RINCIAN ANGGARAN BIAYA (RAB)

PEMBANGUNAN BALE BANJAR DINAS KAMBANG

NAMA PEKERJA : PEMBANGUNAN BALE BANJAR DINAS KAMBANG

LOKASI : BR. DINAS KAMBANG


BONGKASA, KEC. ABIANSEMAL, BADUNG

Biaya Satuan
No Program Kegiatan Volume Satuan Jumlah (Rp.)
Ukur (Rp.)

I PEKERJAAN PERSIAPAN
1 Pasang bowplank dan pengukuran 29,5 m 52.640,00 1.552.880,00
Sub. Total I 1.552.880,00
II PEKERJAAN TANAH & PASIR
1 Galian tanah pondasi menerus 51,66 m3 81.675,00 4.219.330,50
2 Galian pondasi beton poer 50,40 m3 107.790,00 5.432.616,00
3 Urugan tanah kembali 68,46 m3 58.850,00 4.028.871,00
4 Urugan tanah Peninggian Lantai 24,32 m3 58.850,00 1.431.158,44
5 Urugan pasir 5,18 m3 330.000,00 1.707.750,00
Sub. Total II 16.819.725,94
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan batu kosong 16,42 m3 668.477,70 10.973.729,92
2 Pasangan pondasi batu kali 1 : 5 50,97 m3 940.450,00 47.935.618,17
3 Pekerjaan Pasangan tembok batu bata 1 pc : 5 ps 125,25 m2 391.985,00 49.095.494,07
4 Pekerjaan Plesteran tembok 1 pc : 5 ps 220,80 m2 56.630,63 12.503.861,44
5 Pekerjaan Acian 220,80 m2 40.463,50 8.934.211,32
6 Pasang tile lantai granito 60 x 60 cm 116,64 m2 607.641,03 70.875.249,44
7 Pasang plin lantai granito 10 x 60 cm 33,00 m2 165.000,00 5.445.000,00
9 Pasang homogenius tile granito anti slip 60 x 60 cm 38,78 m2 607.641,03 23.561.280,84
10 Pasang finishing Batu Bata Expose pada colom lantai 1 185,58 m2 1.230.567,00 228.368.623,86
11 Pasang finishing Batu Bata Expose pada gayor pintu dan jendela stage 3,00 unit 350.000.000,00 350.000.000,00
12 Pekerjaan Acian Waterprofing dgn Sika semen 103,50 m2 67.765,00 7.013.677,50
Sub. Total IV 814.706.746,56
V PEKERJAAN KUSEN

