Rencanana Anggaran Biaya

RUMAH TIPE 40/72 PERUMAHAN CITRA KEDATON UJUNG BERUNG BANDUNG

Harga Satuan Jumlah Harga


No Jenis Pekerjaan Satuan Volume
(Rp) (Rp)

I
A PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi m2 72.000 25,648.60 1,846,699.20
2 Pengukuran dan pasangan bouwplank m2 18.000 103,586.05 1,864,548.90
B PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1m m3 21.600 125,969.50 2,720,941.20
2 Urugan Tanah Kembali m3 4.800 20,091.17 96,437.63
3 Buangan Tanah Galian m3 16.800 39,915.20 670,575.36
C PEKERJAAN PASANGAN PONDASI
1 Batu kosongan Aanstampeng m3 4.800 594,660.18 2,854,368.86
2 Urugan Pasir m3 2.400 267,110.80 641,065.92
3 Pondasi Batu kali1:5 m3 9.600 1,062,337.70 10,198,441.92
4 Beton Lantai Kerja 1:3:5 m3 0.247 867,089.78 213,954.40
5 Urugan Pasir m3 0.494 267,110.80 131,819.18
6 Urugan Tasirtu m3 0.567 293,774.10 166,569.91
7 Pasangan Pondasi rollag batu bata 1:3 m3 0.08601 260,423.01 22,398.98
D PEKERJAAN BETON
1 Beton Sloof S-4 15/20 m3 1.200 8,449,127.25 10,138,952.70
2 Beton Kolom praktis 15/15 m3 0.936 8,808,654.44 8,244,900.56
3 Beton Balok Latai dan ring balk 15/20 m3 1.200 7,137,629.51 8,565,155.41
4 Beton lisplank t= 15 cm m3 5.387 1,585,548.14 8,540,555.07
E PEKERJAAN PASANGAN DINDING TEMBOK
1 Pasang Dinding Bata Ringan m2 143.658 126,745.63 18,207,990.48
2 Pasang Dinding Batu Palimanan m2 10.050 178,043.40 1,789,336.17
F PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN
1 Plesteran Tebal 15mm Campuran 1 : 3 m2 287.315 83,905.65 24,107,391.10
2 Acian Beton m2 287.315 52,160.70 14,986,575.94
G PEKERJAAN PELAPIS LANTAI DAN DINDING
1 Urugan Pasir m3 4.826 267110.8 1,289,023.36
2 Pemasangan Tegel Keramik Dinding 20x25cm m2 5.916 351,468.00 2,079,284.71
3 Pemasangan Keramik Lantai 20x20 cm m2 1.690 301,473.27 509,489.83
4 Pemasangan Lantai Keramik 40x40cm Polished m2 31.713 309,911.70 9,828,304.29
5 Pekerjaan Floor Hardener m2 18.229 63,387.92 1,155,498.58
H PEKERJAAN PLAFOND
1 Pas. Plafond Gypsumboard 9 mm Rangka Hollow m2 38.850 315,049.20 12,239,661.57
2 Pemasangan List Gypsum m1 56.800 33,584.40 1,907,593.92
I PEKERJAAN CAT
1 Pengerjaan Cat Dinding Interior m2 233.457 52,666.34 12,295,304.26
2 Pengerjaan Cat Plafond m2 49.650 47,506.82 2,358,713.51
3 Pengerjaan Cat besi m2 14.264 42,602.89 607,692.80
4 Pengerjaan Cat Kayu M2 22.562 43,712.89 986,229.91
J Pekerjaan Kusen Pintu dan Jendela
