Anda di halaman 1dari 8

RENCANA ANGGARAN BIAYA PROYEK

PROJEK : VILLA BATU BELIG


LOKASI : BALI
PEMILIK : BAPAK ALEK

UNIT PRICE TOTAL


NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
A PEKERJAAN PERSIAPAN
1 VILLA 8,00 unit 699.910.000,00 5.599.280.000,00
2 COFEE SHOP, PARKING 1,00 unit 412.200.000,00 412.200.000,00

sub total A 6.011.480.000,00


RENCANA ANGGARAN BIAYA PROYEK

PROJEK : VILLA BATU BELIG


LOKASI : BALI
PEMILIK : BAPAK ALEK

UNIT PRICE TOTAL


NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1,00 ls 500.000,00 500.000,00
2 Bedeng Tukang 1,00 ls 3.000.000,00 3.000.000,00
3 Listrik Kerja 1,00 ls 6.500.000,00 6.500.000,00
4 Uetset Lokasi Pengukuran Elevasi 1,00 ls 1.500.000,00 1.500.000,00
5 Pas. Bowplank 53,46 m' 57.500,00 3.073.950,00
sub total A 14.573.950,00
B PEKERJAAN GALIAN & PASIR
1 Galian Tanah ( Pondasi Foot Plat ) 8,82 m3 105.579,00 931.206,78
2 Galian Tanah ( Pondasi Menerus ) dan pondasi praktis 35,47 m3 105.579,00 3.744.887,13
3 Galian tanah Sunken 10,23 m3 105.579,00 1.080.073,17
4 Urugan Pasir Bawah Pondasi Foot Plat 0,34 m2 286.543,00 98.284,25
5 Urugan Pasir Bawah Pondasi Menerus 2,22 m3 286.543,00 636.125,46
6 Urugan Pasir Di bawah Lantai 5,55 m3 286.543,00 1.588.880,94
sub total B 8.079.457,72
C PEKRJAAN PONDASI & URUGAN LANATI
1 Pas. Batu Kosong dari Batu kali 4,58 m3 477.751,80 2.189.417,06
2 Pas. Pondasi Batu kali 24,82 m3 779.275,00 19.341.605,50
3 urugan tanah kembali 5,19 m3 45.700,00 237.183,00
4 Urugan Tanah Peninggi Lantai 16,67 m3 61.905,00 1.032.080,16
5 Wiremesh m5 111,80 m2 55.250,00 6.176.950,00
6 Rabat Lantai 7,83 m3 833.630,00 6.527.322,90
7 Rabat Lantai teras 1,32 m3 833.630,00 1.100.391,60
sub total C 36.604.950,22
D PEKRJAAN STRUKTUR BETON INCLUDE BEGESTING
Pondasi
1 Pek. Beton Rabat 5 cm lantai kerja Foot Plat 0,29 m3 833.630,00 241.752,70
2 Pek. Beton Foot Plat P1
- Besi Beton 111,29 kg 17.106,67 1.903.733,61
- Beton Mutu 1,72 m3 1.159.004,20 1.987.692,20
- Bekisting 2x Pakai 9,80 m2 142.603,00 1.397.509,40
Struktur Lantai I
1 Beton Sloof S1 20/30
- Besi Beton 626,54 kg 17.106,67 10.718.008,78
- Beton Mutu 5,60 m3 1.159.004,20 6.490.191,71
- Bekisting 2x Pakai 56,00 m2 193.921,20 10.859.199,36
2 Beton Sloof 15/25
- Besi Beton 63,91 kg 17.106,67 1.093.284,58
- Beton Mutu 0,67 m3 1.159.004,20 780.154,70
- Bekisting 2x Pakai 8,98 m2 193.921,20 1.740.442,77
3 Beton Kolom K1 30/30
- Besi Beton 520,18 kg 17.106,67 8.898.536,01
- Beton Mutu 3,47 m3 1.159.004,20 4.015.949,55
- Bekisting 2x Pakai 63,00 m2 240.110,00 15.126.930,00
Struktur Lantai Atap
1 Beton Ring Balok B1 20/30
- Besi Beton 527,09 kg 17.106,67 9.016.703,92
- Beton Mutu 4,69 m3 1.159.004,20 5.431.093,67
- Bekisting 2x Pakai 43,74 m2 246.670,00 10.788.359,12
2 Beton Ring Balok Ba 15/25
- Besi Beton 215,22 kg 17.106,67 3.681.688,27
- Beton Mutu 2,01 m3 1.159.004,20 2.325.252,17
- Bekisting 2x Pakai 24,08 m2 246.670,00 5.938.580,25
3 Beton Plat Topian 8 cm
- Besi Beton 82,36 kg 17.106,67 1.408.938,43
- Beton Mutu 1,09 m3 1.159.004,20 1.266.467,07
- Bekisting 2x Pakai 13,66 m2 267.710,00 3.656.650,89
4 Beton Plat Atap 10 cm
- Besi Beton 433,14 kg 17.106,67 7.409.550,61
- Beton Mutu 7,28 m3 1.159.004,20 8.437.550,56
- Bekisting 2x Pakai 72,80 m2 267.710,00 19.489.288,00
5 Pekerjaan Waterprofing sika Lantai atap + rabat 72,80 m2 85.000,00 6.188.000,00
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
sub total D 150.291.508,33
E PEKERJAAN PLAFOND
1 Pek. Pemasngan Plafond Gypsum 9mm dengan Rangka Holow 111,80 m2 98.000,00 10.956.400,00
2 Pekerjaan Sedowline plafond 101,46 m' 25.750,00 2.612.595,00
3 Pekerjaan Cat plafond 111,80 m2 36.680,00 4.100.824,00
4 Pek. Plestr aci Plat Atap topi 14,12 m' 94.800,00 1.338.576,00
5 Pek. Cet Plat topi atap 14,12 m' 47.440,00 669.852,80
Sub Total E 19.678.247,80

