Yogyakarta, 30 Desember2017
Perencana
Daftar Kuantitas dan Harga
RENCANA ANGGARAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH TINGGAL
HARGA HARGA
TOTAL UPAH TOTAL BAHAN TOTAL HARGA
No URAIAN PEKERJAAN VOL. SAT. SATUAN SATUAN
(RUPIAH) (RUPIAH) (RUPIAH)
UPAH BAHAN
I. PEKERJAAN PERSIAPAN
1. Pengukuran dan pas. bouwplank 48.00 m¹ 17,100 94,050 820,800 4,514,400 5,335,200
2. Pembersihan lahan 181.50 m 2 12,500 0 2,268,750 0 2,268,750
3. Penerangan dan air kerja 1.00 ls 0 1,000,000 0 1,000,000 1,000,000
4. Pekerjaan Pagar Proyek 55.00 m¹ 29,200 71,500 1,606,000 3,932,500 5,538,500
5. Pembuatan Sumur 12.00 m¹ 109,275 121,000 1,311,300 1,452,000 2,763,300
V. PEKERJAAN PASANGAN
1. Pas. Batu bata 1:4 tebal 1/2 bata 253.25 m2 30,800 83,000 7,800,100 21,019,750 28,819,850
2. Pek. Plesteran 506.50 m 2
34,700 11,475 17,575,550 5,812,088 23,387,638
3. Pek. Acian 506.50 m 2
19,060 8,500 9,653,890 4,305,250 13,959,140
4. Pas. Batu bata 1:4 tebal 1/2 bata gunung2 33.30 m 2
30,800 83,000 1,025,640 2,763,900 3,789,540
5. Pasanga Dinding Ekspos 24.00 m2 47,500 151,035 1,140,000 3,624,840 4,764,840
6. Rabat beton lantai 5.02 m 3
104,200 507,112 523,084 2,545,702 3,068,786
7. Pas. Lt.Keramik Km/Wc+Rg.Cuci 20x20 cm 7.00 m2 30,810 105,868 215,670 741,076 956,746
8. Pas. Lantai Keramik 30x30 cm 92.25 m2 30,810 110,868 2,842,223 10,227,573 13,069,796
9. Pas. Lantai Keramik kasar 40x40 cm 24.00 m2 29,735 125,868 713,640 3,020,832 3,734,472
10. Pas. Ddg Toilet Keramik 20x40 m,t=2m 24.60 m 2
67,900 120,382 1,670,340 2,961,397 4,631,737
10. KWH Meter 1.00 unit 60,000 100,000 60,000 100,000 160,000
13. Biaya Pasang Listrik Baru 1.00 set 0 4,000,000 0 4,000,000 4,000,000
4. Pek. Kloset duduk 1.00 set 328,200 2,650,000 328,200 2,650,000 2,978,200
9. Pek. Pasang water tower 1.00 unit 21,405 8,600,000 21,405 8,600,000 8,621,405
11. Septic Tank 1.00 unit 1,046,860 6,278,405 1,046,860 6,278,405 7,325,265
12. Sumur Peresapan Air Kotor 1.00 unit 4,347 1,625,552 4,347 1,625,552 1,629,899
13. Sumur Peresapan Air Hujan 2.00 unit 4,347 1,625,552 8,694 3,251,103 3,259,797
14. Bak Kontrol Lemak (45X45 cm) 1.00 unit 308,770 266,300 308,770 266,300 575,070
5361480.501