1 Pintu aluminium Type P9 unit 2.000 2,485,147.91 4,970,295.81
2 Pintu aluminium Type P9 kayu unit 3.000 2,541,468.02 7,624,404.05
3 Jendela aluminium Type J5 unit 4.000 1,992,189.75 7,968,758.98
4 pintu pvc m2 1.575 680,951.30 1,072,498.30
K PEKERJAAN SANITASI
1 Pipa Ø 15 mm / 1/2" m1 5.400 94,479.25 510,187.95
2 Pipa 3/4" m1 18.000 96,885.50 1,743,939.00
3 Pipa.Ø 25 mm / 1" m1 1.300 96,510.50 125,463.65
4 Pipa Ø 100 mm / 4” (PVC "AW" ) m1 5.730 192,185.50 1,101,222.92
5 pipa Ø 50 mm / 2” (PVC "AW" ) m1 13.750 109,835.50 1,510,238.13
6 Clean Out Ø 100 M 0.500 103,116.06 51,558.03
7 Memasang 1 buah Kloset duduk ls 1.000 2,217,626.80 2,217,626.80
8 kran unit 5.000 146,080.00 730,400.00
9 Floor drain Ø 50 ls 1.000 218,800.00 218,800.00
10 pompa 230 watt ls 1.000 938,428.00 938,428.00
11 KITCHEN SINK STAINLESS unit 1.000 816,272.58 816,272.58
12 bak kamar mandi 0,24 M3 unit 1.000 1,027,553.30 1,027,553.30
L PEKERJAAN ELECTRICAL
1 Lampu Down Light 15 Watt bh 6.000 98,240.00 589,440.00
2 Lampu SL 11 WATT bh 1.000 36,560.00 36,560.00
3 Saklar Ganda bh 2.000 65,060.00 130,120.00
4 Stop Kontak 1 Phase, 200 VA bh 4.000 19,560.00 78,240.00
5 Inst. Penerangan, NYM 3x2,5 mm² (o) PVC HI dia. 20mm m 23.400 38,001.11 889,226.00
6 Inst. Stop kontak, NYM 3x2,5 mm² (o) PVC HI dia. 20mm m 20.950 357,829.67 7,496,531.52
7 Saklar Tunggal bh 3.000 32,500.00 97,500.00
8 MCB 1 Phase 10 A/4,5 KA bh 1.000 129,160.00 129,160.00
9 Fiting lampu E 27 bh 1.000 23,560.00 23,560.00
10 Grounding ttk 1.000 2,006,560.00 2,006,560.00
M PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
1 Pemasangan Genteng beton m2 47.010 110,221.30 5,181,503.31
2 PEKERJAAN KONSTRUKSI BAJA RINGAN m2 47.010 144,526.14 6,794,173.94
3 talang air hujan m 10.400 101,338.18 1,053,917.03
4 pipa Ø 50 mm / 2” (PVC "AW" ) m 7.000 109,835.50 768,848.50
N SEPTIC TANK
1 Beton Lantai Kerja 1:3:5 m3 0.068 867,089.78 58,962.10
2 Urugan Pasir m3 0.068 267,110.80 18,163.53
3 Beton K-225 m3 1.760 1,121,687.99 1,974,045.68
4 pipa dia 50 mm m 0.700 109,835.50 76,884.85
5 lapis ijuk m 6.000 51,325.20 307,951.20
6 pasir+split m3 0.793 301,540.80 239,166.70
7 split+pecahan batu m3 0.441 273,270.80 120,389.45
8 batu belah m3 0.430 376,574.00 162,018.64
9 Pasang Dinding Bata 1:5 1/2 Bata m2 4.388 528,382.10 2,318,276.46
JUMLAH
Overhead & Profit 15% x A
dibulatkan
RUNG BANDUNG

