JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
(Rp.)
A. PEKERJAAN PENDAHULUAN
1 Serobong Kerja Ls 1.000 2,300,000.00 2,300,000.00
2 Papan Nama Proyek Ls 1.000 350,000.00 350,000.00
SUB TOTAL PEKERJAAN PENDAHULUAN 2,650,000.00
B. PEKERJAAN TANAH
1 Galian tanah untuk pondasi M³ 4.320 54,375.00 234,900.00
2 Urugan Kembali M³ 1.440 13,560.60 19,527.26
3 Urugan Tanah M³ 460.800 223,125.00 102,816,000.00
4 Urugan Pasir M³ 31.250 540,250.00 16,882,812.50
SUB TOTAL PEKERJAAN TANAH 119,953,239.76
C PEKERJAAN PONDASI
1 Pasangan Batu Gunung 1:4 M³ 2.840 1,568,325.00 4,454,043.00
2 Cerucuk Ulin 10/10-1,5 m Ttk 7.000 210,550.00 1,473,850.00
3 Kalang Ulin 2,5x20-2 M³ 0.100 6,312,850.00 631,285.00
SUB TOTAL PEKERJAAN PONDASI 6,559,178.00
D. PEKERJAAN BETON
I. PEKERJAAN BETON COR
1 Cor BO M³ 28.800 2,189,446.00 63,056,044.80
2 Cor Beton Fc 21,7 Untuk Sloof M³ 0.540 2,414,667.00 1,303,920.18
3 Cor Kolom Practice M³ 1.110 2,275,467.00 2,525,768.37
4 Cor Kolom Padestal M³ 1.310 2,275,467.00 2,980,861.77
5 Cor Beton Fc 21,7 Untuk Kolom Utama M³ 4.780 2,414,667.00 11,542,108.26
6 Cor Beton Fc 21,7 Untuk Balok M³ 15.840 2,414,667.00 38,248,325.28
7 Cor Beton Fc 21,7 Untuk Ring Balk M³ 4.560 2,414,667.00 11,010,881.52
8 Cor Beton Fc 21,7 Untuk Dak M³ 38.400 2,414,667.00 92,723,212.80
9 Cor Beton Listplank M³ 3.600 2,275,467.00 8,191,681.20
10 Cor Beton Fc 21,7 Untuk Kanopy Beton M³ 2.700 2,414,667.00 6,519,600.90
SUB TOTAL PEKERJAAN BETON COR 238,102,405.08
I. PEKERJAAN PLAFON
1 Plafond Gypsum ( Minimalis ) M² 726.000 78,315.00 56,856,690.00
2 Rangka Hollow 4 x 4 cm untuk plafond M² 726.000 238,950.00 173,477,700.00
SUB TOTAL PEKERJAAN PLAFON 230,334,390.00
J. PEKERJAAN KERAMIK
1 Keramik Lantai Keramik Motif 60x60 cm M² 576.000 295,612.00 170,272,512.00
2 Keramik dinding 60x60 ( Granit ) M² 20.000 552,735.00 11,054,700.00
SUB TOTAL PEKERJAAN KERAMIK 181,327,212.00
K. PEKERJAAN LISTRIK
1 Kotak MCB 4 Group Unit 2.00 759,000.00 1,518,000.00
2 Lampu TL 36 Watt x 2 & Instalansi Ttk 30.00 274,000.00 8,220,000.00
3 Saklar Ganda & Instalansi Ttk 5.00 155,770.00 778,850.00
4 Saklar Tunggal & Instalansi Ttk 2.00 91,000.00 182,000.00
5 Stop Kontak & Instalansi Ttk 52.00 106,000.00 5,512,000.00
6 Stop Kontak AC & Instalansi Ttk 8.00 106,000.00
SUB TOTAL PEKERJAAN LISTRIK 16,210,850.00
L. PEKERJAAN FINISHING
1 Pengecatan Kusen dan Pintu M² 53.10 79,402.50 4,216,272.75
2 Ornamen Dinding Masjid M² 31.500 69,537.50 2,190,431.25
3 Penegcatan Dinding, Kolom dan Plafond M² 1,349.220 69,537.50 93,821,385.75
SUB TOTAL PEKERJAAN FINISHING 100,228,089.75