RENCANA ANGGARAN BIAYA

PEKERJAAN FASILITASI PENYUSUNAN RENCANA INDUK SISTEM KEGIATAN

BAK ABR 0

LOKASI KOTA SERANG TAHUN ANGGARAN 2014

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 77.00 52,598.00 4,050,046.00
5 Bambu u/ pekerjaan sementara turap ls 1.00 10,000,000.00 10,000,000.00
JUMLAH A 16,800,046.00
B PEKERJAAN TANAH
1 Galian Tanah (kedalaman > 3m) m3 561.00 107,682.30 60,409,770.30
JUMLAH B 60,409,770.30
C PEKERJAAN PONDASI DAN BETON
1 Urugan Pasir 5cm m3 5.61 114,120.60 640,216.57
2 Lantai Beton t=30cm K-225
- Beton K-225 m3 33.66 1,116,966.11 37,597,079.39
- Tulangan Baja Ulir ( 110 kg/m3) kg 3,702.60 23,014.59 85,213,802.42
- Bekisting Lantai m2 112.20 415,943.55 46,668,866.31
3 Dinding Beton t=30cm K-225
- Beton K-225 m3 95.70 1,116,966.11 106,893,657.08
- Tulangan Baja Ulir ( 110 kg/m3) kg 10,527.00 23,014.59 242,274,536.30
- Bekisting Dinding m2 253.00 415,943.55 105,233,718.15
4 Lantai Dak Beton t=12cm K-225
- Beton K-225 m3 13.46 1,116,966.11 15,038,831.75
- Tulangan Baja Ulir ( 110 kg/m3) kg 1,481.04 23,014.59 34,085,520.97
- Bekisting Lantai m2 112.20 415,943.55 46,668,866.31
5 Tutup Man hole Beton, t= 12 cm K-225 m3 0.43 1,116,966.11 482,529.36
6 Pek Pembesian u/ Kolom K-1 dan K-2 (Ulir) kg 381.76 23,014.59 8,786,133.40
7 Pek Pembesian u/ Ring Balok (Ulir) kg 943.37 23,014.59 21,711,189.14
JUMLAH C 751,294,947.14
D PEKERJAAN MEKANIKAL
1 Pek Pipa PVC AW Ф 6" antar kompartemen m' 126.00 160,066.59 20,168,389.74
2 Aksesoris Penyambung Pipa bh 36.00 159,100.00 5,727,600.00
JUMLAH D 25,895,989.74
E PEKERJAAN DINDING
1 Pas. 1/2 Bata campuran 1:5 m2 654.50 144,840.25 94,797,940.35
2 Plesteran dan Acian 1 : 5 m2 1,309.00 60,668.70 79,415,323.06
3 Waterprofing U/ dinding bak dan dasar m2 230.00 25,000.00 5,750,000.00
4 Membran Bitune untuk Stop cor m2 13.80 74,000.00 1,021,200.00
JUMLAH E 180,984,463.42

F PEKERJAAN LAIN-LAIN
1 Tangga Perawatan bh 10.00 500,000.00 5,000,000.00
2 Bio Media Filter ( Tipe Sarang Tawon) m3 10.40 2,500,000.00 26,000,000.00
3 Pembersihan Sisa Pekerjaan ls 1.00 5,000,000.00 5,000,000.00
JUMLAH F 36,000,000.00
JUMLAH TOTAL 1,071,385,216.60
XIII. ANALISA HARGA SATUAN BREAKDOWN

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M3 Pasang konstruksi kuda-kuda kayu klas IV
Bahan 1.100 m3 Kayu klas IV 2,090,000.00 2,299,000.00
15.000 Kg Besi Strip Tebal 5 mm 23,100.00 346,500.00
5.600 Kg Paku 23,100.00 129,360.00
Tenaga 4.000 Oh Pekerja 85,000.00 340,000.00
12.000 Oh Tukang 93,500.00 1,122,000.00
1.200 Oh Kepala tukang 107,500.00 129,000.00
0.200 Oh Mandor 129,000.00 25,800.00
JUMLAH 4,391,660.00
PROFIT 10 % 4,830,826.00
2 1 M3 Pasang rangka dinding kayu klas IV
Bahan 1.100 m3 Kayu klas IV 2,090,000.00 2,299,000.00
5.600 Kg Paku 23,100.00 129,360.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.450 Oh Tukang 93,500.00 42,075.00
0.045 Oh Kepala tukang 107,500.00 4,837.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 2,497,697.50
PROFIT 10 % 2,747,467.25
3 1 M2 Pasang dinding hard board t. 3 mm
Bahan 0.3500 Kg Hard board t. 3 mm 65,000.00 22,750.00
0.0200 Kg Paku 23,100.00 462.00
Tenaga 0.1000 Oh Pekerja 85,000.00 8,500.00
0.0500 Oh Tukang 93,500.00 4,675.00
0.0050 Oh Kepala tukang 107,500.00 537.50
0.0025 Oh Mandor 129,000.00 322.50
JUMLAH 37,247.00
PROFIT 10 % 40,971.70
4 1 Unit Pembuatan Meja Pedagang
Bahan 0.0298 m3 Kayu klas IV 2,090,000.00 62,227.83
0.0100 Kg Paku 23,100.00 231.00
0.6944 Lbr Hard board t. 3 mm 65,000.00 45,138.89
Tenaga 0.0100 Oh Pekerja 85,000.00 850.00
0.0050 Oh Tukang 93,500.00 467.50
0.0005 Oh Kepala tukang 107,500.00 53.75
0.0003 Oh Mandor 129,000.00 32.25
JUMLAH 109,001.22
PROFIT 10 % 119,901.34
5 1 Unit Pembuatan Tower Air Kap. 1000 Ltr
Bahan 0.8789 m3 Kayu klas IV 2,090,000.00 1,836,871.74
0.2100 m3 Kayu klas II 3,453,780.00 725,293.80
0.6000 m3 Galian Tanah 44,203.50 26,522.10
0.6000 m3 Beton ad. 1pc:2ps:3kr 643,272.30 385,963.38
0.5000 Kg Paku 23,100.00 11,550.00
Tenaga 2.0000 Oh Pekerja 85,000.00 170,000.00
1.0000 Oh Tukang 93,500.00 93,500.00
0.1000 Oh Kepala tukang 107,500.00 10,750.00
0.0100 Oh Mandor 129,000.00 1,290.00
JUMLAH 3,261,741.02
PROFIT 10 % 3,587,915.12
6 Memasang 1 m' pipa PVC type AW dia 1/2"
Bahan 1.200 M1 Pipa PVC AW Ø 1/2" (4 m') 5,500.00 6,600.00
Perlengkapan 35,0 % harga pipa 2,310.00 8,910.00
0.036 Oh Pekerja 85,000.00 3,060.00
Tenaga 0.0060 Oh Kepala tukang 107,500.00 645.00
0.0020 Oh Mandor 129,000.00 258.00
JUMLAH 19,473.00
PROFIT 10 % 21,420.30

7 Memasang 1 m' pipa PVC type AW dia 3/4"


Bahan 1.200 M1 Pipa PVC AW Ø 3/4" (4 m') 6,875.00 8,250.00
Perlengkapan 35,0 % harga pipa 2,887.50 11,137.50
0.036 Oh Pekerja 85,000.00 3,060.00
Tenaga 0.0060 Oh Kepala tukang 107,500.00 645.00
0.0020 Oh Mandor 129,000.00 258.00
JUMLAH 23,350.50
PROFIT 10 % 25,685.55
7 Memasang 1 m' pipa PVC type AW dia 4"
Bahan 1.200 M1 Pipa PVC AW Ø 4" (4 m') 42,047.50 50,457.00
Perlengkapan 35,0 % harga pipa 17,659.95 68,116.95
0.081 Oh Pekerja 85,000.00 6,885.00
Tenaga 0.0135 Oh Kepala tukang 107,500.00 1,451.25
0.0040 Oh Mandor 129,000.00 516.00
JUMLAH 127,426.20
PROFIT 10 % 140,168.82
XIV. ANALISA HARGA SATUAN PEKERJAAN HASIL PERHITUNGAN SENDIRI
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
1 1 M' Pasang Kusen Aluminium T.4 Inci warna silver
Bahan 1.100 M' Profil kusen aluminium 72,000.00 79,200.00
2.000 bh Skrup fixer 800.00 1,600.00
0.060 tube Sealant 9,000.00 540.00
Tenaga 0.043 Oh Pekerja 85,000.00 3,655.00
0.043 Oh Tukang 93,500.00 4,020.50
0.004 Oh Kepala tukang 107,500.00 462.25
0.002 Oh Mandor 129,000.00 270.90
JUMLAH 89,748.65
2 1 M' Pasang Kusen Aluminium T.4 Inci warna hitam
Bahan 1.100 M' Profil kusen aluminium 88,000.00 96,800.00
2.000 bh Skrup fixer 800.00 1,600.00
0.060 tube Sealant 9,000.00 540.00
Tenaga 0.043 Oh Pekerja 85,000.00 3,655.00
0.043 Oh Tukang 93,500.00 4,020.50
0.004 Oh Kepala tukang 107,500.00 462.25
0.002 Oh Mandor 129,000.00 270.90
JUMLAH 107,348.65
3 1 M' Pasang Kusen Aluminium T.4 Inci warna coklat
Bahan 1.100 M' Profil kusen aluminium 92,000.00 101,200.00
2.000 bh Skrup fixer 800.00 1,600.00
0.060 tube Sealant 9,000.00 540.00
Tenaga 0.043 Oh Pekerja 85,000.00 3,655.00
0.043 Oh Tukang 93,500.00 4,020.50
0.004 Oh Kepala tukang 107,500.00 462.25
0.002 Oh Mandor 129,000.00 270.90
JUMLAH 111,748.65
4 1 M2 Pintu kaca rangka aluminium
Bahan 4.400 M' Profil Pintu aluminium 125,000.00 550,000.00
4.250 bh Profil u. kaca 24,000.00 102,000.00
1.000 M2 Kaca bening 5 mm 129,140.00 129,140.00
5.600 M' Karet list 2,700.00 15,120.00
0.270 tube Sealant 9,000.00 2,430.00
2.000 bh Door closer 173,904.50 347,809.00
4.000 bh Door handle 35,376.00 141,504.00
2.000 bh Door stop 19,019.00 38,038.00
Tenaga 0.085 Oh Pekerja 85,000.00 7,225.00
0.085 Oh Tukang 93,500.00 7,947.50
0.009 Oh Kepala tukang 107,500.00 967.50
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 1,342,826.00
5 1 m² Mengeter 2X kuda-kuda kayu
Bahan 0.320 Kg Teer / Residu 1,254.53 401.45
Tenaga 0.200 Oh Pekerja 85,000.00 17,000.00
0.010 Oh Mandor 129,000.00 1,290.00
JUMLAH 18,691.45
6 1 m² Mengapur 3X dinding baru
Bahan 1.400 kg Kapur sirih 5,600.00 7,840.00
Tenaga 0.060 Oh Pekerja 85,000.00 5,100.00
0.010 Oh Tukang 93,500.00 935.00
0.001 Oh Kepala tukang 107,500.00 107.50
JUMLAH 13,982.50
7 Pasang 1 buah bak mandi fibreglass vol. 0,3 m³
Bahan 1.000 bh Bak mandi fibreglass volume 0,30 m³ 285,000.00 285,000.00
18.000 % Perlengkapan (dari harga bak) 2,850.00 51,300.00
Tenaga 1.800 Oh Pekerja 85,000.00 153,000.00
2.700 Oh Tukang 93,500.00 252,450.00
0.540 Oh Kepala tukang 107,500.00 58,050.00
0.110 Oh Mandor 129,000.00 14,190.00
JUMLAH 813,990.00
8 1 m² Pasang Aluminium Foil single set
Bahan 1.100 m² Aluminium foil single set (122 x 100) 12,000.00 13,200.00
0.001 Kg Paku 18,040.00 18.04
Tenaga 0.200 Oh Pekerja 85,000.00 17,000.00
0.020 Oh Tukang 93,500.00 1,870.00
0.002 Oh Kepala tukang 107,500.00 215.00
JUMLAH 32,303.04
9 1 m² Pasang atap genteng metal / zincalum
Bahan 2.600 lbr Atap metal (standar ) 21,000.00 54,600.00
0.020 gross Paku sekrup 18,040.00 360.80
Tenaga 0.020 Oh Pekerja 85,000.00 1,700.00
0.020 Oh Tukang 93,500.00 1,870.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.010 Oh Mandor 129,000.00 1,290.00
JUMLAH 60,895.80
10 1 m² Pasang rangka dinding pemisah plywood rangkap, kayu kelas II
Bahan 0.0265 m³ Kayu klas II 3,453,780.00 91,525.17
0.2000 kg Paku 18,040.00 3,608.00
0.560 kg Lem kayu 13,200.00 7,392.00
1.000 lbr Plywood 4 mm 99,000.00 99,000.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.450 Oh Tukang 93,500.00 42,075.00
0.045 Oh Kepala tukang 107,500.00 4,837.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 270,862.67
11 Pasang 1Bh - Pasang Door Closer
Bahan 1.0000 bh Door closer 150,000.00 150,000.00
Tenaga 0.020 Oh Pekerja 85,000.00 1,700.00
0.050 Oh Tukang 93,500.00 4,675.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 158,095.00
12 Pasang 1Bh - Pasang Door handle
Bahan 1.0000 bh Door handle 25,000.00 25,000.00
Tenaga 0.020 Oh Pekerja 85,000.00 1,700.00
0.040 Oh Tukang 93,500.00 3,740.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 32,160.00
13 Pasang 1Bh - Pasang Door stoper
Bahan 1.0000 bh Door stop 12,000.00 12,000.00
Tenaga 0.020 Oh Pekerja 85,000.00 1,700.00
0.020 Oh Tukang 93,500.00 1,870.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 17,290.00
14 Siring batu bata kecil 5 x 11 x 22 cm, Pc : 4 Ps
Bahan 16.500 Bh Batu Bata kecil 440.00 7,260.00
8.640 Kg Semen 1,595.00 13,780.80
0.042 M3 Pasir pasang 146,630.00 6,158.46
Tenaga 0.020 Oh Pekerja 85,000.00 1,700.00
0.040 Oh Tukang 93,500.00 3,740.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 34,359.26
15 Membuat septicktank 1,5 x 1 x 1,2 m
2.815 M3 Galian 90,535.50 254,875.54
0.352 M3 Timbunan 53,845.00 18,948.06
0.204 M3 Urugan Pasir 114,120.60 23,280.60
2.000 M' Pipa Udara 2 " 17,875.00 35,750.00
6.800 M2 Pas. Bata 1 : 2 159,975.41 1,087,832.78
7.600 M2 Plesteran 1 : 4 62,198.86 472,711.35
0.245 M3 Plat Beton 1:2:3 6,973,305.35 1,707,065.15
2.000 M' Pipa Rembesan 4" 42,047.50 84,095.00
JUMLAH 3,684,558.48
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN BANGKA
TAHUN ANGGARAN 2013

ZONE. 2
NO URAIAN PEKERJAAN HARGA SATUAN
(Rp)

XIV ANALISA HARGA SATUAN PEKERJAAN HASIL PERHITUNGAN SENDIRI


###
1 1 M' Pasang Kusen Aluminium T.4 Inci warna silver 89,748.65
2 1 M' Pasang Kusen Aluminium T.4 Inci warna hitam 107,348.65
3 1 M' Pasang Kusen Aluminium T.4 Inci warna coklat 111,748.65
4 1 M2 Pintu kaca rangka aluminium 1,342,826.00
5 1 m² Mengeter 2X kuda-kuda kayu 18,691.45
6 1 m² Mengapur 3X dinding baru 13,982.50
7 Pasang 1 buah bak mandi fibreglass vol. 0,3 m³ 813,990.00
8 1 m² Pasang Aluminium Foil single set 32,303.04
9 1 m² Pasang atap genteng metal / zincalum 60,895.80
10 1 m² Pasang rangka dinding pemisah plywood rangkap, kayu kelas II 270,862.67
11 Pasang 1Bh - Pasang Door Closer 158,095.00
12 Pasang 1Bh - Pasang Door handle 32,160.00
13 Pasang 1Bh - Pasang Door stoper 17,290.00
14 Siring batu bata kecil 5 x 11 x 22 cm, Pc : 4 Ps 34,359.26
15 Membuat septicktank 1,5 x 1 x 1,2 m 3,684,558.48
16 1 M' Listplank GRC 73,425.00
17 1 M' Bubungan Genteng Metal Biasa 73,425.00
18 1 M' Bubungan Genteng Metal Pasir 110,000.00
###
REKAPITULASI RENCANA ANGGARAN BIAYA

KEGIATAN : FASILITASI PENYUSUNAN RENCANA INDUK SISTEM PENGELOLAAN AIR LIMBAH

LOKASI : Kabupaten Lamongan TAHUN ANGGARAN 2015

URAIAN PEKERJAAN HARGA (Rp)

1 PERSIAPAN LAHAN DAN JALAN 2,965,902,868.33


2 BAK SSC 1,677,218,779.58
3 KOLAM AN-AEROBIK 2,220,156,836.31
4 KOLAM FAKULTATIF 1,186,507,439.75
5 KOLAM MATURASI 924,050,126.45
6 KOLAM INDIKATOR 25,726,239.18
7 PENJEMUR 184,730,498.83
8 GAPURA 262,697,785.28
9 POS JAGA 131,963,956.82
10 KANTOR dan LABORATORIUM 394,893,056.50
11 RUMAH JAGA 377,408,872.70
12 MUSHOLA/ MESJID 184,734,675.91
13 TOWER AIR DAN SUMUR AIR BERSIH 200,111,096.74
14 GUDANG 83,741,801.40
15 GARASI HANGGAR 484,907,569.93
16 CUCI MOBIL 246,010,335.73
17 PAGAR 361,508,358.28

JUMLAH TOTAL PEKERJAAN


### Rp 11,912,270,297.73
REKAPITULASI RENCANA ANGGARAN BIAYA

KEGIATAN : FASILITASI PENYUSUNAN RENCANA INDUK SISTEM PENGELOLAAN AIR LIMBAH

LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

URAIAN PEKERJAAN HARGA (Rp)

1 PERSIAPAN LAHAN DAN JALAN 2,965,902,868.33


2 BAK SSC 1,677,218,779.58
3 KOLAM AN-AEROBIK 2,220,156,836.31
4 KOLAM FAKULTATIF 1,186,507,439.75
5 KOLAM MATURASI 924,050,126.45
6 KOLAM INDIKATOR 25,726,239.18
7 PENJEMUR 184,730,498.83
8 GAPURA 262,697,785.28
9 POS JAGA 131,963,956.82
10 KANTOR dan LABORATORIUM 394,893,056.50
11 RUMAH JAGA 377,408,872.70
12 MUSHOLA/ MESJID 184,734,675.91
13 TOWER AIR DAN SUMUR AIR BERSIH 200,111,096.74
14 GUDANG 83,741,801.40
15 GARASI HANGGAR 484,907,569.93
16 CUCI MOBIL 246,010,335.73
17 PAGAR 361,508,358.28
18 DINDING PENAHAN TANAH 327,034,760.69

JUMLAH TOTAL PEKERJAAN### Rp 12,239,305,058.41


PPn 10% Rp 1,223,930,505.84
Jumlah Total Rp 13,463,235,564.26
Dibulatkan Rp 13,463,235,000.00
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
PERSIAPAN LAHAN DAN JALAN PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Pengadaan Listrik Daya 2200 Watt ls 1.00 3,500,000.00 3,500,000.00
3 Commisioning Test (Airan air pada bak pengolahan) ls 1.00 10,000,000.00 10,000,000.00
JUMLAH A 14,750,000.00
B. PEKERJAAN JALAN JALUR -1, PANJANG 180 meter
I PEKERJAAN TANAH
1 Galian Tanah Biasa, kedalaman 80cm untuk jalur jalan m3 765.35 73,672.50 56,385,056.33
2 Timbunan Sirtu Pengganti galian m3 1,042.48 196,951.70 205,318,365.78
3 Tanah Timbunan m3 1,371.12 196,951.70 270,045,360.27
4 Pembuangan Sisa Galian m3 1,042.48 32,274.00 33,645,025.34

II PEKERJAAN JALAN
1 Lapisan Pondasi Kelas B (LPB) m3 341.68 356,361.13 121,761,326.99
2 Lapisan Pondasi Kelas B (LPB) u/ bahu m3 44.00 356,361.13 15,679,604.46
3 Perkerasan Jalan Beton, t= 25cm, K-350 m3 427.13 1,298,371.18 554,579,255.68
4 Tulangan Ruji dan Dowel u/ Jalan Beton (20 kg/m3) kg 8,542.69 23,014.59 196,606,511.16

III PEKERJAAN DINDING BETON


DPT (Dinding Penahan Tanah) Beton, Sta 0+110 s/d Sta.
1 0+140
- Beton K-250 m3 59.92 1,072,120.50 64,241,460.36
- Tulangan Baja Ulir (125 kg/m3) kg 7,490.00 23,014.59 172,379,241.65
- Bekisting Dinding m2 94.68 415,943.55 39,379,455.60
- Perkuatan Cerucuk Beton @15m Dia. 20cm m' 1,050.00 153,000.00 160,650,000.00
DPT (Dinding Penahan Tanah) Beton, Sta 0+140 s/d Sta
2 0+180
- Beton K-250 m3 89.20 1,072,120.50 95,633,148.60
- Tulangan Baja Ulir (125 kg/m3) kg 11,150.00 23,014.59 256,612,622.75
- Bekisting Dinding m2 148.00 415,943.55 61,559,645.40
- Perkuatan Cerucuk Beton @15m Dia. 20cm m' 2,812.50 153,000.00 430,312,500.00
JUMLAH TOTAL JALUR -1 2,734,788,580.36
JUMLAH TOTAL 2,749,538,580.36
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
PERSIAPAN LAHAN DAN JALAN PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Pengadaan Listrik Daya 2200 Watt ls 1.00 3,500,000.00 3,500,000.00
3 Commisioning Test (Airan air pada bak pengolahan) ls 1.00 10,000,000.00 10,000,000.00
JUMLAH A 14,750,000.00
B. PEKERJAAN JALAN JALUR -1, PANJANG 236,54 meter
I PEKERJAAN TANAH
1 Galian Tanah Biasa, kedalaman 80cm untuk jalur jalan m3 1,513.86 73,672.50 111,529,556.16
2 Timbunan Sirtu Pengganti galian m3 1,816.63 196,951.70 357,787,815.31
3 Tanah Timbunan m3 1,513.86 196,951.70 298,156,512.76
4 Pembuangan Sisa Galian m3 1,816.63 32,274.00 58,629,826.25

II PEKERJAAN JALAN
1 Lapisan Pondasi Kelas B (LPB) m3 378.46 356,361.13 134,869,857.19
2 Lapisan Pondasi Kelas B (LPB) u/ bahu m3 37.85 356,361.13 13,486,985.72
3 Perkerasan Jalan Beton, t= 25cm, K-350 m3 473.08 1,298,371.18 614,233,439.01
4 Tulangan Ruji dan Dowel u/ Jalan Beton (20 kg/m3) kg 9,461.60 23,014.59 217,754,797.44

JUMLAH TOTAL JALUR -1 1,806,448,789.83

C. PEKERJAAN JALAN JALUR -2, PANJANG 59,66 meter


I PEKERJAAN TANAH
1 Galian Tanah Biasa, kedalaman 80cm untuk jalur jalan m3 381.82 73,672.50 28,129,928.64
2 Timbunan Sirtu Pengganti galian m3 458.19 196,951.70 90,241,063.08
3 Tanah Timbunan m3 381.82 196,951.70 75,200,885.90
4 Pembuangan Sisa Galian m3 458.19 32,274.00 14,787,585.33

II PEKERJAAN JALAN
1 Lapisan Pondasi Kelas B (LPB) m3 95.46 356,361.13 34,016,807.64
2 Lapisan Pondasi Kelas B (LPB) u/ bahu m3 9.55 356,361.13 3,401,680.76
3 Perkerasan Jalan Beton, t= 25cm, K-350 m3 119.32 1,298,371.18 154,921,649.49
4 Tulangan Ruji dan Dowel u/ Jalan Beton (20 kg/m3) kg 2,386.40 23,014.59 54,922,005.64

JUMLAH TOTAL JALUR -2 455,621,606.50


D. PEKERJAAN JALAN JALUR -3, PANJANG 58,06 meter
I PEKERJAAN TANAH
1 Galian Tanah Biasa, kedalaman 80cm untuk jalur jalan m3 371.58 73,672.50 27,375,522.24
2 Timbunan Sirtu Pengganti galian m3 445.90 196,951.70 87,820,920.59
3 Tanah Timbunan m3 371.58 196,951.70 73,184,100.49
4 Pembuangan Sisa Galian m3 445.90 32,274.00 14,391,002.42

II PEKERJAAN JALAN
1 Lapisan Pondasi Kelas B (LPB) m3 92.90 356,361.13 33,104,523.16
2 Lapisan Pondasi Kelas B (LPB) u/ bahu m3 9.29 356,361.13 3,310,452.32
3 Perkerasan Jalan Beton, t= 25cm, K-350 m3 116.12 1,298,371.18 150,766,861.71
4 Tulangan Ruji dan Dowel u/ Jalan Beton (20 kg/m3) kg 2,322.40 23,014.59 53,449,072.20