1 Pasang pintu kayu 3,53 m2 577.496,70 2.036.253,36


2 Pasang kusen + Pintu Ukir Style Bali 1,00 unit 6.300.000,00 6.300.000,00
3 Pasang kusen + jendela Ukir Style Bali 2,00 unit 2.500.000,00 5.000.000,00
4 Pasang engsel pintu solid 6,00 bh 55.000,00 330.000,00
5 Pasang kunci pintu solid 2,00 bh 89.000,00 178.000,00
Sub. Total V 13.844.253,36
VI PEKERJAAN BETON
1 Cor beton balok praktis 10/15 4,65 m3 96.173,00 447.204,45
2 Cor beton kolom praktis 13,48 m3 73.689,00 993.327,72
3 Rabat lantai beton K100 29,50 m3 825.148,50 24.341.880,75
-
4 Beton pondasi Poer -
- Bekisting batako 1 : 4 39,52 m2 93.131,50 3.680.556,88
- Cor beton F'c 21.7 Mpa 10,94 m3 1.174.665,79 12.855.542,45
- Besi/baja tulangan 2.245,50 kg 18.741,00 42.082.840,54
-
5 Beton sloof TB1 25/40 -
- Bekisting Sloof (2X pakai) 44,00 m2 86.498,50 3.805.934,00
- Cor beton F'c 21.7 Mpa 10,47 m3 1.174.665,79 12.295.209,78
- Besi/baja tulangan 1.485,73 kg 18.741,00 27.844.003,46
-
6 Beton kolom K1 40x40 cm -
- Bekisting kolom (2X pakai) 132,24 m2 140.750,50 18.612.846,12
- Cor beton F'c 21.7 Mpa 25,69 m3 1.174.665,79 30.173.441,12
- Besi/baja tulangan 2.987,59 kg 18.741,00 55.990.431,69
-
7 Beton balok Induk (35/75) -
- Bekisting balok 67,65 m2 287.276,00 19.434.221,40
- Cor beton F'c 21.7 Mpa 21,23 m3 1.174.665,79 24.937.488,92
- Besi/baja tulangan 1.160,10 kg 18.741,00 21.741.434,10
-
8 Beton balok Anak (25/40) -
- Bekisting balok 16,15 m2 287.276,00 4.639.507,40
- Cor beton F'c 21.7 Mpa 17,63 m3 1.174.665,79 20.708.033,15
- Besi/baja tulangan 671,68 kg 18.741,00 12.587.892,41
-
9 Beton Plat lantai 2 -
- Bekisting plat lantai 103,50 m2 334.301,00 34.600.153,50
- Cor beton F'c 21.7 Mpa 15,29 m3 1.174.665,79 17.965.991,83
- Besi/baja tulangan 984,74 kg 18.741,00 18.454.918,64
-
10 Beton Tangga -
- Bekisting plat lantai 22,05 m2 261.701,00 5.770.507,05
- Cor beton F'c 21.7 Mpa 5,95 m3 1.174.665,79 6.985.366,87
- Besi/baja tulangan 465,63 kg 18.741,00 8.726.309,36

Sub. Total VI 429.675.043,58


VII PEKERJAAN SANITASI
Pek. Instalasi air kotor
1 Pipa PVC AW Ø 3" buangan air hujan 8,00 m 74.987,00 599.896,00
Sub. Total VII 599.896,00
VIII PEKERJAAN INSTALASI MEKANIKAL & ELEKTRIKAL
Pek. Instalasi Listrik
1 Instalasi lampu penerangan, NYM 3x2,5 mm2 dalam konduit Ø20 mm 70,00 m 197.890,00 13.852.300,00
2 Instalasi stop kontak, NYM 3x2,5 mm2 dalam konduit Ø20 mm 30,00 m 214.225,00 6.426.750,00
3 Stop kontak biasa warna putih 5,00 unit 55.000,00 275.000,00
4 Saklar tunggal 3,00 unit 44.000,00 132.000,00
5 Saklar seri 1,00 unit 55.000,00 55.000,00
6 Lampu LED 8 watt + Downlight 5" 9,00 titik 192.500,00 1.732.500,00
7 Lampu LED 8 watt + Fiting 3,00 titik 88.000,00 264.000,00
Sub. Total VIII 22.737.550,00
IX PEKERJAAN PENGECATAN
1 Pengecatan tembok baru Exterior ex. Dulux weathersield 220,80 m2 65.199,00 14.395.730,56
2 Pengecatan Permukaan beton ex. Dulux Watershiel 155,25 m2 65.199,00 10.122.144,75

Sub. Total IX 24.517.875,31


X PEKERJAAN LAIN-LAIN
1 Planter box 20,50 m 300.000,00 6.150.000,00
2 Balai Piyasan 1,00 unit 58.300.000,00 58.300.000,00
3 Padmasana 1,00 unit 11.550.000,00 11.550.000,00
4 Balai Gong 1,00 unit 207.900.000,00 207.900.000,00
5 Balai Pewedaan 1,00 unit 78.250.000,00 78.250.000,00
6 Pelinggih 1,00 unit 12.075.000,00 12.075.000,00
7 Penyengker Pura 20,50 unit 4.935.000,00 101.167.500,00
Sub. Total IX 475.392.500,00
Real Cost 1.798.293.590,75
PPN 10 % 179.829.359,08
Total 1.978.122.949,83
Dibulatkan 1.978.122.000,00