½ M3 bh 11,687,500
1035 Pelampung 1" bh 75,000
1036 Pelampung 2" bh 1,218,750
1037 Pelampung 1" San Ei bh 81,250
1038 Pelampung 2" San Ei (Kuningan) bh 6,531,250
-
T. BIAYA QUALITY CONTROL, IZIN - IZIN, PENGUKURAN BIASA, -
DAN BIAYA PENYAMBUNGAN -
1039 Penyambung Listrik PLN VA 1,562,500
HUNIAN -
1040 Bangunan Sederhana m² 7,750
1041 Bangunan Tidak Sederhana m² 9,000
BANGUNAN AGAMA, SOSIAL & BUDAYA -
1042 Bangunan Sederhana m² 4,625
1043 Bangunan Tidak Sederhana m² 5,500
1044 Bangunan Khusus m² 6,500
BANGUNAN UNTUK USAHA -
1045 Bangunan Sederhana m² 15,375
1046 Bangunan Tidak Sederhana m² 18,000
1047 Bangunan Khusus m² 21,625
1048 Industri m² 20,375
BANGUNAN PELENGKAP -
1049 Membuat/memperbaharui gorong-gorong m1 2,625
1050 Membuat/memperbaharui Benteng Tembok (Branmuur Batas) m1 2,375
1051 Membuat/memperbaharui Pagar Besi (Tembok)/Ram dengan Kawat/Ram m1 2,875
dengan kawat tinggi tidak lebih dari 1,2 m -
1052 Membuat/memperbaharui jembatan m² 3,625
1053 Membuat jalan tanah/koral (Perkerasan Batu) m² 375
1054 Membuat jalan paving block m² 625
1055 Membuat jalan grass block m² 375
1056 Membuat jalan beton m² 1,000
1057 Membuat jalan aspal m² 625
1058 Membuat selokan/grappel m1 500
1059 Membuat bak/kolam/water treatment/tanki air m² 2,250
1060 Membuat rabat, lantai terbuka, jemuran m² 2,750
1061 Bangunan di luar ketentuan ini unit 7,187,500
1062 Sondir Rata - rata 1 ttk 1,078,125
1063 Boring tanah 1 ttk 43,125,000
1064 Pengukuran Site + Patok m² 2,625
1065 Biaya Tes Jalan ( quality control ) ttk 149,500
1066 Biaya Tes 1 Macam Beton 1 spl 327,750
1067 Biaya Pengujian Bahan Agregat 1 spl 113,625
1068 Biaya Pengujian Listrik + gambar + trafo & Adm VA 875
1069 Izin Sumur Artesis Lengkap unit -
21
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
1070 Penyambungan PDAM untuk rumah unit -
1071 Geolistrik unit 2,156,250
1072 Well Loging unit 2,156,250
-
U. ALAT TUKANG -
1073 Palu 0,5 kg bh 75,000
1074 Cangkul bh 60,625
1075 Singkup bh 78,125
1076 Sekrop bh 62,500
1077 Pengki bh 12,500
1078 Linggis bh 87,500
1079 Rool Meter 30 meter ( Bahan Plastik ) bh 93,750
1080 Rool Meter 5 meter ( Bahan Besi ) bh 18,750
1081 Selang Plastik untuk Water Pas dia. 0.5 cm m1 1,875
1082 Water Pas Alumuniumm 60 cm bh 53,750
1083 Kuwas 2" bh 7,500
1084 Kuwas 3" bh 12,500
1085 Kuwas 4" bh 17,500
-
V. STANDARD RATA - RATA SEWA ALAT BESAR , KENDARAAN, TRUK, -
KENDARAAN RODA 4, DAN LAINNYA -
1086 Alat Bantu jam 42,500
