Anda di halaman 1dari 2

RINCIAN ANGGARAN BIAYA

PASAR SAYUR
DEMOLENG KETANGGUNGAN BREBES

SATU VOLU JUMLAH HARGA


NO URAIAN PEKERJAAN AN ME HARGA SATUAN TOTAL TOTAL
(Rp) (Rp) (Rp)
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Bedeng Pekerja + MCK 3x6 m m2 18,00 1.116.373,00 20.094.714,00
2 Pasang Bouwplank m1 186,00 33.004,67 6.138.868,00
3 Pembersihan Lahan m2 798,00 13.875,00 11.072.250,00
4 Pengadaan Listrik kerja Ls Owner -
5 Pengadaan Air Kerja Ls Owner -
Sub Total I (Rp.) 37.305.832,00 37.305.832,00
II PEKERJAAN GALIAN & URUGAN
1 Galian Tanah m3 40,90 85.312,50 3.489.110,63
2 Urugan Pasir Bawah Podasi t=5cm m3 1,57 243.351,00 382.791,12
3 Urugan Pasir Bawah Lantai t=5cm m3 35,00 240.913,50 8.431.972,50
4 Urugan Tanah Peninggian Bangunan m3 378,00 50.000,00 18.900.000,00
Sub Total II (Rp.) 31.203.874,25 31.203.874,25
III PEKERJAAN PONDASI
1 Pek. Kolom Pedestal 300x300
Besi Beton Tul. Utama 8-Ø 13 Kg 475,00 12.743,50 6.053.162,50
Besi Beton Sengkang Ø 8-15 Kg 156,00 12.743,50 1.987.986,00
Cor Beton K-225 m3 5,00 988.413,01 4.942.065,06

2 Pek. Pondasi Pile Cap 1x1x0,2 cm (26 Titik)


Besi Beton Ø 10 Kg 410,00 12.743,50 5.224.835,00
Begisting dengan papan (3x Pakai) m2 21,00 118.855,00 2.495.955,00
Cor Beton K-225 m3 9,80 954.738,01 9.356.432,52

Sub Total III (Rp.) 30.060.436,09 30.060.436,09


IV PEKERJAAN STRUKTUR
STRUKTUR LANTAI 1
1 Pek. Pas. Kolom + Kuda2 WF 250
- WF 250 Kg 4.970,00 25.000,00 124.250.000,00
- WF 200 Kg 4.352,00 26.000,00 113.152.000,00
- Base Plat Lbr 2,00 557.500,00 1.115.000,00
- Ikatan Angin Kg 400,00 19.000,00 7.600.000,00
- Angkur M16 Bh 168,00 75.000,00 12.600.000,00

2 Pek. Rabat Beton Tb. 10 cm M3 85,00 746.659,80 63.466.083,00


- Besi 6 kg 1.556,00 12.000,00 18.672.000,00

3 Pek. Pas. Sloof 15/20


Besi 100kg/m3 Kg 522,00 12.000,00 6.264.000,00
Cor Beton M3 5,22 746.659,80 3.897.564,16
Begisting m2
Sub Total IV (Rp.) 351.016.647,16 351.016.647,16
V PEKERJAAN DINDING
1 Pek. Pas. Bata Hebel m2 110,00 109.425,00 12.036.750,00

12.036.750,00 12.036.750,00
VI PEKERJAAN LANTAI
1 Pek. Screeding+Aci Floor Hardener m2 700,00 78.958,13 55.270.691,84

Sub Total III (Rp.) 55.270.691,84 55.270.691,84


VII PEKERJAAN PENGECETAN
1 Pek. Cat Luar dan Dalam Partisi Luar Ex. Avian Stara m2 150 23.689,10 3.553.365,00
Pek. Cat Lisplang m2 130 48.467,70 6.300.801,00
Sub Total IX (Rp.) 9.854.166,00 9.854.166,00
VIII PEKERJAAN ATAP
1 Pas. Rangka Atap Canal C 100 m2 1.318,00 23.000,00 30.314.000,00
2 Pek. Pas. Penutup Atap Spandek m2 1.128,00 100.552,50 113.423.220,00
3 Pek. Pas. Nok Atap Spandek m1 94,00 65.018,75 6.111.762,50
4 Pek. Pas. Lisplang m1 225,00 85.000,00 19.125.000,00

Sub Total XI (Rp.) 168.973.982,50 168.973.982,50


SATU VOLU JUMLAH HARGA
NO URAIAN PEKERJAAN AN ME HARGA SATUAN TOTAL TOTAL
(Rp) (Rp) (Rp)
1 2 3 4 5 6 7
IX PEKERJAAN SANITAIR & PLUMBING
A INSTALASI PLUMBING
1 Instalasi Air Hujan PVC. 3" D ex. Union Setara m' 98 50.937,00 4.991.826,00
2 Acesories Pipa m' 98 8.252,40 808.735,20
3 Talang PVC 1/2 l 4' m 188 48.500,00 9.118.000,00
4 Grevel m 0 106.000,00 -
Sub Total IX (Rp.) 14.918.561,20 14.918.561,20
JUMLAH TOTAL I S.D IX Rp. 710.640.941,03 710.640.941,03

NOTE :
1. Item Pekerjaaan yang belum masuk dalam list diatas, akan dimasukan dalam pekerjaaan Addendum setelah pekerjaan berjalan

Brebes, 21 Agustus 2021


Disetujui Oleh: Diajukan Oleh :

............................... NASUTION
Owner