I PEKERJAAN PENDAHULUAN
1 Mobilisasi dan demobilisasi 1,000 Ls - -
2 Pek. Pengukuran dan Pas. Bouwplank 54,000 m' 61.300,000 3.310.200,000
Sub Total I 3.310.200,000
IX PEKERJAAN SANITASI
1 pekerjaan pipa air bersih 21,850 M' 42.748,000 934.043,800
2 pekerjaan pipa air kotor 7,000 M' 42.748,000 299.236,000
3 pekerjaan kran air 4,000 Bh 24.200,000 96.800,000
4 pekerjaan closet duduk / jongkok 1,000 Bh 2.320.280,000 2.320.280,000
5 pembuatan Septic tank + peresapan 1,000 Bh 4.196.206,500 4.196.206,500
Sub Total IX 7.846.566,300
XI PEKERJAAN PENGECATAN
A LANTAI 01
1 Pengecatan Dinding 283,717 M2 15.414,000 4.373.216,921
2 Pengecatan Plafond 46,498 M2 13.064,000 607.443,340
3 Pengecatan Kayu dan besi 45,800 M2 26.780,000 1.226.524,000
Sub Total XI 6.207.184,261
XII FINISHING
1 As Built Drawing 1,000 Ls 1.500.000,000 1.500.000,000