Total Harga (Rp)

3,711,248.10

3,487,954.19

14,228,619.18

35,489,563.74

19,997,326.65

39,093,967.04

14,861,600.77

14,147,255.49

16,247,940.48

21,635,957.13

10,991,690.35
11,476,897.52

13,798,442.78

5,275,858.62

224,444,322.04
258,110,970.35
258,110,000.00
Rencanana Anggaran Biaya
RUMAH TIPE 40/72 PERUMAHAN CITRA KEDATON UJUNG BERUNG BANDUNG

Harga Satuan
No Jenis Pekerjaan Satuan Volume
(Rp)

I
A PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi m2 72.000 25,648.60
2 Pengukuran dan pasangan bouwplank m2 18.000 103,586.05
B PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1m m3 8.083 125,969.50
2 Urugan Tanah Kembali m3 4.668 20,091.17
3 Buangan Tanah Galian m3 3.416 39,915.20
C PEKERJAAN PASANGAN PONDASI
1 Beton Lantai Kerja 1:3:5 m3 0.270 867,089.78
2 Urugan Pasir m3 0.539 267,110.80
3 Beton Pondasi Tapak m3 1.214 1,710,273.75
4 Beton Lantai Kerja 1:3:5 m3 0.247 867,089.78
5 Urugan Pasir m3 0.494 267,110.80
6 Urugan Tasirtu m3 0.567 293,774.10
7 Pasangan Pondasi rollag batu bata 1:3 m3 0.08601 260,423.01
D PEKERJAAN BETON
1 Beton Sloof S-4 15/20 m3 1.200 8,449,127.25
2 Beton Kolom praktis 15/15 m3 0.936 8,808,654.44
3 Beton Balok Latai dan ring balk 15/20 m3 1.200 7,137,629.51
4 Beton lisplank t= 15 cm m3 5.387 1,585,548.14
E PEKERJAAN PASANGAN DINDING TEMBOK
1 Pasang Dinding Bata Ringan m2 143.658 126,745.63
2 Pasang Dinding Batu Palimanan m2 10.050 178,043.40
F PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN
1 Plesteran Tebal 15mm Campuran 1 : 3 m2 287.315 83,905.65
2 Acian Beton m2 287.315 52,160.70
G PEKERJAAN PELAPIS LANTAI DAN DINDING
1 Urugan Pasir m3 4.826 267110.8
2 Pemasangan Tegel Keramik Dinding 20x25cm m2 5.916 351,468.00
3 Pemasangan Keramik Lantai 20x20 cm m2 1.690 301,473.27
4 Pemasangan Lantai Keramik 40x40cm Polished m2 31.713 309,911.70
5 Pekerjaan Floor Hardener m2 18.229 63,387.92
H PEKERJAAN PLAFOND
1 Pas. Plafond Gypsumboard 9 mm Rangka Hollow m2 38.850 315,049.20
2 Pemasangan List Gypsum m1 56.800 33,584.40
I PEKERJAAN CAT
1 Pengerjaan Cat Dinding Interior m2 233.457 52,666.34
2 Pengerjaan Cat Plafond m2 49.650 47,506.82
3 Pengerjaan Cat besi m2 14.264 42,602.89
4 Pengerjaan Cat Kayu M2 22.562 43,712.89
J Pekerjaan Kusen Pintu dan Jendela
1 Pintu aluminium Type P9 unit 2.000 2,485,147.91
2 Pintu aluminium Type P9 kayu unit 3.000 2,541,468.02
3 Jendela aluminium Type J5 unit 4.000 1,992,189.75
4 pintu pvc m2 1.575 680,951.30
K PEKERJAAN SANITASI
1 Pipa Ø 15 mm / 1/2" m1 5.400 94,479.25
2 Pipa 3/4" m1 18.000 96,885.50
3 Pipa.Ø 25 mm / 1" m1 1.300 96,510.50
4 Pipa Ø 100 mm / 4” (PVC "AW" ) m1 5.730 192,185.50
5 pipa Ø 50 mm / 2” (PVC "AW" ) m1 13.750 109,835.50
6 Clean Out Ø 100 M 0.500 103,116.06
7 Memasang 1 buah Kloset duduk ls 1.000 2,217,626.80
8 kran unit 5.000 146,080.00
9 Floor drain Ø 50 ls 1.000 218,800.00
10 pompa 230 watt ls 1.000 938,428.00
11 KITCHEN SINK STAINLESS unit 1.000 816,272.58
12 bak kamar mandi 0,24 M3 unit 1.000 1,027,553.30
L PEKERJAAN ELECTRICAL
1 Lampu Down Light 15 Watt bh 6.000 98,240.00
2 Lampu SL 11 WATT bh 1.000 36,560.00
3 Saklar Ganda bh 2.000 65,060.00
4 Stop Kontak 1 Phase, 200 VA bh 4.000 19,560.00
5 Inst. Penerangan, NYM 3x2,5 mm² (o) PVC HI dia. 20mm m 23.400 38,001.11
6 Inst. Stop kontak, NYM 3x2,5 mm² (o) PVC HI dia. 20mm m 20.950 357,829.67
7 Saklar Tunggal bh 3.000 32,500.00
8 MCB 1 Phase 10 A/4,5 KA bh 1.000 129,160.00
9 Fiting lampu E 27 bh 1.000 23,560.00
10 Grounding ttk 1.000 2,006,560.00
M PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
1 Pemasangan Genteng beton m2 47.010 110,221.30
2 PEKERJAAN KONSTRUKSI BAJA RINGAN m2 47.010 144,526.14
3 talang air hujan m 10.400 101,338.18
4 pipa Ø 50 mm / 2” (PVC "AW" ) m 7.000 109,835.50
N SEPTIC TANK
1 Beton Lantai Kerja 1:3:5 m3 0.068 867,089.78
2 Urugan Pasir m3 0.068 267,110.80
3 Beton K-225 m3 1.760 1,121,687.99
4 pipa dia 50 mm m 0.700 109,835.50
5 lapis ijuk m 6.000 51,325.20
6 pasir+split m3 0.793 301,540.80
7 split+pecahan batu m3 0.441 273,270.80
8 batu belah m3 0.430 376,574.00
9 Pasang Dinding Bata 1:5 1/2 Bata m2 4.388 528,382.10
JUMLAH
Overhead & Profit 15% x A
dibulatkan
garan Biaya
KEDATON UJUNG BERUNG BANDUNG

