F PEKERJAAN DINDING
1 Pas. Batako 222,00 m2 110.500,00 24.531.000,00
2 Pek. Beton Kolom Praktis & Ring Praktis 41,60 m' 94.800,00 3.943.680,00
3 Pek. Plesteran Dinding 324,00 m2 55.500,00 17.982.000,00
4 Pek. Acian Dinding 324,00 m2 37.040,00 12.000.960,00
5 Pek. Cat Dinding Dalam 176,00 m2 36.680,00 6.455.680,00
6 Pek. Cat Dinding Luar 148,00 m2 47.440,00 7.021.120,00
Sub Total F 71.934.440,00
G PEKERJAAN KERAMIK DINDING & LANTAI
1 Pek. Keramik Lantai Kamar Mandi 40x40 asia Tile @90.000 20,09 m2 225.810,00 4.536.522,90
2 Pek. Keramik Dinding Kamar Mandi , asia tile 20x40 cm @125.000 78,43 m2 263.340,00 20.653.756,20
3 Pek. Granit Lantai Kamar 60x60, Setara DBS @165.000 38,55 m2 305.800,00 11.788.590,00
4 Pek. Granit Lantai sunken 60x60, Setara DBS @165.000 16,80 m2 305.800,00 5.137.440,00
5 Pek. Granit Lantai kitchen, dining room 60x60, Setara DBS @165.000 35,46 m2 305.800,00 10.843.668,00
6 Plin Keramik 10 cm 87,02 m' 36.307,90 3.159.513,46
7 Pek. Batu Palimanan teras 20x40 18,84 m2 403.544,67 7.602.781,52
Sub Total G 63.722.272,08
I PEKERJAAN LISTRIK
1 Pek. Instalasi Lampu Plafond Kabel 2*1.5 mm 37,00 ttk 225.000,00 8.325.000,00
2 Pek. Instalasi Stop Kontak Kabel 3*2.5 mm 23,00 ttk 245.000,00 5.635.000,00
3 Pas. Lampu downlight 37,00 ttk 75.000,00 2.775.000,00
4 Pas. Saklar Tunggal 4,00 bh 42.000,00 168.000,00
5 Pas. Saklar tukar 2,00 bh 55.000,00 110.000,00
6 Pas. Saklar doble 3,00 bh 42.000,00 126.000,00
7 Pas. Stop Kontak doble 7,00 bh 45.000,00 315.000,00
8 Pas. Stop Kontak lantai 1,00 bh 450.000,00 450.000,00
9 Pas. Stop Kontak meja 1,00 bh 450.000,00 450.000,00
10 Pas. Stop Kontak single 10,00 bh 45.000,00 450.000,00
11 Pas. Stop Kontak TV 3,00 bh 45.000,00 135.000,00
12 Pas. Stop Kontak Data 3,00 bh 45.000,00 135.000,00
13 Pas. Stop Kontak AC 3,00 bh 45.000,00 135.000,00
14 kipas Angin 1,00 bh 2.500.000,00 2.500.000,00
15 MCB 8 Group 1,00 unit 1.200.000,00 1.200.000,00
16 Pas. Kabel Fider 3x6 mm 15,00 m' 65.000,00 975.000,00
sub total I 23.884.000,00
J PEKERJAAN PLUMBING
1 Pas. Pipa PVC 4" Saluran Kloset 33,13 m' 95.000,00 3.147.350,00
2 Pas Pipa saluran floordrain PVC 3" 46,68 m' 78.000,00 3.641.040,00
3 Pas. Pipa PVC 1" saluran air bersih 46,43 m' 42.500,00 1.973.275,00
4 Pas. Pipa PVC 3/4" Saluran Air Bersih 39,00 m' 36.500,00 1.423.500,00
5 Pas. Pip PVC 3/4" saluan pembuangan AC 18,00 m' 36.500,00 657.000,00
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
6 Pas. Pipa PVC 3" Air Hujan 53,86 m' 78.000,00 4.201.080,00
7 Pipa Air Panas PPR DN20 15,00 m' 85.000,00 1.275.000,00
Sanitary
8 Pas. Kloset Duduk american standar 3,00 bh 2.700.000,00 8.100.000,00
9 Pas. Jet Shower + Kran T 3,00 set 225.000,00 675.000,00
10 Pas. Floor Drain Onda 6,00 set 125.000,00 750.000,00
11 Pas. Shower ex. Washer 3,00 set 2.950.000,00 8.850.000,00
12 Pas. Wastafel 2,00 set 1.670.050,00 3.340.100,00
13 Pas. Bathtub 2,00 set 4.250.000,00 8.500.000,00
14 Kran bactube 2,00 set 5.000.000,00 10.000.000,00
15 Septiktank bio 1000 liter 1,00 unit 5.500.000,00 5.500.000,00
16 Resapan Buis Beton D80 3 unit 1,00 set 3.000.000,00 3.000.000,00
17 Pemanas Air Ariston 80 Liter 2,00 set 4.850.000,00 9.700.000,00
18 AC SHARP 1PK dan instalasi pipa 2,00 unit 4.750.000,00 9.500.000,00
Pagar
1 Galian tanah 2,44 m3 105.579,00 257.612,76
2 Urugan Pasir bawah Pondasi 0,15 m3 286.543,00 42.981,45
3 Pas. Batu Kosong 0,61 m3 477.751,80 291.428,60
4 Pas. Batu Kali 1,37 m3 779.275,00 1.067.606,75
5 Beton sloof Praktis 15/20 5,09 m' 94.800,00 482.532,00
