Anda di halaman 1dari 2

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA UMUM KECAMATAN ZONA II


PEKERJAAN : LANJUTAN PEMBANGUNAN MASJID NUR SULAIMAN DESA BENUA BARU ULU KEC. SANGKULIRANG
LOKASI : KECAMATAN SANGKULIRANG
TAHUN ANGGARAN : 2016

JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
(Rp.)

A. PEKERJAAN PENDAHULUAN
1 Serobong Kerja Ls 1.000 2,300,000.00 2,300,000.00
2 Papan Nama Proyek Ls 1.000 350,000.00 350,000.00
SUB TOTAL PEKERJAAN PENDAHULUAN 2,650,000.00

B. PEKERJAAN TANAH
1 Galian tanah untuk pondasi M³ 4.320 54,375.00 234,900.00
2 Urugan Kembali M³ 1.440 13,560.60 19,527.26
3 Urugan Tanah M³ 460.800 223,125.00 102,816,000.00
4 Urugan Pasir M³ 31.250 540,250.00 16,882,812.50
SUB TOTAL PEKERJAAN TANAH 119,953,239.76

C PEKERJAAN PONDASI
1 Pasangan Batu Gunung 1:4 M³ 2.840 1,568,325.00 4,454,043.00
2 Cerucuk Ulin 10/10-1,5 m Ttk 7.000 210,550.00 1,473,850.00
3 Kalang Ulin 2,5x20-2 M³ 0.100 6,312,850.00 631,285.00
SUB TOTAL PEKERJAAN PONDASI 6,559,178.00

D. PEKERJAAN BETON
I. PEKERJAAN BETON COR
1 Cor BO M³ 28.800 2,189,446.00 63,056,044.80
2 Cor Beton Fc 21,7 Untuk Sloof M³ 0.540 2,414,667.00 1,303,920.18
3 Cor Kolom Practice M³ 1.110 2,275,467.00 2,525,768.37
4 Cor Kolom Padestal M³ 1.310 2,275,467.00 2,980,861.77
5 Cor Beton Fc 21,7 Untuk Kolom Utama M³ 4.780 2,414,667.00 11,542,108.26
6 Cor Beton Fc 21,7 Untuk Balok M³ 15.840 2,414,667.00 38,248,325.28
7 Cor Beton Fc 21,7 Untuk Ring Balk M³ 4.560 2,414,667.00 11,010,881.52
8 Cor Beton Fc 21,7 Untuk Dak M³ 38.400 2,414,667.00 92,723,212.80
9 Cor Beton Listplank M³ 3.600 2,275,467.00 8,191,681.20
10 Cor Beton Fc 21,7 Untuk Kanopy Beton M³ 2.700 2,414,667.00 6,519,600.90
SUB TOTAL PEKERJAAN BETON COR 238,102,405.08

II. PEKERJAAN PEMBESIAN


1 Pembesian Untuk Sloof Kg 95.700 21,218.50 2,030,610.45
2 Pembesian Untuk Kolom Kg 1,393.240 21,218.50 29,562,462.94
3 Pembesian Untuk Balok Kg 5,501.660 21,218.50 116,736,972.71
4 Pembesian Untuk Ringbalk Kg 721.490 21,218.50 15,308,935.57
5 Pembesian Untuk Dak Kg 7,950.780 21,218.50 168,703,625.43
6 Pembesian Untuk Kanopy dan Listplank Kg 1,035.900 21,218.50 21,980,244.15
SUB TOTAL PEKERJAAN PEMBESIAN 354,322,851.25

III. PEKERJAAN BAGHESTING


1 Baghesting Untuk Sloof M² 2.400 276,750.00 664,200.00
2 Baghesting Untuk Kolom M² 45.030 276,750.00 12,462,052.50
3 Baghesting Untuk Balok M² 109.200 276,750.00 30,221,100.00
4 Baghesting Untuk Dak M² 160.000 276,750.00 44,280,000.00
5 Baghesting Untuk Kanopy dan Listplank M² 34.300 276,750.00 9,492,525.00
SUB TOTAL PEKERJAAN BAGHESTING 97,119,877.50
JUMLAH TOTAL PEKERJAAN BETON 689,545,133.83

