RENCANA ANGGARAN BIAYA

PEKERJAAN : Rumah Type 2


LOKASI : Kendari, Sulawesi Tenggara
PENDANAAN : Perseorangan
HARGA SAT JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT
(Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Mobilisasi dan demobilisasi 1,000 Ls - -
2 Pek. Pengukuran dan Pas. Bouwplank 54,000 m' 61.300,000 3.310.200,000
Sub Total I 3.310.200,000

II PEKERJAAN TANAH DAN PONDASI


1 Galian Tanah Pondasi Garis 119,624 M3 17.200,000 2.057.527,296
2 Urugan Pasir Bawah Pondasi Garis 5,280 M3 156.800,000 827.904,000
3 Pas. Batu Kosong Pondasi Garis 7,920 M3 304.680,000 2.413.065,600
4 Pas. Pondasi Batu Gunung 16,830 M3 673.800,000 11.340.054,000
Sub Total II 16.638.550,896

III PEKERJAAN STRUKTUR BETON

1 Sloof Beton 15/20 1,980 M3 3.185.570,000 6.307.428,600


2 Kolom 15/15 1,114 M3 3.662.150,000 4.078.719,563
3 Ring balk 15/20 1,275 M3 3.709.190,000 4.729.217,250
Sub Total III 15.115.365,413

IV PEKERJAAN PASANGAN DAN PLESTERAN


1 Pas. Batu Bata 1 : 5 Dinding 111,212 M2 100.985,000 11.230.743,820
2 Tegel dinding keramik warna 20 X 20 (wc) 4,500 M2 118.014,833 531.066,750
3 Plesteran Biasa 1 : 5 Dinding T. 15 mm 283,717 M2 34.750,000 9.859.172,700
4 Acian Dinding 283,717 M2 14.500,000 4.113.899,400
5 Pas. Batu Bata 1 : 5 Kuda kuda 30,647 M2 100.985,000 3.094.846,901
Sub Total IV 28.829.729,571

V PEKERJAAN PINTU DAN JENDELA


1 Pek. Kusen Pintu 0,193 M3 6.497.750,000 1.253.805,840
2 Pek. Jendela ( + Kaca 5mm ) 8,840 M2 183.357,200 1.620.877,648
3 Pek. Daun Pintu Panil 10,306 m2 421.500,000 4.343.810,400
4 Pas. Kunci Pintu 6,000 Bh 131.600,000 789.600,000
5 Pas. Engsel 12,000 Bh 32.540,000 390.480,000
Sub Total V 8.398.573,888

VI PEKERJAAN RANGKA DAN ATAP


1 pekerjaan rangka atap baja ringan 64,948 M2 150.000,000 9.742.170,000
2 pekerjaan atap 64,948 M2 77.560,000 5.037.351,368
3 pekerjaan list plank 41,200 M' 82.594,000 3.402.872,800
Sub Total VI 18.182.394,168

VII PEKERJAAN PLAFOND


1 pekerjaan Rangka Plafond 46,498 M2 76.950,000 3.577.982,625
2 Pek. Plafon 46,498 M2 27.875,000 1.296.117,813
Sub Total VII 4.874.100,438

VIII PEKERJAAN LANTAI


1 pekerjaan lantai keramik 30 x 30 cm 36,209 M2 118.351,364 4.285.349,021
2 pekerjaan lantai keramik 20 x 20 cm 6,088 M2 118.014,833 718.497,908
3 Lapisan Pasir Bawah Lantai 7,160 M3 156.800,000 1.122.688,000
4 Beton 1 Pc : 2 Ps : 3 Kr 1,460 M3 1.052.280,000 1.536.328,800
Sub Total VIII 7.662.863,729

IX PEKERJAAN SANITASI
1 pekerjaan pipa air bersih 21,850 M' 42.748,000 934.043,800
2 pekerjaan pipa air kotor 7,000 M' 42.748,000 299.236,000
3 pekerjaan kran air 4,000 Bh 24.200,000 96.800,000
4 pekerjaan closet duduk / jongkok 1,000 Bh 2.320.280,000 2.320.280,000
5 pembuatan Septic tank + peresapan 1,000 Bh 4.196.206,500 4.196.206,500
Sub Total IX 7.846.566,300

X PEKERJAAN INSTALASI LISTRIK


A LANTAI 01
LISTRIK

1 Instalasi/Pengkabelan 11,000 Bh 147.870,000 1.626.570,000


2 Pas. Sakelar tunggal 3,000 Bh 69.800,000 209.400,000
3 Pas. Sakelar double 4,000 Bh 72.800,000 291.200,000
4 Pas. Stop Kontak 6,000 Bh 32.400,000 194.400,000
5 Pas. Lampu 30 watt 4,000 Bh 28.200,000 112.800,000
6 Pas. Lampu 15 watt 7,000 Bh 28.200,000 197.400,000
7 Lampu Taman 1,000 Bh 28.200,000 28.200,000
8 Sekring 1,000 Bh 138.500,000 138.500,000
Sub Total X 2.798.470,000

XI PEKERJAAN PENGECATAN
A LANTAI 01
1 Pengecatan Dinding 283,717 M2 15.414,000 4.373.216,921
2 Pengecatan Plafond 46,498 M2 13.064,000 607.443,340
3 Pengecatan Kayu dan besi 45,800 M2 26.780,000 1.226.524,000
Sub Total XI 6.207.184,261

XII FINISHING
1 As Built Drawing 1,000 Ls 1.500.000,000 1.500.000,000

TOTAL ANGGARAN 121.363.998,66