1087 Genset jam 35,000
1088 Grass Cutter jam 65,000
1089 Screening Plant jam 287,500
1090 Mesin Gilas / Roller 3 Wheeled 8 - 15 Ton jam 147,500
1091 Roller Pneumatic 8 - 15 Ton jam 337,500
1092 Trailler Towed jam 250,000
1093 Tamdem Roller 8 - 10 Ton jam 268,750
1094 Roller Vibrator - Ped 1 Ton jam 137,500
1095 Roller Vibrator - Self 7 Ton jam 250,000
1096 Loader Wheeled 1-1.6 m3 jam 537,500
1097 Sewa Kran 30 Ton hari 3,000,000
1098 Excavator jam 237,500
1099 Sewa Draklint jam 36,250
1100 Buldozer jam 312,500
1101 Jack Hammer jam 11,250
1102 Motor Grader > 100 HP jam 281,250
1103 Pheumatic Drill Hammer jam 125,000
1104 Vibrator Roller jam 68,750
1105 Pedestrian Roller jam 168,750
1106 Stone Crusher jam 537,500
1107 Mesin Bor Air Bersih jam 562,500
1108 Aspalt Mixing Plant (AMP) jam 5,000,000
1109 Tracktor Equipment hari 71,250
1110 Asphal Finisher jam 237,500
1111 Asphal Melting Kalte jam 781,250
1112 Aspalt Sprayer jam 48,750
1113 Aspalt Sprayer Towed jam 48,750
1114 Sprayer Selfpropelled jam 40,000
1115 Plate Vibrator Stamper jam 20,000
1116 Crusher / SCR jam 712,500
22
NO. JENIS BAHAN BANGUNAN SAT HARGA (Rp.)
RUJUKAN
1 2 3
1117 Concrete Pan Mixer jam 181,250
1118 Concrete Mixer 0.1 - 0.3 m3 jam 48,750
1119 Concrete Mixer 0.3 - 0.6 m3 jam 73,750
1120 Concrete Vibrator jam 41,250
1121 Pick Up jam 61,250
1122 Dump Truck 3.5 Ton jam 237,500
1123 Dump Truck 5 Ton jam 375,000
1124 Flat bed Truck jam 225,000
1125 Truck 3/4 ( Colt Disel ) jam 61,250
1126 Mixer Truck jam 156,250
1127 Truck Fuso jam 137,500
1128 Mobile Crane jam 412,500
1129 Mesin Las Listrik 18 pk jam 41,250
1130 Mesin Pompa Air 3 " jam 18,750
1131 Water pump 70-100 mm jam 28,750
1132 Stamper jam 106,250
1133 Compressor Air 4000-6500 L/M jam 118,750
1134 Pump Water ( 5 cm ) 30 m3 / hari jam 18,750
1135 Water Tank Truck 3000-4500 L jam 275,000
1136 Pumping Test 48 jam 4,250,000
1137 Water Jeting/Kompresor 3 jam 6,437,500
-
W. BAHAN BAKAR DAN PELUMAS -
1138 Minyak Tanah lt 103,750
1139 Kayu Bakar Dari Kayu Karet m³ 187,500
1140 Residu lt 5,500
1141 Minyak Solar lt 11,625
1142 Bensin Premium lt 5,625
1143 Plus Oil lt 26,250
1144 Oli Mesran 40 SAE lt 33,125
1145 Elpiji / botol 15 kg 117,500
1146 Asitilin / botol 15.1 kg 92,500
1147 Angin ( O2 ) / botol btl 96,250
1148 Kawat Las Listrik kg 31,250
1149 Minyak Pelumas lt 35,000
1150 Karbit kg 21,875
23
DAFTAR HARGA STANDARD BAHAN BANGUNAN
TAHUN 2013
