B PEKERJAAN TANAH
1 Galian Tanah Pondasi 148.45 m3 74,875.00 11,114,864.30
2 Timbunan Tanah Kembali dan Leveling Lantai 111.47 m3 20,617.00 2,298,150.19
JUMLAH B 13,413,014.49
C PEKERJAAN ATAP
1 Pasang rangka baja ringan C75-0,75 mm, reng 0,35 mm (SNI) 138.13 m2 139,886.50 19,322,242.47
2 Pasang atap genteng beton flat ex. Mutiara 138.13 m2 158,546.00 21,899,641.89
3 Flashing 35.60 m1 44,900.00 1,598,440.00
4 Pasang Penutup Atap Polycarbonat, rangka baja ringan 16.80 m2 395,000.00 6,636,000.00
JUMLAH C 49,456,324.36
E PEKERJAAN PENGECATAN
Lantai 1
1 Pekerjaan Cat Eksterior ex. No Drop Putih 326.66 m2 28,168.00 9,201,471.55
2 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 420.93 m2 60,763.00 25,576,848.06
3 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 223.29 m2 28,168.00 6,289,765.11
Lantai 1
4 Pekerjaan Cat Eksterior ex. No Drop Putih 258.49 m2 28,168.00 7,281,019.56
5 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 776.31 m2 60,763.00 47,170,772.62
6 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 64.35 m2 28,168.00 1,812,610.80
7 Pekerjaan Cat Plafond ex. Dulux Catylac 103.50 m2 33,168.00 3,432,888.00
JUMLAH E 100,765,375.71
F PEKERJAAN LAIN-LAIN
1 Railing Tangga Besi Hollow + Expanded Metal Mesh + cat 6.70 m1 430,000.00 2,881,000.00
2 Railing Balkon Besi Hollow + Expanded Metal Mesh + cat 33.70 m1 430,000.00 14,491,000.00
3 Tangga atap besi hollow 30x30x2 mm 2.00 unit 960,000.00 1,920,000.00
4 Pintu Pagar Besi + rel 1.00 unit tidak termasuk
5 Box Dudukan meteran PDAM + penutup plat bordes 1.00 unit 665,750.00 665,750.00
JUMLAH F 19,957,750.00
TOTAL II 620,728,932.00
A.4 Pentanahan
1 Instalasi Pentanahan/Grounding Dengan Pipa Tembaga 1.5 meter 1.00 ls tidak termasuk
JUMLAH A.4 -
SUB TOTAL A 65,498,342.76
C. PEKERJAAN PLUMBING
C.1 Pekerjaan Sanitair / Upah Pasang
Lantai 1
1 Floordrain ex. Wasser WRD 03 8.00 unit 230,000.00 1,840,000.00
2 Kran Dinding ex. Wasser TL 010 10.00 unit 180,000.00 1,800,000.00
3 Kitchen Zink ex. Teka by Linea tipe Valencia 1B1D 1.00 unit 1,250,000.00 1,250,000.00
4 Kran Zink ex. Wasser TL2 140 1.00 unit 392,000.00 392,000.00
5 Closet Jongkok ex. TOTO CE 7 6.00 unit 475,000.00 2,850,000.00
Lantai 2
1 Floordrain ex. Wasser WRD 03 9.00 unit 230,000.00 2,070,000.00
2 Kran Dinding ex. Wasser TL 010 9.00 unit 180,000.00 1,620,000.00
3 Closet Jongkok ex. TOTO CE 7 9.00 unit 475,000.00 4,275,000.00
JUMLAH C.1 16,097,000.00
2. Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 MPa (K 100) slump (3-6) cm w/c = 0,87
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 1.200 96,000.00 115,200.00
2 Tukang Batu L.02 OH 0.200 110,000.00 22,000.00