Jumlah Harga (Rp) Total Harga (Rp)

3,711,248.10
1,846,699.20
1,864,548.90
1,248,387.09
1,018,265.01
93,776.35
136,345.73
2,988,882.01
233,680.69
143,972.72
2,076,486.12
213,954.40
131,819.18
166,569.91
22,398.98
35,489,563.74
10,138,952.70
8,244,900.56
8,565,155.41
8,540,555.07
19,997,326.65
18,207,990.48
1,789,336.17
39,093,967.04
24,107,391.10
14,986,575.94
14,861,600.77
1,289,023.36
2,079,284.71
509,489.83
9,828,304.29
1,155,498.58
14,147,255.49
12,239,661.57
1,907,593.92
16,247,940.48
12,295,304.26
2,358,713.51
607,692.80
986,229.91
21,635,957.13
4,970,295.81
7,624,404.05
7,968,758.98
1,072,498.30
10,991,690.35
510,187.95
1,743,939.00
125,463.65
1,101,222.92
1,510,238.13
51,558.03
2,217,626.80
730,400.00
218,800.00
938,428.00
816,272.58
1,027,553.30
11,476,897.52
589,440.00
36,560.00
130,120.00
78,240.00
889,226.00
7,496,531.52
97,500.00
129,160.00
23,560.00
2,006,560.00
13,798,442.78
5,181,503.31
6,794,173.94
1,053,917.03
768,848.50
5,275,858.62
58,962.10
18,163.53
1,974,045.68
76,884.85
307,951.20
239,166.70
120,389.45
162,018.64
2,318,276.46
210,965,017.78
Rp 242,609,770.44
Rp 242,609,000.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH
Update Periode 2019 - 2020 Region 1
Region 2
Region 3
Region 4
###
Kode Region I ###
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan Sumber/Referensi
1 2 3 4 KEPUTUSAN WALI KOTA BANDUNG 5 NOMOR : 027/Kep.
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
A. BAHAN MENGGUNAKAN BESI/LOGAM TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
1 Besi Beton ulir BJTD-40 Rp. 11,400.00 per Kg 2020
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
2 Besi Beton polos BJTP-24 Rp. 11,200.00 per Kg 2021
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
3 reng r33-0.45 Rp. 5,816.67 per m1 2022
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
4 self drilling screw dia 6x20 mm Rp. 5,000.00 per bh 2023
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
5 self drilling screw dia 4x16 mm Rp. 5,000.00 per bh 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
6 dynabolt dia 12-120 mm Rp. 7,400.00 per bh 2025
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
7 c.100.75 Rp. 14,600.00 per m1 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
8 Besi Hollow 20.20.2 MM Rp. 15,000.00 per m1 2027
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
9 Besi Hollow 20.40.2 MM Rp. 8,150.00 per m1 2028
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
10 Besi Hollow 40.40,2,3 MM Rp. 10,766.67 per m1 2029
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
11 Elektrode Baja Rp. 34,100.00 per Kg 2030
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
12 Kawat Bendrat Rp. 20,790.00 per Kg 2031
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
13 seng plat 31,600.00 per m1 2032
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
14 besi strip 14,133.02 per kg KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2033
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
B. BAHAN MENGGUNAKAN BATU, PASIR, PC TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
1 Pasir Beton Rp. 327750 per m3 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
2 Pasir Pasang Rp. 242000 per m3 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
3 Pasir Urug Rp. 181500 per m3 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
4 Air Tawar Rp. 50 per lt 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
5 Semen Portland (1 zak = 50 Kg) Rp. 71610 per zak 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG STANDARISASI
WALI KOTA BANDUNG NOMOR : 027/Kep.
6 Semen Portland (1 zak = 50 Kg) Rp. 1700 per Kg 2024
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
7 Semen Portland (1 zak = 40 Kg) Rp. 57288 per zak 2024
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI HARGA
8 Tasirtu Rp. 206500 per m3 2024
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
ED/Sf
KEPUTUSAN WALI KOTA BANDUNG NOMORSATUAN
38 TAHUN XXV 2019 JURNAL HARGA : 027/Kep.