F PEKERJAAN DINDING
1 Pas. Batako 222,00 m2 110.500,00 24.531.000,00
2 Pek. Beton Kolom Praktis & Ring Praktis 41,60 m' 94.800,00 3.943.680,00
3 Pek. Plesteran Dinding 324,00 m2 55.500,00 17.982.000,00
4 Pek. Acian Dinding 324,00 m2 37.040,00 12.000.960,00
5 Pek. Cat Dinding Dalam 176,00 m2 36.680,00 6.455.680,00
6 Pek. Cat Dinding Luar 148,00 m2 47.440,00 7.021.120,00
Sub Total F 71.934.440,00
G PEKERJAAN KERAMIK DINDING & LANTAI
1 Pek. Keramik Lantai Kamar Mandi 40x40 asia Tile @90.000 20,09 m2 225.810,00 4.536.522,90
2 Pek. Keramik Dinding Kamar Mandi , asia tile 20x40 cm @125.000 78,43 m2 263.340,00 20.653.756,20
3 Pek. Granit Lantai Kamar 60x60, Setara DBS @165.000 38,55 m2 305.800,00 11.788.590,00
4 Pek. Granit Lantai sunken 60x60, Setara DBS @165.000 16,80 m2 305.800,00 5.137.440,00
5 Pek. Granit Lantai kitchen, dining room 60x60, Setara DBS @165.000 35,46 m2 305.800,00 10.843.668,00
6 Plin Keramik 10 cm 87,02 m' 36.307,90 3.159.513,46
7 Pek. Batu Palimanan teras 20x40 18,84 m2 403.544,67 7.602.781,52
Sub Total G 63.722.272,08