JUMLAH TOTAL JALUR -3 443,402,455.13

E. PEKERJAAN SALURAN
I PEKERJAAN SALURAN
1 Galian Tanah Biasa, kedalaman 80cm untuk jalur saluran m3 354.26 73,672.50 26,099,219.85
2 Pasir urug dibawah pondasi t= 5cm m3 17.71 114,120.60 2,021,418.19
3 Lantai Kerja dibawah pondasi t= 5cm m2 354.26 143,338.69 50,779,164.32
4 Saluran Pas. Batu kali camp. 1:4 m3 184.22 726,749.34 133,878,275.39
5 Rabat Beton dasar saluran m3 10.63 143,338.69 1,523,374.93
6 Acian Kasar dasar saluran m2 212.56 28,600.00 6,079,101.60
7 Plesteran bibir saluran m2 283.41 60,668.70 17,193,993.80
8 Acian bibir saluran m2 283.41 28,600.00 8,105,468.80

JUMLAH TOTAL PEKERJAAN SALURAN 245,680,016.87


JUMLAH TOTAL 2,965,902,868.33
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
BAK SSC PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 46.00 65,604.88 3,017,824.48
JUMLAH A 5,767,824.48
B PEKERJAAN TANAH
1 Perkuatan Cerucuk Beton @15m Dia. 20cm m' 400.00 153,000.00 61,200,000.00
JUMLAH B 61,200,000.00
C PEKERJAAN PONDASI DAN BETON
1 Urugan Pasir 5cm m3 5.85 114,120.60 667,605.51
2 Lantai Beton t=30cm K-225
- Beton K-225 m3 29.25 1,116,966.11 32,671,258.82
- Tulangan Baja Ulir (125 kg/m3) kg 3,656.25 23,014.59 84,147,076.41
- Bekisting Lantai m2 58.50 415,943.55 24,332,697.68
3 Dinding Beton t=25cm K-225
- Beton K-225 m3 49.22 1,116,966.11 54,977,072.11
'- Tulangan Baja Ulir (125 kg/m3) kg 6,152.50 23,014.59 141,597,234.21
- Bekisting Dinding m2 72.75 415,943.55 30,259,893.26
4 Kolom Beton 15/15
- Beton K-225 m3 0.68 1,116,966.11 753,952.13
'- Tulangan Baja Ulir (125 kg/m3) kg 84.38 23,014.59 1,941,855.61
- Bekisting Kolom m2 9.00 313,210.92 2,818,898.28
5 Ring Balok Beton 15/20
- Beton K-225 m3 1.32 1,116,966.11 1,474,395.27
'- Tulangan Baja Ulir (125 kg/m3) kg 105.60 23,014.59 2,430,340.18
- Bekisting Balok m2 11.00 324,608.39 3,570,692.33
JUMLAH C 381,642,971.80
D PEKERJAAN MEKANIKAL
1 Pek Pipa PVC AW Ф 4" antar kompartemen m' 6.00 42,047.50 252,285.00
2 Aksesoris Penyambung Pipa bh 16.00 6,500.00 104,000.00
3 Screen Baja Unit 4.00 5,000,000.00 20,000,000.00
JUMLAH D 20,356,285.00
E PEKERJAAN DINDING
1 Plesteran dan Acian 1 : 5 m2 234.30 60,668.70 14,214,675.47
2 Waterprofing U/ dinding bak dan dasar m2 180.00 25,000.00 4,500,000.00
3 Membran Bitune untuk Stop cor m2 13.20 74,000.00 976,800.00
JUMLAH E 19,691,475.47

F PEKERJAAN LAIN-LAIN
1 Atap Baja Ringan m2 152.10 175,000.00 26,617,500.00
2 Penutup atap Genteng m2 152.10 178,094.95 27,088,241.90
3 Pasangan Bubungan Genteng Biasa m' 13.00 110,066.18 1,430,860.29
4 Pembersihan Sisa Pekerjaan ls 1.00 5,000,000.00 5,000,000.00
5 Pagar BRC m' 46.00 223,429.73 10,277,767.59
JUMLAH F 70,414,369.77
JUMLAH TOTAL 559,072,926.53
JUMLAH TOTAL 1,677,218,779.58
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
KOLAM AN-AEROBIK PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 5,899,034.24
B PEKERJAAN TANAH
1 Perkuatan Cerucuk Beton @15m Dia. 20cm m' 650.00 153,000.00 99,450,000.00
2 Galian Tanah Biasa, kedalaman 2 meter m' 115.20 90,535.50 10,429,689.60
JUMLAH B 109,879,689.60
C PEKERJAAN PONDASI DAN BETON
1 Urugan Pasir 5cm m3 4.80 114,120.60 547,778.88
2 Lantai Beton t=50cm K-225
- Beton K-225 m3 48.00 1,116,966.11 53,614,373.46
'- Tulangan Baja Ulir (125 kg/m3) kg 6,000.00 23,014.59 138,087,510.00
- Bekisting Lantai m2 48.00 415,943.55 19,965,290.40
3 Dinding Beton t=25cm K-225
- Beton K-225 m3 70.40 1,116,966.11 78,634,414.40
'- Tulangan Baja Ulir (125 kg/m3) kg 8,800.00 23,014.59 202,528,348.00
- Bekisting Dinding m2 123.20 415,943.55 51,244,245.36
4 Dinding Sekat Beton t=25cm K-225
- Beton K-225 m3 8.00 1,116,966.11 8,935,728.91
'- Tulangan Baja Ulir (125 kg/m3) kg 1,000.00 23,014.59 23,014,585.00
- Bekisting Dinding m2 16.00 415,943.55 6,655,096.80
JUMLAH C 583,227,371.21
D PEKERJAAN MEKANIKAL
1 - m' -
JUMLAH D -
E PEKERJAAN DINDING
1 Buis Beton Dia. 1/2 20cm m' 6.00 77,000.00 462,000.00
2 Pasangan 1 bata campuran 1:5 u/Sekat kolam m2 52.80 301,273.79 15,907,255.90
3 Plesteran dan Acian 1 : 5 u/sekat kolam m2 105.60 60,668.70 6,406,614.30
4 Waterprofing U/ dinding bak dan dasar m2 280.80 25,000.00 7,020,000.00
5 Membran Bitune untuk Stop cor m2 12.00 74,000.00 888,000.00
JUMLAH E 30,683,870.20

F PEKERJAAN LAIN-LAIN
1 Tangga Perawatan Ls 1.00 5,000,000.00 5,000,000.00
2 Pagar BRC m' 48.00 223,429.73 10,724,627.05
JUMLAH F 5,000,000.00
JUMLAH TOTAL 740,052,278.77
JUMLAH 3 UNIT 2,220,156,836.31
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
KOLAM FAKULTATIF PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 52.00 65,604.88 3,411,453.76
JUMLAH A 6,161,453.76
B PEKERJAAN TANAH
1 Perkuatan Cerucuk Beton @15m Dia. 20cm m' 450.00 153,000.00 68,850,000.00
2 Galian Tanah Biasa, kedalaman 2 meter m' 104.00 90,535.50 9,415,692.00
JUMLAH B 78,265,692.00
C PEKERJAAN PONDASI DAN BETON
1 Urugan Pasir 5cm m3 6.00 114,120.60 684,723.60
2 Lantai Beton t=50cm K-225
- Beton K-225 m3 38.40 1,116,966.11 42,891,498.76
'- Tulangan Baja Ulir (125 kg/m3) kg 4,800.00 23,014.59 110,470,008.00
- Bekisting Lantai m2 60.00 415,943.55 24,956,613.00
3 Dinding Beton t=25cm K-225
- Beton K-225 m3 23.76 1,116,966.11 26,539,114.86
'- Tulangan Baja Ulir (125 kg/m3) kg 2,970.00 23,014.59 68,353,317.45
- Bekisting Dinding m2 52.20 415,943.55 21,712,253.31
JUMLAH C 295,607,528.98
D PEKERJAAN MEKANIKAL
1 - m' -
JUMLAH D -
E PEKERJAAN DINDING
1 Pasangan 1/2 bata campuran 1:5 u/saluran terbuka m2 3.60 144,840.25 521,424.88
2 Plesteran dan Acian 1 : 5 u/saluran terbuka m2 3.60 60,668.70 218,407.31
3 Buis Beton Dia. 1/2 20cm m' 6.00 77,000.00 462,000.00
4 Waterprofing U/ dinding bak dan dasar m2 199.20 25,000.00 4,980,000.00
5 Membran Bitune untuk Stop cor m2 13.20 74,000.00 976,800.00
JUMLAH E 7,158,632.19

F PEKERJAAN LAIN-LAIN
1 Tangga Perawatan Ls 1.00 2,500,000.00 2,500,000.00
2 Pagar BRC m' 52.00 223,429.73 11,618,345.97
JUMLAH F 2,500,000.00
JUMLAH TOTAL 395,502,479.92
JUMLAH 3 UNIT 1,186,507,439.75
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
KOLAM MATURASI PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 140.00 65,604.88 9,184,683.20
JUMLAH A 11,934,683.20
B PEKERJAAN TANAH
1 Perkuatan Cerucuk untuk tanah @15m m' 300.00 153,000.00 45,900,000.00
2 Galian Tanah Biasa, kedalaman 1 meter m' 140.00 73,672.50 10,314,150.00
JUMLAH B 56,214,150.00
C PEKERJAAN PONDASI DAN BETON
1 Urugan Pasir 5cm m3 4.00 114,120.60 456,482.40
2 Lantai Beton t=50cm K-225
- Beton K-225 m3 32.00 1,116,966.11 35,742,915.64
'- Tulangan Baja Ulir (125 kg/m3) kg 4,000.00 23,014.59 92,058,340.00
- Bekisting Lantai m2 40.00 415,943.55 16,637,742.00
3 Dinding Beton t=25cm K-225
- Beton K-225 m3 10.80 1,116,966.11 12,063,234.03
'- Tulangan Baja Ulir (125 kg/m3) kg 1,350.00 23,014.59 31,069,689.75
- Bekisting Dinding m2 24.00 415,943.55 9,982,645.20
JUMLAH C 198,011,049.01
D PEKERJAAN MEKANIKAL
1 - m' -
JUMLAH D -
E PEKERJAAN DINDING
1 Pasangan 1/2 bata campuran 1:5 u/saluran terbuka m2 7.20 144,840.25 1,042,849.76
2 Plesteran dan Acian 1 : 5 u/saluran terbuka m2 7.20 60,668.70 436,814.61
3 Buis Beton Dia. 1/2 20cm m' 12.00 77,000.00 924,000.00
4 Gorong - Gorong Beton Melintas Jalan Dia. 60 m' 10.00 423,500.00 4,235,000.00
6 Waterprofing U/ dinding bak dan dasar m2 122.00 25,000.00 3,050,000.00
7 Membran Bitune untuk Stop cor m2 12.00 74,000.00 888,000.00
JUMLAH E 10,576,664.38

F PEKERJAAN LAIN-LAIN
1 Pagar BRC m' 140.00 223,429.73 31,280,162.23
JUMLAH F 31,280,162.23
JUMLAH TOTAL 308,016,708.82
JUMLAH 3 UNIT 924,050,126.45
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PANDEGLANG
TAHUN ANGGARAN 2014
ZONE. 2
NO URAIAN PEKERJAAN HARGA SATUAN
(Rp)

I. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


###
1 1 M1 Pagar sementara dari kayu tinggi 2 meter 295,654.77
2 1 M1 Pagar sementara dari seng gelombang tinggi 2 m 352,288.77
3 1 M1 Pengukuran dan pemasangan bowplank 65,604.88
4 1 M2 Pembuatan kantor sementara lantai plesteran 1,150,179.14
5 1 M2 Pembuatan gudang semen dan peralatan 973,131.39
6 1 M2 membersihkan lapangan dan peralatan 10,059.50
7 1 M2 Pembuatan bedeng pekerja 1,057,982.64
8 1 M2 Pembuatan jalan sementara 132,329.70
9 1 M3 Bongkaran beton bertulang 1,341,234.40
10 1 M3 Bongkaran dinding tembok bata merah 670,617.20

II. ANALISA HARGA SATUAN PEKERJAAN TANAH ###


###
1 1 M3 Galian tanah biasa sedalam 1 m 73,672.50
2 1 M3 Galian tanah biasa sedalam 2 m 90,535.50
3 1 m3 Galian tanah biasa sedalam 3 m 107,682.30
4 1 M3 Galian tanah keras sedalam 1 m 98,040.80
5 1 M3 Galian tanah cadas sedalam 1 m 148,764.00
6 1 M3 Galian tanah lumpur sedalam 1 m 118,585.50
7 1 M3 Pekerjaan stripping tanah tebing setinggi 1 m 5,384.50
8 1 M3 Pembuangan tanah sejauh 30 m 32,274.00
9 1 M3 Urugan kembali 53,845.00
10 1 M3 Pemadatan tanah 53,845.00
11 1 M3 Urugan pasir urug 114,120.60
12 1 M3 Urugan sirtu padat 196,951.70
13 1 M3 Urugan tanah puru 201,162.50
14 1 M2 Pembuatan jalan Sementara, tebal 25 cm 152,731.04
###
III. ANALISA HARGA SATUAN PEKERJAAN PONDASI ###
###
1 1 M3 Pasang pondasi batu belah. 1 Pc : 4 Ps 770,249.81
2 1 M3 Pasang pondasi batu belah. 1 Pc : 5 Ps 726,749.34
3 1 M3 Pasang Batu kosong (anstamping) 356,361.13
4 1 M3 Pasang pondasi sumuran diameter 100 cm 901,290.50
###
IV. ANALISA HARGA SATUAN PEKERJAAN PASANG DINDING ###
###
1 1 M2 pasangan bata merah tebal 1 bata. 1 Pc : 4 ps 307,454.22
2 1 M2 pasangan bata merah tebal 1 bata. 1 Pc : 5 ps 301,273.79
3 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 2 ps 159,975.41
4 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 4 ps 147,710.85
5 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 5 ps 144,840.25
6 1 M2 Pasang Bataco 94,176.94
7 1 M2 Pasangan dinding roster 20/20 518,961.36
###
V. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN

1 1 M2 Plesteran 1 pc : 2 ps, tebal 15 mm 68,543.62


2 1 M2 Plesteran 1 pc : 4 ps, tebal 15 mm 62,198.86
3 1 M2 Plesteran 1 pc : 5 ps, tebal 15 mm 60,668.70
###
NO URAIAN PEKERJAAN HARGA SATUAN
(Rp)

VI. ANALISA HARGA SATUAN PEKERJAAN KAYU ###


###
1 1 M3 Pasang kusen pintu dan jendela 7,266,034.60
2 1 M2 Pasang pintu panel kayu klas II 603,846.32
3 1 M2 Pasang pintu dan jendela kaca, kayu klas II 588,929.79
4 1 M2 Pasang jalusi kusen kayu klas II 570,457.58
5 1 M3 Pasang konstruksi kuda-kuda kayu klas II 6,369,970.20
6 1 M2 Pasang Rangka atap genteng keramik, kayu klas II 86,061.71
7 1 M2 Pasang Rangka atap genteng beton, kayu klas II 86,061.71
8 1 M2 Pasang rangka langit-langit 1x1 m, kayu klas II 100,910.55
9 1 M2 Pasang rangka langit-langit (50x100) cm, kayu klas II 121,545.83
10 1 M1 Pasang lisplank ukuran 3/20 kayu klas II 75,777.44
11 1 M1 Pasang lisplank ukuran 3/30 kayu klas II 76,009.81
12 1 M1 Pasang list plafond, kayu profil 28,819.89
13 1 M2 Pasang rangka dinding pemisah triplek rangkap, kayu klas III 257,843.85

VII. ANALISA HARGA SATUAN PEKERJAAN BETON ###


###
1 1 M3 Membuat beton tumbuk, 1 pc : 3 ps : 5 kr 876,768.42
2 1 M2 membuat lantai kerja beton tumbuk, 1 pc : 3 ps : 5 kr tebal 5 cm 143,338.69
3 1 M3 membuat beton, 1 pc : 2 ps : 3 kr 1,072,120.50
4 1 M3 Membuat pondasi beton bertulang (150 Kg besi+bekisting) 5,416,779.50
5 1 M3 Membuat sloop beton bertulang (200 Kg besi + bekisting ) 6,764,619.95
6 1 M3 Membuat kolom beton bertulang ( 300 kg besi + bekisting ) 11,023,407.45
7 1 M3 Membuat kolom beton bertulang ( 150 kg besi + bekisting ) 7,388,805.05
8 1 M3 Membuat dinding beton bertulang (150 Kg besi + bekesting) 7,126,122.30
9 1 M3 Membuat balok beton bertulang (150 Kg besi + bekesting) 6,819,617.75
10 1 M3 Membuat balok beton bertulang (200 Kg besi + bekesting) 7,881,090.25
11 1 M3 Membuat pelat beton bertulang (150 Kg besi + bekesting) 6,973,305.35
12 1 M1 Membuat kolom praktis beton bertulang ( 11 x 11 cm ) 130,730.47
13 1 M1 Membuat Ring balok beton bertulang (10 x 15) cm 136,843.21
14 1 M3 Membuat beton mutu fc' =14,5 Mpa (K.175), slump (12 ± 2) cm, w/c = 0,66 1,046,519.42
15 1 M3 Membuat beton mutu fc' =19,3 Mpa (K.225), slump (12 ± 2) cm, w/c = 0,58 1,116,966.11
16 1 M3 Membuat beton mutu fc' =21,7 Mpa (K.275), slump (12 ± 2) cm, w/c = 0,53 1,177,571.48
17 1 M3 Membuat beton mutu fc' =26,4 Mpa (K.300), slump (12 ± 2) cm, w/c = 0,52 1,188,587.31
18 1 M2 Begesting pasang jembatan cor 105,742.45

VIII. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP


###
1 1 M2 Pasang atap genteng biasa 178,094.95
2 1 M1 Pasang genteng bubung biasa 110,066.18
3 1 M2 Pasang atap asbes gelombang 3M X 1,05 M X 4 mm 59,854.08
4 1 M2 Pasang atap genteng beton 132,006.82
5 1 M1 Pasang bubungan genteng beton 117,920.18
6 1 M2 Pasang atap genteng Keramik glassur 226,991.82
7 1 M1 Pasang bubungan genteng Keramik 184,421.78
###
IX. ANALISA HARGA SATUAN PEKERJAAN LANGIT-LANGIT ###

1 1 M2 langit-langit asbes 1x1 m 39,549.29


2 1 M2 langit-langit gypsum board, tebal 9 mm 61,315.39
3 1 M2 langit-langit plywood 4 mm + rangka kayu klas III 140,327.22
###
###
###
###
NO URAIAN PEKERJAAN HARGA SATUAN
(Rp)

X. ANALISA HARGA SATUAN PEKERJAAN PIPA DAN SANITAIR ###


###
1 Memasang 1 buah closet duduk/monoblok 2,818,381.50
2 Memasang 1 buah closet jongkok biasa 519,850.43
3 Memasang 1 buah bak mandi batu bata volume 0,3 m3 1,859,691.02
4 Memasang 1 m' pipa beton, diameter 15 - 20 Cm 119,621.00
5 Memasang 1 buah, bak kontrol pasangan batu bata uk.30x30 tinggi 50 cm 553,987.53
6 Memasang 1 Bh, bak kontrol pasangan batu bata uk.45x45 tinggi 50 cm 771,636.47
7 Memasang 1 m' pipa galvanis dia 1" 71,473.05
8 Memasang 1 m' pipa galvanis dia 2" 122,111.55
9 Memasang 1 m' pipa PVC type AW dia 1" 31,637.12
10 Memasang 1 m' pipa PVC type AW dia 2" 42,280.84
11 Memasang 1 m' pipa PVC type AW dia 3" 68,239.92
###
XI. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING
###
1 1 M2 Pasang lantai keramik 210,375.94
2 1 M2 Pasang dinding keramik 236,379.37
3 1 M2 Pasang Lantai Keramik Anti Gores 1:4 212,311.94
4 1 M' Pasang Plint Keramik 10/20 32,955.88
5 1 M2 Pasang lantai dari conblok tebal 6 cm 93,120.50
6 1 M2 Pasangan tegel abu-abu 122,726.84
###
XII. ANALISA HARGA SATUAN PEKERJAAN PENGECATAN

1 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 21,195.39
2 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 15,483.05
3 1 M2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 42,416.70
4 1 M2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup) 45,059.58
5 1 M2 Pekerjaan cat genteng 41,526.65

XIII. ANALISA HARGA SATUAN PEKERJAAN BESI

1 1 M2 Pasang pintu lipat 521,083.75


2 1 M2 Pasang rolling door 519,931.50
3 1 M2 Pasang terali besi 510,697.62
4 1 M1 Pasang talang datar, seng BJLS 28 149,890.51
5 1 Kg Rangka kuda-kuda baja IWF 36,015.10
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
KOLAM INDIKATOR PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Admnistrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
3 Air kerja & Listrik Kerja ls 1.00 1,500,000.00 1,500,000.00
4 Pek. Bouwplank m' 28.00 65,604.88 1,836,936.64
JUMLAH A 4,586,936.64
B PEKERJAAN TANAH
1 Galian Tanah Biasa, kedalaman 1 meter m' 4.84 73,672.50 356,574.90
3 Pasir urug untuk resapan, t= 10cm m3 0.20 114,120.60 22,824.12
JUMLAH B 379,399.02
C PEKERJAAN PONDASI DAN BETON
1 Dinding Beton t=20cm K-225
- Beton K-225 m3 1.60 1,116,966.11 1,787,145.78
'- Tulangan Baja Ulir (80 kg/m3) kg 128.00 23,014.59 2,945,866.88
- Bekisting Dinding m2 4.00 415,943.55 1,663,774.20
2 Pondasi Beton t=50cm K-225
- Beton K-225 m3 0.96 1,116,966.11 1,072,287.47
'- Tulangan Baja Ulir (80 kg/m3) kg 76.80 23,014.59 1,767,520.13
JUMLAH C 9,236,594.46
D PEKERJAAN MEKANIKAL
1 Pemasangan Pipa Menuju Pembuangan , PVC type AW Dia.6" m' 55.00 160,066.59 8,803,662.19
JUMLAH D 8,803,662.19
E PEKERJAAN DINDING
1 Plesteran dan Acian 1 : 5 m2 8.00 60,668.70 485,349.57
JUMLAH E 485,349.57

F PEKERJAAN LAIN-LAIN
1 Pagar BRC m' 10.00 223,429.73 2,234,297.30
JUMLAH F 2,234,297.30
JUMLAH TOTAL 25,726,239.18
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
PENJEMUR PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.4 Air kerja & Listrik Kerja ls 1.00 750,000.00 750,000.00
A.6 Pek. Bouwplank m' 32.00 65,604.88 2,099,356.16
JUMLAH A 3,599,356.16
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi Batu kali m3 15.36 73,672.50 1,131,609.60
B.1.2 Urugan pasir Bawah Pondasi Bt Kali 5 cm m3 0.96 114,120.60 109,555.78
B.1.3 Urgan tanah kembali m3 7.00 53,845.00 376,915.00

B.2 PEKERJAAN PONDASI


B.2.1 Pondasi Aanstamping Batu Kali t=15 cm m3 2.88 356,361.13 1,026,320.04
B.2.2 Pondasi Batu Kali 1 : 5 m3 7.20 726,749.34 5,232,595.26
B.2.3 Beton Sloof 15/20 Beton K 175
- Beton K-225 m3 0.72 1,116,966.11 804,215.60
- Tulangan Baja Ulir / polos (80 kg/m3) kg 57.60 23,014.59 1,325,640.10
- Bekisting Balok m2 2.80 324,608.39 908,903.50
JUMLAH B 10,915,754.88
C PEKERJAAN STRUKTUR
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom K1 20/20 Beton K 225
- Beton K-225 m3 0.58 1,116,966.11 647,840.35
- Tulangan Baja Ulir / polos (80 kg/m3) kg 46.40 23,014.59 1,067,876.74
- Bekisting Kolom m2 1.69 313,210.92 529,848.47
C.1.2 Kolom Praktis K2 10/10 K 175
- Beton K-225 m3 0.07 1,116,966.11 78,187.63
- Tulangan Baja Ulir / polos (80 kg/m3) kg 5.60 23,014.59 128,881.68
- Bekisting Kolom m2 0.20 313,210.92 63,947.23
C.1.3 Kolom K3 15/15 K 175
- Beton K-225 m3 0.34 1,116,966.11 379,768.48
- Tulangan Baja Ulir / polos (80 kg/m3) kg 27.20 23,014.59 625,996.71
- Bekisting Kolom m2 0.99 313,210.92 310,600.83
C.1.4 Ring Balk 15/20 K 175
- Beton K-225 m3 0.72 1,116,966.11 804,215.60
- Tulangan Baja Ulir / polos (80 kg/m3) kg 57.60 23,014.59 1,325,640.10
- Bekisting Balok m2 2.10 324,608.39 681,677.63