9 Batu bata merah Rp. 2300 per bh 2024
BAHAN BANGUNAN, KONSTRUKSI & INTERIOR KAB
806-BPKA/2019
KEPUTUSAN TENTANG STANDARISASI HARGA
WALI KOTA BANDUNG NOMOR : 027/Kep.
10 Bata Ringan t 10 cm Rp. 6,400.00 per bh BANDUNG
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG STANDARISASI HARGA
WALI KOTA BANDUNG NOMOR : 027/Kep.
11 Batu kali belah 15/20 Rp. 281,012.00 per m3 2041
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
12 Batu pecah mesin 1/2 Rp. 190,600.00 per m3 2042
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG STANDARISASI
WALI KOTA BANDUNG NOMOR : 027/Kep.
13 Batu pecah mesin 2/3 Rp. 183,600.00 per m3 2043
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
14 Batu susun Palimanan Rp. 100,900.00 per m2 2044
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG STANDARISASI
WALI KOTA BANDUNG NOMOR : 027/Kep.
15 Split 2/3 Pecah Mesin Rp. 183,600.00 per m3 2045
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
16 Semen Berwaran Yiyitan Rp. 20,000.00 per Kg 2046
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
17 Ijuk Rp. 11,410.00 per Kg 2047
C BAHAN CAT/MINYAK/KUAS KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
https://www.tokopedia.com/buanaartagraha/cat-besi-
: 027/Kep.
1 Cat Besi Rp. 59,500.00 per Kg TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN dan-kayu-avian-1-kg?src=topads
TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
2 Cat Kayu Rp. 70,600.00 per Kg 2046
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
3 Cat Tembok Interior Rp. 56,976.00 per Kg 2048
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
4 Cat Tembok Exterior Rp. 42,644.00 per Kg 2049
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
5 Kuas Cat 4" Rp. 10,000.00 per Bh 2051
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
6 Minyak Cat (Thiner A) Rp. 28,875.00 per ltr 2053
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
7 Minyak begesting Rp. 2,800.00 per ltr 2054
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
8 Minyak Pelumas Rp. 5,600.00 per ltr 2055
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
9 Alkalin Rp. 163,900.00 per Kg 2056
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
10 Solar Rp. 9,800.00 per ltr 2057
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
11 Sealent Rp. 19,500.00 per tube 2059
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
12 Oli Rp. 65,000.00 per ltr 2060
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
13 Perekat bata ringan mortar lv Rp. 1,700.00 per kg KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2065
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
D BAHAN KAYU, TRIPLEK, MULTIPLEK TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
1 kayu acuan Rp. 1,613,400 per m3 2065
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI HARGA
2 papan kayu Rp. 7,000,000 per m3 2067
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
3 Kayu Dolken O 8- 10 Panjang 4 m1 Rp. 48,400 per btg KEPUTUSAN
2073 WALI KOTA BANDUNG NOMOR : 027/Kep.
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
https://www.tokopedia.com/bampro/hpl-aica-mb-021-d-m-
4 HPL (122x244 cm) Rp. 108,100 per lbr TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSANgosend-grab-bandung?whid=325921
WALI KOTA BANDUNG NOMOR : 027/Kep.
5 HPL Rp. 36,314.16 per m2 2075
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
6 Multiplex 12 mm 120x240 Rp. 193,600 per Lbr 2076
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
7 Multiplex 9 mm 120x240 Rp. 151,300 per Lbr 2077
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI HARGA
8 plywood t= 18 mm (122X244 cm 288,200per lbr 2080
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
9 Lis Gypsum Rp. 15,000 per m KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2081
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
E BAHAN PAKU, BAUT MUR, ANGKUR TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
1 Paku 2 s/d 5" Rp. 19,100 per Kg 2081
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