H PEKERJAAN PINTU & AKSESORIS


1 Pas. Pintu Toilet Kayu Kelas II 80x240 cm, 2,00 unit 2.417.404,00 4.834.808,00
2 Pas. Pintu Kayu Kelas II 90x240 cm, 1,00 unit 2.197.640,00 2.197.640,00
3 Pas. Pintu Kayu Kelas II 100x240 cm, 1,00 unit 1.758.112,00 1.758.112,00
4 pas. Pintu Sleding Alumunium 230x280 1,00 unit 7.733.748,00 7.733.748,00
5 pas. Pintu Sleding Alumunium 553x280 1,00 unit 17.576.700,00 17.576.700,00
6 pas. Pintu Sleding Alumunium 320x280 1,00 unit 9.374.240,00 9.374.240,00
7 pas. Jendela Mati Alumunium 90x280 1,00 unit 1.941.450,00 1.941.450,00
8 Kunci Biasa 1,00 bh 165.850,00 165.850,00
9 Kunci Alumunium 3,00 bh 144.850,00 434.550,00
10 Kunci Km/Wc 3,00 bh 185.120,00 555.360,00
11 Engsel Pintu 6,00 bh 67.935,00 407.610,00
12 Handle Pintu 4,00 bh 213.050,00 852.200,00
13 Pas.Kaca Bening 24,60 m2 295.000,00 7.257.000,00
Sub Total H 55.089.268,00

I PEKERJAAN LISTRIK
1 Pek. Instalasi Lampu Plafond Kabel 2*1.5 mm 37,00 ttk 225.000,00 8.325.000,00
2 Pek. Instalasi Stop Kontak Kabel 3*2.5 mm 23,00 ttk 245.000,00 5.635.000,00
3 Pas. Lampu downlight 37,00 ttk 75.000,00 2.775.000,00
4 Pas. Saklar Tunggal 4,00 bh 42.000,00 168.000,00
5 Pas. Saklar tukar 2,00 bh 55.000,00 110.000,00
6 Pas. Saklar doble 3,00 bh 42.000,00 126.000,00
7 Pas. Stop Kontak doble 7,00 bh 45.000,00 315.000,00
8 Pas. Stop Kontak lantai 1,00 bh 450.000,00 450.000,00
9 Pas. Stop Kontak meja 1,00 bh 450.000,00 450.000,00
10 Pas. Stop Kontak single 10,00 bh 45.000,00 450.000,00
11 Pas. Stop Kontak TV 3,00 bh 45.000,00 135.000,00
12 Pas. Stop Kontak Data 3,00 bh 45.000,00 135.000,00
13 Pas. Stop Kontak AC 3,00 bh 45.000,00 135.000,00
14 kipas Angin 1,00 bh 2.500.000,00 2.500.000,00
15 MCB 8 Group 1,00 unit 1.200.000,00 1.200.000,00
16 Pas. Kabel Fider 3x6 mm 15,00 m' 65.000,00 975.000,00
sub total I 23.884.000,00

J PEKERJAAN PLUMBING
1 Pas. Pipa PVC 4" Saluran Kloset 33,13 m' 95.000,00 3.147.350,00
2 Pas Pipa saluran floordrain PVC 3" 46,68 m' 78.000,00 3.641.040,00
3 Pas. Pipa PVC 1" saluran air bersih 46,43 m' 42.500,00 1.973.275,00
4 Pas. Pipa PVC 3/4" Saluran Air Bersih 39,00 m' 36.500,00 1.423.500,00
5 Pas. Pip PVC 3/4" saluan pembuangan AC 18,00 m' 36.500,00 657.000,00
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
6 Pas. Pipa PVC 3" Air Hujan 53,86 m' 78.000,00 4.201.080,00
7 Pipa Air Panas PPR DN20 15,00 m' 85.000,00 1.275.000,00
Sanitary
8 Pas. Kloset Duduk american standar 3,00 bh 2.700.000,00 8.100.000,00
9 Pas. Jet Shower + Kran T 3,00 set 225.000,00 675.000,00
10 Pas. Floor Drain Onda 6,00 set 125.000,00 750.000,00
11 Pas. Shower ex. Washer 3,00 set 2.950.000,00 8.850.000,00
12 Pas. Wastafel 2,00 set 1.670.050,00 3.340.100,00
13 Pas. Bathtub 2,00 set 4.250.000,00 8.500.000,00
14 Kran bactube 2,00 set 5.000.000,00 10.000.000,00
15 Septiktank bio 1000 liter 1,00 unit 5.500.000,00 5.500.000,00
16 Resapan Buis Beton D80 3 unit 1,00 set 3.000.000,00 3.000.000,00
17 Pemanas Air Ariston 80 Liter 2,00 set 4.850.000,00 9.700.000,00
18 AC SHARP 1PK dan instalasi pipa 2,00 unit 4.750.000,00 9.500.000,00