3 Kepala Tukang L.16 OH 0.020 110,000.00 2,200.00
4 Mandor L.17 OH 0.060 115,000.00 6,900.00
JUMLAH HARGA TENAGA KERJA 146,300.00
B BAHAN
1 Portland cement M.481 kg 230.0 1,080.00 248,400.00
2 Pasir urug (quarry - lokasi pekerjaan) M.24 m³ 0.525 236,300.00 124,057.50
3 Batu pecah M.30 kg 1027.000 200.00 205,400.00
4 Air, M.958 liter 200.0 200.00 40,000.00
JUMLAH HARGA BAHAN 617,857.50
C PERALATAN
JUMLAH HARGA ALAT 0
D Jumlah (A+B+C) 764,157.50
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 764,157.50
3. Membuat 1 m3 beton mutu f'c = 14,5 MPa (K 175) slump (12± 2) cm w/c = 0,66 perbandingan 1:2:3
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 1.650 96,000.00 158,400.00
2 Tukang Batu L.02 OH 0.275 110,000.00 30,250.00
3 Kepala Tukang L.16 OH 0.028 110,000.00 3,080.00
4 Mandor L.17 OH 0.083 115,000.00 9,545.00
JUMLAH HARGA TENAGA KERJA 201,275.00
B BAHAN
1 Portland cement M.481 kg 326.000 1,080.00 352,080.00
2 Pasir urug (quarry - lokasi pekerjaan) M.24 m³ 0.447 236,300.00 105,626.10
3 Batu pecah M.30 kg 1029.000 200.00 205,800.00
4 Air, M.958 liter 215.000 200.00 43,000.00
JUMLAH HARGA BAHAN 706,506.10
C PERALATAN
JUMLAH HARGA ALAT 0
4 Pemasangan 1 m2 acian.
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 0.140 96,000.00 13,440.00
2 Kepala Tukang L.16 OH 0.010 110,000.00 1,100.00
3 Mandor L.17 OH 0.010 115,000.00 1,150.00
JUMLAH HARGA TENAGA KERJA 15,690.00
B BAHAN
1 Portland cement M.481 kg 3.250 1,080.00 3,510.00
JUMLAH HARGA BAHAN 3,510.00
C PERALATAN
1 Pengecatan 1 m2 tembok baru (1 lps plamuur, 1 lps cat dasar, 2 lps cat penutup) - interior
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 0.020 96,000.00 1,920.00
2 Tukang Cat L.08 OH 0.063 110,000.00 6,930.00
3 Kepala Tukang L.16 OH 0.0063 110,000.00 693.00
4 Mandor L.17 OH 0.003 115,000.00 345.00
JUMLAH HARGA TENAGA KERJA 9,888.00
B BAHAN
1 Cat dasar (cat tembok interior) M.514 kg 0.10 46,750.00 4,675.00
2 Cat penutup (cat tembok interior) M.515 kg 0.25 184,800.00 46,200.00
JUMLAH HARGA BAHAN 50,875.00
C PERALATAN
2 Pengecatan 1 m2 tembok baru ( 1 lps cat dasar, 2 lps cat penutup) - exterior
Jumlah Harga
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 0.020 96,000.00 1,920.00
2 Tukang Cat L.08 OH 0.063 110,000.00 6,930.00
3 Kepala Tukang L.16 OH 0.0063 110,000.00 693.00
4 Mandor L.17 OH 0.003 115,000.00 345.00
JUMLAH HARGA TENAGA KERJA 9,888.00
B BAHAN
1 Cat dasar (cat tembok exterior) M.516 kg 0.12 51,500.00 6,180.00
2 Cat penutup (cat tembok exterior) M.517 kg 0.25 48,400.00 12,100.00
JUMLAH HARGA BAHAN 18,280.00
C PERALATAN
HARGA
NO URAIAN SATUAN KODE SATUAN (Rp.)