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SAT
(Rp)
A BAHAN AGREGAT KASAR & BAHAN PEREKAT
1 Tanah Urug m3 75,000.00
2 Abu Batu m3 200,000.00
3 Pasir Urug m3 100,000.00
4 Pasir Pasang m3 175,000.00
5 Pasir Beton m3 187,500.00
6 Pasir Batu (Sirtu) m3 175,000.00
7 Batu Belah Pondasi m3 181,250.00
8 Batu Pecah Mesin 1/2 m3 212,500.00
9 Batu Pecah Mesin 2/3 m3 200,000.00
10 Batu Pecah Mesin 3/5 m3 187,500.00
11 Batu Pecah Mesin 5/7 m3 175,000.00
12 Batu Templek Hitam m2 150,000.00
13 Batu Templek Hijau m2 112,500.00
14 Batu Templek Palimanan m2 100,000.00
15 Semen/PC Tiga Roda kg 1,350.00
16 Semen Putih kg 2,250.00
17 Semen Warna Muda kg 3,000.00
18 Semen Warna Tua kg 3,125.00
19 Semen Warna Khusus (Biru) kg 3,625.00
20 Semen Merah, Bahan Bata Merah Tumbuk m3 175,000.00
21 Lem Kuning kg 23,750.00
22 Lem Putih Fox kg 8,750.00
23 Lem Vinil kg 23,750.00
B BAHAN LOGAM
1 Besi Beton U-24, rata-rata uk. dia 8 s.d. 16 mm kg 11,250.00
2 Besi Beton U-24, rata-rata uk. dia 19 s.d. 22 mm kg 11,250.00
3 Besi Beton Ulir, rata-rata uk. dia 12 s.d. 22 mm kg 13,125.00
4 Besi Profil IWF, rata-rata ex. DN-SII kg 13,750.00
5 Besi Kanal "C" s.d. 150.65.20.3,2 kg 15,762.50
6 Besi Kanal "C" s.d. 200.75.20.3,2 kg 16,975.00
7 Seng BJLS 0,20, L = 55 cm ( 1 rol = 50 m' ) m' 38,800.00
8 Seng BJLS 0,30, L = 55 cm ( 1 rol = 50 m' ) m' 56,381.25
9 Seng Plat BJLS 25 uk. 90 x 180 cm lbr 60,625.00
10 Seng Plat BJLS 30 uk. 90 x 180 cm lbr 60,625.00
11 Seng Gelombang BJLS 25 uk. 0.90 x 1.80 m lbr 75,781.25
12 Seng Gelombang BJLS 30 uk. 0.90 x 1.80 m kg 106,700.00
13 Kawat Beton kg 21,461.25
14 Kawat Duri ( 1 rol = 80 m = 10 kg ) rol 53,350.00
15 Kawat Raam m2 12,250.00
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SAT
(Rp)
16 Kawat Nyamuk Hijau m2 18,375.00
17 Paku uk. 2" - 5" kg 14,550.00
18 Paku uk. 5" - 7" kg 14,550.00
19 Paku uk. 7" - 10" kg 14,550.00
20 Paku Ramset / Dina Bolt bh 1,455.00
21 Paku Anti Karat u / Genteng Metal (35.00 m 2 / kg) kg 30,312.50
22 Paku Seng kg 12,125.00
23 Hak Kait Asbes 7 cm lengkap bh 909.38
24 Paku Kait Asbes kg 9,700.00
25 Paku Gypsum (20.00 m2 / kg) kg 30,312.50
26 Paku Sekrup bh 303.13
27 Baja Ringan kg 8,487.50
28 Baud dia 12 mm bh 15,156.25
29 Plat besi kg 10,912.50
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SAT
NO. JENIS BAHAN BANGUNAN SAT
(Rp)
-
H BAHAN FINISHING -
1 Cat Dasar Tembok, Indo 9000 Saeler Water Base kg 27,584.38
2 Cat Dasar Kayu ltr 19,703.13