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 64.00 187,000.00 11,968,000.00
C.2.2 Pek. Pasangan Genteng Biasa m2 64.00 178,094.95 11,398,076.80
C.2.3 Pek. Pemasangan Bubungan genteng Biasa m1 8.00 110,066.18 880,529.41
C.2.4 Pek. Pemasangan Listplank Kayu Kelas II m1 16.00 75,777.44 1,212,439.01
JUMLAH C 32,103,526.66
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Bata Merah Spesi 1 : 5 m2 19.20 144,840.25 2,780,932.70
D.1.2 Plesteran Spesi 1 : 5 m2 38.40 60,668.70 2,329,677.93
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
PENJEMUR PENGELOLAAN AIR LIMBAH
LOKASI KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.2 PEKERJAAN LANTAI
D.2.1 Urugan Pasir Bawah Lantai t = 5 Cm m3 1.80 114,120.60 205,417.08
D.2.2 Pek Rabat Lantai T=10 Cm Beton K 225 m3 3.60 876,768.42 3,156,366.31

D.3 PEKERJAAN PLAFOND

-
D.4 PEKERJAAN PENGECATAN
D.4.1 Dinding Sek. "VINILEX" m² 38.40 42,416.70 1,628,801.22

D.5 PEK. MEKANIKAL ELEKTRIKAL


D.5.1 Instalasi Titik Lampu ttk 11.00 140,000.00 1,540,000.00
D.5.2 Instalasi Stop Kontak + saklar ttk 10.00 140,000.00 1,400,000.00
D.5.3 Armateur stop kontak Setara Broco bh 5.00 45,000.00 225,000.00
D.5.4 Armateur Saklar Ganda Setara Broco bh 5.00 45,000.00 225,000.00
D.5.5 Armateur Lampu TL 1 x 18 watt Setara Philips bh 1.00 217,000.00 217,000.00
D.5.6 Armateur Lampu SL 25 watt Setara Philips bh 10.00 50,000.00 500,000.00
JUMLAH D 14,208,195.24
E PEKERJAAN LAIN-LAIN
E.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 750,000.00 750,000.00
JUMLAH E 750,000.00
JUMLAH TOTAL 61,576,832.94
JUMLAH 3 UNIT 184,730,498.83
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
GAPURA PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.3 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.4 Pek. Bouwplank m' 30.00 43,324.00 1,299,720.00
JUMLAH A 2,549,720.00
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi Telapak m3 14.40 73,672.50 1,060,884.00
B.1.2 Lantai Kerja 5 cm, m3 0.45 60,668.70 27,300.91
B.1.3 Urugan Pasir 10 cm m3 0.90 114,120.60 102,708.54
B.1.4 Urugan Tanah Kembali m3 12.00 53,845.00 646,140.00

B.2 PEKERJAAN PONDASI


B.2.1 Pondasi Poor 1.5X1.5X0.2 m Beton K 225 m3 1.80 5,416,779.50 9,750,203.10
B.2.2 Kolom Stump 20/25 Beton K 225 m3 1.28 7,388,805.05 9,457,670.46
B.2.3 Beton Sloof 20/25 K 225 m3
- Beton K-225 m3 1.65 1,116,966.11 1,842,994.09
- Tulangan Baja Ulir / polos (80 kg/m3) kg 132.00 23,014.59 3,037,925.22
- Bekisting Balok m2 3.85 324,608.39 1,249,742.32
JUMLAH B 27,175,568.64
C PEKERJAAN STRUKTUR
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom K1 20/25 Beton K 225 m3
- Beton K-225 m3 6.20 1,116,966.11 6,925,189.90
- Tulangan Baja Ulir / polos (80 kg/m3) kg 496.00 23,014.59 11,415,234.16
- Bekisting Kolom m2 14.47 313,210.92 4,531,117.98
C.1.2 Ring Balk 20/25 K 22
- Beton K-225 m3 4.95 1,116,966.11 5,528,982.26
- Tulangan Baja Ulir / polos (80 kg/m3) kg 396.00 23,014.59 9,113,775.66
- Bekisting Balok m2 11.55 324,608.39 3,749,226.95
C.1.3 Beton Tumbuk Beton K 175 m3 3.00 876,768.42 2,630,305.26
C.1.4 Pemasangan PIPA GIP 3" m1 127.00 183,167.33 23,262,250.28
C.1.5 Pemasangan Baud Angkur Ø 16 bh 12.00 22,400.00 268,800.00
JUMLAH C 67,424,882.45
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Bata Merah Spesi 1 : 5 m2 150.00 144,840.25 21,726,036.75
D.1.2 Plesteran ban Spesi 1 : 5 m2 75.00 60,668.70 4,550,152.20
D.1.3 Finishing Acian Kolom K2 m2 25.92 60,668.70 1,572,532.60
D.1.4 Tulisan di atas GAPURA ls 1.00 5,850,000 5,850,000.00
JUMLAH D 33,698,721.55
E PEKERJAAN LAIN-LAIN
E.1 PEKERJAAN PEMBERSIHAN SISA - SISA PEKERJAAN ls 1.00 500,000.00 500,000.00
JUMLAH E 500,000.00
JUMLAH TOTAL 131,348,892.64
JUMLAH 2 UNIT 262,697,785.28
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
POS JAGA PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.3 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.4 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 4,399,034.24
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian tanah pondasi m3 12.60 73,672.50 928,273.50
B.1.2 Urugan tanah kembali m3 7.35 53,845.00 395,760.75
B.1.3 Urugan pasir di bawah pondasi m3 0.84 114,120.60 95,861.30
B.1.4 Urugan pasir di bawah lantai m3 3.36 114,120.60 383,901.70
B.1.5 Urugan pasir di bawah saluran keliling bangunan m3 1.20 114,120.60 136,944.72
Aanstamping bat
B.2 PEKERJAAN PONDASI Pondasi batu bel
B.2.1 Aanstamping batu belah m3 2.03 356,361.13 723,413.09
B.2.2 Pondasi batu belah 1:5 m3 3.92 726,749.34 2,845,223.67
B.2.3 Sloof Beton 15/20 Kolom praktis 12
- Beton K-225 m3 0.36 1,116,966.11 402,107.80
- Tulangan Baja Ulir / polos (80 kg/m3) kg 28.80 23,014.59 662,820.05
- Bekisting Balok m2 0.84 324,608.39 272,671.05
JUMLAH B 6,846,977.63
C PEKERJAAN STRUKTUR m2
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom beton 25/25 m2
- Beton K-225 m3 1.36 1,116,966.11 1,519,073.91
- Tulangan Baja Ulir / polos (80 kg/m3) kg 108.80 23,014.59 2,503,986.85
- Bekisting Kolom m2 3.17 313,210.92 993,922.65
C.1.2 Kolom praktis 12/12 m1
- Beton K-225 m3 0.14 1,116,966.11 156,375.26
- Tulangan Baja Ulir / polos (80 kg/m3) kg 11.20 23,014.59 257,763.35
- Bekisting Kolom m2 0.33 313,210.92 102,315.57
C.1.3 Ring balok beton 15/20 m1
- Beton K-225 m3 0.44 1,116,966.11 491,465.09
- Tulangan Baja Ulir / polos (80 kg/m3) kg 35.20 23,014.59 810,113.39
- Bekisting Balok m2 1.03 324,608.39 333,264.62

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 26.52 187,000.00 4,959,707.50
C.2.2 Pek. Pasangan Genteng Biasa m2 26.52 178,094.95 4,723,523.31
C.2.3 Pek. Pemasangan Bubungan genteng biasa m1 14.56 110,066.18 1,602,563.52
C.2.4 Pek. Pemasangan List plank Kayu kelas II m1 20.00 75,777.44 1,515,548.76
JUMLAH C 19,969,623.78
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Pasangan 1/2 bata 1:5 m2 34.40 144,840.25 4,982,504.43
D.1.2 Plesteran + Acian 1:5 m2 58.80 60,668.70 3,567,319.32

D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES


D.2.1 Pek. Kusen Kayu Kelas II m3 0.19 7,266,034.60 1,380,546.57
D.2.2 Pek Daun Pintu Panel kayu Kelas II m2 1.68 603,846.32 1,014,461.82
D.2.3 Pek. Pintu PVC bh 1.00 300,000.00 300,000.00
D.2.4 Pek. Pemasangn engsel pintu m2 2.00 37,045.00 74,090.00
D.2.5 Pek. Pemasangan Kunci Pintu 2 slaag bh 1.00 125,000.00 125,000.00

D.3 PEKERJAAN LANTAI


D.3.1 Adukan spesi lantai 1:5 m3 1.68 62,198.86 104,494.09
D.3.2 Pas. Keramik 30/30 DN putih Setara Mulia m2 32.50 210,375.94 6,837,217.89
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.3.3 Pas. Keramik 20/20 WC/anti slip m2 16.00 210,375.94 3,366,014.96
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

D.4 PEKERJAAN PLAFOND


D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 26.52 140,327.22 3,721,828.69
D.4.2 List Plafond kayu 5 cm m1 80.00 12,000.00 960,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Pek. Cat dinding Setara Vinilex m2 68.80 21,195.39 1,458,243.11
D.5.2 Pek. Cat Plafon Setara Vinilex m2 33.64 42,416.70 1,426,897.74
D.5.3 Pek. Cat Listplank Setara Avian m2 8.80 42,416.70 373,266.95
D.5.4 Pek. Cat kusen Setara Avian m2 10.13 42,416.70 429,681.16
D.5.5 Pek. Cat daun pintu Setara Avian m2 10.21 42,416.70 433,074.49
D.5.6 Pek. Cat daun jendela Setara Avian m2 2.88 42,416.70 122,160.09

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Pek. Pasangan Instalasi saklar (Broco), Kabel NYM 3x2.5 mm titik 2.00 140,000.00 280,000.00
D.6.2 Pek. Pasangan Instalasi stop kontak (Broco) Kabel NYM 3x2.5 mm titik 1.00 140,000.00 140,000.00
D.6.3 Pek. Pasangan titik lampu pijar 25 watt Setara Philips titik 3.00 75,000.00 225,000.00
D.6.4 Accessories ls 1.00 150,000.00 150,000.00
JUMLAH D 31,471,801.30
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 1.00 1,859,691.02 1,859,691.02
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 1.00 519,850.43 519,850.43
E.1.3 Pek. Pemasangan Kran 3/4" bh 1.00 105,000.00 105,000.00
E.1.4 Pek. Pemasangan Floor draine Steinlest Ei Flast HN 5080 bh 1.00 35,000.00 35,000.00
E.1.5 Pek. Pemasangan pipa PVC 3/4 ' Setara Maspion m' 12.00 25,000.00 25,000.00
JUMLAH E 2,544,541.45
F PEKERJAAN LAIN-LAIN
F.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 750,000.00 750,000.00
JUMLAH F 750,000.00
JUMLAH TOTAL 65,981,978.41
JUMLAH 2 UNIT 131,963,956.82
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
KANTOR dan LABORATORIUM PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.3 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.4 Pek. Bouwplank m' 58.40 65,604.88 3,831,324.99
JUMLAH A 5,081,324.99
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi Setempat Selasar m3 6.14 73,672.50 452,643.84
B.1.2 Galian Tanah Pondasi Batu kali menerus m3 49.49 73,672.50 3,646,140.43
B.1.3 Urugan pasir Bawah Pondasi Bt Kali m3 3.48 114,120.60 396,820.15

B.2 PEKERJAAN PONDASI


B.2.1 Pondasi Aanstamping Batu Kali t=15 cm m3 10.43 356,361.13 3,716,133.82
B.2.2 Pondasi Batu Kali 1 : 5 m3 43.47 726,749.34 31,588,160.15
B.2.3 Beton Sloof 15/20
- Beton K-225 m3 3.11 1,116,966.11 3,473,764.61
- Tulangan Baja Ulir / polos (80 kg/m3) kg 248.80 23,014.59 5,726,028.75
- Bekisting Balok m2 7.26 324,608.39 2,355,574.91
JUMLAH B 51,355,266.67
C PEKERJAAN STRUKTUR
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom K1 25/25
- Beton K-225 m3 1.48 1,116,966.11 1,653,109.85
- Tulangan Baja Ulir / polos (80 kg/m3) kg 118.40 23,014.59 2,724,926.86
- Bekisting Kolom m2 3.45 313,210.92 1,081,621.71
C.1.2 Kolom K2 15/15
- Beton K-225 m3 0.97 1,116,966.11 1,083,457.13
- Tulangan Baja Ulir / polos (80 kg/m3) kg 77.60 23,014.59 1,785,931.80
- Bekisting Kolom m2 2.26 313,210.92 708,900.72
C.1.3 Kolom Praktis 12/12
- Beton K-225 m3 0.50 1,116,966.11 558,483.06
- Tulangan Baja Ulir / polos (80 kg/m3) kg 40.00 23,014.59 920,583.40
- Bekisting Kolom m2 1.17 313,210.92 365,412.74
C.1.4 Ring Balk 15/20
- Beton K-225 m3 2.69 1,116,966.11 3,004,638.85
- Tulangan Baja Ulir / polos (80 kg/m3) kg 215.20 23,014.59 4,952,738.69
- Bekisting Balok m2 6.28 324,608.39 2,037,458.69

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 136.00 187,000.00 25,432,000.00
C.2.2 Pek. Pasangan Genteng Biasa m2 136.00 178,094.95 24,220,913.20
C.2.3 Pek. Pemasangan Bubungan genteng biasa m1 275.45 110,066.18 30,317,728.18
C.2.4 Pek. Pemasangan List plank Kayu kelas II m1 70.50 75,777.44 5,342,309.38
C.2.5 Pek. Konsol Baja Ringan m2 4.50 187,000.00 841,500.00
C.2.6 Pek. Pasangan Genteng Biasa m2 4.50 178,094.95 801,427.28
C.2.7 Pek. seng Plesing m1 10.40 159,149.00 1,655,149.60
JUMLAH C 109,488,291.12
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Bata Merah Spesi 1 : 5 m2 316.42 144,840.25 45,830,929.68
D.1.2 Plesteran Spesi 1 : 5 m2 632.85 60,668.70 38,394,062.93
D.1.3 Finishing Acian Kolom K2 m2 25.92 60,668.70 1,572,532.60
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES
D.2.1 Kusen Pintu P1 Kayu Kelas II m³ 0.06 7,266,034.60 435,962.08
D.2.2 Kusen Pintu P2 Kayu Kelas II m³ 0.16 7,266,034.60 1,173,827.89
D.2.3 Kusen PVC u/ Kamar Mandi unit 2.00 300,000.00 600,000.00
D.2.4 Kusen Jendela J1 m³ 0.35 7,266,034.60 2,526,836.19
D.2.5 kusen Bouvenlegh m³ 0.04 7,266,034.60 292,966.52
D.2.6 Daun pintu panil Kayu P1 kelas II m² 3.36 603,846.32 2,028,923.64
D.2.7 Daun pintu panil Kayu P2 Kelas II m² 3.36 603,846.32 2,028,923.64
D.2.8 Daun jendela J1 m² 1.52 603,846.32 919,054.10
D.2.9 Pasangan kunci Union/Royal Type Besar bh 3.00 125,000.00 375,000.00
D.2.10 Pasang engsel pintu bh 8.00 35,000.00 280,000.00
D.2.11 Pasang engsel Jendela bh 24.00 35,000.00 840,000.00
D.2.12 Hak Angin bh 12.00 35,000.00 420,000.00
D.2.13 Pasang Grendel Jendela bh 12.00 25,000.00 300,000.00
D.2.14 Pasang Espagnolet Pintu P1 bh 2.00 59,477.00 118,954.00

D.3 PEKERJAAN LANTAI


D.3.1 Urugan Pasir Bawah Lantai t = 5 Cm m3 51.54 196,951.70 10,151,678.42
D.3.2 Keramik lantai 30x30 Sek"Mulya" m2 158.80 210,375.94 33,407,698.48
D.3.3 Keramik lantai kamar Mandi & Dinding 20x20 Sek"Mulia" m2 43.60 210,375.94 9,173,232.27
D.3.4 Plint keramik dinding Kamar Mandi m1 22.12 32,955.88 728,984.04
D.3.5 Pemasangan Gravel Buis Beton m1 72.80 77,000.00 5,605,600.00
D.3.6 pemasangan Rabat beton tumbuk m³ 6.30 876,768.42 5,523,641.05

D.4 PEKERJAAN PLAFOND


D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 202.40 140,327.22 28,402,790.64
D.4.2 List Plafond kayu 5 cm m² 42.00 12,000.00 504,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Pengecatan Tembok Sek. "VINILEX" m² 632.85 21,195.39 13,413,462.70
D.5.1 Plafond Sek. "VINILEX" m² 42.00 42,416.70 1,781,501.34
D.5.2 Lisplank Kayu Sek. "AVIAN" m² 14.10 42,416.70 598,075.45
D.5.3 Kusen Pintu, jendela Dan Bouvenlegh Sek. "AVIAN" m² 12.13 42,416.70 514,361.85
D.5.4 Daun Pintu dan daun Jendela Sek. "AVIAN" m² 11.60 42,416.70 492,118.54

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Instalasi Titik Lampu ttk 11.00 140,000.00 1,540,000.00
D.6.2 Instalasi Stop Kontak + saklar ttk 10.00 140,000.00 1,400,000.00
D.6.3 Armateur stop kontak Setara Broco bh 5.00 45,000.00 225,000.00
D.6.4 Armateur Saklar Ganda Setara Broco bh 5.00 45,000.00 225,000.00
D.6.5 Armateur Lampu TL 1 x 18 watt Setara Philips bh 1.00 175,000.00 175,000.00
D.6.6 Armateur Lampu SL 25 watt Setara Philips bh 10.00 75,000.00 750,000.00
JUMLAH D 212,750,118.03
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 2.00 1,859,691.02 3,719,382.04
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 2.00 519,850.43 1,039,700.86
E.1.3 Pek. Pemasangan Kran 3/4" bh 3.00 25,000.00 75,000.00
E.1.4 Pek. Pemasangan Floordraine Steinles bh 2.00 110,110.00 220,220.00
E.1.5 Pek. Pemasangan Wastafel Setara TOTO unit 1.00 1,284,800.00 1,284,800.00
E.1.6 Pek. Pemasangan pipa PVC dia 3/4' Setara Maspion m' 30.00 25,000.00 750,000.00
JUMLAH 7,089,102.90
F PEKERJAAN SEPTICTANK
F.1 Galian tanah m3 3.38 73,672.50 249,013.05
F.2 Urugan Pasir t = 5 cm m3 0.28 114,120.60 31,953.77
F.3 Pekerjaan Plat Lantai atas dan bawah t = 12 cm Beton Tumbuk m3 0.99 876,768.42 868,000.74
F.4 Tie Beam 15/20 Beton K 175 m3 0.23 1,116,966.11 256,902.21
F.5 Kolom Praktis 15/15 Beton K 175 m3 0.20 23,014.59 4,602.92
F.6 Pemasangan Pipa PVC 4" Setara Maspion m' 20.00 85,924.01 1,718,480.12
JUMLAH 3,128,952.79
G PEKERJAAN LAIN-LAIN
G.1 Pembuatan Papan Nama Kantor ls 1.00 5,000,000.00 5,000,000.00
G.2 Pekerjaan Pembersihan Sisa-Sisa Pekerjaan ls 1.00 1,000,000.00 1,000,000.00
JUMLAH G 6,000,000.00
JUMLAH TOTAL 394,893,056.50
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
RUMAH JAGA PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.4 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.6 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 4,399,034.24
B PEKERJAAN TANAH DAN PONDASI RB
B.1 PEKERJAAN TANAH
B.1.1 Galian tanah pondasi m3 27.20 73,672.50 2,003,892.00
B.1.2 Urugan tanah kembali m3 8.90 53,845.00 479,220.50
B.1.3 Urugan pasir di bawah pondasi m3 1.40 114,120.60 159,768.84
B.1.4 Urugan pasir di bawah lantai m3 4.52 114,120.60 516,281.59
B.1.5 Urugan pasir di bawah saluran keliling bangunan m3 1.68 114,120.60 191,722.61

B.2 PEKERJAAN PONDASI


B.2.1 Aanstamping batu belah m3 3.50 356,361.13 1,247,263.94
B.2.2 Pondasi batu belah 1:5 m3 5.40 726,749.34 3,924,446.45
B.2.3 Sloof Beton 15/20 (K-175) ###
- Beton K-225 m3 0.60 1,116,966.11 670,179.67
- Tulangan Baja Ulir / polos (80 kg/m3) kg 48.00 23,014.59 1,104,700.08
- Bekisting Balok m2 1.40 324,608.39 454,451.75
JUMLAH B 10,752,049.96
C PEKERJAAN STRUKTUR ###
C.1 PEKERJAAN KOLOM DAN RING BALK ###
C.1.1 Kolom beton 25/25 C.3.2
- Beton K-225 m3 0.78 1,116,966.11 871,233.57
- Tulangan Baja Ulir / polos (80 kg/m3) kg 62.40 23,014.59 1,436,110.10
- Bekisting Kolom m2 1.46 313,210.92 456,035.10
C.1.2 Kolom praktis 15/15 C.3.3
- Beton K-225 m3 0.30 1,116,966.11 335,089.83
- Tulangan Baja Ulir / polos (80 kg/m3) kg 24.00 23,014.59 552,350.04
- Bekisting Kolom m2 0.70 313,210.92 219,247.64
C.1.3 Ring balok beton 15/20 C.3.4
- Beton K-225 m3 0.60 1,116,966.11 670,179.67
- Tulangan Baja Ulir / polos (80 kg/m3) kg 48.00 23,014.59 1,104,700.08
- Bekisting Balok m2 1.40 324,608.39 454,451.75
C.1.4 Jurai Beton 12/12
- Beton K-225 m3 0.07 1,116,966.11 78,187.63
- Tulangan Baja Ulir / polos (80 kg/m3) kg 5.60 23,014.59 128,881.68
- Bekisting Balok m2 0.16 324,608.39 53,019.37

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 185.00 187,000.00 34,595,000.00
C.2.3 Pek. Pasangan Genteng Biasa m2 185.00 178,094.95 32,947,565.75
C.2.4 Pek. Pemasangan Bubungan genteng biasa m1 15.00 110,066.18 1,650,992.64
C.2.5 Pek. Pemasangan List plank Kayu kelas II m1 60.00 75,777.44 4,546,646.28
C.2.6 Pek seng Plesing m1 8.00 159,149.00 1,273,192.00
JUMLAH C 81,372,883.14
D PEKERJAAN ARSITEKTUR B.2.4.1
D.1 PEKERJAAN DINDING B.2.4.2
D.1.1 Pasangan 1/2 bata 1:5 m2 106.83 144,840.25 15,473,283.37
D.1.2 Pasangan 1/2 bata 1:5 (Ampig ) m2 25.20 144,840.25 3,649,974.17
D.1.3 Plesteran + Acian 1:5 m2 226.25 60,668.70 13,726,292.47
D.1.4 Ban 5x10 cm m' 9.40 60,668.70 570,285.74
D.1.5 Pasangan Saluran keliling bangunan (Buis beton Dia 20 cm) m' 34.60 77,000.00 2,664,200.00
j1
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
RUMAH JAGA PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES ###
D.2.1 Pek. Kusen Kayu Kelas II m3 0.59 7,266,034.60 4,286,960.41
D.2.2 Pek Daun Pintu Panel kayu Kelas II m2 6.09 603,846.32 3,677,424.09
D.2.3 Pek. Daun jendela kaca kayu Kelas II m2 4.48 603,846.32 2,705,231.51
D.2.4 Pek. Pintu PVC bh 1.00 300,000.00 300,000.00
D.2.5 Pek. Pemasangn engsel pintu bh 8.00 35,000.00 280,000.00
D.2.6 Pek. Pemasangn engsel jendela bh 30.00 35,000.00 1,050,000.00
D.2.7 Pek. Pemasangan Kunci Pintu 2 slaag bh 4.00 175,000.00 700,000.00
D.2.8 Pek. Pemasangan Kunci grendel jendela bh 15.00 25,000.00 375,000.00
D.2.9 Pek. Pemasangan hak angin jendela bh 15.00 35,000.00 525,000.00
m3
D.3 PEKERJAAN LANTAI m2
D.3.1 Adukan spesi lantai 1:5 m3 2.25 876,768.42 1,972,728.95
D.3.2 Pas. Keramik 30/30 DN putih (setara Roman) m2 42.75 210,375.94 8,993,571.22
D.3.3 Pas. Keramik 20/20 WC/anti slip m2 2.25 210,375.94 473,345.85
D.3.4 Dinding Keramik 20/20 DN putih (setara Roman) m2 7.86 236,379.37 1,857,941.88
D.3.5 Plin keramik WC 10/20 warna m' 5.20 32,955.88 171,370.57
Pek. Konsol Kayu
D.4 PEKERJAAN PLAFOND Pek. Rangka atap
D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 72.00 140,327.22 10,103,559.84
D.4.2 List Plafond kayu 5 cm m² 42.00 12,000.00 504,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Pek. Cat dinding (sanlex) 3x m2 226.25 21,195.39 4,795,457.89
D.5.2 Pek. Cat Plafon (sanlex) 3x m2 49.80 42,416.70 2,112,351.59
D.5.3 Pek. Cat Listplank m2 29.04 42,416.70 1,231,780.92
D.5.4 Pek. Cat kusen m2 31.46 42,416.70 1,334,429.33
D.5.5 Pek. Cat daun pintu m2 12.18 42,416.70 516,635.39
D.5.6 Pek. Cat daun jendela m2 8.96 42,416.70 380,053.62

