RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN RUMAH TIPE 32


BINTANG PRATAMA REGENCY
LOKASI : WONOSARI KABUPATEN GUNUNG KIDUL
TAHUN : 2019

NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH


I PEKERJAAN PERSIAPAN
1 Uitzet dan Pas. Bowplang 1.000 ls 448,000 448,000
3 Pembersihan/Perapihan 1.000 ls 500,000 500,000
JUMLAH I 948,000

II PEKERJAAN TANAH
1 Galian Tanah 10.425 m3 55,786 581,569
2 Urugan peninggian peil lantai 3.003 m3 192,390 577,747
3 Pasir urug bawah lantai 0.901 m 3
192,390 173,343
JUMLAH II 1,332,660

III PEKERJAAN PASANGAN DAN BETON


1 Pas. Pondasi 7.819 m3 495,590 3,875,018
2 Sloof 12/15 0.537 m3 5,632,549 3,024,679
3 Plat t=10cm (atas teras dan KM/WC) 0.585 m 3
2,892,900 1,692,347
4 Plat t=10cm (atas jendela) 0.220 m3 2,892,900 636,438
5 Balok Ring 12/15 0.615 m3 6,838,105 4,205,435
6 Kolom Praktis 55.400 m' 0
7 Balok Latai 6.000 m' 0
8 Pas. Hebel 139.275 m2 107,600 14,985,990
9 Rabat beton bawah lantai 0.901 m 3
633,199 570,512
10 Pasang lantai keramik 40x40 polos 27.593 m 2
134,389 3,708,196
11 Pasang lantai keramik 40x40 tekstur 2.438 m2 143,952 350,955
12 Pasang dinding keramik 20x40 6.720 m2 152,357 1,023,839
13 Sponengan 112.150 m 2
11,924 1,337,277
14 Plesteran 1:8 263.150 m 2
33,759 8,883,576
15 Acian 263.150 m2 24,865 6,543,225
JUMLAH III 50,837,485

IV PEKERJAAN ATAP DAN PLAFON


1 Rangka atap baja ringan + penutup atap metal 41.273 m2 194,346 8,021,254
2 Pasang Kalsiplank 32.400 m' 75,250 2,438,100
3 Plafon Gypsum rangka Hollow 30.030 m2 115,063 3,455,342
4 List Plafon 28.100 m' 19,438 546,208
JUMLAH IV 14,460,904

V PEKERJAAN PINTU JENDELA


1 Kusen Alumunium 35.320 m' 173,686 6,134,590
2 Daun Pintu Multipleks + Asesoris 6.510 m 2
1,138,579 7,412,152
3 Daun Jendela Multipleks + Asesoris 2.380 m2 666,087 1,585,288
4 Kaca 5 mm 2.710 m 2
152,990 414,603
JUMLAH V 15,546,633

VI PEKERJAAN INSTALASI LISTRIK


1 Titik Lampu dan Stop Kontak 8.000 ttk 180,000 1,440,000
2 Stop Kontak Ex. Broco 3.000 bh 50,000 150,000
3 Saklar Ex. Broco 4.000 bh 45,000 180,000
4 Lampu LED 4W 2.000 bh 48,083 96,166
5 Lampu LED 7W 3.000 bh 65,683 197,050
JUMLAH VI 623,216
VII PEKERJAAN AIR DAN PERPIPAAN
1 Kloset Jongkok 1.000 bh 748,660 748,660
2 Floor Drain 1.000 bh 47,437 47,437
3 Kran air 2.000 bh 64,806 129,612
4 Pipa PVC 1/2" dr pipa distribusi 16.000 m' 22,581 361,296
5 Pipa PVC 2" dr floor drain/cucian 8.000 m' 49,670 397,360
6 Pipa PVC 3" dr kloset 4.000 m' 57,130 228,520
7 Septictank dan peresapan 1.000 un 5,000,000 5,000,000
JUMLAH VII 6,912,885

VIII PEKERJAAN CAT DAN FINISHING


1 Cat tembok dan plafon 293.180 m2 15,071 4,418,516
2 Cat kayu 21.120 m 2
37,455 791,050
JUMLAH VIII 5,209,565

JUMLAH I - VIII 95,871,348


DIBULATKAN