REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

Total Luas Lantai = 101,5 m²

HARGA TOTAL HARGA


NO. PEKERJAAN HARGA UPAH
BAHAN (Rupiah)

I. PEKERJAAN PERSIAPAN 6,006,850 10,898,900 16,905,750


II. PEKERJAAN TANAH DAN PASIR 3,485,742 14,737,500 18,223,242
III. PEKERJAAN PONDASI 5,236,072 17,376,642 22,612,714
IV. PEKERJAAN STRUKTUR 14,049,370 38,707,352 52,756,722
V. PEKERJAAN PASANGAN 43,160,137 57,022,408 100,182,544
VI. PEKERJAAN ATAP DAN PLAFOND 18,350,865 50,336,060 68,686,925
VII. PEKERJAAN PINTU DAN JENDELA 4,175,489 34,883,880 39,059,369
VIII. PEKERJAAN LISTRIK 878,430 50,890,000 51,768,430
IX. PEKERJAAN PENGECATAN 1,981,019 6,269,008 8,250,027
X. PEKERJAAN SANITASI DAN PLUMBING 2,464,336 39,473,563 41,937,899
XI. PEKERJAAN LAIN-LAIN 0 27,300,000 27,300,000

TOTAL BIAYA PEMBANGUNAN 99,788,309 347,895,312 447,683,622

BIAYA PEMBANGUNAN (dibulatkan) 447,600,000


BIAYA PENGAWASAN 7 % (dibulatkan) 31,300,000
GRAND TOTAL ANGGARAN BIAYA 478,900,000

Yogyakarta, 30 Desember2017

Perencana
Daftar Kuantitas dan Harga
RENCANA ANGGARAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

Total Luas Lantai = 101,5 m²

HARGA HARGA
TOTAL UPAH TOTAL BAHAN TOTAL HARGA
No URAIAN PEKERJAAN VOL. SAT. SATUAN SATUAN
(RUPIAH) (RUPIAH) (RUPIAH)
UPAH BAHAN

I. PEKERJAAN PERSIAPAN
1. Pengukuran dan pas. bouwplank 48.00 m¹ 17,100 94,050 820,800 4,514,400 5,335,200
2. Pembersihan lahan 181.50 m 2 12,500 0 2,268,750 0 2,268,750
3. Penerangan dan air kerja 1.00 ls 0 1,000,000 0 1,000,000 1,000,000
4. Pekerjaan Pagar Proyek 55.00 m¹ 29,200 71,500 1,606,000 3,932,500 5,538,500
5. Pembuatan Sumur 12.00 m¹ 109,275 121,000 1,311,300 1,452,000 2,763,300

TOTAL PEKERJAAN PERSIAPAN : 6,006,850 10,898,900 16,905,750

II. PEKERJAAN TANAH DAN PASIR


1. Galian tanah pondasi batu belah 35.50 m3 51,750 0 1,837,125 0 1,837,125
2. Urugan tanah kembali pondasi 11.80 m3 17,250 0 203,550 0 203,550
3. Pasir urug bawah pondasi 8.90 m3 20,700 270,000 184,230 2,403,000 2,587,230
4. Urugan pasir bawah lantai 15.23 m 3
20,700 270,000 315,261 4,112,100 4,427,361
5. Urugan Tanah bawah lantai (mendatangkan) 45.68 m 3
20,700 180,000 945,576 8,222,400 9,167,976

TOTAL PEKERJAAN TANAH DAN PASIR : 3,485,742 14,737,500 18,223,242

III. PEKERJAAN PONDASI


1. Pasang Rollag (1PC:4PS) 6.28 m² 9,240 25,862 58,027 162,413 220,441
2. Pasang Pondasi batu belah (1PC:4PS) 31.67 m3 163,500 543,550 5,178,045 17,214,229 22,392,274

TOTAL PEKERJAAN PONDASI : 5,236,072 17,376,642 22,612,714

IV. PEKERJAAN STRUKTUR (1Pc:2Ps:3Kr)


1. Sloof Beton 15/30 4.99 m3 797,610 2,605,043 3,980,074 12,999,165 16,979,238
2. Kolom Praktis Beton 15/15 2.30 m 3
797,610 2,605,043 1,834,503 5,991,599 7,826,102
3. Balok Ring 15/25 5.00 m 3
797,610 2,605,043 3,988,050 13,025,215 17,013,265
4. Atap Dak Beton 12 mm 2.30 m3 1,846,410 2,909,293 4,246,743 6,691,374 10,938,117