2 Paku Asbes Rp. 29,600 per Kg 2082
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
3 Paku Sekrup Rp. 67.63 per bh 2087
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
4 Skrup/ Ripet Rp. 312.50 per Bh KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2088
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
F BAHAN PENUTUP ATAP TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
1 Genteng beton Rp. 7,100 per bh 2088
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
2 Kalsiboard EG Uk. 240x120x 6 mm Rp. 75,000.00 per Lbr 2089
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
3 Gypsum Board Uk. 240x120x 9 mm Rp. 65,000.00 per Lbr 2090
G BAHAN KACA
Page9/76
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan 806-BPKA/2019 TENTANG STANDARISASI HARGA
Sumber/Referensi
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
1 Kaca Polos tebal 5 mm Rp. 88,900 per m2 KEPUTUSAN
2090 WALI KOTA BANDUNG NOMOR : 027/Kep.
806-BPKA/2019 TENTANG STANDARISASI HARGA
H BAHANG ENGSEL, GRENDEL, KUNCI, HANDLE TERTINGGI SATUAN BARANG/JASA
ED/Sf 38 TAHUN
KEPUTUSAN WALIXXV 2019
KOTA JURNAL TAHUN
BANDUNG HARGA ANGGARAN
NOMORSATUAN
: 027/Kep.
1 Casement 12 " Rp. 45,800 per bh 2090 BANGUNAN,
BAHAN KONSTRUKSI & INTERIOR KAB
806-BPKA/2019 TENTANG STANDARISASI HARGA
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2 pintu pvc 324000 per m2 BANDUNG
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
3 Lockase case cylinder Rp. 156,400 per set 2100
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
4 Lockase Window Bolt Rp. 156,400 per set 2101
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
5 Engsel pintu steinlish 4x3x3 mm Rp. 48,700 per stel 2104
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
6 Lever Handle Rp. 244,900 per stel 2108
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
7 handle pintu alumunium Rp. 166,800 per stel 2109
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
8 rambucis Rp. 54,100 per stel 2110
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
9 kunci tanam 2 slaag 174,700 per stel KEPUTUSAN
2111 WALI KOTA BANDUNG NOMOR : 027/Kep.
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
I BAHAN ALUMINIUM TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
1 Aluminium kusen pintu & jendela 4"X1 3/4" Rp. 96,300 per m1 2111
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
2 Aluminium kusen pintu & jendela 3"X1 3/4" Rp. 96,300 per m1 2112
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
3 Aluminium frame daun jendela Rp. 55,900 per m1 2113
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
4 Aluminium frame daun pintu 4,5x6,5 cm Rp. 55,900 per m1 2114
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI KOTA STANDARISASI
BANDUNG NOMOR : 027/Kep.
5 Aluminium frame daun pintu 4,5x11 cm Rp. 92,300.00 per m1 2115
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
6 Aluminium ventilasi 1 'x 3 " Rp. 24,000.00 per m1 2116
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
7 Aluminium frame vison Rp. 43,600.00 per m1 2117
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
8 Spigot aluminium Rp. 13,600.00 per m1 2118
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
9 Aluminium Composit Panel (ACP) Rp. 179,200.00 per m2 2119
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
10 Aluminium Composit Panel Perforeted 3 mm (ACP) Rp. 253,000.00 per m2 2120
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
11 Karet Kusen Aluminium Rp. 4,000 per m 1
2121
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
12 Sielent Rp. 1,950.00 per m1 KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2122
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
J BAHAN PELAPIS LANTAI DAN DINDING TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
1 Keramik 40x40 Polished Rp. 62000 per m2 2122
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI HARGA
2 Tegel Keramik Dinding 20x25 cm Rp. 57,300 per m2 2124
TERTINGGI SATUAN
ED/Sf 38 TAHUN XXVBARANG/JASA