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Pek. Pasangan Instalasi saklar (Broco), Kabel NYM 3x2.5 mm titik 6.00 140,000.00 840,000.00
D.6.2 Pek. Pasangan Instalasi stop kontak (Broco) Kabel NYM 3x2.5 mm titik 3.00 140,000.00 420,000.00
D.6.3 Pek. Pasangan titik lampu pijar 40 watt titik 10.00 150,000.00 1,500,000.00
D.6.4 Pek. Pemasangan Panel Listrik Unit 1.00 750,000.00 750,000.00
D.6.5 Accessories ls 1.00 350,000.00 350,000.00
JUMLAH D 88,290,878.83
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 1.00 1,859,691.02 1,859,691.02
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 1.00 519,850.43 519,850.43
E.1.3 Pek. Pemasangan Kran 3/4" bh 2.00 25,000.00 50,000.00
E.1.4 Pek. Pemasangan Floordraine Steinles bh 1.00 110,110.00 110,110.00
E.1.5 Pek. Pemasangan pipa PVC dia 3/4' Setara Maspion m1 24.00 25,000.00 600,000.00
JUMLAH E 3,139,651.45
F PEKERJAAN LAIN-LAIN ###
F.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 750,000.00 750,000.00
JUMLAH F 750,000.00
JUMLAH TOTAL 188,704,436.35
JUMLAH 2 UNIT 377,408,872.70
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
MUSHOLA/ MESJID PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.4 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.6 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 4,399,034.24
B PEKERJAAN TANAH DAN PONDASI RB
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi Setempat Selasar m3 4.10 73,672.50 301,762.56
B.1.2 Galian Tanah Pondasi Batu kali menerus & Km/wc m3 25.22 73,672.50 1,857,725.76
B.1.3 Urugan pasir Bawah Pondasi Bt Kali m3 1.83 114,120.60 209,068.94

B.2 PEKERJAAN PONDASI


B.2.1 Pondasi Aanstamping Batu Kali t=15 cm m3 5.50 356,361.13 1,958,560.75
B.2.2 Pondasi Batu Kali 1 : 5 m3 13.74 726,749.34 9,985,535.96
B.2.3 Beton Sloof S1 15/20 Beton m3
- Beton K-225 m3 1.02 1,116,966.11 1,139,305.44
- Tulangan Baja Ulir / polos (80 kg/m3) kg 81.60 23,014.59 1,877,990.14
- Bekisting Balok m2 2.38 324,608.39 772,567.98
B.2.4 Beton Sloof S2 15/15 Beton ###
- Beton K-225 m3 0.58 1,116,966.11 647,840.35
- Tulangan Baja Ulir / polos (80 kg/m3) kg 46.40 23,014.59 1,067,876.74
- Bekisting Balok m2 1.35 324,608.39 439,303.36
JUMLAH B 20,257,537.97
C PEKERJAAN STRUKTUR ###
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom K1 15/15 Beton C.3.2
- Beton K-225 m3 1.00 1,116,966.11 1,116,966.11
- Tulangan Baja Ulir / polos (80 kg/m3) kg 80.00 23,014.59 1,841,166.80
- Bekisting Kolom m2 2.33 313,210.92 730,825.48
C.1.2 Kolom K2 15/15 Beton C.3.3
- Beton K-225 m3 0.54 1,116,966.11 603,161.70
- Tulangan Baja Ulir / polos (80 kg/m3) kg 43.20 23,014.59 994,230.07
- Bekisting Kolom m2 1.26 313,210.92 394,645.76
C.1.3 Kolom K3 15/15 Beton C.3.4
- Beton K-225 m3 0.34 1,116,966.11 379,768.48
- Tulangan Baja Ulir / polos (80 kg/m3) kg 27.20 23,014.59 625,996.71
- Bekisting Kolom m2 0.79 313,210.92 248,480.66
C.1.4 Ring Balk 15/20 Beton K - 175
- Beton K-225 m3 0.74 1,116,966.11 826,554.92
- Tulangan Baja Ulir / polos (80 kg/m3) kg 59.20 23,014.59 1,362,463.43
- Bekisting Balok m2 1.73 324,608.39 560,490.49
C.1.5 Plat Beton Mimbar & Kamar Mandi T = 10cm Beton m3 1.75 4,544,500.00 7,973,325.25

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 31.36 187,000.00 5,864,320.00
C.2.2 Pek. Pasangan Genteng Biasa m2 31.36 178,094.95 5,585,057.63
C.2.3 Pek. Pemasangan Bubungan genteng biasa m1 15.84 110,066.18 1,743,448.23
C.2.4 Pek. Pemasangan List plank Kayu kelas II m1 46.66 40,959.00 1,911,146.94
C.2.5 Pek. Konsol Baja Ringan m2 7.84 187,000.00 1,466,080.00
C.2.6 Pek. Pasangan Genteng Biasa m2 7.84 178,094.95 1,396,264.41
JUMLAH C 35,624,393.09
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
MUSHOLA/ MESJID PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D PEKERJAAN ARSITEKTUR B.2.4.1
D.1 PEKERJAAN DINDING B.2.4.2
D.1.1 Bata Merah Spesi 1 : 5 m2 95.00 144,840.25 13,759,823.28
D.1.2 Plesteran Spesi 1 : 5 m2 190.00 60,668.70 11,527,052.24
D.1.3 Finishing Acian Kolom K2 m2 25.92 60,668.70 1,572,532.60
D.1.4 Pemasangan Glass block 20 x 20 m2 1.00 817,927.00 817,927.00
bv
D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES ###
D.2.1 Kusen Pintu P1 Borneo Super m³ 0.06 7,266,034.60 435,962.08
D.2.2 Kusen Pintu P2 Borneo Super m³ 0.11 7,266,034.60 782,551.93
D.2.3 Kusen PVC u/ Kamar Mandi unit 2.00 300,000.00 600,000.00
D.2.4 Kusen Jendela J1 m³ 0.35 7,266,034.60 2,526,836.19
D.2.5 kusen Bouvenlegh m³ 0.04 7,266,034.60 292,966.52
D.2.6 Daun pintu panil Kayu P1 kelas II m² 3.36 603,846.32 2,028,923.64
D.2.7 Daun pintu panil Kayu P2 Kelas II m² 3.36 603,846.32 2,028,923.64
D.2.8 Daun jendela J1 m² 1.52 603,846.32 919,054.10
D.2.9 Pasangan kunci Union/Royal Type Besar bh 3.00 250,000.00 750,000.00
D.2.10 Pasang engsel pintu bh 8.00 35,000.00 280,000.00
D.2.11 Pasang engsel Jendela bh 24.00 35,000.00 840,000.00
D.2.12 Hak Angin bh 12.00 35,000.00 420,000.00
D.2.13 Pasang Grendel Jendela bh 12.00 25,000.00 300,000.00
D.2.14 Pasang Espagnolet Pintu P1 bh 2.00 50,000.00 100,000.00
Pek. Kuda-ku
D.3 PEKERJAAN LANTAI Pek. Rangka a
D.3.1 Urugan Pasir Bawah Lantai t = 5 Cm m3 13.94 196,951.70 2,745,506.70
D.3.2 Keramik lantai 30x30 Sek"Mulia" m2 158.80 210,375.94 33,407,698.48
D.3.3 Keramik lantai kamar Mandi 20x20 Anti Slip Sek"Roman" m2 6.00 210,375.94 1,262,255.61
D.3.4 Keramik Dinding 20 x 25 Sek ' Roman ' m2 17.80 236,379.37 4,207,552.86
###
D.4 PEKERJAAN PLAFOND ###
D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 164.80 140,327.22 23,125,925.86
D.4.3 Pasangan List Plafond Gypsum 7 cm m1 35.00 12,000.00 420,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Plafond Sek. "VINILEX" m² 164.80 42,416.70 6,990,271.91
D.5.2 Lisplank Kayu Sek. "AVIAN" m² 9.33 42,416.70 395,832.63
D.5.3 Kusen Pintu, jendela Dan Bouvenlegh Sek. "AVIAN" m² 12.13 42,416.70 514,361.85
D.5.4 Daun Pintu dan daun Jendela Sek. "AVIAN" m² 11.60 42,416.70 492,118.54
D.5.5 Dinding Sek. "VINILEX" m² 1.00 21,195.39 21,195.39

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Instalasi Titik Lampu ttk 11.00 140,000.00 1,540,000.00
D.6.2 Instalasi Stop Kontak + saklar ttk 10.00 140,000.00 1,400,000.00
D.6.3 Armateur stop kontak Setara Broco bh 5.00 45,000.00 225,000.00
D.6.4 Armateur Saklar Ganda Setara Broco bh 5.00 45,000.00 225,000.00
D.6.5 Armateur Lampu TL 1 x 18 watt Setara Philips bh 1.00 175,000.00 175,000.00
D.6.6 Armateur Lampu SL 25 watt Setara Philips bh 10.00 75,000.00 750,000.00
JUMLAH D 117,880,273.02
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 2.00 1,407,095.80 2,814,191.60
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 2.00 398,013.00 796,026.00
E.1.3 Pek. Pemasangan Kran 3/4" bh 3.00 25,000.00 75,000.00
E.1.4 Pek. Pemasangan Floordraine Steinles bh 2.00 110,110.00 220,220.00
E.1.5 Pek. Pemasangan Wastafel Setara TOTO unit 1.00 1,168,000.00 1,168,000.00
E.1.6 Pek. Pemasangan pipa PVC dia 3/4' Setara Maspion m' 30.00 25,000.00 750,000.00
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
MUSHOLA/ MESJID PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
JUMLAH 5,823,437.60
I PEKERJAAN LAIN-LAIN Pek. Pemasan
I.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 750,000.00 750,000.00
JUMLAH 750,000.00
JUMLAH TOTAL 184,734,675.91
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
TOWER AIR DAN SUMUR AIR BERSIH PENGELOLAAN AIR LIMBAH
LOKASI : TAHUN ANGGARAN 2016
Harga Satuan Jumlah Harga
No Uraian Pekerjaan Satuan Volume
(Rp) (Rp)
A Pekerjaan Persiapan
1 Pas. Bouwplank m2 20 65,604.88 1,312,097.60

JUMLAH A 1,312,097.60
B Pekerjaan Galian dan Urugan
1 Galian tanah pondasi m3 4 73,672.50 294,690.00
2 Urugan tanah kembali m3 140.96 53,845.00 7,589,991.20
3 Urugan pasir di bawah pondasi 5 cm m3 0.4 114,120.60 45,648.24
4 Cerucuk Dia. 8 - 10 cm, L= 4m, dipasang jarak 30cm pada Pondasi m 177.77778 24,267.10 4,314,151.11
JUMLAH B 12,244,480.55
C Pekerjaan Pondasi dan Beton
1 Pondasi Telapak 1.00 x 1.00 x 30 cm beton K - 225 m3 0.8 5,416,779.50 4,333,423.60
2 Kolom 25/25
- Beton K-225 m3 1.875 1,116,966.11 2,094,311.46
- Tulangan Baja Ulir / polos (80 kg/m3) kg 150.00 23,014.59 3,452,187.75
- Bekisting Kolom m2 3.50 313,210.92 1,096,238.22
3 Sloof Beton 20/20
- Beton K-225 m3 0.48 1,116,966.11 536,143.73
- Tulangan Baja Ulir / polos (80 kg/m3) kg 38.40 23,014.59 883,760.06
- Bekisting Kolom m2 1.40 313,210.92 438,495.29
4 Balok beton 20/25 (Beton K-225)
- Beton K-225 m3 0.6 1,116,966.11 670,179.67
- Tulangan Baja Ulir / polos (80 kg/m3) kg 48.00 23,014.59 1,104,700.08
- Bekisting Balok m2 1.75 324,608.39 568,064.69
5 Balok beton 20/30 (Beton K-225)
- Beton K-225 m3 0.72 1,116,966.11 804,215.60
- Tulangan Baja Ulir / polos (80 kg/m3) kg 57.60 23,014.59 1,325,640.10
- Bekisting Balok m2 2.10 324,608.39 681,677.63
6 Plat Beton T=20 Cm (Beton K-225)
- Beton K-225 m3 5.4 1,116,966.11 6,031,617.01
- Tulangan Baja Ulir / polos (80 kg/m3) kg 432.00 23,014.59 9,942,300.72
- Bekisting Plat m2 9.00 415,943.55 3,743,491.95
JUMLAH C 37,706,447.57
D Pekerjaan Pasangan dan Plesteran
1 Plesteran + Acian 1:3 m2 70.8 60,668.70 4,295,343.68
JUMLAH D 4,295,343.68
E Pekerjaan Atap dan Tangga
1 Pek. Kuda-kuda Baja Ringan m2 10.47 170,000.00 1,779,069.77
2 Pek. Pemasangan atap Zincalum + Accessories (Ex. Interup warna Dop) m2 10.47 132,000.00 1,381,395.35
3 Tangga Besi m2 3 750,000.00 2,250,000.00
JUMLAH E 5,410,465.12
F Pekerjaan Pengecatan
1 Pek. Cat dinding Setara Vinilex m2 52.8 19,115.00 1,009,272.00
JUMLAH F 1,009,272.00
G Pekerjaan Sumur Bor Air Bersih
1 Pekerjaan Galian Sumur Bor, Dia 25cm (10") m' 120 750,000.00 90,000,000.00
2 Pemasangan Pipa Type AW Dia. 6" u/ konstruksi (Pipa Berlubang) m' 120 160,066.59 19,207,990.23
3 Pipa GI Medium 2" m' 100 57,750.00 5,775,000.00
4 Accessories Pipa Ls 1 150,000.00 150,000.00
5 Beton Tumbuk dan Cap Pipa Ls 1 500,000.00 500,000.00
6 Panel Listrik Unit 1 2,500,000.00 2,500,000.00
7 Pompa Listrik
- Pompa Submersiblle (1x 220) 3" Depth 98m, 2.3kW Unit 1 17,500,000.00 17,500,000.00
- Stabilizer unit 1 1,500,000.00 1,500,000.00
- Kabel Ls 1 1,000,000.00 1,000,000.00
JUMLAH G 138,132,990.23
JUMLAH TOTAL 200,111,096.74
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
GUDANG PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.4 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.6 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 4,399,034.24
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian tanah pondasi m3 27.20 73,672.50 2,003,892.00
B.1.2 Urugan tanah kembali m3 8.90 114,120.60 1,015,673.34
B.1.3 Urugan pasir di bawah pondasi m3 1.40 114,120.60 159,768.84
B.1.4 Urugan pasir di bawah lantai m3 4.52 114,120.60 516,281.59
B.1.5 Urugan pasir di bawah saluran keliling bangunan m3 1.68 114,120.60 191,722.61

B.2 PEKERJAAN PONDASI


B.2.1 Aanstamping batu belah m3 3.50 356,361.13 1,247,263.94
B.2.2 Pondasi batu belah 1:5 m3 5.40 726,749.34 3,924,446.45
B.2.3 Sloof Beton 15/20
- Beton K-225 m3 0.60 1,116,966.11 670,179.67
- Tulangan Baja Ulir / polos (80 kg/m3) kg 48.00 23,014.59 1,104,700.08
- Bekisting Balok m2 1.40 324,608.39 454,451.75
JUMLAH B 11,288,380.27
C PEKERJAAN STRUKTUR
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom beton 25/25
- Beton K-225 m3 0.78 1,116,966.11 871,233.57
- Tulangan Baja Ulir / polos (80 kg/m3) kg 62.40 23,014.59 1,436,110.10
- Bekisting Kolom m2 1.46 313,210.92 456,035.10
C.1.2 Kolom praktis 15/15
- Beton K-225 m3 0.30 1,116,966.11 335,089.83
- Tulangan Baja Ulir / polos (80 kg/m3) kg 24.00 23,014.59 552,350.04
- Bekisting Kolom m2 0.56 313,210.92 175,398.12
C.1.3 Ring balok beton 15/20
- Beton K-225 m3 0.60 1,116,966.11 670,179.67
- Tulangan Baja Ulir / polos (80 kg/m3) kg 48.00 23,014.59 1,104,700.08
- Bekisting Balok m2 1.40 324,608.39 454,451.75
C.1.4 Jurai Beton 12/12
- Beton K-225 m3 0.07 1,116,966.11 78,187.63
- Tulangan Baja Ulir / polos (80 kg/m3) kg 5.60 23,014.59 128,881.68
- Bekisting Balok m2 0.16 324,608.39 53,019.37

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 26.52 187,000.00 4,959,707.50
C.2.2 Pek. Pasangan Genteng Biasa m2 26.52 178,094.95 4,723,523.31
C.2.3 Pek. Pemasangan Bubungan genteng biasa m1 14.56 110,066.18 1,602,563.52
C.2.4 Pek. Pemasangan List plank Kayu kelas II m1 20.00 75,777.44 1,515,548.76
JUMLAH C 19,116,980.03
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Pasangan 1/2 bata 1:5 m2 57.60 144,840.25 8,342,798.11
D.1.2 Pasangan 1/2 bata 1:5 (Ampig) m2 10.40 144,840.25 1,506,338.55
D.1.3 Plesteran + Acian 1:3 m2 125.56 60,668.70 7,617,561.47
D.1.4 Pasangan Saluran keliling bangunan (Buis beton) m' 28.00 77,000.00 2,156,000.00
D.1.5 Pas. Rooster 20/20 kayu bh 2.00 55,000.00 110,000.00

D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES


D.2.1 Pek. Kusen Kayu Kelas II m3 0.19 7,266,034.60 7,266,034.60
D.2.2 Pek Daun Pintu Panel kayu Kelas II m2 1.68 603,846.32 603,846.32
D.2.3 Pek. Pintu PVC bh 1.00 300,000.00 300,000.00
D.2.4 Pek. Pemasangn engsel pintu m2 2.00 35,000.00 35,000.00
D.2.5 Pek. Pemasangan Kunci Pintu 2 slaag bh 1.00 125,000.00 125,000.00
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
GUDANG PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.3 PEKERJAAN LANTAI
D.3.1 Adukan spesi lantai 1:3 m3 2.26 60,668.70 137,111.25
D.3.2 Pas. Keramik 30/30 DN putih (setara Roman) m2 45.24 210,375.94 9,517,407.30

D.4 PEKERJAAN PLAFOND


D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 26.52 140,327.22 3,721,828.69
D.4.2 List Plafond Kayu 5 cm m1 80.00 12,000.00 960,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Pek. Cat dinding Setara Vinilex m2 125.56 21,195.39 2,661,293.67
D.5.2 Pek. Cat Plafon Setara Vinilex m2 34.80 42,416.70 1,476,101.11
D.5.3 Pek. Cat Listplank Setara Avian m2 12.76 42,416.70 541,237.07
D.5.4 Pek. Cat kusen Setara Avian m2 5.30 42,416.70 224,808.50
D.5.5 Pek. Cat daun pintu Setara Avian m2 6.72 42,416.70 285,040.21

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Pek. Pasangan Instalasi saklar (Broco), Kabel NYM 3x2.5 mm titik 2.00 140,000.00 280,000.00
D.6.2 Pek. Pasangan titik lampu pijar 40 watt titik 2.00 85,000.00 170,000.00
D.6.3 Accessories ls 1.00 150,000.00 150,000.00
JUMLAH D 48,187,406.86
E PEKERJAAN LAIN-LAIN
E.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 750,000.00 750,000.00
JUMLAH E 750,000.00
JUMLAH TOTAL 83,741,801.40
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
GARASI HANGGAR PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Papan Nama Proyek ls 1.00 250,000.00 250,000.00
A.3 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.4 Pek. Bouwplank m' 58.00 65,604.88 3,805,083.04
JUMLAH A 5,055,083.04
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi Setempat m3 16.80 73,672.50 1,237,698.00
B.1.2 Galian Tanah Pondasi Batu kali menerus m3 59.22 73,672.50 4,362,885.45
B.1.3 Urugan pasir m3 3.62 114,120.60 413,116.57
B.1.4 Lantai Kerja Spasi 1 : 5 m3 0.40 876,768.42 350,707.37
B.1.5 Cerucuk Dia. 8 - 10 cm, L= 4m, dipasang jarak 30cm pada m 350.00 24,267.10 8,493,485.00
Pondasi

B.2 PEKERJAAN PONDASI


B.2.1 Pondasi Aanstamping Batu Kali t=15 cm m3 5.01 356,361.13 1,786,557.11
B.2.2 Pondasi Batu Kali 1 : 5 m3 17.23 726,749.34 12,524,313.66
B.2.3 Beton Sloof 15/20
- Beton K-225 m3 1.88 1,116,966.11 2,099,896.29
- Tulangan Baja Ulir / polos (80 kg/m3) kg 150.40 23,014.59 3,461,393.58
- Bekisting Balok m2 7.31 324,608.39 2,373,248.04
B.2.4 Pondasi poor 1.00x1.00x0.2 m Beton K 225 m3 1.60 5,416,779.50 8,666,847.20
B.2.5 Kolom Stump K1 30x30 Beton K 225
- Beton K-225 m3 0.69 1,116,966.11 766,983.40
- Tulangan Baja Ulir / polos (80 kg/m3) kg 54.93 23,014.59 1,264,267.87
- Bekisting Kolom m2 0.89 313,210.92 278,796.39
JUMLAH B 48,080,195.93
C PEKERJAAN STRUKTUR
C.1 PEKERJAAN KOLOM DAN RING BALK
C.1.1 Kolom K1 30/0 Beton
- Beton K-225 m3 4.50 1,116,966.11 5,026,347.51
- Tulangan Baja Ulir / polos (80 kg/m3) kg 360.00 23,014.59 8,285,250.60
- Bekisting Kolom m2 5.83 313,210.92 1,827,063.70
C.1.2 Kolom KP 15/15 Beton
- Beton K-225 m3 0.37 1,116,966.11 417,000.68
- Tulangan Baja Ulir / polos (80 kg/m3) kg 29.87 23,014.59 687,368.94
- Bekisting Kolom m2 1.94 313,210.92 606,314.47
C.1.3 Ring Balk 20/35 Beton m3 4.39 4,958,521.00 21,751,378.79
- Beton K-225 m3 4.39 1,116,966.11 4,899,758.02
- Tulangan Baja Ulir / polos (80 kg/m3) kg 350.93 23,014.59 8,076,585.03
- Bekisting Balok m2 7.31 324,608.39 2,373,248.04
C.1.4 Ring Balk 15/20 Beton -
- Beton K-225 m3 0.30 1,116,966.11 335,089.83
- Tulangan Baja Ulir / polos (80 kg/m3) kg 24.00 23,014.59 552,350.04
- Bekisting Balok m2 1.17 324,608.39 378,709.79

C.2 PEKERJAAN STRUKTUR ATAP


C.2.1 Pek. Rangka Atap Baja Ringan m2 126.67 170,000.00 21,533,333.33
C.2.2 Pek. Pasangan Genteng Zincalum t = 0.35 cm m2 126.67 132,000.00 16,720,000.00
C.2.3 Pek. Pemasangan Bubungan Zincalum m1 20.00 130,200.00 2,604,000.00
C.2.4 Pek. Pemasangan List plank Kayu Borneo Super 2/20 m1 50.00 75,777.44 3,788,871.90
C.2.7 Pek. seng Plesing m1 6.93 159,149.00 1,103,433.07
JUMLAH C 100,966,103.74
D PEKERJAAN ARSITEKTUR
D.1 PEKERJAAN DINDING
D.1.1 Bata Merah Spesi 1 : 5 m2 239.80 144,840.25 34,732,690.75
D.1.2 Bata Merah Spesi 1 : 3 m2 16.67 159,975.41 2,666,256.82
D.1.3 Plesteran Spesi 1 : 5 m2 479.60 60,668.70 29,096,706.60
D.1.4 Plesteran Spesi 1 : 3 m2 16.67 68,543.62 1,142,393.63
D.1.5 Pemasangan Folding Gate m2 21.33 350,000.00 7,466,666.67
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
GARASI HANGGAR PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES
D.2.1 Kusen Pintu P1 Kayu Kelas II m³ 0.24 7,266,034.60 1,743,848.30
D.2.2 Kusen Pintu PB Kayu Kelas II m³ 0.11 7,266,034.60 782,551.93
D.2.3 Kusen PVC u/ Kamar Mandi unit 1.00 300,000.00 300,000.00
D.2.4 Kusen Bouvenlegh BV 1 m³ 0.01 7,266,034.60 87,192.42
D.2.5 kusen Bouvenlegh BV 2 m³ 0.26 7,266,034.60 1,889,169.00
D.2.6 Daun pintu panil Kayu P1 B. Super m² 1.12 603,846.32 676,307.88
D.2.7 Kusen Pintu dan Daun pintu Besi m² 1.12 1,200,000.00 1,344,000.00
D.2.8 Pasangan kunci Union/Royal Type Besar bh 2.00 475,310.00 950,620.00
D.2.9 Pasang engsel pintu bh 4.00 35,000.00 140,000.00

D.3 PEKERJAAN LANTAI


D.3.1 Urugan Sirtu dipadatkan 20 cm m3 37.33 114,120.60 4,260,502.40
D.3.1 Urugan Pasir Bawah Lantai t = 10 Cm m3 18.67 114,120.60 2,130,251.20
D.3.2 Pasangan Lantai Kerja Spasi 1 : 3 Cm t = 5 cm m3 9.33 876,768.42 8,183,171.92
D.3.3 Keramik lantai 30x30 Sek"Mulia" m2 26.67 210,375.94 5,610,024.93
D.3.4 Keramik lantai kamar Mandi Anti Slip 20x20 Sek"Mulia" m2 2.17 168,279.00 364,604.50
D.3.5 Keramik Dinding 20x20 sekualitas Roman m2 8.67 236,379.37 2,048,621.24
D.3.6 Pemasangan Gravel Ø 30 cm m1 56.67 110,880.00 6,283,200.00
D.3.7 Pemasangan Wiremash M 8 m2 186.67 611,000.00 114,053,333.33
D.3.8 Pemasangan Beton t = 30 cm K 225 m³ 56.00 1,116,966.11 62,550,102.36
D.3.9 pemasangan Rabat beton m³ 4.20 876,768.42 3,682,427.36

