REKAPITULASI BIAYA

PROYEK : PEMBANGUNAN RUMAH TINGGAL 2 LANTAI UK. 17X8


LOKASI : KOTA BLITAR
PEMILIK : RAHMAD SANTOSO
TAHUN : 2023

NO ITEM PEKERJAAN JUMLAH HARGA


1 2 3
I. PEKERJAAN PERSIAPAN Rp 17,758,417
II. PEKERJAAN TANAH Rp 19,379,462
III.
PEKERJAAN PASANGAN Rp 194,823,528

IV.
PEKERJAAN BETON Rp 261,094,610

V. PEKERJAAN KUSEN PINTU & JENDELA Rp 184,943,320


VI.
PEKERJAAN ATAP & LANGiT-LANGIT Rp 151,044,248

VII.
PEKERJAAN PENUTUP LANTAI & DINDING Rp 110,518,327

VIII.
PEKERJAAN LISTRIK Rp 37,269,142

IX.
PEKERJAAN SANITASI Rp 70,591,062

X. PEKERJAAN CAT-CATAN Rp 62,207,040


XI.
PEKERJAAN LAIN-LAIN Rp 91,250,000

JUMLAH ANGGARAN RUMAH TEMPAT TINGGAl Rp 1,100,000,000


JUMLAH ANGGARAN TOKO Rp 350,000,000
JUMLAH KESELURUHAN Rp 1,450,000,000
RENCANA ANGGARAN BIAYA

PROYEK : PEMBANGUNAN RUMAH TINGGAL 2 LANTAI UK. 17X8


LOKASI : KOTA BLITAR
PEMILIK : RAHMAD SANTOSO
TAHUN : 2023

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOL. SAT
SATUAN HARGA
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1. Pengawasan 1.00 LS 10,000,000 20,000,000
2. Pembersihan Lokasi Pekerjaan 1.00 LS 2,640,000 2,640,000
3. Pekerjaan Pengukuran / Bowplank 57.00 M1 63,481 3,618,417
Persediaan Air& Listrik selama Proyek
4. 5.00 Bln 300.000 1,500,000
Berlangsung
SUB TOTAL 17,758,417
II. PEKERJAAN TANAH
1. Galian Tanah
a. Footplat 28.00 M3 62,375 1,746,500
b. Pondasi Batu Kali 35.55 M3 62,375 2,217,431
2. Urugan Kembali 15.89 M3 44,750 710,966
3. Urugan Tanah Peninggian Lantai 81.50 M3 121,375 9,892,063
4. Urugan Pasir
a. Footplat 1.40 M3 232,910 326,074
b. Pondasi Batu Kali 2.96 M3 232,910 689,996
c. Bawah Lantai 16.30 M3 232.910 3,796.433
SUB TOTAL 19,379,462
III. PEKERJAAN PASANGAN
1. Pas. Anstampeng 11.85 M3 525,795 6,230,671
2. Pas. Pondasi Batu Kali 1:5 26.66 M3 841,275 22,430,495
3. Pas. Bata Ringan
a. Lantai 1 224.61 M2 120,823 27,138,272
b. Lantai 2 301.62 M2 120,823 36,442,822
1,052.4
4. Plesteran Dinding M2 54,597 57,462,126
7
1,052.4
5. Acian Dinding M2 33,560 35,320,893
7
6. Benangan
a. Sudut Dinding 208.00 M1 17,497 3,639,350
b. Tali Air 352.00 M1 17,497 6,158,900
SUB TOTAL 194,823,528
IV. PEKERJAAN BETON
1. Membuat Beton K-225
a. Footplat 80x80x20 3.58 M3 1,048,403 3,757,475
b. Kolom Pedestal 20x20 1.34 M3 1,048,403 1,409,053
c. Sloof 20/30 5.93 M3 1,048,403 6,211,785
d. Kolom Struktur 10x30 5.80 M3 1,048,403 6,076,541
e. Kolom Praktis 0.47 M3 1,048,403 489,604
f. KolomTeras 3.24 M3 1,048,403 3,396,824
g. Balok 15/30 4.44 M3 1,048,403 4,658,839
h. Dak Lantai T=12 cm 13.56 M3 1,048,403 14,216,338
i. Listplang Beton L=70cm 4.59 M3 1,048,403 4,814.264
j. Listplang Beton L=60cm 3.22 M3 1,048,403 3,371,662
k. Kanopi beton 1.50 M3 1,048,403 1,572,604
l. Tangga Beton 1.73 M3 1,048,403 1,816,357
2. Pembesian
a. Footplat 80x80x20 466.75 Kg 14,834 6,923,770
b. Kolom Pedestal 20x20 201.60 Kg 14,834 2,990,534
c. Sloof 20/30 888.75 Kg 14,834 13,183,718