sub total J 84.233.345,00


K PEKERJAAN KOLAM RENANG
Pek Galian dan Pasir
1 Pas. Bowplank 23,49 m' 57.500,00 1.350.675,00
2 Pek. Galian Tanah 36,39 m3 105.579,00 3.842.019,81
3 Urugan pasir 0,98 m3 286.543,00 280.812,14
Pek pondasi
1 Pek. Pasangan batako 29,50 m2 110.500,00 3.259.750,00
2 Rabat Lantai kerja 1,07 m3 833.630,00 891.984,10
Pek Struktor Beton
1 Beton Sloof 20/30
- Besi Beton 172,43 kg 17.106,67 2.949.767,56
- Beton Mutu 1,24 m3 1.159.004,20 1.437.165,21
- Bekisting 2x Pakai 13,20 m2 193.921,20 2.559.759,84
2 Beton Dinding dan Lantai
- Besi Beton 473,47 kg 17.106,67 8.099.529,26
- Beton Mutu 6,75 m3 1.159.004,20 7.823.278,34
- Bekisting 2x Pakai 44,00 m2 114.251,60 5.027.070,40
Pek. Phinising Kolam
1 Pek. Waterprofing 44,00 m2 85.000,00 3.740.000,00
2 Pek. Kamprot Dinding 44,00 m2 49.970,00 2.198.680,00
3 Batu Hijau 10 x 20 44,00 m2 312.000,00 13.728.000,00
4 Pek. Pasangan Batu Toping 30 x 60 tebal 4 cm 12,00 m' 245.000,00 2.940.000,00
Ruang Mesin
1 Pek. Galian Tanah 1,44 m3 105.579,00 152.033,76
2 Pek. Rabatan Lantai kerja 0,07 m3 833.630,00 58.354,10
3 Pek. Dinding Batako 4,80 m2 110.500,00 530.400,00
4 Pek. Beton Lantai dan dinding besi 1 lapis 0,62 m3 3.450.675,00 2.139.418,50
5 Pek. Beton Tutup Ruang mesin besi 1 lapis 0,08 m3 3.450.675,00 276.054,00
6 Bak Kontrol 1,00 unit 750.000,00 750.000,00
Pek Instalasi MEP
1 Intalasi Listrik lampu 10,00 m' 55.000,00 550.000,00
2 Supply&instal pipa pvc aw dia.1" ex. Maspion 10,00 m' 45.000,00 450.000,00
3 Supply&instal pipa pvc aw dia.1 1/2" ex. Maspion 20,00 m' 52.000,00 1.040.000,00
4 Supply&instal pipa pvc aw dia.2" ex. Maspion 8,00 m' 67.500,00 540.000,00
5 Pek. Instalasi Main Drain sp 1153 1,00 bh 1.350.000,00 1.350.000,00
6 Pek. Instalasi Inlet 2,00 bh 250.000,00 500.000,00
7 Pek. Instalasi Lampu Kolam 2,00 bh 900.000,00 1.800.000,00
8 Pek. Instalasi Skimer 1,00 bh 1.475.000,00 1.475.000,00
9 Pek. Instalasi pump1/2 hp ex hayward swimpro 1,00 bh 3.350.000,00 3.350.000,00
10 Pek. Instalasi Filter ex hayward swimpro 1,00 bh 4.450.000,00 4.450.000,00
11 Pek. Instalasi travo local 100w/12volt 2,00 bh 540.000,00 1.080.000,00
12 instal item main poolequipment (poin 1,2 dan 3) 1,00 set 2.500.000,00 2.500.000,00
13 Alat Vacum 1,00 set 1.850.000,00 1.850.000,00