3 Cat Tembok Sanlex kg 7,275.00
4 Cat Tembok Sanlex Wonder kg 10,306.25
5 Cat Tembok Vinilex kg 12,125.00
6 Cat Tembok Wiratex kg 9,063.44
7 Cat Kayu / Besi Seiv kg 39,406.25
8 Cat Kayu / Besi Avian kg 43,346.88
9 Meni Kayu / Besi kg 18,187.50
10 Soda Coustic kg 7,881.25
11 Cat Sinchromate Bola Mas kg 19,703.13
12 Plint Coat ltr 23,643.75
13 Dempul Tembok (Plamir) Sanlex kg 6,305.00
14 Dempul Kayu Cap Kucing kg 18,915.00
15 Dempul Halus Impra kg 26,796.25
16 Dempul Lilin kg 5,122.81
17 Dempul Plastik kg 23,643.75
18 Terpentine (Minyak Cat) ltr 4,728.75
19 Solignem ( 1 blek = 10 ltr ) ltr 2,364.38
20 Thiner A ltr 11,033.75
21 Thiner B ltr 21,279.38
22 Oker kg 5,516.88
23 Oten (Pewarna Plituran) bks 1,024.56
24 Sirlax ex. India kg 94,575.00
25 Spirtus ltr 10,245.63
26 Politur ltr 23,643.75
27 Politur Jadi Ultran ltr 39,406.25
28 Teak Oil ltr 29,554.69
29 Vernis ltr 39,406.25
30 Minyak Tanah ltr 7,093.13
31 Kwass 3-4" bh 11,821.88
32 Ampelas lbr 2,364.38
33 Roll Cat bh 23,643.75
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SAT
(Rp)
I BAHAN PERPIPAAN
1 Pipa Pralon PVC. (AW) dia 1/2", Rucika (Abu-abu) btg 28,125.00
2 Pipa Pralon PVC. (AW) dia 3/4", Rucika (Abu-abu) btg 37,500.00
3 Pipa Pralon PVC. (AW) dia 1", Rucika (Abu-abu) btg 50,000.00
4 Pipa Pralon PVC. (AW) dia 1 1/4", Rucika (Abu-abu) btg 62,500.00
5 Pipa Pralon PVC. (AW) dia 1 1/2", Rucika (Abu-abu) btg 87,500.00
6 Pipa Pralon PVC. (AW) dia 2", Rucika (Abu-abu) btg 112,500.00
7 Pipa Pralon PVC. (AW) dia 2 1/2", Rucika (Abu-abu) btg 150,000.00
8 Pipa Pralon PVC. (AW) dia 3", Rucika (Abu-abu) btg 175,000.00
9 Pipa Pralon PVC. (AW) dia 4", Rucika (Abu-abu) btg 218,750.00
10 Pipa Pralon PVC. (AW) dia 6", Rucika (Abu-abu) btg 887,500.00
11 Pipa Pralon PVC. ( D ) dia 1 1/2", Rucika btg 37,500.00
12 Pipa Pralon PVC. ( D ) dia 2", Rucika btg 50,000.00
13 Pipa Pralon PVC. ( D ) dia 2 1/2", Rucika btg 62,500.00
14 Pipa Pralon PVC. ( D ) dia 3", Rucika btg 87,500.00
15 Pipa Pralon PVC. ( D ) dia 4", Rucika btg 112,500.00
16 Pipa Pralon PVC. ( D ) dia 5", Rucika btg 187,500.00
17 Pipa GIV Klas Medium dia 1 1/2" btg 187,500.00
18 Pipa GIV Klas Medium dia 2" btg 250,000.00
19 Pipa Slang PE, dia 1" m' 8,669.38
20 Buis Beton dia 20 cm - 1.00 m bh 39,406.25
21 Buis Beton dia 30 cm - 1.00 m bh 63,050.00
22 Pipa Tanah dia 15 cm bh 19,703.13
23 Pipa Tanah dia 20 cm bh 31,525.00
24 Grevel Beton 1/2 dia 20 cm bh 22,067.50
25 Grevel Beton 1/2 dia 30 cm bh 39,406.25