1 2 3 4 5
I. TENAGA
1 Pekerja OH L.01 96,000.00
2 Tukang Batu OH L.02 110,000.00
3 Tukang Kayu OH L.03 115,000.00
4 Tukang Besi OH L.04 115,000.00
5 Tukang Pipa OH L.06 110,000.00
6 Tukang Las OH L.07 110,000.00
7 Tukang Cat OH L.08 110,000.00
8 Tukang erection OH L.10 110,000.00
9 Tukang Alumunium OH L.12 105,000.00
10 Tukang gali OH L.13 105,000.00
11 Tukang aspal OH L.14 105,000.00
12 Tukang listrik OH L.15 110,000.00
13 Kepala Tukang OH L.16 110,000.00
14 Mandor OH L.17 115,000.00
15 Juru ukur OH L.18 155,000.00
16 Operator alat berat OH L.19 220,000.00
17 Operator pompa OH L.20 105,000.00
18 Mekanik alat berat OH L.21 190,000.00
19 Pembantu operator alat berat OH L.22 105,000.00
20 Pembantu mekanik alat berat OH L.23 105,000.00
21 Koordinator driller OH L.24 140,000.00
22 Driller OH L.25 105,000.00
23 Pembantu driller OH L.26 105,000.00
24 Crew driller OH L.27 96,000.00
25 Ahli geologist OH L.28 375,000.00
26 Administrasi bor OH L.29 96,000.00
27 Sopir OH L.30 165,000.00
Supir kendaraan < 2 ton (termasuk
28 sedan) OH L.31 136,000.00
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 148.45 m3 74,875.00 11,114,864.30
2 Timbunan Tanah Kembali dan Leveling Lantai 111.47 m3 20,617.00 2,298,150.19
JUMLAH B 13,413,014.49
C PEKERJAAN ATAP
1 Pasang rangka baja ringan C75-0,75 mm, reng 0,35 mm (SNI) 138.13 m2 22,775.00 3,145,865.20
2 Pasang atap genteng beton flat ex. Mutiara 138.13 m2 37,750.00 5,214,332.00
3 Flashing 35.60 m1 12,500.00 445,000.00
4 Pasang Penutup Atap Polycarbonat, rangka baja ringan 16.80 m2 40,000.00 672,000.00
JUMLAH C 9,477,197.20
E PEKERJAAN PENGECATAN
Lantai 1
1 Pekerjaan Cat Eksterior ex. No Drop Putih 326.66 m2 9,888.00 3,230,053.63
2 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 420.93 m2 9,888.00 4,162,136.06
3 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 223.29 m2 9,888.00 2,207,937.99
Lantai 1
4 Pekerjaan Cat Eksterior ex. No Drop Putih 258.49 m2 9,888.00 2,555,904.62
5 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 776.31 m2 9,888.00 7,676,128.56
6 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 64.35 m2 9,888.00 636,292.80
7 Pekerjaan Cat Plafond ex. Dulux Catylac 103.50 m2 9,888.00 1,023,408.00
JUMLAH E 21,491,861.67
F PEKERJAAN LAIN-LAIN
1 Railing Tangga Besi Hollow + Expanded Metal Mesh + cat 6.70 m1 55,000.00 368,500.00
2 Railing Balkon Besi Hollow + Expanded Metal Mesh + cat 33.70 m1 55,000.00 1,853,500.00
3 Tangga atap besi hollow 30x30x2 mm 2.00 unit 275,000.00 550,000.00
4 Pintu Pagar Besi + rel 1.00 unit tidak termasuk
5 Box Dudukan meteran PDAM + penutup plat bordes 1.00 unit 175,000.00 175,000.00
JUMLAH F 2,947,000.00
TOTAL II 234,362,406.69
A.4 Pentanahan
1 Instalasi Pentanahan/Grounding Dengan Pipa Tembaga 1.5 meter 1.00 ls tidak termasuk
JUMLAH A.4 -
SUB TOTAL A 17,195,000.00
C. PEKERJAAN PLUMBING
C.1 Pekerjaan Sanitair / Upah Pasang
Lantai 1