TOTAL PEKERJAAN STRUKTUR : 14,049,370 38,707,352 52,756,722

V. PEKERJAAN PASANGAN
1. Pas. Batu bata 1:4 tebal 1/2 bata 253.25 m2 30,800 83,000 7,800,100 21,019,750 28,819,850
2. Pek. Plesteran 506.50 m 2
34,700 11,475 17,575,550 5,812,088 23,387,638
3. Pek. Acian 506.50 m 2
19,060 8,500 9,653,890 4,305,250 13,959,140
4. Pas. Batu bata 1:4 tebal 1/2 bata gunung2 33.30 m 2
30,800 83,000 1,025,640 2,763,900 3,789,540
5. Pasanga Dinding Ekspos 24.00 m2 47,500 151,035 1,140,000 3,624,840 4,764,840
6. Rabat beton lantai 5.02 m 3
104,200 507,112 523,084 2,545,702 3,068,786
7. Pas. Lt.Keramik Km/Wc+Rg.Cuci 20x20 cm 7.00 m2 30,810 105,868 215,670 741,076 956,746
8. Pas. Lantai Keramik 30x30 cm 92.25 m2 30,810 110,868 2,842,223 10,227,573 13,069,796
9. Pas. Lantai Keramik kasar 40x40 cm 24.00 m2 29,735 125,868 713,640 3,020,832 3,734,472
10. Pas. Ddg Toilet Keramik 20x40 m,t=2m 24.60 m 2
67,900 120,382 1,670,340 2,961,397 4,631,737

TOTAL PEKERJAAN PASANGAN : 43,160,137 57,022,408 100,182,544

VI. PEKERJAAN ATAP DAN PLAFOND


1. Pasang Rangka Atap Baja Ringan 117.50 m2 0 165,000 0 19,387,500 19,387,500
2. Pasang Penutup Atap genteng Metal 118.00 m2 51,300 160,720 6,053,400 18,964,960 25,018,360
3. Pasang Genteng Bubungan Metal 13.05 m¹ 51,300 52,000 669,465 678,600 1,348,065
4. Pas. Plafond gypsum board 9 mm dgn 85.00 m 2
136,800 133,000 11,628,000 11,305,000 22,933,000

rangka besi hollow 20x40 mm+list profil

TOTAL PEKERJAAN ATAP DAN PLAFOND : 18,350,865 50,336,060 68,686,925

VII. PEKERJAAN PINTU DAN JENDELA


1. Pas. Kayu Kusen Pintu + Jendela 0.72 m3 565,000 9,942,500 406,800 7,158,600 7,565,400
2. P1, Daun Pintu 1,3x 2,4 m 3.12 m2 129,910 1,080,750 405,319 3,371,940 3,777,259
3. P2, Daun Pintu 0,8x2,15 m 8.60 m 2
129,910 1,080,750 1,117,226 9,294,450 10,411,676
4. P3, Daun Pintu 0,65x2,15 m (km/wc) 2.80 m 2
129,910 1,080,750 363,748 3,026,100 3,389,848
5. P4, Daun Pintu Dobel 0,7x2,15 m (2 daun) 6.02 m 2
129,910 1,080,750 782,058 6,506,115 7,288,173
6. J1, DaunJendela kaca 5 mm (0,77x1,9 m) 5.90 m2 129,910 652,500 766,469 3,849,750 4,616,219

J2, DaunJendela kaca 5 mm (0,75x1,9 m) 1.33 m 2


129,910 652,500 172,780 867,825 1,040,605
7. J2, DaunJendela kaca 5 mm (0,75x1,25 m) 0.94 m 2
129,910 652,500 122,115 613,350 735,465