sub total K 84.969.752,01


L PEKERJAAN ATAP
1 pas. Batako Leher Atap 31,87 m2 110.500,00 3.521.635,00
2 Pek. Plester Leher Atap 31,87 m2 55.500,00 1.768.785,00
3 Pek. Aci Leher Atap 31,87 m2 37.040,00 1.180.464,80
4 Pek. Cat Leher Atap 31,87 m2 36.680,00 1.168.991,60
5 Pas. Rangka atap Baja Ringan C7 66,25 m2 215.000,00 14.243.750,00
6 Pas. Papan Listplank 36,67 m' 137.520,00 5.042.858,40
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
7 Pas. Genteng Beton Minier 84,50 m2 168.762,00 14.260.389,00
8 Pas. Bubungan Duko 22,50 m' 139.900,00 3.147.750,00

sub total L 44.334.623,80


M PEKERJAAN ANGKUL - ANGKUL & PAGAR
Angkul - Angkul
1 Galian tanah 0,15 m3 105.579,00 15.836,85
2 Pekerjaan beton 0,22 m3 7.450.000,00 1.639.000,00
3 Pek. Plester Aci Beton 6,72 m2 95.000,00 638.400,00
4 Pek. Cat 6,72 m2 47.440,00 318.796,80
5 Pasangan Pintu Kayu Bingkirai 1,00 set 10.500.000,00 10.500.000,00

Pagar
1 Galian tanah 2,44 m3 105.579,00 257.612,76
2 Urugan Pasir bawah Pondasi 0,15 m3 286.543,00 42.981,45
3 Pas. Batu Kosong 0,61 m3 477.751,80 291.428,60
4 Pas. Batu Kali 1,37 m3 779.275,00 1.067.606,75
5 Beton sloof Praktis 15/20 5,09 m' 94.800,00 482.532,00
6 Beton Kolom Praktis 15/20 7,00 m' 94.800,00 663.600,00
7 Beton Ring Praktis 15/20 5,09 m' 94.800,00 482.532,00
8 Pasangan Batako 12,22 m2 110.500,00 1.350.310,00
9 Pekerjaan Plesteran 24,44 m2 55.500,00 1.356.420,00
10 Pekerjaan Acian 24,44 m2 37.040,00 905.257,60
11 Pekerjaan Cat 24,44 m2 47.440,00 1.159.433,60

sub total M 21.171.748,41


N PEKERJAAN SUPLAY AIR DAN TOWER
1 Sumur Bor Casing Pipa 4" Dalam 60 m 1,00 set 6.000.000,00 6.000.000,00
2 Mesin SumersibleYork 3/4 Hp 1,00 unit 2.650.000,00 2.650.000,00
3 pipa 1" 10,00 bt 50.000,00 500.000,00
4 Tower Air PVC 1000 Liter 1,00 unit 4.200.000,00 4.200.000,00
5 Mesin Pendorong Simitsu 1,00 set 1.500.000,00 1.500.000,00
6 Pengadaan listrik PLN daya 5500 1,00 unit 6.500.000,00 6.500.000,00
sub total N 21.350.000,00

