Pekerjaan :
Lokasi :
LANTAI -2
A PEKERJAAN PERSIAPAN
1 Pembongkaran dinding m2 225.70 15,000.00 3,385,500.00
2 Pembongkaran Atap m2 112.00 15,000.00 1,680,000.00
3 Bongkar Tangga Ls 1.00 500,000.00 500,000.00
4 Buang Hasil Bongkaran Ls 1.00 1,500,000.00 1,500,000.00
JUMLAH I 7,065,500.00
B PEKERJAAN TANAH
1 Galian Tanah Pondasi m³ 21.60 78,700.00 1,699,920.00
2 Urugan Kembali m³ 5.40 57,500.00 310,500.00
3 Urugan Tanah m³ 22.40 166,700.00 3,734,080.00
JUMLAH I 5,744,500.00
5 Pekerjaan Balok 20 x 30
Beton K.225 m3 5.45 1,126,400.00 6,136,627.20
Pembesian Polos Kg 877.13 11,200.00 9,823,833.60
Begesting m2 50.85 165,000.00 8,389,920.00
6 Pekerjaan Balok 15 x 25
Beton K.225 m3 1.28 1,126,400.00 1,436,160.00
Pembesian Polos Kg 170.85 11,200.00 1,913,520.00
Begesting m2 13.94 165,000.00 2,300,100.00
6 Balok Tangga
Beton K.225 m3 0.12 1,126,400.00 135,168.00
Pembesian Polos Kg 16.08 11,200.00 180,096.00
Begesting 2 x Pakai m2 1.60 198,000.00 316,800.00
JUMLAH 109,446,776.34
RENCANA ANGGARAN BIAYA ( RAB )
JUMLAH 58,587,340.00
G PEKERJAAN SANITAIR
1 Kloset duduk Ex Toto / America Standart unit 1.00 2,500,000.00 2,500,000.00
2 Floor drain stainlees Steel bh 1.00 277,300.00 277,300.00
3 Kran air, setara toto bh 3.00 413,000.00 1,239,000.00
4 Septictank + resapan Unit 1.00 3,500,000.00 3,500,000.00
JUMLAH 7,516,300.00
H PEKERJAAN PENGECATAN
1 Cat dinding dalam m²
DIKERJAKAN TAHAP 2
2 Cat Dinding Luar m²
3 Cat Plafond m² 95.50 26,100.00 2,492,550.00
JUMLAH 2,492,550.00
I PEKERJAAN PENERANGAN
1 Exhaust Fan unit 1.00 485,000.00 485,000.00
2 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC Cond. 20 mm unit 22.00 220,000.00 4,840,000.00
3 Saklar Tunggal bh 5.00 37,300.00 186,500.00
4 Saklar Ganda bh 11.00 43,300.00 476,300.00
5 Stop Kontak bh 12.00 40,500.00 486,000.00
6 Inst. Stop Kontak NYM 3 x 2,5 mm2 + PVC Cond. 20 mm bh 12.00 250,000.00 3,000,000.00
JUMLAH 9,473,800.00
RENCANA ANGGARAN BIAYA ( RAB )
6 Pekerjaan Balok 15 x 25
Beton K.225 m3 2.63 1,126,400.00 2,956,800.00
Pembesian Polos Kg 351.75 11,200.00 3,939,600.00
Begesting m2 45.50 165,000.00 7,507,500.00
51,000,056.80
K PEKERJAAN ATAP
35,619,640.00
D PEKERJAAN PASANGAN DAN PLESTERAN lt.2
1 Pasangan dinding (Bata Merah) 1PC : 5Ps m² 248.15 117,800.00 29,232,070.00
2 Plesteran dinding bata m² 488.30 83,000.00 40,528,900.00
3 Acian m² 488.30 39,900.00 19,483,170.00
4 Benangan m' 393.08 21,100.00 8,293,988.00
27 Pengecatan 1 m² tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) interior
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.0063 140,000.00 882.00
Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 11,522.00
B BAHAN
Plamuur Kg 0.100 30,000.00 3,000.00
Cat dasar Kg 0.100 50,200.00 5,020.00
Cat penutup Kg 0.260 25,600.00 6,656.00
JUMLAH HARGA BAHAN 14,676.00
C PERALATAN
45 Pemasangan 1 m² dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 5PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 100,000.00 30,000.00
Tukang batu L.02 OH 0.100 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,650.00
B BAHAN
Bata merah bh 70.000 650.00 45,500.00
Semen Portland Kg 9.680 1,325.00 12,826.00
pasir pasang m³ 0.045 285,000.00 12,825.00
JUMLAH HARGA BAHAN 71,151.00
C PERALATAN
54 Pengurugan 1 m³ Pudel
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 100,000.00 25,000.00
Mandor L.04 OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 28,750.00
B BAHAN
sirtu m³ 1.200 115,000.00 138,000.00
JUMLAH HARGA BAHAN 138,000.00
C PERALATAN
Membuat 1 m³ beton mutu f' = 19,3 MPac (K 225), slump (12 ••2) cm, w/c = 0,58
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
Mandor L.04 OH 0.083 150,000.00 12,450.00
JUMLAH TENAGA KERJA 217,120.00
B BAHAN
Semen Portland Kg 371.000 1,325.00 491,575.00
Pasir Beton m³ 0.498 325,000.00 161,850.00
Kerikil (Maks 30mm) m³ 0.722 350,000.00 252,700.00
Air Liter 215 15.00 3,225.00
JUMLAH HARGA BAHAN 909,350.00
C PERALATAN