8. J3, Jendela kaca mati Bv.5 mm (0,3x0,5mx2) 0.30 m 2


129,910 652,500 38,973 195,750 234,723

TOTAL PEKERJAAN KAYU PINTU DAN JENDELA : 4,175,489 34,883,880 39,059,369

VIII. PEKERJAAN LISTRIK


1. Pas. Titik lampu 14.00 ttk 0 150,000 0 2,100,000 2,100,000

2. Pas. Stop Kontak Dinding 7.00 ttk 0 120,000 0 840,000 840,000


3. Pas. Stop Kontak AC 3.00 ttk 0 120,000 0
4. Pas. Saklar tunggal 7.00 ttk 0 120,000 0 840,000 840,000
5. Pas. Saklar seri 3.00 ttk 0 120,000 0 360,000 360,000

6. Lampu Downlight 12.00 bh 0 1,000,000 0 12,000,000 12,000,000

7. Lampu Dinding 2.00 bh 0 500,000 0 1,000,000 1,000,000

8. Box MCB 16 A 1.00 unit 90,000 150,000 90,000 150,000 240,000

9. Rel MCB 10.00 m 1


60,000 100,000 600,000 1,000,000 1,600,000

10. KWH Meter 1.00 unit 60,000 100,000 60,000 100,000 160,000

11. Pasang AC indoor 3.00 bh 21,405 4,750,000 64,215 14,250,000 14,314,215

12. Pasang AC outdoor 3.00 bh 21,405 4,750,000 64,215 14,250,000 14,314,215

13. Biaya Pasang Listrik Baru 1.00 set 0 4,000,000 0 4,000,000 4,000,000

TOTAL PEKERJAAN LISTRIK : 878,430 50,890,000 51,768,430

IX. PEKERJAAN PENGECATAN


1. Pengecatan Dinding 207.50 m2 7,645 28,140 1,586,338 5,839,050 7,425,388
2. Pengecatan Pintu dan jendela 26.75 m2 6,275 7,433 167,856 198,833 366,689
3. Pengecatan Plafond 21.50 m2 10,550 10,750 226,825 231,125 457,950

TOTAL PEKERJAAN PENGECATAN : 1,981,019 6,269,008 8,250,027

X. PEKERJAAN SANITASI DAN PLUMBING


1. Pipa PVC air bersih Æ 3/4 " 19.00 m1 8,280 12,788 157,320 242,963 400,283
2. Pipa PVC air kotor/bekas Æ 3" 14.00 m 1
18,570 37,975 259,980 531,650 791,630
3. Pipa PVC air kotor Æ 4" 12.00 m1 20,405 63,163 244,860 757,950 1,002,810

4. Pek. Kloset duduk 1.00 set 328,200 2,650,000 328,200 2,650,000 2,978,200

5. Shower set 1.00 set 12,650 3,000,100 12,650 3,000,100 3,012,750

6. Kran 5.00 bh 12,100 50,068 60,500 250,340 310,840

7. Pek. Floor drain 1.00 bh 10,750 19,200 10,750 19,200 29,950

8. Tempat Cuci piring 1.00 set 0 2,000,000 0 2,000,000 2,000,000

9. Pek. Pasang water tower 1.00 unit 21,405 8,600,000 21,405 8,600,000 8,621,405

10. Pasang Pompa+Pendorong Air Bersih 1.00 ls 0 10,000,000 0 10,000,000 10,000,000

11. Septic Tank 1.00 unit 1,046,860 6,278,405 1,046,860 6,278,405 7,325,265

12. Sumur Peresapan Air Kotor 1.00 unit 4,347 1,625,552 4,347 1,625,552 1,629,899

13. Sumur Peresapan Air Hujan 2.00 unit 4,347 1,625,552 8,694 3,251,103 3,259,797

14. Bak Kontrol Lemak (45X45 cm) 1.00 unit 308,770 266,300 308,770 266,300 575,070

TOTAL PEKERJAAN SANITASI DAN PLUMBING : 2,464,336 39,473,563 41,937,899

XI. PEKERJAAN LAIN-LAIN


1. Tanam Rumput 51.00 m2 0 50,000 0 2,550,000 2,550,000
2. Pagar Besi (bagian depan, t = 2 m) 33.00 m 2
0 750,000 0 24,750,000 24,750,000

TOTAL PEKERJAAN LAIN-LAIN : 0 27,300,000 27,300,000

GRAND TOTAL : 99,788,309 347,895,312 447,683,622


83.5

5361480.501