2019 JURNAL TAHUN
HARGA ANGGARAN
SATUAN
3 Tegel Keramik Lantai 20x20 cm Rp. 60,900 per m2 2125
BAHAN BANGUNAN, KONSTRUKSI & INTERIOR KAB
4 Floor Hardener 3 kg/m2 Rp. 8,000.00 per kg KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
BANDUNG
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
K SANITAIR TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
1 Closet Duduk Rp. 1,311,000 per unit 2124
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
2 KITCHEN SINK Rp. 705,100.00 per unit KEPUTUSAN
2125 WALI KOTA BANDUNG NOMOR : 027/Kep.
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
https://www.tokopedia.com/solusirumahku/toilet-shower-
3 TOILET SPRAYER Rp. 85,890.00 per bh TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG
WALI KOTA STANDARISASI
chrome-semprotan-air-bidet-spray-krom-kloset-wc-
KEPUTUSAN BANDUNG NOMOR : 027/Kep.
4 Floor Drain Rp. 218,800.00 per bh 2124
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019 ryuichi?whid=2610805
TENTANG STANDARISASI HARGA
5 Kran Rp. 93,600.00 per bh KEPUTUSAN WALI
2125 KOTA BANDUNG NOMOR : 027/Kep.
TERTINGGI SATUAN
806-BPKA/2019 BARANG/JASA
TENTANG TAHUNHARGA
STANDARISASI ANGGARAN
6 Kitchen Zink + Kran Rp. 677,300.00 per bh KEPUTUSAN
2126 WALI KOTA BANDUNG NOMOR : 027/Kep.
TERTINGGI SATUAN
806-BPKA/2019 BARANG/JASA
TENTANG TAHUN
STANDARISASI ANGGARAN
HARGA
7 Floor drain 3 " Rp. 218,800.00 per bh KEPUTUSAN WALI
2127 KOTA BANDUNG NOMOR : 027/Kep.
TERTINGGI SATUAN
806-BPKA/2019 BARANG/JASA
TENTANG TAHUNHARGA
STANDARISASI ANGGARAN
8 water drain Rp. 50,000.00 per bh 2128
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
9 bak kamar mandi 0,24 M3 Rp. 800,000.00 per bh KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2129
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
M UPAH TENAGA KERJA TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN WALI TENTANG STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
1 Pekerja Rp. 161,636 per hari 2128
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
2 Tukang kayu Rp. 160,500 per hari 2129
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
3 Kepala Tukang kayu Rp. 177,600 per hari 2130
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMORHARGA
: 027/Kep.
4 Tukang batu Rp. 160,500.00 per hari 2131
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
5 Kepala Tukang Batu Rp. 177,600.00 per hari 2132
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019
KEPUTUSAN TENTANG
WALI STANDARISASI
KOTA BANDUNG NOMOR : 027/Kep.
6 Tukang besi Rp. 160,500.00 per hari 2133
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
7 Kepala tukang besi Rp. 177,600.00 per hari 2134
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
8 Tukang cat Rp. 160,500.00 per hari 2135
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
9 Kepala tukang cat Rp. 177,600.00 per hari 2136
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
10 Tukang listrik Rp. 160,500.00 per hari 2137
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
11 Kepala tukang listrik Rp. 177,600.00 per hari 2138
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
12 Mandor Rp. 189,700 per hari 2139
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
13 Operator Rp. 189,700 per hari 2140
TERTINGGI SATUAN BARANG/JASA TAHUNHARGA
ANGGARAN
806-BPKA/2019 TENTANG STANDARISASI
14 Tukang Pipa Rp. 160,500.00 per hari 2141
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
15 Tukang Las Rp. 160,500.00 per hari KEPUTUSAN WALI KOTA BANDUNG NOMOR : 027/Kep.
2142
806-BPKA/2019 TENTANG STANDARISASI HARGA
N SEWA PERALATAN TERTINGGI SATUAN BARANG/JASA
ED/Sf 38 TAHUN
KEPUTUSAN WALIXXV 2019
KOTA JURNAL TAHUN
BANDUNG HARGA ANGGARAN
NOMORSATUAN
: 027/Kep.
1 Sewa alat bantu (1 set @3alat) Rp. 14,600 ls 2142
BAHAN BANGUNAN, KONSTRUKSI & INTERIOR PROV
806-BPKA/2019 TENTANG STANDARISASI HARGA
2 Sewa welding set (min 5 jam) Rp. 440,000.00 per hari JABAR
TERTINGGI SATUAN BARANG/JASA TAHUN ANGGARAN
3 Sewa Tamper Rp. 91,400 per jam 2142