TOTAL PEKERJAAN 699.917.563,37


DIBULATKAN 699.910.000,00
RENCANA ANGGARAN BIAYA PROYEK

PROJEK : COFFE SHOP & JALAN


LOKASI : BALI
PEMILIK : BAPAK ALEK

UNIT PRICE TOTAL


NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1,00 ls 1.500.000,00 1.500.000,00
2 Uetset Lokasi Pengukuran Elevasi 1,00 ls 2.500.000,00 2.500.000,00
3 Pas. Bowplank 27,50 m' 57.500,00 1.581.250,00
sub total A 5.581.250,00
B PEKERJAAN GALIAN & PASIR
1 Galian Tanah ( Pondasi Foot Plat ) 5,10 m3 105.579,00 538.030,58
2 Galian Tanah ( Pondasi Menerus ) dan pondasi praktis 21,60 m3 105.579,00 2.916.000,00
3 Urugan Pasir Bawah Pondasi Foot Plat 0,20 m2 286.543,00 123.250,00
4 Urugan Pasir Bawah Pondasi Menerus 1,35 m3 286.543,00 573.750,00
5 Urugan Pasir Di bawah Lantai 2,64 m3 286.543,00 1.122.000,00
sub total B 5.273.030,58
C PEKRJAAN PONDASI & URUGAN LANATI
1 Pas. Batu Kosong dari Batu kali 3,98 m3 477.751,80 2.571.750,00
2 Pas. Pondasi Batu kali 16,96 m3 779.275,00 13.216.504,00
3 urugan tanah kembali 6,48 m3 45.700,00 296.136,00
4 Urugan Tanah Peninggi Lantai 13,20 m3 61.905,00 817.146,00
5 Wiremesh m5 49,50 m2 55.250,00 2.734.875,00
6 Rabat Lantai 3,69 m3 833.630,00 3.076.094,70
sub total C 22.712.505,70
D PEKRJAAN STRUKTUR BETON INCLUDE BEGESTING
Pondasi
1 Pek. Beton Rabat 5 cm lantai kerja Foot Plat 0,20 m3 833.630,00 163.391,48
2 Pek. Beton Foot Plat P1
- Besi Beton 63,59 kg 17.106,67 1.087.847,77
- Beton Mutu 0,98 m3 1.159.004,20 1.135.824,11
- Bekisting 2x Pakai 5,60 m2 142.603,00 798.576,80
Struktur Lantai I
1 Beton Sloof S1 20/30
- Besi Beton 305,21 kg 17.106,67 5.221.159,05
- Beton Mutu 2,70 m3 1.159.004,20 3.129.311,34
- Bekisting 2x Pakai 27,00 m2 193.921,20 5.235.872,40
2 Beton Sloof 15/25
- Besi Beton 30,47 kg 17.106,67 521.191,21
- Beton Mutu 0,30 m3 1.159.004,20 347.701,26
- Bekisting 2x Pakai 4,00 m2 193.921,20 775.684,80
3 Beton Kolom K1 30/30
- Besi Beton 245,44 kg 17.106,67 4.198.694,72
- Beton Mutu 1,62 m3 1.159.004,20 1.877.586,80
- Bekisting 2x Pakai 32,40 m2 240.110,00 7.779.564,00
Struktur Lantai Atap
1 Beton Ring Balok B1 20/30
- Besi Beton 303,60 kg 17.106,67 5.193.645,96
- Beton Mutu 2,70 m3 1.159.004,20 3.129.311,34
- Bekisting 2x Pakai 25,20 m2 246.670,00 6.216.084,00
2 Beton Ring Balok Ba 15/25
- Besi Beton 36,90 kg 17.106,67 631.246,94
- Beton Mutu 0,30 m3 1.159.004,20 347.701,26
- Bekisting 2x Pakai 3,60 m2 246.670,00 888.012,00
3 Beton Plat Topian 8 cm
- Besi Beton 65,25 kg 17.106,67 1.116.216,38
- Beton Mutu 0,80 m3 1.159.004,20 927.203,36
- Bekisting 2x Pakai 10,00 m2 267.710,00 2.677.100,00
4 Beton Plat Atap 10 cm
- Besi Beton 292,96 kg 17.106,67 5.011.583,73
- Beton Mutu 4,95 m3 1.159.004,20 5.737.070,78
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
- Bekisting 2x Pakai 49,50 m2 267.710,00 13.251.645,00
5 Pekerjaan Waterprofing Lantai atap + rabat 59,50 m2 85.000,00 5.057.500,00
sub total D 82.456.726,48
E PEKERJAAN PLAFOND
1 Pek. Pemasngan Plafond Gypsum 9mm dengan Rangka Holow 49,50 m2 98.000,00 4.851.000,00
2 Pekerjaan Sedowline plafond 72,10 m' 25.750,00 1.856.575,00
3 Pekerjaan Cat plafond 49,50 m2 42.000,00 2.079.000,00
4 Pek. Plestr aci Plat Atap topi 18,60 m' 94.800,00 1.763.280,00
5 Pek. Cet Plat topi atap 18,60 m' 47.440,00 882.384,00
Sub Total E 11.432.239,00
F PEKERJAAN DINDING
1 Pas. Batako 130,18 m2 110.500,00 14.384.890,00
2 Pek. Beton Kolom Praktis & Ring Praktis 27,50 m' 94.800,00 2.607.000,00
3 Pek. Plesteran Dinding 243,84 m2 55.500,00 13.533.120,00
4 Pek. Acian Dinding 243,84 m2 37.040,00 9.031.833,60
5 Pek. Cat Dinding Dalam 147,59 m2 36.680,00 5.413.601,20
6 Pek. Cat Dinding Luar 96,25 m2 47.440,00 4.566.100,00
Sub Total F 49.536.544,80
G PEKERJAAN KERAMIK DINDING & LANTAI
1 Pek. Keramik Lantai Kamar Mandi 40x40 asia Tile @90.000 2,70 m2 225.810,00 609.687,00
2 Pek. Keramik Dinding Kamar Mandi Tinggi 280, asia tile 20x40 cm @125.000 16,52 m2 263.340,00 4.350.376,80
3 Pek. Granit Lantai 60x60, Setara DBS @165.000 46,80 m2 305.800,00 14.311.440,00
4 Plin Keramik 10 cm 37,70 m' 36.307,90 1.368.807,83
Sub Total G 20.640.311,63