E. PASANGAN DINDING DAN PLESTERAN


1 Pasangan Batu Bata Merah 1:4 M² 354.560 205,375.00 72,817,760.00
2 Plesteran 1:4 Tebal 15mm M² 709.120 99,455.00 70,525,529.60
3 Acian Dinding dan Kolom M² 623.220 10,921.35 6,806,403.75
SUB TOTAL PASANGAN DINDING DAN PLESTERAN 150,149,693.35

F. PEKERJAAN RANGKA ATAP / ATAP


1 Rangka Atap Baja Ringan M² 441.730 235,125.00 103,861,766.25
2 Aluminium Foil M² 441.730 56,000.00 24,736,880.00
3 Atap Metal M² 441.730 168,575.00 74,464,634.75
4 Bubungan Atap M' 64.800 105,580.00 6,841,584.00
5 Listplank M' 89.000 77,130.00 6,864,570.00
SUB TOTAL PEKERJAAN RANGKA ATAP / ATAP 216,769,435.00
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
(Rp.)

G. PEKERJAAN PINTU DAN JENDELA


1 Pasangan Daun Pintu Panil Kayu Kelas I M² 24.70 436,500.00 10,781,550.00
2 Pasang Kunci Tanam Bh 10.00 231,025.00 2,310,250.00
3 Pasang Engsel Pintu, Engsel Kupu - Kupu Besar Bh 80.00 49,400.00 3,952,000.00
4 Pasang Kaca Tempred, Tebal 10 mm M² 65.000 300,625.00 19,540,625.00
5 Pasang Kusen Kayu Kelas I M' 210.000 76,112.50 15,983,625.00
6 Pasang Gagang Pintu Utama Unit 12.000 148,457.50 1,781,490.00
SUB TOTAL PEKERJAAN PINTU DAN JENDELA 37,305,740.00

H. PEKERJAAN ACP DAN PARTISI


1 Pasangan Dinding ACP + Rangka M² 85.900 249,925.00 21,468,557.50
SUB TOTAL PEKERJAAN ACP DAN PARTISI 21,468,557.50

I. PEKERJAAN PLAFON
1 Plafond Gypsum ( Minimalis ) M² 726.000 78,315.00 56,856,690.00
2 Rangka Hollow 4 x 4 cm untuk plafond M² 726.000 238,950.00 173,477,700.00
SUB TOTAL PEKERJAAN PLAFON 230,334,390.00

J. PEKERJAAN KERAMIK
1 Keramik Lantai Keramik Motif 60x60 cm M² 576.000 295,612.00 170,272,512.00
2 Keramik dinding 60x60 ( Granit ) M² 20.000 552,735.00 11,054,700.00
SUB TOTAL PEKERJAAN KERAMIK 181,327,212.00

K. PEKERJAAN LISTRIK
1 Kotak MCB 4 Group Unit 2.00 759,000.00 1,518,000.00
2 Lampu TL 36 Watt x 2 & Instalansi Ttk 30.00 274,000.00 8,220,000.00
3 Saklar Ganda & Instalansi Ttk 5.00 155,770.00 778,850.00
4 Saklar Tunggal & Instalansi Ttk 2.00 91,000.00 182,000.00
5 Stop Kontak & Instalansi Ttk 52.00 106,000.00 5,512,000.00
6 Stop Kontak AC & Instalansi Ttk 8.00 106,000.00
SUB TOTAL PEKERJAAN LISTRIK 16,210,850.00

L. PEKERJAAN FINISHING
1 Pengecatan Kusen dan Pintu M² 53.10 79,402.50 4,216,272.75
2 Ornamen Dinding Masjid M² 31.500 69,537.50 2,190,431.25
3 Penegcatan Dinding, Kolom dan Plafond M² 1,349.220 69,537.50 93,821,385.75
SUB TOTAL PEKERJAAN FINISHING 100,228,089.75

Anda mungkin juga menyukai