d. Kolom Struktur 10x30 869.40 Kg 14,834 12,896,680
e. Kolom Praktis 93.40 Kg 14,834 1,385,496
f. Kolom Teras 486.00 Kg 14,834 7,209,324
g. Balok 15/30 666.56 Kg 14,834 9,887,788
1,627.2
h. Dak Lantai T=12 cm Kg 14,834 24,137,885
0
i. Listplang Beton L=70cm 459.20 Kg 14,834 6,811,773
j. Listplang Beton L=60cm 321.60 Kg 14,834 4,770,614
k. Kanopi beton 150.00 Kg 14,834 2,225,100
l. Tangga Beton 259.88 Kg 14,834 3,854,986
3. Membuat Begisting
a. Footplat 80x80x20 17.92 M2 115,685 2,073,075
b. Kolom Pedestal 20x20 24.96 M2 145,736 3,637,577
c. Sloof 20/30 59.25 M2 125,214 7,418,915
d. Kolom Struktur 10x30 115.80 M2 145,736 16,876,258
e. Kolom Praktis 14.10 M2 145,736 2,054,881
f. Kolom Teras 43.20 M2 145,736 6,295,806
g. Balok 15/30 74.06 M2 197,736 14,644,823
h. Dak Lantai T=12 cm 113.00 M2 216,219 24,432,719
i. Listplang Beton L=70cm 52.48 M2 197,736 10.377.1B5
j. Listplang Beton L=60cm 37.52 M2 197,736 7,419,055
k. Kanopi beton 18.90 M2 197,736 3,737,210
l. Tangga Beton 10.40 M2 216,219 2,248,675
4. Membuat Beton Lantai Kerja 1:3:5
a. Lantai Kerja Footplat 1.79 M3 824,565 1,477,620
b. Rabat Lantai 12.53 M3 824,565 10,331,799
SUB TOTAL 261,094,610
V. PEKERJAAN KUSEN PINTU & JENDELA
1. Pas. Kusen pintu dan jendela kayu balau 1.82 M3 36,840,650 66,972,618
2. Pas. Daun pintu kayu 16.00 Bh 3,316,750 53,068,000
3. Pas. Daun jendela kayu 29.00 Bh 1,222,770 35,460,330
4. Pas. Daun bovenlis kayu 6.00 Bh 611,385 3,668,310
5. Pas. Kunci selot ex ses (setara) 16.00 Bh 306,895 4,910,320
6. Pas. Handle Píntu Kupu Tarung 10.00 Bh 570,285 5,702,850
7. Pas. Handle Pintu Kamar Tidur 6.00 Bh 285,143 1,710,855
8. Pas. Grendel tanam 6.00 Bh 52,948 317,685
9. Pas. Engsel pintu 16.00 Set 55,452 887,232
10. Pas. Engsel jendela 29.00 Bh 29,348 851,078
11. Pas. Hak angin ex ses (setara) 29.00 Bh 47,648 1,381,778
12. Pas. Grendel jendela ex ses (setara) 29.00 Bh 35,648 1,033,778
13. Pas. Kaca bening tebal 5 mm 26.35 M2 135,806 3,578,488
Uni
14. Pas. Kusen & Daun Pintu Kamar Mandi 4.00 1,350,000 5,400,000
t
SUB TOTAL 184,943,320
VI. PEKERJAAN ATAP & LANGIT-LANGIT
1. Rangka Atap Galvalum C.075 Ex. Kencana 227.50 M2 215,000 48,912,500
2. Pas. Genteng Flat Keramik Ex. M-Class 227.50 M2 246,085 55,984,338
3. Pas. Bubungan 49.00 M2 172,090 8,432,410
4. Pas. Listplang Kalsiplank 57.00 M1 120,000 6,840,000
5. Pas. Plafond Gypsum Rangka Hollow 139.00 M2 185,000 25,715,000
6. Pas. Plafond Kalsiboard Teritis 43.00 M2 120,000 5,160,000
SUB TOTAL 151,044.248
VII. PEKERJAAN PENUTUP LANTAl & DINDING
1 Kramik Granit Lantai 60x60 244.00 M2 284,920 69,520,480
Keramik Lantai Kamar Mandi & R. Loundry
2 27.00 M2 217,448 5,871,096
30x30
3 Keramik Carport 50x50 30.00 M2 217,448 6.523,440
4 Keramik Dinding Kamar Mandi 30x60 50.00 M2 233,581 11,679,063
5 Granit Dinding 60x120 30.00 M2 427,380 12,821,400
6 KeramikTangga 12.00 M2 341,904 4,102,848
SUB TOTAL 110,516,327
VIII.
PEKERJAAN LISTRIK