H PEKERJAAN PINTU
1 Pas. Pintu Toilet Kayu Kelas II 80x240 cm, 1,00 unit 2.417.404,00 2.417.404,00
2 Pas. Pintu Kayu Kelas II 90x240 cm, 2,00 unit 2.197.640,00 4.395.280,00
3 Kunci Biasa 1,00 bh 165.850,00 165.850,00
4 Kunci Km/Wc 2,00 bh 185.120,00 370.240,00
5 Engsel Pintu 4,00 bh 67.935,00 271.740,00
6 Handle Pintu 1,00 bh 213.050,00 213.050,00
7 pas. Kaca mati 5 mm 2,00 unit 150.000,00 300.000,00
Sub Total H 8.133.564,00

I PEKERJAAN LISTRIK
1 Pek. Instalasi Lampu Plafond Kabel 2*1.5 mm 17,00 ttk 225.000,00 3.825.000,00
2 Pek. Instalasi Stop Kontak Kabel 3*2.5 mm 8,00 ttk 245.000,00 1.960.000,00
3 Pas. Lampu downlight 18,00 ttk 75.000,00 1.350.000,00
4 Pas. Saklar Tunggal 5,00 bh 42.000,00 210.000,00
5 Pas. Saklar doble 2,00 bh 42.000,00 84.000,00
6 Pas. Stop Kontak doble 7,00 bh 45.000,00 315.000,00
7 Pas. Kipas angin 2,00 bh 2.500.000,00 5.000.000,00
8 Pas. Stop Kontak single 2,00 bh 45.000,00 90.000,00
9 MCB 4 Group 1,00 unit 1.200.000,00 1.200.000,00
10 Pas. Kabel Fider 3x6 mm 5,00 m' 65.000,00 325.000,00
sub total I 14.359.000,00