66 Pemasangan 1 m2 Paving
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 100,000.00 25,000.00
Tukang Batu L.02 OH 0.500 130,000.00 65,000.00
Kepala tukang L.03 OH 0.025 140,000.00 3,500.00
Mandor L.04 OH 0.001 150,000.00 195.00
JUMLAH TENAGA KERJA 93,695.00
B BAHAN
Paving conblok tebal 8cm m2 1.010 90,000.00 90,900.00
Pasir Pasang m3 0.05 285,000.00 14,250.00
JUMLAH HARGA BAHAN 105,150.00
C PERALATAN
67 Pengecatan 1 m² zincromate
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.02 100,000.00 2,000.00
Tukang cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.0063 140,000.00 882.00
Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 11,522.00
B BAHAN
Cat dasar/zincromate 1x Kg 0.100 40,000.00 4,000.00
77 1 m2 ,Pemasangan panggung rangka hollow besi 50.50.1,7 lapis Kalsifloor 20mm , ( Tribun )
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 100,000.00 20,000.00
Tukang batu L.03 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 43,850.00
B BAHAN
Hollow besi 50.50.1,7mm m' 21.420 37,500.00 803,250.00
Kalsifloor 20mm lbr 0.364 598,000.00 217,672.00
Elektroda baja 1.000 16,065.00 16,065.00
Sekrup bh 20.000 100.00 2,000.00
Pengecatan Zincromate m2 4.284 15,522.00 66,496.25
JUMLAH HARGA BAHAN 1,105,483.25
C PERALATAN
Pasang ACP rangka hollow (background Cipta Indra Cakti Dharma) 767,900.00
80 Pemasangan 1 m² atap genteng Glasur
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 100,000.00 15,000.00
Tukang kayu L.03 OH 0.075 130,000.00 9,750.00
Kepala Tukang L.11 OH 0.008 140,000.00 1,120.00
Mandor L.15 OH 0.008 150,000.00 1,200.00
JUMLAH TENAGA KERJA 27,070.00
B BAHAN
Genteng Glazur Bh 14.00 15,000.00 210,000.00
JUMLAH HARGA BAHAN 210,000.00
C PERALATAN
86 1m2 pekerjaan cutting plat galvanis 1,6mm (ornamen Batik) + finishing cat duco
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A BAHAN
Cutting plat galvanis t.1,6mm m2 1.00 2,250,000.00 2,250,000.00
(Ornamen Batik termasuk rangka dan
Pemasangan, Finish Cat Duco
Kebutuhan Scafolding
= 56 set
Kebutuhan Scafolding
No. Nama Barang Standar Satuan Spesifikasi Standar Harga Satuan (Rp) Ket.
1 2 3 4 5 6
I BAHAN PASIR
1 ~ Tanah Urug ( Lokal ) m3 Lokal 200,000.00
2 ~ Pasir Pasang ( Lokal ) m3 Lokal 250,000.00
3 ~ Pasir Pasang ( Jawa Halus ) m3 Jawa 325,000.00
4 ~ Pasir Pasang (Sedang) m3 285,000.00
5 ~ Pasir Beton (Kasar) m3 325,000.00
6 ~ Pasir Urug (Lokal) m3 200,000.00
7 ~ Sirtu ( Jawa ) m3 Jawa 280,000.00
8 ~ Pudel ( Lokal ) Kuning m3 Lokal 70,000.00
9 ~ Pudel ( Lokal ) Putih m3 Lokal 115,000.00
10 ~ Abu Batu m3 - 350,000.00
11 Tanah Taman / tanah humus m3 200,000.00
II BAHAN BATU
1 ~ Batu Gunung Belah 15/20 ( Lokal ) m3 15/20 (Lokal) 175,000.00
V PORTLAND CEMENT ( PC )
1 ~ Semen Gresik 40 Kg Zak 40 Kg 53,000.00
2 ~ Semen Gresik 40 Kg 1 Kg 1,325.00
3 ~ Semen Instan Perekat (Ex.Prime Mortar) 40 Kg Zak 65,000.00
4 ~ Semen Instan Plesteran (Ex.Prime Mortar) 40 Kg Zak 70,000.00
5 ~ Semen Instan Acian (Ex.Prime Mortar) 40 Kg Zak 80,000.00
6 ~ Semen Instan Nat Kg 18,500.00
7 ~ Coumpon Join Kg 4,900.00
X BAHAN KAYU
1 ~ Kayu Kamper Balok 4,00 m Klas I m3 Balok 4,00 M Klas I 9,000,000.00
2 ~ Kayu Papan Begesting 2 / 20 X 4,00 m' m 3
Uk.2/20x4,00 M' 1,250,000.00
3 ~ Kayu kelas III m3 1,500,000.00
4 ~ Kayu kelapa Btg 2,200,000.00
5 ~ Kayu Untuk Perancah m3 2,000,000.00
6 ~ Kayu Dolken Btg 18,000.00
7 ~ Kayu Kamper 4/6 m1 21,600.00
8 ~ bingkai profil Kayu 10cm m1 115,000.00
XVIII SANITAIR
1 ~ Closed Jongkok Keramik ( Ex.Ina) Bh 175,000.00
2 ~ Closed Jongkok Keramik ( Ex. toto) Bh 404,000.00
3 ~ Kraan Air 3/4 Bh 3/4' crom 65,000.00
4 ~ Kraan Air 1/2 Steinleessteel Bh 1/2 Stenlistteel 300,000.00
5 ~ Floor Drain stainlessteel toto Bh stainlessteel 225,000.00
6 ~ Jetshower bh 250,000.00
7 ~ Handhower bh 1,500,000.00
PEKERJAAN :
ARS DAN SIPIL PEMBANGUNAN GEDUNG DPRD
KAB. BANGKALAN (LANJUTAN)
TAHUN 2020
LOKASI :
KABUPATEN BANGKALAN
KONSULTAN PERENCANA