D.4 PEKERJAAN PLAFOND


D.4.1 Pekerjaan Rangka Plafond dan Plywood m² 26.67 140,327.22 3,742,059.20
D.4.2 List Plafond kayu 5 cm m² 35.00 12,000.00 420,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Plafond Sek. "VINILEX" m² 26.67 42,416.70 1,131,111.96
D.5.2 Lisplank Kayu Sek. "AVIAN" m² 33.33 42,416.70 1,413,889.95
D.5.3 Kusen Pintu, jendela Dan Bouvenlegh Sek. "AVIAN" m² 15.00 42,416.70 636,250.48
D.5.4 Daun Pintu dan daun Jendela Sek. "AVIAN" m² 2.24 42,416.70 95,013.40
D.5.5 Dinding Sek. "VINILEX" m² 496.27 21,195.39 10,518,567.53

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Instalasi Titik Lampu ttk 8.00 140,000.00 1,120,000.00
D.6.2 Instalasi Stop Kontak ttk 5.00 140,000.00 700,000.00
D.6.3 Instalasi saklar ttk 3.00 140,000.00 420,000.00
D.6.4 Armateur stop kontak Setara Broco bh 5.00 45,000.00 225,000.00
D.6.5 Armateur Saklar Setara Broco bh 3.00 45,000.00 135,000.00
D.6.6 Armateur Lampu TL 2 x 16 watt Setara Philips bh 5.00 275,000.00 1,375,000.00
D.6.7 Armateur Lampu SL 25 watt Setara Philips bh 7.00 75,000.00 525,000.00
D.6.8 pemasangan Tray Horozontal m' 35.00 350,000.00 12,250,000.00
JUMLAH D 326,891,535.77
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 1.00 1,859,691.02 1,859,691.02
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 1.00 519,850.43 519,850.43
E.1.3 Pek. Pemasangan Kran 3/4" bh 2.00 25,000.00 50,000.00
E.1.4 Pek. Pemasangan Floordraine Steinles bh 1.00 110,110.00 110,110.00
E.1.5 Pek. Pemasangan pipa PVC dia 3/4' Setara Maspion m' 15.00 25,000.00 375,000.00
JUMLAH E 2,914,651.45
F PEKERJAAN LAIN-LAIN
F.1 PEKERJAAN PEMBERSIHAN SISA - SISA PEKERJAAN ls 1.00 1,000,000.00 1,000,000.00
JUMLAH F 1,000,000.00
JUMLAH TOTAL 484,907,569.93
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM PENGELOLAAN
CUCI MOBIL AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.3 Pek. Bouwplank m' 48.00 65,604.88 3,149,034.24
JUMLAH A 4,149,034.24
B PEKERJAAN TANAH DAN PONDASI
B.1 PEKERJAAN TANAH
B.1.1 Galian tanah pondasi m3 54.20 73,672.50 3,993,049.50
B.1.2 Galian Saluran Air kotor m3 36.09 73,672.50 2,658,693.18
B.1.3 Galian Tanah Sloof m3 3.52 73,672.50 259,327.20
B.1.4 Urugan pasir t = 10 cm m3 0.96 114,120.60 109,555.78
B.1.5 Urugan tanah kembali m3 28.00 53,845.00 1,507,660.00
B.1.6 Pasangan lantai Kerja 5 cm Spasi 1 : 5 m3 0.48 60,668.70 29,363.65
B.1.7 Cerucuk Dia. 8 - 10 cm, L= 4m, dipasang jarak 30cm pada Pondasi m3 355.56 24,267.10 8,628,302.22

B.2 PEKERJAAN PONDASI


B.2.1 Urugan Pasir t = 5 cm m3 0.53 114,120.60 60,483.92
B.2.1 Aanstamping batu belah t = 10 cm m3 0.89 356,361.13 317,161.40
B.2.2 Pondasi batu belah Spasi 1:5 m3 6.64 726,749.34 4,825,615.63
B.2.3 Pasangan Sloof Beton 20/25 Sloof Beton 20/25 (
- Beton K-225 m3 2.60 1,116,966.11 2,904,111.90
- Tulangan Baja Ulir / polos (80 kg/m3) kg 208.00 23,014.59 4,787,033.68
- Bekisting Balok m2 6.07 324,608.39 1,969,290.92
B.2.4 Pasangan Sloof Beton 15/20
- Beton K-225 m3 0.50 1,116,966.11 558,483.06
- Tulangan Baja Ulir / polos (80 kg/m3) kg 40.00 23,014.59 920,583.40
- Bekisting Balok m2 1.94 324,608.39 631,182.99
B.2.5 Pasangan Kolom Stump 30 x 30
- Beton K-225 m3 1.08 1,116,966.11 1,206,323.40
- Tulangan Baja Ulir / polos (80 kg/m3) kg 86.40 23,014.59 1,988,460.14
- Bekisting Kolom m2 1.40 313,210.92 438,495.29
B.2.6 Pondasi beton Poor 1.00 x 1.00 x 0.3 cm Beton K-225 m3 3.03 5,416,779.50 16,429,092.22
JUMLAH B 54,222,269.48
C PEKERJAAN STRUKTUR Lantai kerja pondas
C.1 PEKERJAAN KOLOM DAN RING BALK Pondasi beton + tia
C.1.1 Kolom 30/30 Beton Kolom beton 30/30
- Beton K-225 m3 3.48 1,116,966.11 3,887,042.08
- Tulangan Baja Ulir / polos (80 kg/m3) kg 278.40 23,014.59 6,407,260.46
- Bekisting Kolom m2 4.51 313,210.92 1,412,929.26
C.1.2 Kolom Praktis Kp 15x15 beton
- Beton K-225 m3 0.48 1,116,966.11 536,143.73
- Tulangan Baja Ulir / polos (80 kg/m3) kg 38.40 23,014.59 883,760.06
- Bekisting Kolom m2 2.49 313,210.92 779,547.18
C.1.3 Ring balok beton 20/30 Sloof beton 15/20 (
- Beton K-225 m3 3.35 1,116,966.11 3,741,836.48
- Tulangan Baja Ulir / polos (80 kg/m3) kg 268.00 23,014.59 6,167,908.78
- Bekisting Balok m2 6.51 324,608.39 2,114,463.01
C.1.4 Ring balok beton 15/20 Pondasi batu belah
- Beton K-225 m3 0.35 1,116,966.11 390,938.14
- Tulangan Baja Ulir / polos (80 kg/m3) kg 28.00 23,014.59 644,408.38
- Bekisting Balok m2 1.36 324,608.39 441,828.09
C.1.5 Beton Cyclop u/ landasan (K-225) m3 10.06 3,584,066.53 36,070,045.56
C.1.6 Rabat beton untuk landasan beton tumbuk m3 2.84 876,768.42 2,490,022.31
Ring balok beton 15
C.2 PEKERJAAN STRUKTUR ATAP DAN GRILL
PEKERJAA ATAP BAJA
C.2.1 Pek. Kuda-kuda Baja IWF 200.100 kg 794.67 25,280.00 20,089,257.60
C.2.2 Pek. Gordeng Baja Channel kg 938.75 25,280.00 23,731,600.00
C.2.3 Accessories Baja ls 1.00 150,000.00 150,000.00
C.2.4 Pek. Pemasangan atap Zincalum + Accessories (Ex. Interup warna Dop) m2 142.50 132,000.00 18,810,000.00
C.2.5 Papan Ruiter 2/20 Kayu 2/20 (Borneo super) m' 12.50 40,959.00 511,987.50
C.2.6 Pek. Pemasangan Nok Atap Zincalum m' 12.00 130,200.00 1,562,400.00
C.2.7 Pek. Lisplank kayu (Borneo Super) 2/20 u/ Konsol m' 25.00 40,959.00 1,023,975.00
Pekerjaan Grill
C.2.8 Pek. Pemasangan Baja kanal 75.40 kg 309.67 25,280.00 7,828,457.60
C.2.9 Pek. Pemasangan Baja kanal 150.75 kg 74.48 25,280.00 1,882,854.40
C.2.10 Pek. Pemasangan Baja Siku 40.40.4 kg 55.13 25,280.00 1,393,736.96
Atap Kayu
C.2.11 Pek. Kuda-kuda + konsol (Borneo super) m3 0.30 4,646,653.00 1,393,995.90
C.2.12 Pek. Rangka atap genteng (Kaso 5/7, Reng 3/4 Kayu Borneo Super) m2 14.58 59,029.00 860,347.67
C.2.13 Pek. Pasangan Genteng Plentong Ex. Jatiwangi m2 14.58 58,800.00 857,010.00
C.2.14 Pek. List Plank 2/20 kayu (Borneo Super) m' 11.00 40,959.00 450,549.00
JUMLAH C 146,514,305.17
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM PENGELOLAAN
CUCI MOBIL AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)
D PEKERJAAN ARSITEKTUR Pek. Pemasangan
D.1 PEKERJAAN DINDING Papan Ruiter 2/20 K
D.1.1 Pasangan Dinding bata 1/2 bata 1:5 m2 34.40 144,840.25 4,982,504.43
D.1.2 Plesteran + Acian 1:5 m2 58.80 60,668.70 3,567,319.32
D.1.3 Pasangan 1/2 bata 1:5 u/ saluran m2 34.70 144,840.25 5,025,956.50
D.1.4 Plesteran + Acian 1:5 m2 34.70 60,668.70 2,105,203.75

D.2 PEKERJAAN KUSEN PINTU , JENDELA DAN ASSESORIES


D.2.1 Pek. Kusen Kayu Kelas II m3 0.10 7,266,034.60 726,603.46
D.2.2 Pek Daun Pintu Panel kayu Kelas II m2 1.68 603,846.32 1,014,461.82
D.2.3 Pek. Pintu PVC bh 1.00 300,000.00 300,000.00
D.2.4 Pek. Pemasangan handel pintu bh 1.00 75,000.00 75,000.00
D.2.5 Pek. Pemasangan engsel pintu bh 2.00 35,000.00 70,000.00
D.2.6 Pek. Pemasangan kunci gembok + gembok (globe) bh 1.00 150,000.00 150,000.00

D.3 PEKERJAAN LANTAI


D.3.1 urugan pasir 5 cm m3 1.68 196,951.70 330,878.86
D.3.2 Pas. Keramik 30/30 DN putih (setara Roman) m2 32.50 210,375.94 6,837,217.89
D.3.3 Pas. Keramik 20/20 WC/anti slip m2 16.00 210,375.94 3,366,014.96

D.4 PEKERJAAN PLAFOND


D.4.1 Pekerjaan Rangka Plafond dan Plywood m2 5.25 140,327.22 736,717.91
D.4.2 List Plafond kayu 5 cm m2 11.50 12,000.00 138,000.00

D.5 PEKERJAAN PENGECATAN


D.5.1 Pek. Cat dinding Setara Vinilex m2 64.40 21,195.39 1,364,983.37
D.5.2 Pek. Cat Plafon Vinilex m2 5.25 42,416.70 222,687.67
D.5.3 Pek. Cat Listplank Setara Avian m2 11.00 42,416.70 466,583.68
D.5.4 Pek. Cat kusen Setara Avian m2 4.17 42,416.70 176,877.63
D.5.5 Pek. Cat daun pintu Setara Avian m2 3.36 42,416.70 142,520.11

D.6 PEK. MEKANIKAL ELEKTRIKAL


D.6.1 Pek. Instalasi saklar, Kabel NYM 3x2.5 mm ttk 4.00 140,000.00 560,000.00
D.6.2 Pek. Instalasi stop kontak Kabel NYM 3x2.5 mm ttk 2.00 140,000.00 280,000.00
D.6.3 Pek. Instalasi Titik lampu ttk 7.00 140,000.00 980,000.00
D.6.4 Pek. Pemasangan Saklar Setara broco bh 4.00 45,000.00 180,000.00
D.6.5 Pek. Pemasangan Stop Kontak Setara Broco bh 2.00 45,000.00 90,000.00
D.6.6 Pek. Pasangan titik lampu pijar 40 watt bh 3.00 150,000.00 450,000.00
D.6.7 Pek. Pemasangan titik lampu TL 40 watt bh 4.00 295,000.00 1,180,000.00
D.6.8 Pek. Pemasangan Panel Listrik unit 1.00 750,000.00 750,000.00
D.6.9 Accessories ls 1.00 150,000.00 150,000.00
JUMLAH D 36,419,531.36
E PEKERJAAN SANITAIR
E.1 PEK. SANITASI
E.1.1 Pek. Pemasangan Bak mandi batu bata bh 1.00 1,859,691.02 1,859,691.02
E.1.2 Pek. Pemasangan Kloset jongkok Standar Ex INA bh 1.00 519,850.43 519,850.43
E.1.3 Pek. Pemasangan Kran 3/4" bh 4.00 25,000.00 100,000.00
E.1.4 Pek. Pemasangan Floordraine Steinles bh 1.00 110,110.00 110,110.00
E.1.5 Pek Pemasangan pipa PVC 3/4" Setara Maspion m' 24.00 25,000.00 600,000.00
E.1.6 Pek. Pemasangan pipa PVC 4 " Setara Maspion m' 6.00 85,924.01 515,544.03
JUMLAH E 3,705,195.48
F PEKERJAAN LAIN-LAIN
F.1 Pemberesan dan angkutan sisa pekerjaan ls 1.00 1,000,000.00 1,000,000.00
JUMLAH F 1,000,000.00
JUMLAH TOTAL 246,010,335.73
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
PAGAR PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.4 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.6 Pek. Bouwplank m' 92.00 65,604.88 6,035,648.96
JUMLAH A 7,035,648.96
B PEKERJAAN PAGAR DEPAN, L= 145 meter
B.1 PEKERJAAN TANAH
B.1.1 Galian Tanah Pondasi m3 2.04 73,672.50 150,600.37
B.1.2 Pemasangan Angkur dia 12 cm bh 192.89 6,000.00 1,157,360.00
B.1.3 Beton Tumbuk m3 2.04 876,768.42 1,792,278.69
B.1.4 Pemasangan Pagar BRC m2 144.67 202,000.00 29,223,340.00
JUMLAH B 32,323,579.07
C PEKERJAAN PAGAR SAMPING DAN BELAKANG, L= 433 meter
C.1 PEKERJAAN TANAH
C.1.1 Galian Tanah Pondasi m3 64.95 73,672.50 4,785,028.88
C.1.2 Pondasi Plat Setempat bh 181.42 563,345.07 102,200,184.42
C.1.3 Pemasangan Pagar Beton Precast t=2,8 m m1 433.00 495,182.26 214,413,916.96
JUMLAH C 321,399,130.25
D PEKERJAAN LAIN-LAIN
D.1 PEKERJAAN PEMBERSIHAN SISA - SISA PEKERJAAN ls 1.00 750,000.00 750,000.00
JUMLAH D 750,000.00
JUMLAH TOTAL 361,508,358.28
RENCANA ANGGARAN BIAYA
ITEM PEKERJAAN : PEKERJAAN
FASILITASI PENYUSUNAN RENCANA INDUK SISTEM
DINDING PENAHAN TANAH PENGELOLAAN AIR LIMBAH
LOKASI : KOTA SERANG TAHUN ANGGARAN 2016

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Admnistrasi dan Dokumentasi ls 1.00 500,000.00 500,000.00
A.2 Air kerja & Listrik Kerja ls 1.00 500,000.00 500,000.00
A.3 Pek. Profil DPT/Bouwplank Per 5m m' 291.00 13,120.98 3,818,204.02
JUMLAH A 4,818,204.02
B PEKERJAAN DINDING PENAHAN TANAH, L= 291 meter
B.1 Pek. Galian Tanah Pondasi m3 291.00 73,672.50 21,438,697.50
B.2 Pek. Pasir urug dibawah pondasi t= 5cm m3 11.64 114,120.60 1,328,363.78
B.3 Pek. Lantai Kerja dibawah pondasi t= 5cm m2 232.80 143,338.69 33,369,247.03
B.4 Pek. Pasangan Batu kali camp. 1Pc : 5 Ps m3 320.10 726,749.34 232,632,464.37
B.5 Pek. Plesteran kepala DPT camp. 1Pc : 5 Ps m2 145.50 60,668.70 8,827,295.27
B.6 Pek. Acian Kepala DPT m2 145.50 28,600.00 4,161,300.00
B.7 Pek. Pasangan pasang pipa sulingan dia. 2" m1 291.00 42,280.84 12,303,723.71
B.8 Pek. Pasangan pasang ijuk Kg 291.00 7,500.00 2,182,500.00
B.9 Pek. Urugan Tanah Kembali m3 97.00 53,845.00 5,222,965.00
JUMLAH B 321,466,556.67
C PEKERJAAN LAIN-LAIN
C.1 PEKERJAAN PEMBERSIHAN SISA - SISA PEKERJAAN ls 1.00 750,000.00 750,000.00
JUMLAH C 750,000.00
JUMLAH TOTAL 327,034,760.69
I. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M1 Pagar sementara dari kayu tinggi 2 meter
Bahan 1.250 Btg Kayu cerucuk diameter 8 - 10 Cm 24,200.00 30,250.00
5.000 Kg Semen 1,595.00 7,975.00
0.005 M3 Pasir beton 146,630.00 733.15
0.090 M3 Batu pecah 2/3 225,830.00 20,324.70
0.072 M3 Kayu klas IV 2,090,000.00 150,480.00
0.060 Kg Paku 18,040.00 1,082.40
0.400 Ltr Teer / Residu 1,254.53 501.81
Tenaga 0.200 Oh Tukang 93,500.00 18,700.00
0.400 Oh Pekerja 85,000.00 34,000.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.020 Oh Mandor 129,000.00 2,580.00
JUMLAH 268,777.06
PROFIT 10 % 295,654.77
2 1 M1 Pagar sementara dari seng gelombang tinggi 2 m
Bahan 1.250 Btg Kayu cerucuk diameter 8 - 10 Cm 24,200.00 30,250.00
2.500 Kg Semen 1,595.00 3,987.50
1.200 Lbr Seng gelombang 39,600.00 47,520.00
0.005 M3 Pasir beton 146,630.00 733.15
0.009 M3 batu pecah 2/3 225,830.00 2,032.47
0.072 M3 Kayu klas IV 2,090,000.00 150,480.00
0.060 Kg Paku 18,040.00 1,082.40
0.450 Kg Cat meni besi 55,660.00 25,047.00
Tenaga 0.400 Oh Tukang 93,500.00 37,400.00
0.200 Oh Pekerja 85,000.00 17,000.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.020 Oh Mandor 129,000.00 2,580.00
JUMLAH 320,262.52
PROFIT 10 % 352,288.77
3 1 M1 Pengukuran dan pemasangan bowplank
Bahan 0.012 M3 Kayu klas IV 2,090,000.00 25,080.000
0.020 Kg Paku 18,040.00 360.800
0.007 M3 Kayu klas IV 2,090,000.00 14,630.000
Tenaga 0.100 Oh Tukang 93,500.00 9,350.000
0.100 Oh Pekerja 85,000.00 8,500.000
0.010 Oh Kepala tukang 107,500.00 1,075.000
0.005 Oh Mandor 129,000.00 645.000
JUMLAH 59,640.80
PROFIT 10 % 65,604.88
4 1 M2 Pembuatan kantor sementara lantai plesteran
Bahan 1.250 Btg Kayu cerucuk diameter 8 - 10 Cm 24,200.00 30,250.00
0.180 M3 Kayu klas IV 2,090,000.00 376,200.00
0.080 Kg Paku 18,040.00 1,443.20
1.100 Kg Besi strip 18,260.00 20,086.00
35.000 Kg Semen 1,595.00 55,825.00
0.150 M3 Pasir pasang 146,630.00 21,994.50
0.100 M3 Pasir beton 146,630.00 14,663.00
0.150 M3 Batu pecah 2/3 225,830.00 33,874.50
30.000 Bh Batu bata besar 1,595.00 47,850.00
0.250 Lbr Seng gelombang 39,600.00 9,900.00
0.200 Bh Jendela kaca nako rayben 5 mm (lengkap) 35,200.00 7,040.00
0.080 M2 Kaca bening 5 mm 129,140.00 10,331.20
0.150 Bh Kunci tanam 2 x putar 96,800.00 14,520.00
0.060 Lbr Plywood 4 mm 99,000.00 5,940.00
Tenaga 2.000 Oh Tukang 93,500.00 187,000.00
2.000 Oh Pekerja 85,000.00 170,000.00
0.300 Oh Kepala tukang 107,500.00 32,250.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 1,045,617.40
PROFIT 10 % 1,150,179.14
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
5 1 M2 Pembuatan gudang semen dan peralatan
Bahan 1.700 Btg Kayu cerucuk diameter 8 - 10 Cm 24,200.00 41,140.00
0.210 M3 Kayu klas IV 2,090,000.00 438,900.00
0.300 Kg Paku 18,040.00 5,412.00
10.500 Kg Semen 1,595.00 16,747.50
0.030 M3 Pasir beton 146,630.00 4,398.90
0.050 M3 Batu pecah 2/3 225,830.00 11,291.50
1.500 Lbr Seng gelombang 39,600.00 59,400.00
0.250 Lbr Seng plat 29,700.00 7,425.00
Tenaga 2.000 Oh Tukang 93,500.00 187,000.00
1.000 Oh Pekerja 85,000.00 85,000.00
0.200 Oh Kepala tukang 107,500.00 21,500.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 884,664.90
PROFIT 10 % 973,131.39
6 1 M2 membersihkan lapangan dan peralatan
Bahan 0.100 Oh Pekerja 85,000.00 8,500.00
0.005 Oh mandor 129,000.00 645.00
JUMLAH 9,145.00
PROFIT 10 % 10,059.50
7 1 M2 Pembuatan bedeng pekerja
Bahan 1.250 Btg Kayu cerucuk diameter 8 - 10 Cm 24,200.00 30,250.00
0.186 M3 Kayu klas IV 2,090,000.00 388,740.00
0.300 Kg Paku 18,040.00 5,412.00
18.000 Kg Semen 1,595.00 28,710.00
0.030 M3 Pasir beton 146,630.00 4,398.90
0.050 M3 Batu pecah 2/3 225,830.00 11,291.50
1.500 Lbr Seng gelombang 39,600.00 59,400.00
1.350 Lbr Plywood 4 mm 99,000.00 133,650.00
Tenaga 2.000 Oh Tukang 93,500.00 187,000.00
1.000 Oh Pekerja 85,000.00 85,000.00
0.200 Oh Kepala tukang 107,500.00 21,500.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 961,802.40
PROFIT 10 % 1,057,982.64
8 1 M2 Pembuatan jalan sementara
Bahan 0.150 M3 Batu Belah / Batu Gunung 123,860.00 18,579.000
0.090 M3 Batu pecah 5/7 176,990.00 15,929.100
0.001 M3 Pasir pasang 146,630.00 146.630
Tenaga 1.000 Oh Pekerja 85,000.00 85,000.000
0.005 Oh Mandor 129,000.00 645.000
JUMLAH 120,299.73
PROFIT 10 % 132,329.70
9 1 M3 Bongkaran beton bertulang
Tenaga 13.334 Oh Pekerja 85,000.00 1,133,390.00
0.666 Oh Mandor 129,000.00 85,914.00
JUMLAH 1,219,304.00
PROFIT 10 % 1,341,234.40
10 1 M3 Bongkaran dinding tembok bata merah
Tenaga 6.667 Oh Pekerja 85,000.00 566,695.00
0.333 Oh Mandor 129,000.00 42,957.00
JUMLAH 609,652.00
PROFIT 10 % 670,617.20
II. ANALISA HARGA SATUAN PEKERJAAN TANAH