-
J BAHAN / ALAT-ALAT SANITAIR -
1 Kloset Jongkok Perselin TOTO, Standard Lengkap, Putih bh 275,843.75
2 Kloset Jongkok Perselin INA, Standard Lengkap, Putih bh 236,437.50
3 Kloset Duduk Perselin TOTO, Standard Lengkap, Putih bh 1,891,500.00
4 Wastafel Lengkap + Cermin, ex. INA type LW. 230 bh 1,182,187.50
5 Kloset Duduk Perselin INA, Standard Lengkap, Warna Tua bh 1,158,543.75
6 Kloset Jongkok Putih ex. Lokal bh 63,050.00
7 Urinoir Lengkap Standard ex. TOTO bh 630,500.00
8 Penyekat Urinoir ex. TOTO bh 244,318.75
9 Bak Mandi Fiber Glass, uk. Kecil bh 394,062.50
10 Bak Mandi Fiber Glass, uk. Besar bh 126,100.00
11 Bak Mandi Teraso bh 86,693.75
12 Kran Air Lokal Leher Angsa dia 1/2" bh 38,618.13
13 Kran Tembok Sun EI dia 1/2" bh 110,337.50
14 Kran Tembok Lokal dia 1/2" bh 39,406.25
15 Kran Panas / Dingin bh 606,856.25
16 Floor Drain Sun Ei bh 267,962.50
17 Floor Drain Lokal bh 39,406.25
18 Bak Cuci Piring Stainless Steel bh 315,250.00
-
K BAHAN BAKAR/PELUMAS -
1 Sewa alat ls 212,187.50
2 Bahan bakar solar lt 4,500.00
3 Pelumas lt 24,250.00
4 Alat Bantu ls 12,125.00
5 Grease Kg 28,125.00
6 Karet Piston Psng 75,000.00
7 Bentonite Zak 187,500.00
8 Mata Bor Bh 625,000.00
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SAT
(Rp)
L BAHAN ELEKTRIKAL
1 Pas. Box Sikring bh 118,218.75
2 Pas. Pipa PVC 5/8" m1 12,610.00
3 Pas. Elbow (Terminal) bh 3,152.50
4 Pas. Inbow bh 3,152.50
5 Pas. Fitting Lampu bh 12,610.00
6 Pas. Saklar Inbow Tunggal Broco bh 39,406.25
7 Pas. Saklar Inbow Seri Broco bh 47,287.50
8 Pas. Stop Kontak Broco bh 47,287.50
9 Pas. Kabel NYM 3 x 2.5 rol 433,468.75
10 Pas. Kabel NYM 2 x 2.5 rol 315,250.00
11 Pas. Klem pack 5,573.75
DAFTAR HARGA STANDAR UPAH PEKERJA BANGUNAN
TAHUN ANGGARAN 2012
UPAH
NO JENIS PEKERJA 1 HARI /8 JAM
Rp
1 PEKERJA 55,000.00
2 TUKANG GALI 75,000.00
3 TUKANG BATU 60,000.00
4 KEPALA TUKANG BATU 65,000.00
5 TUKANG KAYU 60,000.00
6 KEPALA TUKANG KAYU 65,000.00
7 TUKANG CAT / PLITUR 60,000.00
8 KEPALA TUKANG CAT / PLITUR 65,000.00
9 TUKANG BESI BETON 60,000.00
10 KEPALA TUKANG BESI BETON 65,000.00
11 TUKANG BESI PROPIL 60,000.00
12 KEPALA TUKANG BESI PROPIL 65,000.00
13 MANDOR 80,000.00
14 OPRATOR ALAT BESAR 65,000.00
15 PEMBANTU OPRATOR / MEKANIK 55,000.00
16 JURU BOR 65,000.00
17 ASISTEN JURU BOR 60,000.00
18 MEKANIK 55,000.00
19 SUPIR TRUK 65,000.00
20 KENEK TRUK 45,000.00
21 PENJAGA MALAM 50,000.00
UPAH RATA-RATA PERHARI 61,666.67