J PEKERJAAN PLUMBING
1 Pas. Pipa PVC 4" Saluran Kloset 13,00 m' 95.000,00 1.235.000,00
2 Pas Pipa saluran floordrain PVC 3" 13,00 m' 78.000,00 1.014.000,00
3 Pas. Pipa PVC 1" saluran air bersih 36,00 m' 42.500,00 1.530.000,00
4 Pas. Pipa PVC 3/4" Saluran Air Bersih 6,00 m' 36.500,00 219.000,00
5 Pas. Pipa PVC 3" Air Hujan 36,00 m' 78.000,00 2.808.000,00
Sanitary
6 Pas. Kloset Duduk 1,00 bh 2.700.000,00 2.700.000,00
7 Pas. Floor Drain Onda 1,00 set 125.000,00 125.000,00
8 Pas. Wastafel 1,00 set 1.670.050,00 1.670.050,00
9 Septiktank bio 1000 liter 1,00 unit 5.500.000,00 5.500.000,00
10 Resapan Buis Beton D80 3 unit 1,00 set 3.000.000,00 3.000.000,00
sub total J 19.801.050,00
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
K PEKERJAAN PAGAR
Pagar
1 Galian tanah 16,69 m3 105.579,00 1.762.113,51
2 Urugan Pasir bawah Pondasi 1,04 m3 286.543,00 298.004,72
3 Pas. Batu Kosong 3,13 m3 477.751,80 1.495.363,13
4 Pas. Batu Kali 15,65 m3 779.275,00 12.195.653,75
5 Beton sloof Praktis 15/20 41,79 m' 94.800,00 3.961.692,00
6 Beton Kolom Praktis 15/20 22,00 m' 94.800,00 2.085.600,00
7 Beton Ring Praktis 15/20 41,79 m' 94.800,00 3.961.692,00
8 Pasangan Batako 83,48 m2 110.500,00 9.224.540,00
9 Pekerjaan Plesteran 166,96 m2 55.500,00 9.266.280,00
10 Pekerjaan Acian 166,96 m2 37.040,00 6.184.198,40
11 Pekerjaan Cat 166,96 m2 47.440,00 7.920.582,40
sub total K 58.355.719,91
L PEKERJAAN JALAN, GOT PEMBUANGAN GERBANG
Jalan
1 Urugan Pasir dan Pemadatan 15,00 m3 286.543,00 4.298.145,00
2 Pasangan Paving 300,00 m2 181.905,00 54.571.500,00
3 Kuncian Paving 136,41 m' 43.000,00 5.865.630,00
Got Pembuangan
1 Galian Tanah 11,59 m3 105.579,00 1.223.660,61
2 Pasangan Pipa 8'' 77,30 m' 485.000,00 37.490.500,00
3 Pek bak Kontrol + tutup Besi 10,00 unit 755.000,00 7.550.000,00
Gerbang
1 Galian Tanah 0,38 m3 105.579,00 40.120,02
2 Rabatan 0,20 m3 125.000,00 25.000,00
3 Pas. Batako 11,52 m2 110.500,00 1.272.960,00
4 Beton tutup atas 0,36 m3 975.000,00 351.000,00
5 Pekerjaan Plesteran 8,79 m2 55.500,00 487.845,00
6 Pekerjaan Acian 8,79 m2 37.040,00 325.581,60
7 Pekerjaan Cat 8,79 m2 47.440,00 416.997,60
8 Pintu Gerbang set

sub total L 113.918.939,83

TOTAL PEKERJAAN 412.200.881,94


DIBULATKAN 412.200.000,00

Anda mungkin juga menyukai