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M3 Galian tanah biasa sedalam 1 m
Tenaga 0.750 Oh Pekerja 85,000.00 63,750.00
0.025 Oh Mandor 129,000.00 3,225.00
JUMLAH 66,975.00
PROFIT 10 % 73,672.50
2 1 M3 Galian tanah biasa sedalam 2 m
Tenaga 0.900 Oh Pekerja 85,000.00 76,500.00
0.045 Oh Mandor 129,000.00 5,805.00
JUMLAH 82,305.00
PROFIT 10 % 90,535.50
3 1 m3 Galian tanah biasa sedalam 3 m
Tenaga 1.050 Oh Pekerja 85,000.00 89,250.00
0.067 Oh Mandor 129,000.00 8,643.00
JUMLAH 97,893.00
PROFIT 10 % 107,682.30
4 1 M3 Galian tanah keras sedalam 1 m
Tenaga 1.000 Oh Pekerja 85,000.00 85,000.00
0.032 Oh Mandor 129,000.00 4,128.00
JUMLAH 89,128.00
PROFIT 10 % 98,040.80
5 1 M3 Galian tanah cadas sedalam 1 m
Tenaga 1.500 Oh Pekerja 85,000.00 127,500.00
0.060 Oh Mandor 129,000.00 7,740.00
JUMLAH 135,240.00
PROFIT 10 % 148,764.00
6 1 M3 Galian tanah lumpur sedalam 1 m
Tenaga 1.200 Oh Pekerja 85,000.00 102,000.00
0.045 Oh Mandor 129,000.00 5,805.00
JUMLAH 107,805.00
PROFIT 10 % 118,585.50
7 1 M3 Pekerjaan stripping tanah tebing setinggi 1 m
Tenaga 0.050 Oh Pekerja 85,000.00 4,250.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 4,895.00
PROFIT 10 % 5,384.50
8 1 M3 Pembuangan tanah sejauh 30 m
Tenaga 0.330 Oh Pekerja 85,000.00 28,050.00
0.010 Oh Mandor 129,000.00 1,290.00
JUMLAH 29,340.00
PROFIT 10 % 32,274.00
9 1 M3 Urugan kembali
Tenaga 0.500 Oh Pekerja 85,000.00 42,500.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 48,950.00
PROFIT 10 % 53,845.00
10 1 M3 Pemadatan tanah
Tenaga 0.500 Oh Pekerja 85,000.00 42,500.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 48,950.00
PROFIT 10 % 53,845.00
11 1 M3 Urugan pasir urug
Bahan 1.200 M3 Pasir urug 64,130.00 76,956.00
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.010 Oh Mandor 129,000.00 1,290.00
JUMLAH 103,746.00
PROFIT 10 % 114,120.60
12 1 M3 Urugan sirtu padat
Bahan 1.200 M3 Sirtu 128,810.00 154,572.00
Tenaga 0.250 Oh Pekerja 85,000.00 21,250.00
0.025 Oh mandor 129,000.00 3,225.00
JUMLAH 179,047.00
PROFIT 10 % 196,951.70
13 1 M3 Urugan tanah puru
Bahan 1.200 M3 Tanah puru 132,000.00 158,400.00
Tenaga 0.250 Oh Pekerja 85,000.00 21,250.00
0.025 Oh mandor 129,000.00 3,225.00
JUMLAH 182,875.00
PROFIT 10 % 201,162.50
14 1 M2 Pembuatan jalan Sementara, tebal 25 cm
Bahan 0.250 M3 Batu belah 123,860.00 30,965.00
0.030 M3 Batu pecah 2/3 225,830.00 6,774.90
0.050 M3 Pasir urug 64,130.00 3,206.50
Tenaga 1.000 Oh Pekerja 85,000.00 85,000.00
0.100 Oh Mandor 129,000.00 12,900.00
JUMLAH 138,846.40
PROFIT 10 % 152,731.04
III. ANALISA HARGA SATUAN PEKERJAAN PONDASI

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M3 Pasang pondasi batu belah. 1 Pc : 4 Ps
Bahan 1.20 M3 Batu Belah / Batu Gunung 123,860.00 148,632.00
163.00 Kg Semen 1,595.00 259,985.00
0.52 M3 Pasir pasang 146,630.00 76,247.60
Tenaga 1.500 Oh Pekerja 85,000.00 127,500.00
0.750 Oh Tukang 93,500.00 70,125.00
0.075 Oh Kepala tukang 107,500.00 8,062.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 700,227.10
PROFIT 10 % 770,249.81
2 1 M3 Pasang pondasi batu belah. 1 Pc : 5 Ps
Bahan 1.20 M3 Batu Belah / Batu Gunung 123,860.00 148,632.00
136.00 Kg Semen 1,595.00 216,920.00
0.544 M3 Pasir pasang 146,630.00 79,766.72
Tenaga 1.500 Oh Pekerja 85,000.00 127,500.00
0.750 Oh Tukang 93,500.00 70,125.00
0.075 Oh Kepala tukang 107,500.00 8,062.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 660,681.22
PROFIT 10 % 726,749.34
3 1 M3 Pasang Batu kosong (anstamping)
Bahan 1.20 M3 Batu Belah / Batu Gunung 123,860.00 148,632.00
0.432 M3 Pasir pasang 146,630.00 63,344.16
Tenaga 0.780 Oh Pekerja 85,000.00 66,300.00
0.390 Oh Tukang 93,500.00 36,465.00
0.039 Oh Kepala tukang 107,500.00 4,192.50
0.039 Oh Mandor 129,000.00 5,031.00
JUMLAH 323,964.66
PROFIT 10 % 356,361.13
4 1 M3 Pasang pondasi sumuran diameter 100 cm
Bahan 0.45 M3 Batu Belah / Batu Gunung 123,860.00 55,737.00
194.00 Kg Semen 1,595.00 309,430.00
0.312 M3 Pasir beton 146,630.00 45,748.56
0.468 M3 Batu pecah 2/3 225,830.00 105,688.44
Tenaga 2.400 Oh Pekerja 85,000.00 204,000.00
0.800 Oh Tukang 93,500.00 74,800.00
0.080 Oh Kepala tukang 107,500.00 8,600.00
0.119 Oh Mandor 129,000.00 15,351.00
JUMLAH 819,355.00
PROFIT 10 % 901,290.50
IV. ANALISA HARGA SATUAN PEKERJAAN PASANG DINDING
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
1 1 M2 pasangan bata merah tebal 1 bata. 1 Pc : 4 ps
Bahan 90.000 Bh Batu bata besar 1,595.00 143,550.00
26.550 Kg Semen 1,595.00 42,347.25
0.093 M3 Pasir pasang 146,630.00 13,636.59
Tenaga 0.650 Oh Pekerja 85,000.00 55,250.00
0.200 Oh Tukang 93,500.00 18,700.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.030 Oh Mandor 129,000.00 3,870.00
JUMLAH 279,503.84
PROFIT 10 % 307,454.22
2 1 M2 pasangan bata merah tebal 1 bata. 1 Pc : 5 ps
Bahan 90.000 Bh Batu bata besar 1,595.00 143,550.00
22.200 Kg Semen 1,595.00 35,409.00
0.102 M3 Pasir pasang 146,630.00 14,956.26
Tenaga 0.650 Oh Pekerja 85,000.00 55,250.00
0.200 Oh Tukang 93,500.00 18,700.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.030 Oh Mandor 129,000.00 3,870.00
JUMLAH 273,885.26
PROFIT 10 % 301,273.79
3 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 2 ps
Bahan 45.000 Bh Batu bata besar 1,595.00 71,775.00
18.950 Kg Semen 1,595.00 30,225.25
0.038 M3 Pasir pasang 146,630.00 5,571.94
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 145,432.19
PROFIT 10 % 159,975.41
4 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 4 ps
Bahan 45.000 Bh Batu bata besar 1,595.00 71,775.00
11.500 Kg Semen 1,595.00 18,342.50
0.043 M3 Pasir pasang 146,630.00 6,305.09
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 134,282.59
PROFIT 10 % 147,710.85
5 1 M2 pasangan bata merah tebal 1/2 bata. 1 Pc : 5 ps
Bahan 45.000 Bh Batu bata besar 1,595.00 71,775.00
9.680 Kg Semen 1,595.00 15,439.60
0.045 M3 Pasir pasang 146,630.00 6,598.35
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 131,672.95
PROFIT 10 % 144,840.25
6 1 M2 Pasang Bataco
Bahan 12.50 Bh Bataco 10 X 18 X 40 Cm ( kosong ) 1,650.00 20,625.00
10.50 Kg Semen 1,595.00 16,747.50
0.03 M3 Pasir pasang 146,630.00 4,398.90
Tenaga 0.02 Oh Pekerja 85,000.00 1,700.00
0.012 Oh Tukang 93,500.00 1,122.00
0.36 Oh Kepala tukang 107,500.00 38,700.00
0.018 Oh Mandor 129,000.00 2,322.00
JUMLAH 85,615.40
PROFIT 10 % 94,176.94
7 1 M2 Pasangan dinding roster 20/20
Bahan 25.000 Bh Roster 20/20 Beton (Biasa) 16,335.00 408,375.00
12.800 Kg Semen 1,595.00 20,416.00
0.035 M3 Pasir pasang 146,630.00 5,132.05
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 471,783.05
PROFIT 10 % 518,961.36
V. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
1 1 M2 Plesteran 1 pc : 2 ps, tebal 15 mm
Bahan 10.224 Kg Semen 1,595.00 16,307.28
0.020 M3 Pasir pasang 146,630.00 2,932.60
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.150 Oh Tukang 93,500.00 14,025.00
0.015 Oh Kepala tukang 107,500.00 1,612.50
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 62,312.38
PROFIT 10 % 68,543.62
2 1 M2 Plesteran 1 pc : 4 ps, tebal 15 mm
Bahan 6.240 Kg Semen 1,595.00 9,952.80
0.024 M3 Pasir pasang 146,630.00 3,519.12
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.150 Oh Tukang 93,500.00 14,025.00
0.015 Oh Kepala tukang 107,500.00 1,612.50
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 56,544.42
PROFIT 10 % 62,198.86
3 1 M2 Plesteran 1 pc : 5 ps, tebal 15 mm
Bahan 5.184 Kg Semen 1,595.00 8,268.48
0.026 M3 Pasir pasang 146,630.00 3,812.38
Tenaga 0.300 Oh Pekerja 85,000.00 25,500.00
0.150 Oh Tukang 93,500.00 14,025.00
0.015 Oh Kepala tukang 107,500.00 1,612.50
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 55,153.36
PROFIT 10 % 60,668.70
VI. ANALISA HARGA SATUAN PEKERJAAN KAYU

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M3 Pasang kusen pintu dan jendela
Bahan 1.200 M3 Kayu klas II 3,453,780.00 4,144,536.00
1.250 Kg Paku 18,040.00 22,550.00
1.000 Kg Lem Kayu 13,200.00 13,200.00
Tenaga 6.000 Oh Pekerja 85,000.00 510,000.00
18.000 Oh Tukang 93,500.00 1,683,000.00
1.800 Oh Kepala tukang 107,500.00 193,500.00
0.300 Oh Mandor 129,000.00 38,700.00
JUMLAH 6,605,486.00
PROFIT 10 % 7,266,034.60
2 1 M2 Pasang pintu panel kayu klas II
Bahan 0.040 M3 Kayu klas II 3,453,780.00 138,151.20
0.500 Kg Lem Kayu 13,200.00 6,600.00
Tenaga 1.000 Oh Pekerja 85,000.00 85,000.00
3.000 Oh Tukang 93,500.00 280,500.00
0.300 Oh Kepala tukang 107,500.00 32,250.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 548,951.20
PROFIT 10 % 603,846.32
3 1 M2 Pasang pintu dan jendela kaca, kayu klas II
Bahan 0.024 M3 Kayu klas II 3,453,780.00 82,890.72
1.000 M2 Kaca bening 5 mm 129,140.00 129,140.00
Tenaga 0.800 Oh Pekerja 85,000.00 68,000.00
2.400 Oh Tukang 93,500.00 224,400.00
0.240 Oh Kepala tukang 107,500.00 25,800.00
0.040 Oh Mandor 129,000.00 5,160.00
JUMLAH 535,390.72
PROFIT 10 % 588,929.79
4 1 M2 Pasang jalusi kusen kayu klas II
Bahan 0.060 M3 Kayu klas II 3,453,780.00 207,226.80
0.150 Kg Paku 18,040.00 2,706.00
Tenaga 0.670 Oh Pekerja 85,000.00 56,950.00
2.000 Oh Tukang 93,500.00 187,000.00
0.200 Oh Kepala tukang 107,500.00 21,500.00
0.335 Oh Mandor 129,000.00 43,215.00
JUMLAH 518,597.80
PROFIT 10 % 570,457.58
5 1 M3 Pasang konstruksi kuda-kuda kayu klas II
Bahan 1.100 M3 Kayu klas II 3,453,780.00 3,799,158.00
15.000 Kg Besi Strip Tebal 5 mm 18,260.00 273,900.00
5.600 Kg Paku 18,040.00 101,024.00
Tenaga 4.000 Oh Pekerja 85,000.00 340,000.00
12.000 Oh Tukang 93,500.00 1,122,000.00
1.200 Oh Kepala tukang 107,500.00 129,000.00
0.200 Oh Mandor 129,000.00 25,800.00
JUMLAH 5,790,882.00
PROFIT 10 % 6,369,970.20
6 1 M2 Pasang Rangka atap genteng keramik, kayu klas II
Bahan 0.014 M3 Kayu klas II 3,453,780.00 48,352.92
0.250 Kg Paku 18,040.00 4,510.00
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 78,237.92
PROFIT 10 % 86,061.71
7 1 M2 Pasang Rangka atap genteng beton, kayu klas II
Bahan 0.014 M3 Kayu klas II 3,453,780.00 48,352.92
0.250 Kg Paku 18,040.00 4,510.00
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.050 Oh Mandor 129,000.00 6,450.00
JUMLAH 78,237.92
PROFIT 10 % 86,061.71
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
8 1 M2 Pasang rangka langit-langit 1x1 m, kayu klas II
Bahan 0.012 M3 Kayu klas II 3,453,780.00 41,445.36
0.100 Kg Paku 18,040.00 1,804.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.250 Oh Tukang 93,500.00 23,375.00
0.025 Oh Kepala tukang 107,500.00 2,687.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 91,736.86
PROFIT 10 % 100,910.55
9 1 M2 Pasang rangka langit-langit (50x100) cm, kayu klas II
Bahan 0.0154 M3 Kayu klas II 3,453,780.00 53,188.21
0.200 Kg Paku 18,040.00 3,608.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.300 Oh Tukang 93,500.00 28,050.00
0.030 Oh Kepala tukang 107,500.00 3,225.00
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 110,496.21
PROFIT 10 % 121,545.83
10 1 M1 Pasang lisplank ukuran 3/20 kayu klas II
Bahan 0.0108 M3 Kayu klas II 3,453,780.00 37,991.58
0.100 Kg Paku 18,040.00 902.00
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.200 Oh Tukang 93,500.00 18,700.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 68,888.58
PROFIT 10 % 75,777.44
11 1 M1 Pasang lisplank ukuran 3/30 kayu klas II
Bahan 0.0110 M3 Kayu klas II 3,453,780.00 37,300.82
0.050 Kg Paku 18,040.00 1,804.00
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.200 Oh Tukang 93,500.00 18,700.00
0.020 Oh Kepala tukang 107,500.00 2,150.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 69,099.82
PROFIT 10 % 76,009.81
12 1 M1 Pasang list plafond, kayu profil
Bahan 1.050 M1 Kayu profil 15,400.00 16,170.00
0.010 Kg Paku 18,040.00 180.40
Tenaga 0.050 Oh Pekerja 85,000.00 4,250.00
0.050 Oh Tukang 93,500.00 4,675.00
0.005 Oh Kepala tukang 107,500.00 537.50
0.003 Oh Mandor 129,000.00 387.00
JUMLAH 26,199.90
PROFIT 10 % 28,819.89
13 1 M2 Pasang rangka dinding pemisah triplek rangkap, kayu klas III
Bahan 0.027 M3 Kayu klas III 3,058,000.00 82,566.00
0.200 Kg Paku 18,040.00 3,608.00
0.560 Kg Lem kayu 13,200.00 7,392.00
1.000 Lbr Triplek Uk. 4,0 mm 71,500.00 71,500.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.450 Oh Tukang 93,500.00 42,075.00
0.045 Oh Kepala tukang 107,500.00 4,837.50
0.075 Oh Mandor 129,000.00 9,675.00
JUMLAH 234,403.50
PROFIT 10 % 257,843.85
VII. ANALISA HARGA SATUAN PEKERJAAN BETON
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
1 1 M3 Membuat beton tumbuk, 1 pc : 3 ps : 5 kr
Bahan 218.000 Kg Semen 1,595.00 347,710.00
0.520 M3 Pasir beton 146,630.00 76,247.60
0.870 M3 Batu pecah 2/3 225,830.00 196,472.10
Tenaga 1.650 Oh Pekerja 85,000.00 140,250.00
0.250 Oh Tukang 93,500.00 23,375.00
0.025 Oh Kepala tukang 107,500.00 2,687.50
0.080 Oh Mandor 129,000.00 10,320.00
JUMLAH 797,062.20
PROFIT 10 % 876,768.42
2 1 M2 membuat lantai kerja beton tumbuk, 1 pc : 3 ps : 5 kr tebal 5 cm
Bahan 10.000 Kg Semen 1,595.00 15,950.00
0.026 M3 Pasir beton 146,630.00 3,812.38
0.044 M3 Batu pecah 2/3 225,830.00 9,936.52
Tenaga 1.150 Oh Pekerja 85,000.00 97,750.00
0.020 Oh Tukang 93,500.00 1,870.00
0.002 Oh Kepala tukang 107,500.00 215.00
0.006 Oh Mandor 129,000.00 774.00
JUMLAH 130,307.90
PROFIT 10 % 143,338.69
3 1 M3 membuat beton, 1 pc : 2 ps : 3 kr
Bahan 336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
Tenaga 1.650 Oh Pekerja 85,000.00 140,250.00
0.250 Oh Tukang 93,500.00 23,375.00
0.025 Oh Kepala tukang 107,500.00 2,687.50
0.080 Oh Mandor 129,000.00 10,320.00
JUMLAH 974,655.00
PROFIT 10 % 1,072,120.50
3a 1 M3 membuat beton cyclop , 1 pc : 2 ps : 3 kr, 60% Beton, 40% Batu Belah
Bahan 194.000 Kg Semen 1,595.00 309,430.00
0.312 M3 Pasir beton 146,630.00 45,748.56
0.468 M3 Batu pecah 2/3 225,830.00 105,688.44
0.480 M3 Batu Belah 123,860.00 59,452.80
126.000 kg Besi Beton 18,260.00 2,300,760.00
1.800 kg Kawat beton 20,900.00 37,620.00
Tenaga 3.400 Oh Pekerja 85,000.00 289,000.00
0.850 Oh Tukang 93,500.00 79,475.00
0.085 Oh Kepala tukang 107,500.00 9,137.50
0.170 Oh Mandor 129,000.00 21,930.00
JUMLAH 3,258,242.30
PROFIT 10 % 3,584,066.53
4 1 M3 Membuat pondasi beton bertulang (150 Kg besi+bekisting)
Bahan 0.200 M3 Kayu klas IV 2,090,000.00 418,000.00
1.500 Kg Paku 18,040.00 27,060.00
157.500 Kg Besi beton 18,260.00 2,875,950.00
2.250 Kg Kawat beton 20,900.00 47,025.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
Tenaga 5.300 Oh Pekerja 85,000.00 450,500.00
0.275 Oh Tukang Batu 93,500.00 25,712.50
1.300 Oh Tukang Kayu 93,500.00 121,550.00
1.050 Oh Tukang Besi 93,500.00 98,175.00
0.262 Oh Kepala tukang 107,500.00 28,165.00
0.265 Oh Mandor 129,000.00 34,185.00
JUMLAH 4,924,345.00
PROFIT 10 % 5,416,779.50
5 1 M3 Membuat sloop beton bertulang (200 Kg besi + bekisting )
Bahan 0.270 M3 Kayu klas IV 2,090,000.00 564,300.00
2.000 Kg Paku 18,040.00 36,080.00
210.000 Kg Besi beton 18,260.00 3,834,600.00
3.000 Kg Kawat beton 20,900.00 62,700.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
Tenaga 5.650 Oh Pekerja 85,000.00 480,250.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.560 Oh Tukang kayu 93,500.00 145,860.00
1.400 Oh Tukang besi 93,500.00 130,900.00
0.323 Oh Kepala tukang 107,500.00 34,722.50
0.283 Oh Mandor 129,000.00 36,507.00
JUMLAH 6,149,654.50
PROFIT 10 % 6,764,619.95
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
6 1 M3 Membuat kolom beton bertulang ( 300 kg besi + bekisting )
Bahan 0.400 M3 Kayu klas IV 2,090,000.00 836,000.00
4.000 Kg Paku 18,040.00 72,160.00
315.000 Kg Besi beton 18,260.00 5,751,900.00
4.500 Kg Kawat beton 20,900.00 94,050.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.150 M3 Kayu klas III 3,058,000.00 458,700.00
3.500 Lbr Plywood 9 mm 132,000.00 462,000.00
20.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 484,000.00
Tenaga 7.050 Oh Pekerja 85,000.00 599,250.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.650 Oh Tukang kayu 93,500.00 154,275.00
2.100 Oh Tukang besi 93,500.00 196,350.00
0.403 Oh Kepala tukang 107,500.00 43,322.50
0.353 Oh Mandor 129,000.00 45,537.00
JUMLAH 10,021,279.50
PROFIT 10 % 11,023,407.45
7 1 M3 Membuat kolom beton bertulang ( 150 kg besi + bekisting )
Bahan 0.320 M3 Kayu klas IV 2,090,000.00 668,800.00
3.200 Kg Paku 18,040.00 57,728.00
157.500 Kg Besi beton 18,260.00 2,875,950.00
2.250 Kg Kawat beton 20,900.00 47,025.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.120 M3 Kayu klas III 3,058,000.00 366,960.00
2.800 Lbr Plywood 9 mm 132,000.00 369,600.00
32.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 774,400.00
Tenaga 5.300 Oh Pekerja 85,000.00 450,500.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.300 Oh Tukang kayu 93,500.00 121,550.00
1.050 Oh Tukang besi 93,500.00 98,175.00
0.265 Oh Kepala tukang 107,500.00 28,487.50
0.265 Oh Mandor 129,000.00 34,185.00
JUMLAH 6,717,095.50
PROFIT 10 % 7,388,805.05
8 1 M3 Membuat dinding beton bertulang (150 Kg besi + bekesting)
Bahan 0.240 M3 Kayu klas IV 2,090,000.00 501,600.00
3.200 Kg Paku 18,040.00 57,728.00
157.500 Kg Besi beton 18,260.00 2,875,950.00
2.250 Kg Kawat beton 20,900.00 47,025.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.160 M3 Kayu klas III 3,058,000.00 489,280.00
2.800 Lbr Plywood 9 mm 132,000.00 369,600.00
24.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 580,800.00
Tenaga 5.300 Oh Pekerja 85,000.00 450,500.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.300 Oh Tukang kayu 93,500.00 121,550.00
1.050 Oh Tukang besi 93,500.00 98,175.00
0.262 Oh Kepala tukang 107,500.00 28,165.00
0.265 Oh Mandor 129,000.00 34,185.00
JUMLAH 6,478,293.00
PROFIT 10 % 7,126,122.30
9 1 M3 Membuat balok beton bertulang (150 Kg besi + bekesting)
Bahan 0.320 M3 Kayu klas IV 2,090,000.00 668,800.00
3.200 Kg Paku 18,040.00 57,728.00
157.500 Kg Besi beton 18,260.00 2,875,950.00
2.250 Kg Kawat beton 20,900.00 47,025.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.140 M3 Kayu klas III 3,058,000.00 428,120.00
16.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 387,200.00
Tenaga 6.350 Oh Pekerja 85,000.00 539,750.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.650 Oh Tukang kayu 93,500.00 154,275.00
1.500 Oh Tukang besi 93,500.00 140,250.00
0.333 Oh Kepala tukang 107,500.00 35,797.50
0.318 Oh Mandor 129,000.00 41,022.00
JUMLAH 6,199,652.50
PROFIT 10 % 6,819,617.75
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
10 1 M3 Membuat balok beton bertulang (200 Kg besi + bekesting)
Bahan 0.320 M3 Kayu klas IV 2,090,000.00 668,800.00
3.200 Kg Paku 18,040.00 57,728.00
210.000 Kg Besi beton 18,260.00 3,834,600.00
3.000 Kg Kawat beton 20,900.00 62,700.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.140 M3 Kayu klas III 3,058,000.00 428,120.00
16.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 387,200.00
Tenaga 6.350 Oh Pekerja 85,000.00 539,750.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.650 Oh Tukang kayu 93,500.00 154,275.00
1.400 Oh Tukang besi 93,500.00 130,900.00
0.333 Oh Kepala tukang 107,500.00 35,797.50
0.318 Oh Mandor 129,000.00 41,022.00
JUMLAH 7,164,627.50
PROFIT 10 % 7,881,090.25
11 1 M3 Membuat pelat beton bertulang (150 Kg besi + bekesting)
Bahan 0.320 M3 Kayu klas IV 2,090,000.00 668,800.00
3.200 Kg Paku 18,040.00 57,728.00
157.500 Kg Besi beton 18,260.00 2,875,950.00
2.250 Kg Kawat beton 20,900.00 47,025.00
336.000 Kg Semen 1,595.00 535,920.00
0.540 M3 Pasir beton 146,630.00 79,180.20
0.810 M3 Batu pecah 2/3 225,830.00 182,922.30
0.120 M3 Kayu klas III 3,058,000.00 366,960.00
32.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 774,400.00
Tenaga 5.300 Oh Pekerja 85,000.00 450,500.00
0.275 Oh Tukang batu 93,500.00 25,712.50
1.300 Oh Tukang kayu 93,500.00 121,550.00
1.050 Oh Tukang besi 93,500.00 98,175.00
0.265 Oh Kepala tukang 107,500.00 28,487.50
0.202 Oh Mandor 129,000.00 26,058.00
JUMLAH 6,339,368.50
PROFIT 10 % 6,973,305.35
12 1 M1 Membuat kolom praktis beton bertulang ( 11 x 11 cm )
Bahan 0.002 M3 Kayu klas IV 2,090,000.00 4,180.00
0.010 Kg Paku 18,040.00 180.40
3.000 Kg Besi beton 18,260.00 54,780.00
0.450 Kg Kawat beton 20,900.00 9,405.00
4.000 Kg Semen 1,595.00 6,380.00
0.006 M3 Pasir beton 146,630.00 879.78
0.090 M3 Batu pecah 2/3 225,830.00 20,324.70
Tenaga 0.180 Oh Pekerja 85,000.00 15,300.00
0.020 Oh Tukang batu 93,500.00 1,870.00
0.020 Oh Tukang kayu 93,500.00 1,870.00
0.020 Oh Tukang besi 93,500.00 1,870.00
0.006 Oh Kepala tukang 107,500.00 645.00
0.009 Oh Mandor 129,000.00 1,161.00
JUMLAH 118,845.88
PROFIT 10 % 130,730.47
13 1 M1 Membuat Ring balok beton bertulang (10 x 15) cm
Bahan 0.003 M3 Kayu klas IV 2,090,000.00 6,270.00
0.020 Kg Paku 18,040.00 360.80
3.600 Kg Besi beton 18,260.00 65,736.00
0.050 Kg Kawat beton 20,900.00 1,045.00
5.500 Kg Semen 1,595.00 8,772.50
0.009 M3 Pasir beton 146,630.00 1,319.67
0.015 M3 Batu pecah 2/3 225,830.00 3,387.45
Tenaga 0.297 Oh Pekerja 85,000.00 25,245.00
0.033 Oh Tukang batu 93,500.00 3,085.50
0.033 Oh Tukang kayu 93,500.00 3,085.50
0.033 Oh Tukang besi 93,500.00 3,085.50
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.015 Oh Mandor 129,000.00 1,935.00
JUMLAH 124,402.92
PROFIT 10 % 136,843.21
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
14 1 M3 Membuat beton mutu fc' =14,5 Mpa (K.175), slump (12 ± 2) cm, w/c = 0,66
Bahan 326.000 Kg Semen 1,595.00 519,970.00
0.543 M3 Pasir beton 146,630.00 79,599.14
0.762 M3 Batu pecah 2/3 225,830.00 172,132.64
Tenaga 1.650 Oh Pekerja 85,000.00 140,250.00
0.275 Oh Tukang 93,500.00 25,712.50
0.028 Oh Kepala tukang 107,500.00 3,010.00
0.083 Oh Mandor 129,000.00 10,707.00
JUMLAH 951,381.29
PROFIT 10 % 1,046,519.42
15 1 M3 Membuat beton mutu fc' =19,3 Mpa (K.225), slump (12 ± 2) cm, w/c = 0,58
Bahan 371.000 Kg Semen 1,595.00 591,745.00
0.499 M3 Pasir beton 146,630.00 73,105.53
0.776 M3 Batu pecah 2/3 225,830.00 175,143.71
Tenaga 1.600 Oh Pekerja 85,000.00 136,000.00
0.275 Oh Tukang 93,500.00 25,712.50
0.028 Oh Kepala tukang 107,500.00 3,010.00
0.083 Oh Mandor 129,000.00 10,707.00
JUMLAH 1,015,423.74
PROFIT 10 % 1,116,966.11
16 1 M3 Membuat beton mutu fc' =21,7 Mpa (K.275), slump (12 ± 2) cm, w/c = 0,53
Bahan 406.000 Kg Semen 1,595.00 647,570.00
0.489 M3 Pasir beton 146,630.00 71,639.23
0.760 M3 Batu pecah 2/3 225,830.00 171,630.80
Tenaga 1.650 Oh Pekerja 85,000.00 140,250.00
0.275 Oh Tukang 93,500.00 25,712.50
0.028 Oh Kepala tukang 107,500.00 3,010.00
0.083 Oh Mandor 129,000.00 10,707.00
JUMLAH 1,070,519.53
PROFIT 10 % 1,177,571.48
17 1 M3 Membuat beton mutu fc' =26,4 Mpa (K.300), slump (12 ± 2) cm, w/c = 0,52
Bahan 413.000 Kg Semen 1,595.00 658,735.00
0.486 M3 Pasir beton 146,630.00 71,325.02
0.756 M3 Batu pecah 2/3 225,830.00 170,794.39
Tenaga 1.650 Oh Pekerja 85,000.00 140,250.00
0.275 Oh Tukang 93,500.00 25,712.50
0.028 Oh Kepala tukang 107,500.00 3,010.00
0.083 Oh Mandor 129,000.00 10,707.00
JUMLAH 1,080,533.91
PROFIT 10 % 1,188,587.31
17a 1 M3 Membuat beton mutu fc' =31,2 Mpa (K.300), slump (12 ± 2) cm, w/c = 0,48
Bahan 448.000 Kg Semen 1,595.00 714,560.00
0.477 M3 Pasir beton 146,630.00 69,963.46
0.741 M3 Batu pecah 2/3 225,830.00 167,281.48
Tenaga 2.100 Oh Pekerja 85,000.00 178,500.00
0.350 Oh Tukang 93,500.00 32,725.00
0.035 Oh Kepala tukang 107,500.00 3,762.50
0.105 Oh Mandor 129,000.00 13,545.00
JUMLAH 1,180,337.44
PROFIT 10 % 1,298,371.18
18 1 M2 Begesting pasang jembatan cor
Bahan 0.026 M3 Kayu klas IV 2,090,000.00 54,340.00
0.600 Kg Paku 18,040.00 10,824.00
0.500 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 12,100.00
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.050 Oh Tukang 93,500.00 4,675.00
0.0050 Oh Kepala tukang 107,500.00 537.50
0.0070 Oh Mandor 129,000.00 903.00
JUMLAH 96,129.50
PROFIT 10 % 105,742.45
19 1 M2 Membuat Bekisting Plat untuk beton
Bahan 0.040 M3 Kayu klas IV 2,090,000.00 83,600.00
0.400 Kg Paku 18,040.00 7,216.00
0.350 Lbr Multipleks 9 mm 135,300.00 47,355.00
6.000 Btg Dolken Kayu Ø 8 - 10 Cm 24,200.00 145,200.00
Tenaga 0.660 Oh Pekerja 85,000.00 56,100.00
0.330 Oh Tukang kayu 93,500.00 30,855.00
0.033 Oh Kepala tukang 107,500.00 3,547.50
0.033 Oh Mandor 129,000.00 4,257.00
JUMLAH 378,130.50
PROFIT 10 % 415,943.55
20 1 M2 Membuat Bekisting Kolom untuk beton
Bahan 0.040 M3 Kayu klas IV 2,090,000.00 83,600.00
0.400 Kg Paku 18,040.00 7,216.00
0.350 Lbr Multipleks 9 mm 135,300.00 47,355.00
0.015 M3 Kayu klas II 3,453,780.00 51,806.70
Tenaga 0.660 Oh Pekerja 85,000.00 56,100.00
0.330 Oh Tukang kayu 93,500.00 30,855.00
0.033 Oh Kepala tukang 107,500.00 3,547.50
0.033 Oh Mandor 129,000.00 4,257.00
JUMLAH 284,737.20
PROFIT 10 % 313,210.92
21 1 M2 Membuat Bekisting Balok untuk beton
Bahan 0.040 M3 Kayu klas IV 2,090,000.00 83,600.00
0.400 Kg Paku 18,040.00 7,216.00
0.350 Lbr Multipleks 9 mm 135,300.00 47,355.00
0.018 M3 Kayu klas II 3,453,780.00 62,168.04
Tenaga 0.660 Oh Pekerja 85,000.00 56,100.00
0.330 Oh Tukang kayu 93,500.00 30,855.00
0.033 Oh Kepala tukang 107,500.00 3,547.50
0.033 Oh Mandor 129,000.00 4,257.00
JUMLAH 295,098.54
PROFIT 10 % 324,608.39
21 1 M' Membuat Pagar Beton Precast (t=2,8 m)
Bahan 0.986 Lbr Panel beton pracetak 101,200.00 99,783.20
0.525 Btg Kolom beton pracetak 351,037.50 184,294.69
0.074 M3 Pasir beton 146,630.00 10,850.62
0.146 M3 Batu pecah 2/3 225,830.00 32,971.18
45.000 Kg Semen 1,595.00 71,775.00
Tenaga 0.375 Oh Pekerja 93,500.00 35,062.50
0.125 Oh Tukang 93,500.00 11,687.50
0.012 Oh Kepala tukang 107,500.00 1,290.00
0.019 Oh Mandor 129,000.00 2,451.00
JUMLAH 450,165.69
PROFIT 10 % 495,182.26
Catatan : Bobot isi pasir 1400 kg/m3, bobot isi batu pecah 1350 Kg/m3
VIII. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M2 Pasang atap genteng biasa
Bahan 25.0000 Bh Genteng soka / kodok 5,610.00 140,250.00
Tenaga 0.1500 Oh Pekerja 85,000.00 12,750.00
0.075 Oh Tukang 93,500.00 7,012.50
0.0080 Oh Kepala tukang 107,500.00 860.00
0.0080 Oh Mandor 129,000.00 1,032.00
JUMLAH 161,904.50
PROFIT 10 % 178,094.95
2 1 M1 Pasang genteng bubung biasa
Bahan 5.000 Bh Genteng bubungan soka 5,500.00 27,500.00
8.000 Kg Semen 1,595.00 12,760.00
0.032 M3 Pasir pasang 146,630.00 4,692.16
Tenaga 0.400 Oh Pekerja 85,000.00 34,000.00
0.200 Oh Tukang 93,500.00 18,700.00
0.0200 Oh Kepala tukang 107,500.00 2,150.00
0.002 Oh Mandor 129,000.00 258.00
JUMLAH 100,060.16
PROFIT 10 % 110,066.18
3 1 M2 Pasang atap asbes gelombang 3M X 1,05 M X 4 mm
Bahan 0.350 Lbr Asbes gelombang t = 5 mm 91,850.00 32,147.50
0.120 Kg Paku sekrup 18,040.00 2,164.80
Tenaga 0.140 Oh Pekerja 85,000.00 11,900.00
0.070 Oh Tukang 93,500.00 6,545.00
0.0070 Oh Kepala tukang 107,500.00 752.50
0.0070 Oh Mandor 129,000.00 903.00
JUMLAH 54,412.80
PROFIT 10 % 59,854.08
4 1 M2 Pasang atap genteng beton
Bahan 11.000 Kp Genteng beton 8,250.00 90,750.00
0.030 Kg Paku 18,040.00 541.20
Tenaga 0.200 Oh Pekerja 85,000.00 17,000.00
0.100 Oh Tukang 93,500.00 9,350.00
0.0100 Oh Kepala tukang 107,500.00 1,075.00
0.0100 Oh Mandor 129,000.00 1,290.00
JUMLAH 120,006.20
PROFIT 10 % 132,006.82
5 1 M1 Pasang bubungan genteng beton
Bahan 3.500 Bh Genteng rabung Beton 7,700.00 26,950.00
0.050 Kg Paku 18,040.00 902.00
10.800 Kg Semen 1,595.00 17,226.00
0.032 M3 Pasir pasang 146,630.00 4,692.16
Tenaga 0.400 Oh Pekerja 85,000.00 34,000.00
0.200 Oh Tukang 93,500.00 18,700.00
0.0200 Oh Kepala tukang 107,500.00 2,150.00
0.0200 Oh Mandor 129,000.00 2,580.00
JUMLAH 107,200.16
PROFIT 10 % 117,920.18
6 1 M2 Pasang atap genteng Keramik glassur
Bahan 14.000 Kp Genteng Keramik Glassur 12,650.00 177,100.00
0.030 Kg Paku 18,040.00 541.20
Tenaga 0.200 Oh Pekerja 85,000.00 17,000.00
0.100 Oh Tukang 93,500.00 9,350.00
0.0100 Oh Kepala tukang 107,500.00 1,075.00
0.0100 Oh Mandor 129,000.00 1,290.00
JUMLAH 206,356.20
PROFIT 10 % 226,991.82
7 1 M1 Pasang bubungan genteng Keramik
Bahan 3.500 Bh Genteng bubungan keramik 24,200.00 84,700.00
0.200 Kg Paku 18,040.00 3,608.00
10.800 Kg Semen 1,595.00 17,226.00
0.032 M3 Pasir pasang 146,630.00 4,692.16
Tenaga 0.400 Oh Pekerja 85,000.00 34,000.00
0.200 Oh Tukang 93,500.00 18,700.00
0.0200 Oh Kepala tukang 107,500.00 2,150.00
0.0200 Oh Mandor 129,000.00 2,580.00
JUMLAH 167,656.16
PROFIT 10 % 184,421.78
IX. ANALISA HARGA SATUAN PEKERJAAN LANGIT-LANGIT

