RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : RENOVASI RUMAH TANGGA


LOKASI : JL. BUKIT WATUWILA III D IX/10

HARGA JUMLAH
NO JENIS PEKERJAAN VOL/SAT
SATUAN HARGA (Rp)
1 Pekerjaan bongkar upah tenaga bongkaran 1 unit 10,000,000

II PEKERJAAN ATAP
1 Pasang rangka atap baja ringan 98.65 M2 185,000 18,250,250
2 Pasang alumunium voil 98.65 M2 35,000 3,452,750
3 Pasang genteng + cat genteng 98.65 M 2
90,000 8,878,500
4 Pasang kardus + ban banan 28 M 145,000 4,060,000
5 Ganti Genteng 49.32 M 2
120,000 5,918,400
6 Pasang atap teras 30 M2 250,000 7,500,000
Jumlah 48,059,900
III PEKERJAAN PASANGAN, PLESTERAN, BETON
1 Pasangan Batu 114.25 M2 120,000 13,710,000
2 Plesteran + Acian 228.50 M2 75,000 17,137,500
3 Pek. Cor beton bertulang (slot, kolom, ring ball, talang) 2.86 M 3
4,500,000 12,870,000
4 Pasang lantai keramik 30x30 83.75 M2 235,000 19,681,250
Jumlah 63,398,750
IV PEKERJAAN LISTRIK
1 Pasang instalasi listrik komplit 8,500,000

V PEKERJAAN PLAFON + CAT


1 Pek. Plafon + Lis 110.25 M2 190,000 20,947,500
2 Pek. Cat tembok 478.37 M 2
55,000 26,310,350
3 Pek. Melamin pintu jendela 20.40 M2 180,000 3,672,000
4 Pek. Cat melamin kusen 17.40 M 120,000 2,088,000
5 Pek. Cat pintu 12.80 M2 70,000 896,000
6 Pek. Cat kusen 37.15 M 50,000 1,857,500
7 Pek. Lesplang 17.15 M 90,000 1,543,500
Jumlah 57,314,850
VI PEKERJAAN KAYU
1 Pek. Pintu + daun jendela 14.55 M2 950,000 13,822,500
2 Pek. Kusen 6/5 16.50 M2 300,000 4,950,000
3 Loster kayu 12 biji 15,000 180,000
Jumlah 18,952,500
VII PEKERJAAN LAIN-LAIN
1 Tutup bak tandon 1 unit 450,000
2 Pembersihan dan lain-lain 13,000,000
Jumlah 13,450,000