6 Beton Kolom Praktis 15/20 7,00 m' 94.800,00 663.600,00
7 Beton Ring Praktis 15/20 5,09 m' 94.800,00 482.532,00
8 Pasangan Batako 12,22 m2 110.500,00 1.350.310,00
9 Pekerjaan Plesteran 24,44 m2 55.500,00 1.356.420,00
10 Pekerjaan Acian 24,44 m2 37.040,00 905.257,60
11 Pekerjaan Cat 24,44 m2 47.440,00 1.159.433,60
H PEKERJAAN PINTU
1 Pas. Pintu Toilet Kayu Kelas II 80x240 cm, 1,00 unit 2.417.404,00 2.417.404,00
2 Pas. Pintu Kayu Kelas II 90x240 cm, 2,00 unit 2.197.640,00 4.395.280,00
3 Kunci Biasa 1,00 bh 165.850,00 165.850,00
4 Kunci Km/Wc 2,00 bh 185.120,00 370.240,00
5 Engsel Pintu 4,00 bh 67.935,00 271.740,00
6 Handle Pintu 1,00 bh 213.050,00 213.050,00
7 pas. Kaca mati 5 mm 2,00 unit 150.000,00 300.000,00
Sub Total H 8.133.564,00
I PEKERJAAN LISTRIK
1 Pek. Instalasi Lampu Plafond Kabel 2*1.5 mm 17,00 ttk 225.000,00 3.825.000,00
2 Pek. Instalasi Stop Kontak Kabel 3*2.5 mm 8,00 ttk 245.000,00 1.960.000,00
3 Pas. Lampu downlight 18,00 ttk 75.000,00 1.350.000,00
4 Pas. Saklar Tunggal 5,00 bh 42.000,00 210.000,00
5 Pas. Saklar doble 2,00 bh 42.000,00 84.000,00
6 Pas. Stop Kontak doble 7,00 bh 45.000,00 315.000,00
7 Pas. Kipas angin 2,00 bh 2.500.000,00 5.000.000,00
8 Pas. Stop Kontak single 2,00 bh 45.000,00 90.000,00
9 MCB 4 Group 1,00 unit 1.200.000,00 1.200.000,00
10 Pas. Kabel Fider 3x6 mm 5,00 m' 65.000,00 325.000,00
sub total I 14.359.000,00
J PEKERJAAN PLUMBING
1 Pas. Pipa PVC 4" Saluran Kloset 13,00 m' 95.000,00 1.235.000,00
2 Pas Pipa saluran floordrain PVC 3" 13,00 m' 78.000,00 1.014.000,00
3 Pas. Pipa PVC 1" saluran air bersih 36,00 m' 42.500,00 1.530.000,00
4 Pas. Pipa PVC 3/4" Saluran Air Bersih 6,00 m' 36.500,00 219.000,00
5 Pas. Pipa PVC 3" Air Hujan 36,00 m' 78.000,00 2.808.000,00
Sanitary
6 Pas. Kloset Duduk 1,00 bh 2.700.000,00 2.700.000,00
7 Pas. Floor Drain Onda 1,00 set 125.000,00 125.000,00
8 Pas. Wastafel 1,00 set 1.670.050,00 1.670.050,00
9 Septiktank bio 1000 liter 1,00 unit 5.500.000,00 5.500.000,00
10 Resapan Buis Beton D80 3 unit 1,00 set 3.000.000,00 3.000.000,00
sub total J 19.801.050,00
UNIT PRICE TOTAL
NO. URAIAN PEKERJAAN VOLUME UNIT PRICE
( Rp ) ( Rp )
K PEKERJAAN PAGAR
Pagar
1 Galian tanah 16,69 m3 105.579,00 1.762.113,51
2 Urugan Pasir bawah Pondasi 1,04 m3 286.543,00 298.004,72
3 Pas. Batu Kosong 3,13 m3 477.751,80 1.495.363,13
4 Pas. Batu Kali 15,65 m3 779.275,00 12.195.653,75
5 Beton sloof Praktis 15/20 41,79 m' 94.800,00 3.961.692,00
6 Beton Kolom Praktis 15/20 22,00 m' 94.800,00 2.085.600,00
7 Beton Ring Praktis 15/20 41,79 m' 94.800,00 3.961.692,00
8 Pasangan Batako 83,48 m2 110.500,00 9.224.540,00
9 Pekerjaan Plesteran 166,96 m2 55.500,00 9.266.280,00
10 Pekerjaan Acian 166,96 m2 37.040,00 6.184.198,40
11 Pekerjaan Cat 166,96 m2 47.440,00 7.920.582,40
sub total K 58.355.719,91
L PEKERJAAN JALAN, GOT PEMBUANGAN GERBANG
Jalan
1 Urugan Pasir dan Pemadatan 15,00 m3 286.543,00 4.298.145,00
2 Pasangan Paving 300,00 m2 181.905,00 54.571.500,00
3 Kuncian Paving 136,41 m' 43.000,00 5.865.630,00
Got Pembuangan
1 Galian Tanah 11,59 m3 105.579,00 1.223.660,61
2 Pasangan Pipa 8'' 77,30 m' 485.000,00 37.490.500,00
3 Pek bak Kontrol + tutup Besi 10,00 unit 755.000,00 7.550.000,00
Gerbang
1 Galian Tanah 0,38 m3 105.579,00 40.120,02
2 Rabatan 0,20 m3 125.000,00 25.000,00
3 Pas. Batako 11,52 m2 110.500,00 1.272.960,00
4 Beton tutup atas 0,36 m3 975.000,00 351.000,00
5 Pekerjaan Plesteran 8,79 m2 55.500,00 487.845,00
6 Pekerjaan Acian 8,79 m2 37.040,00 325.581,60
7 Pekerjaan Cat 8,79 m2 47.440,00 416.997,60
8 Pintu Gerbang set