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M2 langit-langit asbes 1x1 m
Bahan 1.100 Lbr Eternit 1 x 1 m 23,100.00 25,410.00
0.010 Kg Paku 18,040.00 180.40
Tenaga 0.030 Oh Pekerja 85,000.00 2,550.00
0.070 Oh Tukang 93,500.00 6,545.00
0.007 Oh Kepala tukang 107,500.00 752.50
0.004 Oh Mandor 129,000.00 516.00
JUMLAH 35,953.90
PROFIT 10 % 39,549.29
2 1 M2 langit-langit gypsum board, tebal 9 mm
Bahan 0.364 Lbr Gypsum board 9 X 120 x 240 mm 108,240.00 39,399.36
0.110 Kg Paku 18,040.00 1,984.40
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.050 Oh Tukang 93,500.00 4,675.00
0.005 Oh Kepala tukang 107,500.00 537.50
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 55,741.26
PROFIT 10 % 61,315.39
3 1 M2 langit-langit plywood 4 mm + rangka kayu klas III
Bahan 0.375 Lbr Plywood 4 mm 99,000.00 37,125.00
0.030 Kg Paku 18,040.00 541.20
0.023 M3 Kayu klas III 3,058,000.00 70,334.00
Tenaga 0.100 Oh Pekerja 85,000.00 8,500.00
0.100 Oh Tukang 93,500.00 9,350.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 127,570.20
PROFIT 10 % 140,327.22
X. ANALISA HARGA SATUAN PEKERJAAN PIPA DAN SANITAIR

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 Memasang 1 buah closet duduk/monoblok
Bahan 1.000 Bh Closet duduk/monoblok 2,035,000.00 2,035,000.00
Kg Perlengkapan 6 % harga Closet 2,035,000.00 122,100.00
Tenaga 3.300 Oh Pekerja 85,000.00 280,500.00
1.100 Oh Tukang 93,500.00 102,850.00
0.0100 Oh Kepala tukang 107,500.00 1,075.00
0.1600 Oh Mandor 129,000.00 20,640.00
JUMLAH 2,562,165.00
PROFIT 10 % 2,818,381.50
2 Memasang 1 buah closet jongkok biasa
Bahan 1.000 Bh Closet jongkok porselin 199,540.00 199,540.00
6.000 Kg Semen 1,595.00 9,570.00
0.010 M3 Pasir pasang 146,630.00 1,466.30
Tenaga 1.000 Oh Pekerja 85,000.00 85,000.00
1.500 Oh Tukang 93,500.00 140,250.00
0.1500 Oh Kepala tukang 107,500.00 16,125.00
0.1600 Oh Mandor 129,000.00 20,640.00
JUMLAH 472,591.30
PROFIT 10 % 519,850.43
3 Memasang 1 buah bak mandi batu bata volume 0,3 m3
Bahan 200.000 Kp Batu bata besar 1,595.00 319,000.00
120.000 Kg Semen 1,595.00 191,400.00
0.300 M3 Pasir pasang 146,630.00 43,989.00
4.356 M2 Keramik 68,200.00 297,079.20
6.000 Kg Semen putih 2,090.00 12,540.00
Tenaga 6.000 Oh Pekerja 85,000.00 510,000.00
3.000 Oh Tukang 93,500.00 280,500.00
0.3000 Oh Kepala tukang 107,500.00 32,250.00
0.0300 Oh Mandor 129,000.00 3,870.00
JUMLAH 1,690,628.20
PROFIT 10 % 1,859,691.02
4 Memasang 1 m' pipa beton, diameter 15 - 20 Cm
Bahan 1.100 Bh Pipa beton 15 - 20 Cm 66,000.00 72,600.00
0.027 M3 Batu bata besar 1,595.00 43.07
3.92 Kg Semen 1,595.00 6,252.40
0.056 M3 Pasir pasang 146,630.00 8,211.28
0.024 M3 Pasir urug 64,130.00 1,539.12
Tenaga 0.140 Oh Pekerja 85,000.00 11,900.00
0.070 Oh Tukang 93,500.00 6,545.00
0.0070 Oh Kepala tukang 107,500.00 752.50
0.0070 Oh Mandor 129,000.00 903.00
JUMLAH 108,746.36
PROFIT 10 % 119,621.00
5 Memasang 1 buah, bak kontrol pasangan batu bata uk.30x30 tinggi 50 cm
Bahan 0.145 M3 Batu bata besar 1,595.00 231.28
44.000 Kg Semen 1,595.00 70,180.00
0.070 M3 Pasir pasang 146,630.00 10,264.10
0.070 M3 Batu pecah 2/3 225,830.00 15,808.10
1.600 Kg Besi beton 18,260.00 29,216.00
0.060 M3 Pasir beton 146,630.00 8,797.80
Tenaga 3.200 Oh Pekerja 85,000.00 272,000.00
1.015 Oh Tukang 93,500.00 94,902.50
0.0015 Oh Kepala tukang 107,500.00 161.25
0.0160 Oh Mandor 129,000.00 2,064.00
JUMLAH 503,625.03
PROFIT 10 % 553,987.53
6 Memasang 1 Bh, bak kontrol pasangan batu bata uk.45x45 tinggi 50 cm
Bahan 70.000 Bh Batu bata besar 1,595.00 111,650.00
77.000 Kg Semen 1,595.00 122,815.00
0.130 M3 Pasir pasang 146,630.00 19,061.90
0.020 m3 Batu pecah 2/3 225,830.00 4,516.60
2.600 Kg Besi beton 18,260.00 47,476.00
0.090 M3 Pasir beton 146,630.00 13,196.70
Tenaga 3.200 Oh Pekerja 85,000.00 272,000.00
1.150 Oh Tukang 93,500.00 107,525.00
0.0110 Oh Kepala tukang 107,500.00 1,182.50
0.0160 Oh Mandor 129,000.00 2,064.00
JUMLAH 701,487.70
PROFIT 10 % 771,636.47
NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH
(Rp) (Rp)
7 Memasang 1 m' pipa galvanis dia 1"
Bahan 1.200 M1 Pipa galvanis 29,333.33 35,200.00
Perlengkapan 35,0 % harga pipa 35,200.00 12,320.00
Tenaga 0.054 Oh Pekerja 85,000.00 4,590.00
0.090 Oh Tukang 93,500.00 8,415.00
0.0090 Oh Kepala tukang 107,500.00 967.50
0.0270 Oh Mandor 129,000.00 3,483.00
JUMLAH 64,975.50
PROFIT 10 % 71,473.05
8 Memasang 1 m' pipa galvanis dia 2"
Bahan 1.200 M1 Pipa galvanis 57,750.00 69,300.00
Perlengkapan 35,0 % harga pipa 69,300.00 24,255.00
Tenaga 0.054 Oh Pekerja 85,000.00 4,590.00
0.090 Oh Tukang 93,500.00 8,415.00
0.0090 Oh Kepala tukang 107,500.00 967.50
0.0270 Oh Mandor 129,000.00 3,483.00
JUMLAH 111,010.50
PROFIT 10 % 122,111.55
9 Memasang 1 m' pipa PVC type AW dia 1"
Bahan 1.200 M1 Pipa PVC AW Ø 1" (4 m') 14,245.00 17,094.00
Perlengkapan 35,0 % harga pipa 5,982.90 2,094.02
Tenaga 0.036 Oh Pekerja 85,000.00 3,060.00
0.060 Oh Tukang 93,500.00 5,610.00
0.0060 Oh Kepala tukang 107,500.00 645.00
0.0020 Oh Mandor 129,000.00 258.00
JUMLAH 28,761.02
PROFIT 10 % 31,637.12
10 Memasang 1 m' pipa PVC type AW dia 2"
Bahan 1.200 M1 Pipa PVC AW Ø 2" (4 m') 17,875.00 21,450.00
Perlengkapan 35,0 % harga pipa 7,507.50 2,627.62
Tenaga 0.054 Oh Pekerja 85,000.00 4,590.00
0.090 Oh Tukang 93,500.00 8,415.00
0.0090 Oh Kepala tukang 107,500.00 967.50
0.0030 Oh Mandor 129,000.00 387.00
JUMLAH 38,437.13
PROFIT 10 % 42,280.84
11 Memasang 1 m' pipa PVC type AW dia 3"
Bahan 1.200 M1 Pipa PVC AW Ø 3" (4 m') 30,112.50 36,135.00
Perlengkapan 35,0 % harga pipa 12,647.25 4,426.54
Tenaga 0.081 Oh Pekerja 85,000.00 6,885.00
0.135 Oh Tukang 93,500.00 12,622.50
0.0135 Oh Kepala tukang 107,500.00 1,451.25
0.0040 Oh Mandor 129,000.00 516.00
JUMLAH 62,036.29
PROFIT 10 % 68,239.92
12 Memasang 1 m' pipa PVC type AW dia 4"
Bahan 1.200 M1 Pipa PVC AW Ø 4" (4 m') 42,047.50 50,457.00
Perlengkapan 35,0 % harga pipa 17,659.95 6,180.98
Tenaga 0.081 Oh Pekerja 85,000.00 6,885.00
0.135 Oh Tukang 93,500.00 12,622.50
0.0135 Oh Kepala tukang 107,500.00 1,451.25
0.0040 Oh Mandor 129,000.00 516.00
JUMLAH 78,112.73
PROFIT 10 % 85,924.01
12 Memasang 1 m' pipa PVC type AW dia 6"
Bahan 1.200 M1 Pipa PVC AW Ø 6" (4 m') 88,082.50 105,699.00
Perlengkapan 35,0 % harga pipa 36,994.65 12,948.13
Tenaga 0.101 Oh Pekerja 85,000.00 8,610.50
0.169 Oh Tukang 93,500.00 15,782.80
0.0169 Oh Kepala tukang 107,500.00 1,816.75
0.0051 Oh Mandor 129,000.00 657.90
JUMLAH 145,515.08
PROFIT 10 % 160,066.59
12 Memasang 1 m' pipa PVC type AW dia 8"
Bahan 1.200 M1 Pipa PVC AW Ø 8" (4 m') 181,775.00 218,130.00
Perlengkapan 35,0 % harga pipa 76,345.50 26,720.93
Tenaga 0.127 Oh Pekerja 85,000.00 10,761.00
0.211 Oh Tukang 93,500.00 19,719.15
0.0211 Oh Kepala tukang 107,500.00 2,268.25
0.0064 Oh Mandor 129,000.00 825.60
JUMLAH 278,424.93
PROFIT 10 % 306,267.42
XI. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M2 Pasang lantai keramik
Bahan 1.000 M2 Keramik 68,200.00 68,200.00
10.000 Kg Semen 1,595.00 15,950.00
0.045 M3 Pasir pasang 146,630.00 6,598.35
Tenaga 0.700 Oh Pekerja 85,000.00 59,500.00
0.350 Oh Tukang 93,500.00 32,725.00
0.035 Oh Kepala tukang 107,500.00 3,762.50
0.035 Oh Mandor 129,000.00 4,515.00
JUMLAH 191,250.85
PROFIT 10 % 210,375.94
2 1 M2 Pasang dinding keramik
Bahan 1.000 M2 Keramik 68,200.00 68,200.00
9.300 Kg Semen 1,595.00 14,833.50
0.018 M3 Pasir pasang 146,630.00 2,639.34
Tenaga 0.900 Oh Pekerja 85,000.00 76,500.00
0.450 Oh Tukang 93,500.00 42,075.00
0.045 Oh Kepala tukang 107,500.00 4,837.50
0.045 Oh Mandor 129,000.00 5,805.00
JUMLAH 214,890.34
PROFIT 10 % 236,379.37
3 1 M2 Pasang Lantai Keramik Anti Gores 1:4
Bahan 1.000 M2 Keramik Anti Gores 69,960.00 69,960.00
10.000 Kg Semen 1,595.00 15,950.00
0.045 M3 Pasir pasang 146,630.00 6,598.35
Tenaga 0.700 Oh Pekerja 85,000.00 59,500.00
0.350 Oh Tukang 93,500.00 32,725.00
0.035 Oh Kepala tukang 107,500.00 3,762.50
0.035 Oh Mandor 129,000.00 4,515.00
JUMLAH 193,010.85
PROFIT 10 % 212,311.94
4 1 M' Pasang Plint Keramik 10/20
Bahan 5.300 kpg Keramik Plint 10/20 1,364.00 7,229.20
1.140 Kg Semen 1,595.00 1,818.30
0.003 M3 Pasir pasang 146,630.00 439.89
Tenaga 0.090 Oh Pekerja 85,000.00 7,650.00
0.090 Oh Tukang 93,500.00 8,415.00
0.035 Oh Kepala tukang 107,500.00 3,762.50
0.005 Oh Mandor 129,000.00 645.00
JUMLAH 29,959.89
PROFIT 10 % 32,955.88
5 1 M2 Pasang lantai dari conblok tebal 6 cm
Bahan 1.000 M2 Conblock T=6 cm 60,500.00 60,500.00
Tenaga 0.050 Oh Pekerja 85,000.00 4,250.00
0.160 Oh Tukang 93,500.00 14,960.00
0.010 Oh Kepala tukang 107,500.00 1,075.00
0.030 Oh Mandor 129,000.00 3,870.00
JUMLAH 84,655.00
PROFIT 10 % 93,120.50
6 1 M2 Pasangan tegel abu-abu
Bahan 26.500 Kp Ubin abu - abu 20 x 20 cm Polos 1,867.92 49,500.00
10.400 Kg Semen 1,595.00 16,588.00
0.045 M3 Pasir pasang 146,630.00 6,598.35
Tenaga 0.270 Oh Pekerja 85,000.00 22,950.00
0.135 Oh Tukang 93,500.00 12,622.50
0.014 Oh Kepala tukang 107,500.00 1,505.00
0.014 Oh Mandor 129,000.00 1,806.00
JUMLAH 111,569.85
PROFIT 10 % 122,726.84
XII. ANALISA HARGA SATUAN PEKERJAAN PENGECATAN