Uni
1. Instalasi Meteran Kwh 1300Watt 1.00 2,200,000 2,200,000
t
Uni
2. Instalasi Mcb 2 Group 1.00 350,000 350,000
t
3. Pas. Instalasi lampu 50.00 Ttk 171,000 8,550,000
4. Pas. Instalasi stop kontak 17.00 Ttk 171,000 2,907,000
5. Pas. Stop kontak 17.00 Bh 25,000 425,000
6. Pas. Saklar ganda 13.00 Bh 25,194 327,522
7. Pas. Saklar tunggal 6.00 Bh 15,618 93,708
8. Pas. Lampu led 10 watt 16.00 Bh 85,500 1,368,000
9. Pas. Lampu led 5 watt 34.00 Bh 39,900 1,356,600
10. Pas. Lampu spot LED 5 w 4.00 Bh 193,800 775,200
11. Pas. Lampu Gantung Teras 2.00 Bh 3,500,000 7,000,000
12. Pas. Lampu Gantung Void 2.00 Bh 5,000,000 10,000,000
13. Pas. Blower Kamar Mandi 4.00 Bh 479,028 1,916,112
SUB TOTAL 37,269,142
IX. PEKERJAAN SANITASI
1. Pas. Pipa 1/2" 12.00 M1 14,525 174,300
2. Pas. Pipa T' 34.00 M1 26,180 890,120
3. Pas. Pipa 3" (air kotor dan hujan) 64.00 M1 74,280 4,753,920
4. Pas. Pipa 4" 32.00 M1 101,095 3,235,040
Uni
5. Pas. Wastafel lengkap 2.00 712,215 1,424,430
t
6. Pas. Kran air 10.00 Bh 69,433 694,328
Uni
7. Pas. Kloset Duduk Monoblok Ex.TOTO 3.00 3,348,592 10,045,776
t
Uni
8. Pas. Kloset Jongkok Ex.lna 1.00 432,875 432,875
t
9. Pas. Hand Shower 2.00 Bh 350,000 700,000
10. Pas. Shower Tiang Km Utama 1.00 Bh 3,500,000 3,500,000
11. Pas. Floordrain 5.00 Bh 75,000 375,000
12. Pas. TempatSabun 4.00 Bh 200,000 800,000
Uni
13. Pas. Zink Bak Cuci Piring + Aksesoris 2.00 858,925 1,717,850
t
14. Pek. Septitank 1x2.5x1.5m
a. GalianTanah 3.75 M3 62,375 233,906
b. Cor Dasar Septictank 0.25 M3 4,500,000 1,125,000
c. Pas. Bata Merah 13.50 M2 120,823 1,631,105
d. Plesteran dan Aaan 16.00 M2 88,157 1,410,518
e. Cor Tutup Septictank 0.25 M3 4,500,000 1,125,000
15. Pek. Peresapan
a. GalianTanah 2.36 M3 62,375 146,893
b. Pas. Buis Beton 100cm 5.00 Bh 150,000 750,000
c. Pas, Media Resapan 1.00 Ls 1,000,000 1,000,000
d. Pas. Tutup Resapan L00 Bh 150,000 150,000
16. Tandon Air 1000L Stainlees steel 2.00 Bh 3,500,000 7,000,000
17. Sumur Bor Kedalaman 16m Pipa 4" Maspion 1.00 Ls 4,000,000 4,000,000
Uni
18. Wasser Submersible Deep Well / 1.00 2,650,000 2,650,000
t
Pompa Satelit 3 lnchSD-P307K-2
Uni
19. Water Heater Ariston Slim2 30RS 30 Liter 3 00 4 750,000 14 250 000
t
a. Aksesoris Pipa,Knee dll 3.00 Set 1,187,500 3,562,500
Uni
20. Pompa Pendorong Shimitzu PLW-200 Bit 1.00 2,250,000 2,250,000
t
a. Aksesoris Pipa.Knee dll 1.00 Set 562,500 562,500
SUB TOTAL 70,591,062
X. PEKERJAAN CAT-CATAN
1,052.4
1. Cat Dinding M2 30,202 31,786,699
7
2. Cat Plafond 182.00 M2 20,433 3,713,300
3. Cat Kusen Kayu 185.50 M1 40,170 7,451,535
4. Cat Ducco Pintu 16.00 Bh 750,000 12,000,000
5. Cat Ducco Jendela 29.00 Bh 250,000 7,250,000
SUB TOTAL 62,207,040
XI. PEKERJAAN LAIN-LAIN
1. Ralllng Balkon Besi Fln.Cat 11.00 M1 1,000,000 11,000,000
Railing Tangga dan Void Staínless + Kaca
2. 21.00 M1 2,750,000 57,750,000
Tempered
3. Atap Akrilik Carport 600 M2 1,500,000 9,000,000
4. Atap Akrlllk Loundry 9.00 M2 1,500,000 13,500,000
SUB TOTAL 91,250,000

JUMLAH ANGGARAN RUMAH TEMPAT


A. TINGGAL 1,100,000.000
B. JUMLAH ANGGARAN TOKO 350,000.000
C. JUMLAH KESELURUHAN TOTAL ANGGARAN 1,450,000,000