1 Floordrain ex. Wasser WRD 03 8.00 unit 35,000.00 280,000.00
2 Kran Dinding ex. Wasser TL 010 10.00 unit 35,000.00 350,000.00
3 Kitchen Zink ex. Teka by Linea tipe Valencia 1B1D 1.00 unit 150,000.00 150,000.00
4 Kran Zink ex. Wasser TL2 140 1.00 unit 35,000.00 35,000.00
5 Closet Jongkok ex. TOTO CE 7 6.00 unit 100,000.00 600,000.00
Lantai 2
1 Floordrain ex. Wasser WRD 03 9.00 unit 35,000.00 315,000.00
2 Kran Dinding ex. Wasser TL 010 9.00 unit 35,000.00 315,000.00
3 Closet Jongkok ex. TOTO CE 7 9.00 unit 100,000.00 900,000.00
JUMLAH C.1 2,945,000.00
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 148.45 m3 - -
2 Timbunan Tanah Kembali dan Leveling Lantai 111.47 m3 - -
JUMLAH B -
C PEKERJAAN ATAP
1 Pasang rangka baja ringan C75-0,75 mm, reng 0,35 mm (SNI) 138.13 m2 117,111.50 16,176,377.27
2 Pasang atap genteng beton flat ex. Mutiara 138.13 m2 120,796.00 16,685,309.89
3 Flashing 35.60 m1 32,400.00 1,153,440.00
4 Pasang Penutup Atap Polycarbonat, rangka baja ringan 16.80 m2 355,000.00 5,964,000.00
JUMLAH C 39,979,127.16
E PEKERJAAN PENGECATAN
Lantai 1
1 Pekerjaan Cat Eksterior ex. No Drop Putih 326.66 m2 18,280.00 5,971,417.92
2 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 420.93 m2 50,875.00 21,414,712.00
3 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 223.29 m2 18,280.00 4,081,827.12
Lantai 1
4 Pekerjaan Cat Eksterior ex. No Drop Putih 258.49 m2 18,280.00 4,725,114.94
5 Pekerjaan Cat Interior ex. Stucco Cement Grey SV 09-58 776.31 m2 50,875.00 39,494,644.06
6 Pekerjaan Cat Dak Ekspose ex. No Drop Putih 64.35 m2 18,280.00 1,176,318.00
7 Pekerjaan Cat Plafond ex. Dulux Catylac 103.50 m2 23,280.00 2,409,480.00
JUMLAH E 79,273,514.04
F PEKERJAAN LAIN-LAIN
1 Railing Tangga Besi Hollow + Expanded Metal Mesh + cat 6.70 m1 375,000.00 2,512,500.00
2 Railing Balkon Besi Hollow + Expanded Metal Mesh + cat 33.70 m1 375,000.00 12,637,500.00
3 Tangga atap besi hollow 30x30x2 mm 2.00 unit 685,000.00 1,370,000.00
4 Pintu Pagar Besi + rel 1.00 unit tidak termasuk
5 Box Dudukan meteran PDAM + penutup plat bordes 1.00 unit 490,750.00 490,750.00
JUMLAH F 17,010,750.00
TOTAL II 386,366,525.31
A.4 Pentanahan
1 Instalasi Pentanahan/Grounding Dengan Pipa Tembaga 1.5 meter 1.00 ls tidak termasuk
JUMLAH A.4 -
SUB TOTAL A 48,303,342.76
C. PEKERJAAN PLUMBING
C.1 Pekerjaan Sanitair / Upah Pasang
Lantai 1
1 Floordrain ex. Wasser WRD 03 8.00 unit 195,000.00 1,560,000.00
2 Kran Dinding ex. Wasser TL 010 10.00 unit 145,000.00 1,450,000.00
3 Kitchen Zink ex. Teka by Linea tipe Valencia 1B1D 1.00 unit 1,100,000.00 1,100,000.00
4 Kran Zink ex. Wasser TL2 140 1.00 unit 357,000.00 357,000.00
5 Closet Jongkok ex. TOTO CE 7 6.00 unit 375,000.00 2,250,000.00
Lantai 2
1 Floordrain ex. Wasser WRD 03 9.00 unit 195,000.00 1,755,000.00
2 Kran Dinding ex. Wasser TL 010 9.00 unit 145,000.00 1,305,000.00
3 Closet Jongkok ex. TOTO CE 7 9.00 unit 375,000.00 3,375,000.00
JUMLAH C.1 13,152,000.00