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan 0.1000 Kg Plamir 22,977.90 2,297.79
0.1000 Kg Cat dasar 23,100.00 2,310.00
0.2600 Kg Cat penutup 23,100.00 6,006.00
Tenaga 0.0200 Oh Pekerja 85,000.00 1,700.00
0.0630 Oh Tukang 93,500.00 5,890.50
0.0063 Oh Kepala tukang 107,500.00 677.25
0.0030 Oh Mandor 129,000.00 387.00
JUMLAH 19,268.54
PROFIT 10 % 21,195.39
2 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Bahan 0.1200 Kg Cat dasar 23,100.00 2,772.00
0.1800 Kg Cat penutup 23,100.00 4,158.00
Tenaga 0.0280 Oh Pekerja 85,000.00 2,380.00
0.0420 Oh Tukang 93,500.00 3,927.00
0.0042 Oh Kepala tukang 107,500.00 451.50
0.0030 Oh Mandor 129,000.00 387.00
JUMLAH 14,075.50
PROFIT 10 % 15,483.05
3 1 M2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan 0.2000 Kg Cat menie 55,660.00 11,132.00
0.1500 Kg Plamir 22,977.90 3,446.69
0.1700 Kg Cat dasar 22,935.00 3,898.95
0.2600 Kg Cat penutup 45,870.00 11,926.20
0.0300 Kg Pengencer 11,110.00 333.30
Tenaga 0.0700 Oh Pekerja 85,000.00 5,950.00
0.0090 Oh Tukang 93,500.00 841.50
0.0060 Oh Kepala tukang 107,500.00 645.00
0.0030 Oh Mandor 129,000.00 387.00
JUMLAH 38,560.64
PROFIT 10 % 42,416.70
4 1 M2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup)
Bahan 0.2000 Kg Cat menie 16,335.00 3,267.00
0.1500 Kg Plamir 5,500.00 825.00
0.1700 Kg Cat dasar 22,935.00 3,898.95
0.3500 Kg Cat penutup 45,870.00 16,054.50
0.0300 Kg Pengencer 11,110.00 333.30
Tenaga 0.0700 Oh Pekerja 85,000.00 5,950.00
0.1050 Oh Tukang 93,500.00 9,817.50
0.0040 Oh Kepala tukang 107,500.00 430.00
0.0030 Oh Mandor 129,000.00 387.00
JUMLAH 40,963.25
PROFIT 10 % 45,059.58
5 1 M2 Pekerjaan cat genteng
Bahan 0.3000 Kg Cat genteng 43,230.00 12,969.00
Tenaga 0.1000 Oh Pekerja 85,000.00 8,500.00
0.1500 Oh Tukang 93,500.00 14,025.00
0.0150 Oh Kepala tukang 107,500.00 1,612.50
0.0050 Oh Mandor 129,000.00 645.00
JUMLAH 37,751.50
PROFIT 10 % 41,526.65
XIII. ANALISA HARGA SATUAN PEKERJAAN BESI

NO ANALISA URAIAN PEKERJAAN HARGA SATUAN JUMLAH


(Rp) (Rp)
1 1 M2 Pasang pintu lipat
Bahan 1.00 M2 Pintu lipat 275,000.00 275,000.00
Tenaga 1.050 Oh Pekerja 85,000.00 89,250.00
1.050 Oh Tukang 93,500.00 98,175.00
0.105 Oh Kepala tukang 107,500.00 11,287.50
JUMLAH 473,712.50
PROFIT 10 % 521,083.75
2 1 M2 Pasang rolling door
Bahan 1.00 M2 Rolling door 247,500.00 247,500.00
Tenaga 1.200 Oh Pekerja 85,000.00 102,000.00
1.200 Oh Tukang 93,500.00 112,200.00
0.102 Oh Kepala tukang 107,500.00 10,965.00
JUMLAH 472,665.00
PROFIT 10 % 519,931.50
3 1 M2 Pasang terali besi
Bahan 6.177 Kg Besi strip 18,260.00 112,792.02
27.08 cm Pengelasan, pengecatan 913.00 24,724.04
Tenaga 1.670 Oh Pekerja 85,000.00 141,950.00
1.670 Oh Tukang 93,500.00 156,145.00
0.167 Oh Kepala tukang 107,500.00 17,952.50
0.083 Oh Mandor 129,000.00 10,707.00
JUMLAH 464,270.56
PROFIT 10 % 510,697.62
4 1 M1 Pasang talang datar, seng BJLS 28
Bahan 1.050 M1 Seng plat 3x6' BJLS 28 29,700.00 31,185.00
0.015 Kg Paku 18,040.00 270.60
0.019 M3 Kayu klas III 3,058,000.00 58,102.00
0.025 Kg Cat meni besi 55,660.00 1,391.50
Tenaga 0.150 Oh Pekerja 85,000.00 12,750.00
0.300 Oh Tukang 93,500.00 28,050.00
0.030 Oh Kepala tukang 107,500.00 3,225.00
0.010 Oh Mandor 129,000.00 1,290.00
JUMLAH 136,264.10
PROFIT 10 % 149,890.51
5 1 Kg Rangka kuda-kuda baja IWF
Bahan 1.150 Kg Besi Baja WF 18,260.00 20,999.00
Tenaga 0.060 Oh Pekerja 85,000.00 5,100.00
0.060 Oh Tukang 93,500.00 5,610.00
0.006 Oh Kepala tukang 107,500.00 645.00
0.003 Oh Mandor 129,000.00 387.00
JUMLAH 32,741.00
PROFIT 10 % 36,015.10
DAFTAR HARGA SATUAN MATERIAL/BAHAN DAN UPAH TENAGA KERJA
TAHUN ANGGARAN 2016

SATUAN
HARGA DASAR PROFIT JUMLAH HARGA
NO. UPAH UNIT KODE
(Rp) (Rp) (Rp)
1 Mandor Lapangan 1 L_061 129,000.00 129,000.00
2 Mekanik 1 L_071 93,500.00 93,500.00
3 Mekanik Pembantu 1 L_072 85,000.00 85,000.00
4 Kepala tukang 1 L_073 107,500.00 107,500.00
5 Tukang 1 L_079 93,500.00 93,500.00
6 Operator Terlatih 1 L_081 107,500.00 107,500.00
7 Operator Kurang Terlatih 1 L_082 93,500.00 93,500.00
8 Pembantu Operator 1 L_083 85,000.00 85,000.00
9 Supir 1 L_091 93,500.00 93,500.00
10 Pembantu Supir / Kenek 1 L_099 85,000.00 85,000.00
11 Pekerja / Buruh Lapangan Tak Terlatih 1 L_101 85,000.00 85,000.00
12 Buruh Lapangan Agak Terlatih 1 L_103 90,000.00 90,000.00
13 Buruh Lapangan Terlatih 1 L_106 93,500.00 93,500.00
14 Penjaga 1 - 93,500.00 93,500.00
15 Pemasak Aspal 1 - 93,500.00 93,500.00
SATUAN
HARGA DASAR PROFIT JUMLAH HARGA
NO. BAHAN / MATERIAL UNIT KODE
(Rp) (Rp) (Rp)
1 Batu Belah / Batu Gunung M3 M_010 123,860.00 123,860.00
2 Batu belah untuk saluran pasangan M3 M_010 175,120.00 175,120.00
3 Batu Pecah 5/7 M3 M_022 176,990.00 176,990.00
4 Batu Pecah 3/5 M3 M_023 225,830.00 225,830.00
5 Batu pecah 2/3 M3 M_024 225,830.00 225,830.00
6 Batu Pecah 1/2 M3 M_025 225,830.00 225,830.00
7 Batu pecah 0,5~1 cm M3 M_026 268,510.00 268,510.00
8 Batu Bata kecil Bh - 440.00 440.00
9 Batu bata besar Bh - 1,595.00 1,595.00
10 Bataco 10 X 18 X 40 Cm ( kosong ) Kp 1,650.00 1,650.00
11 Bataco 10 X 10 X 20 Cm Kp 1,650.00 1,650.00
12 Bataco 10 X 18 X 40 Cm ( padat ) Kp 1,650.00 1,650.00
13 Pasir urug M3 M_040 64,130.00 64,130.00
14 Pasir Beton M3 146,630.00 146,630.00
15 Pasir Pasang M3 M_041 146,630.00 146,630.00
16 Tanah puru M3 M_150 132,000.00 132,000.00
17 Semen Kg M_080 1,595.00 1,595.00
18 Semen putih Kg 2,090.00 2,090.00
19 Semen Nat Kg 4,400.00 4,400.00
20 Kayu klas II M3 - 3,453,780.00 3,453,780.00
21 Kayu klas III M3 M_180 3,058,000.00 3,058,000.00
22 Kayu klas IV M3 - 2,090,000.00 2,090,000.00
23 Kayu Bakar M3 M_070 288,750.00 288,750.00
24 Kayu cerucuk diameter 8 - 10 Cm Btg - 24,200.00 24,200.00
25 Dolken Kayu Ø 8 - 10 Cm Btg - 24,200.00 24,200.00
26 Lem kayu Kg 13,200.00 13,200.00
27 Lem Putih Kg - 22,000.00 22,000.00
28 Besi Beton Kg M_167 18,260.00 18,260.00
29 Kawat Beton Kg M_168 20,900.00 20,900.00
30 Kawat harmonika Haas M2 33,000.00 33,000.00
31 Kawat duri Kg 27,500.00 27,500.00
32 Kawat Bronjong M2 45,738.00 45,738.00
33 Paku Kg M_166 18,040.00 18,040.00
34 Paku sekrup Gros 18,040.00 18,040.00
35 Paku ulir Kg 18,040.00 18,040.00
36 Paku sumbat Biasa Kg 18,040.00 18,040.00
37 Paku seng Kg 18,040.00 18,040.00
38 Aspal Kg M_061 14,630.00 14,630.00
39 Besi Siku L.70.70.7 Btg 421,080.00 421,080.00
40 Besi Siku L.50.50.5 Btg 248,820.00 248,820.00
41 Besi Siku L.30.30.3 Btg 89,760.00 89,760.00
42 Besi Siku L.40.40.4 Btg 61,050.00 61,050.00
43 Besi Kanal 100.50.5 Btg 133,100.00 133,100.00
44 Gorong - gorong Ø 40 Cm. Bh 338,800.00 338,800.00
45 Gorong - gorong Ø 60 Cm. Bh M_031 423,500.00 423,500.00
46 Gorong - gorong Ø 80 Cm. Bh M_033 484,000.00 484,000.00
47 Gorong - gorong Ø 100 Cm. Bh M_035 544,500.00 544,500.00
48 Rubber Bearing Cm3 - 399.30 399.30
49 Alat Bantu Set M_170 181,500.00 181,500.00
50 Panel beton bertulang 240x40x5 cm Lbr - 101,200.00 101,200.00
51 Tiang beton bertulang 370x18x17 cm Btg - 351,037.50 351,037.50

CATATAN :
Jam Kerja 1 ( satu ) hari = 7 Jam ( Kerja )
SATUAN
HARGA DASAR PROFIT JUMLAH HARGA
NO. BAHAN / MATERIAL UNIT KODE
(Rp) (Rp) (Rp)
50 Cat Perak Kg - 51,700.00 51,700.00
51 Cat tembok Kg - 23,100.00 23,100.00
52 Cat besi galvanis Kg 55,660.00 55,660.00
53 Cat kayu Kg 45,870.00 45,870.00
54 Cat meni besi Kg 55,660.00 55,660.00
55 Cat genteng Kg 43,230.00 43,230.00
56 Cat waterprofing Kg 43,450.00 43,450.00
57 Cat coating Kg 55,000.00 55,000.00
58 Minyak cat Ltr 11,110.00 11,110.00
59 Minyak Solar Lt M_183 13,750.00 13,750.00
60 Minyak tanah Lt M_065 9,350.00 9,350.00
61 Minyak Olie Lt M_185 27,500.00 27,500.00
62 Minyak Gemuk Klg - 24,200.00 24,200.00
63 Bensin / Premium Ltr M_184 9,900.00 9,900.00
64 Teer / Residu Klg - 31,363.20 31,363.20
65 Plamir Kg 22,977.90 22,977.90
66 Dempul Kg 25,300.00 25,300.00
67 Kapur Kg 8,250.00 8,250.00
68 Roster 20/20 Beton (Biasa) Bh 16,335.00 16,335.00
69 Glass Block Bh 27,500.00 27,500.00
70 Conblock T=6 cm M2 60,500.00 60,500.00
71 Kanstin block beton cetak Bh 38,500.00 38,500.00
72 Pagar panel beton tinggi = 2 m M1 385,000.00 385,000.00
73 Keramik Kw. I M2 71,060.00 71,060.00
74 Keramik Kw. II M2 68,200.00 68,200.00
75 Keramik Kw. III M2 60,500.00 60,500.00
76 Keramik Anti Gores 40/40 M2 69,960.00 69,960.00
77 Keramik Anti Gores 60/60 M2 203,500.00 203,500.00
78 Ubin abu - abu 20 x 20 cm Polos M2 49,500.00 49,500.00
79 Tegel plint 10/20 cm Kp 5,500.00 5,500.00
80 Eternit 1 x 1 m Lbr 23,100.00 23,100.00
81 Triplek Lbr 47,300.00 47,300.00
82 Triplek Uk. 3,0 mm Lbr 51,700.00 51,700.00
83 Triplek Uk. 4,0 mm Lbr 71,500.00 71,500.00
84 Triplek Uk. 6,0 mm Lbr 85,800.00 85,800.00
85 Milamin 1,2 x 2,4 m Kp 88,000.00 88,000.00
86 Teakwood Lbr 138,600.00 138,600.00
87 Multipleks 9 mm Kp 135,300.00 135,300.00
88 Multipleks 12 mm Kp 164,780.00 164,780.00
89 Plywood 4 mm Lbr 99,000.00 99,000.00
90 Plywood 9 mm Lbr 132,000.00 132,000.00
91 Gypsum board 9 X 120 x 240 mm M2 108,240.00 108,240.00
92 Calsiboard M2 71,500.00 71,500.00
93 GRC board M2 72,600.00 72,600.00
94 Kayu profil M1 15,400.00 15,400.00
95 Lis kayu kembang 5/7 M' 33,000.00 33,000.00
96 List Gypsum 9 mm M1 55,000.00 55,000.00
97 Seng gelombang Feet 6,600.00 6,600.00
98 Seng plat 3x6' BJLS 28 M2 29,700.00 29,700.00
99 Seng Aluminium 3 mm M2 79,750.00 79,750.00
100 Asbes gelombang t = 5 mm Feet 9,185.00 9,185.00
101 Genteng soka / kodok Kp 5,610.00 5,610.00
102 Genteng bubungan soka Kp 5,500.00 5,500.00
103 Genteng beton Kp 8,250.00 8,250.00
104 Genteng flat Kp 7,425.00 7,425.00
105 Genteng rabung Beton Kp 7,700.00 7,700.00
106 Genteng Keramik Glassur Kp 12,650.00 12,650.00
107 Genteng bubungan keramik Kp 24,200.00 24,200.00
108 Karpet talang M' 11,000.00 11,000.00
109 Aluminium T = 0,8 mm M2 141,570.00 141,570.00
110 Kaca bening 3 mm M2 63,470.00 63,470.00
111 Kaca bening 5 mm M2 129,140.00 129,140.00
112 Kaca rayben 5 mm M2 145,640.00 145,640.00
113 Jendela kaca nako rayben 5 mm (lengkap) Daun/60cm 35,200.00 35,200.00
114 Closet duduk Bh 1,753,400.00 1,753,400.00
115 Closet jongkok Bh 199,540.00 199,540.00
116 Closet monoblok porslint (duduk) KW2 Bh 2,035,000.00 2,035,000.00
117 Closet jongkok keramik KW 2 Bh 330,000.00 330,000.00
118 Wastafel / keramik (Lengkap + Kran) Set 1,284,800.00 1,284,800.00
119 Shower WC Bh 134,200.00 134,200.00
120 Floor drain Bh 21,230.00 21,230.00
121 Kran air 1/2 Bh 22,000.00 22,000.00
122 Kran air 3/4 Bh 23,100.00 23,100.00
123 Tangki Air 500 Liter Bh 990,000.00 990,000.00
124 Tangki Air 1000 Liter Bh 1,432,200.00 1,432,200.00
125 Kunci tanam 2 x putar Set 96,800.00 96,800.00
126 Kunci tanam 2 x putar kuningan Set 127,600.00 127,600.00
127 Grandel kuningan Bh 14,300.00 14,300.00
128 Kait angin Bh 11,000.00 11,000.00
129 Buis Beton Dia. 20cm m 77,000.00 77,000.00

SATUAN
HARGA DASAR PROFIT JUMLAH HARGA
NO. BAHAN / MATERIAL UNIT KODE
(Rp) (Rp) (Rp)
129 Engsel kuningan Bh 86,020.00 86,020.00
130 Pipa besi medium f1" (6 m') Btg 176,000.00 176,000.00
131 Pipa besi medium f 2" (6 m') Btg 346,500.00 346,500.00
132 Pipa besi medium f 3" (6 m') Btg 550,000.00 550,000.00
133 Pipa besi medium f 4" (6 m') Btg 660,000.00 660,000.00
134 Pipa besi medium f 6" (6 m') Btg 1,375,000.00 1,375,000.00
135 Pipa PVC AW Ø 1/2" (4 m') M' 5,500.00 5,500.00
136 Pipa PVC AW Ø 3/4" (4 m') M' 6,875.00 6,875.00
137 Pipa PVC AW Ø 1" (4 m') M' 14,245.00 14,245.00
138 Pipa PVC AW Ø 2" (4 m') M' 17,875.00 17,875.00
139 Pipa PVC AW Ø 3" (4 m') M' 30,112.50 30,112.50
140 Pipa PVC AW Ø 4" (4 m') M' 42,047.50 42,047.50
141 Pipa PVC AW Ø 6" (4 m') M' 88,082.50 88,082.50
142 Pipa PVC AW Ø 8" (4 m') M' 181,775.00 181,775.00
143 Pipa PVC AW Ø 10" (4 m') M' 303,187.50 303,187.50
144 Pipa beton 15 - 20 Cm Bh 66,000.00 66,000.00
145 Pipa listrik 5/8 inci Bh 7,700.00 7,700.00
146 Bola Lampu SL. 24 watt Bh 42,350.00 42,350.00
147 Lampu pijar Bh 7,150.00 7,150.00
148 Lampu XL. 18 watt Bh 35,200.00 35,200.00
149 Saklar Unit 12,100.00 12,100.00
150 Stop kontak Unit 13,200.00 13,200.00
151 Box sekring Unit 28,050.00 28,050.00
152 Pipa conduit Listrik 5/8" Btg 5,500.00 5,500.00
153 Pintu lipat M2 275,000.00 275,000.00
154 Folding gate t = 0.4 mm M2 522,500.00 522,500.00
155 Folding gate t = 0.5 mm M2 577,500.00 577,500.00
156 Folding gate t = 0.8 mm M2 797,500.00 797,500.00
157 Rolling door M2 247,500.00 247,500.00
158 Rangka Besi Hollow + Plafond Gypsum M2 132,000.00 132,000.00
159 Baja Ringan M2 187,000.00 187,000.00
Pintu Rangka Aluminium, Kaca T.5 mm 1,375,000.00
160 Unit 1,375,000.00
(Kusen warna silver lengkap) 0.00
Pintu Rangka Aluminium, Kaca T.5 mm 1,650,000.00
161 Unit 1,650,000.00
(Kusen warna hitam lengkap) 0.00
Pintu Rangka Aluminium, Kaca T.5 mm 1,650,000.00
162 Unit 1,650,000.00
(Kusen warna coklat lengkap) 0.00
163 Kusen Aluminium T.3 Inci warna silver M1 550,000.00 550,000.00
164 Kusen Aluminium T.3 Inci warna hitam M1 60,500.00 60,500.00
165 Kusen Aluminium T.3 Inci warna coklat M1 60,500.00 60,500.00
166 Kusen Aluminium T.4 Inci warna silver M1 104,500.00 104,500.00
167 Kusen Aluminium T.4 Inci warna hitam M1 110,000.00 110,000.00
168 Kusen Aluminium T.4 Inci warna coklat M1 110,000.00 110,000.00
Jendela Rangka Aluminium, 275,000.00
169 Unit 275,000.00
kaca T.5 mm < (60 cm) 0.00
Jendela Rangka Aluminium, 550,000.00
170 Unit 550,000.00
kaca T.5 mm > (60 cm) 0.00
171 Metal Roof (Biasa) M2 71,500.00 71,500.00
172 Metal Roof (Pasir) M2 110,000.00 110,000.00
173 Bubungan genteng metal (biasa) M1 73,425.00 73,425.00
174 Bubungan genteng metal (pasir) M1 110,000.00 110,000.00
175 Listplank GRC M1 73,425.00 73,425.00
176 Batu alam palimanan M2 165,000.00 165,000.00
177 Batu alam andesit M2 220,000.00 220,000.00
178 Door closer alumunium Bh 167,750.00 167,750.00
DAFTAR HARGA SATUAN MATERIAL/BAHAN DAN UPAH TENAGA KERJA
TAHUN ANGGARAN 2016

SATUAN
HARGA DASAR JUMLAH HARGA
NO. BAHAN / MATERIAL UNIT KODE
(Rp) (Rp)
1 Dop PVC Dia. 110 bh 96,000.00
2 Dop PVC Dia. 160 bh 159,100.00
3 Dop PVC Dia. 200 bh 339,300.00
4 Bend Double socket (vinilon) Dia. 110 bh 106,500.00
5 Bend Double socket (vinilon) Dia. 160 bh 241,200.00
6 Bend Double socket (vinilon) Dia. 210 bh 431,900.00
7 Tee PVC Dia.110 bh 97,600.00
8 Tee PVC Dia.160 bh 104,000.00
9 Tee PVC Dia.210 bh 132,000.00
10 Aspal Curah/ beton kg 13,000.00
I. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN

HARGA SATUAN JUMLAH


NO ANALISA SAT KOEFISIEN
(Rp) (Rp)
1 35 m2 Lapisan Penetrasi Aspal
1 Bahan :
- Batu Pecah 3/5 m³ 1.78 225,830.00 401,977.40
- Batu Pecah 1/2 m³ 0.56 225,830.00 126,464.80
- Abu Batu m³ 0.30 146,630.00 43,989.00
- Aspal kg 180.00 13,000.00 2,340,000.00
- Alat Bantu set 1.00 75,000.00 75,000.00
2 Alat Kerja :
- Alat Perkerasan 1.00 250,000.00 250,000.00
3 Tenaga Kerja : -
- Operator Terlatih Oh 0.15 107,500.00 16,125.00
- Pembantu Operator Oh 0.15 85,000.00 12,750.00
- Sopir Truck Oh 0.08 93,500.00 7,012.50
- Pembantu Sopir Oh 0.08 85,000.00 6,375.00
- Buruh Lapangan Tak Terlatih Oh 4.95 90,000.00 445,500.00
- Buruh Lapangan Oh 0.15 93,500.00 14,025.00
- Mandor Lapangan Oh 0.15 129,000.00 19,350.00
JUMLAH 35 m2 Lapisan Penetrasi Aspal 3,758,568.70
PROFIT 10% 4,134,425.57
2 10 kg Tulangan Beton Polos/ Ulir
1 Bahan :
- Besi Beton Polos Kg 10.5000 18,260.00 191,730.00
- Kawat Beton kg 0.1500 20,900.00 3,135.00
2 Tenaga Kerja :
- Pekerja Oh 0.0700 93,500.00 6,545.00
- Tukang Besi Oh 0.0700 93,500.00 6,545.00
- Kepala Tukang Besi Oh 0.0070 107,500.00 752.50
- Mandor Oh 0.0040 129,000.00 516.00
JUMLAH 10 kg Tulangan Beton Polos/ Ulir 209,223.50
PROFIT 10% 230,145.85
3 1m Pemasangan Cerucuk Dolken dia. 8-10 cm
1 Bahan :
- Kayu Dolken m 1.0000 15,000.00 15,000.00
2 Tenaga Kerja :
- Pekerja Oh 0.0700 93,500.00 6,545.00
- Mandor Oh 0.0040 129,000.00 516.00
JUMLAH 1m Pemasangan Cerucuk Dolken dia. 8-10 cm 22,061.00
PROFIT 10% 24,267.10