Page10/76
ANALISA HARGA SATUAN PEKERJAAN
DATA PEMBAHARUAN & PENYESUAIAN 2019

No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)


1 2 3 5. 6.
I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi m2 1.000
Pekerja OH 0.100 161,636.00
Mandor OH 0.050 189,700.00
Jumlah
2 Pengukuran dan pasangan bouwplank m 1.000
kayu acuan m3 0.012 1,613,400.00
Paku biasa 2" - 5 " kg 0.020 19,100.00
papan kayu m3 0.007 7,000,000.00
Pekerja oh 0.100 161,636.00
Tukang Kayu oh 0.100 160,500.00
Kepala Tukang Kayu oh 0.010 177,600.00
Mandor oh 0.005 189,700.00
Jumlah
II. PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1m m3 1.000
Pekerja OH 0.750 161,636.00
Mandor OH 0.025 189,700.00
Jumlah
2 Urugan Pasir m3 1.000
Pasir Urug m3 1.100 181,500.00
Pekerja OH 0.300 161,636.00
Mandor OH 0.100 189,700.00
Jumlah
3 pasir+split m3 1.000
pasir m3 0.550 242,000.00
split m3 0.550 183,600.00
Pekerja OH 0.300 161,636.00
Mandor OH 0.100 189,700.00
Jumlah
4 split+pecahan batu m3 1.000
batu pecah m3 0.550 190,600.00
split m3 0.550 183,600.00
Pekerja OH 0.300 161,636.00
Mandor OH 0.100 189,700.00
Jumlah
5 batu belah m3 1.000
batu belah m3 1.100 281,012.00
Pekerja OH 0.300 161,636.00
Mandor OH 0.100 189,700.00
Jumlah

11/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

6 Urugan Tasirtu m3 1.000


Tasirtu m3 1.200 206,500.00
Sewa stemper hari 0.009 91,400.00
Pekerja OH 0.250 161,636.00
Mandor OH 0.025 189,700.00
Jumlah
7 Urugan Tanah Kembali m3 1.000
Pekerja OH 0.102 161,636.00
Mandor OH 0.019 189,700.00
Jumlah
8 Buangan Tanah Galian m3 1.000
Pekerja OH 0.200 161,636.00
Mandor OH 0.040 189,700.00
Jumlah
III. PEKERJAAN PASANGAN PONDASI
1 Batu kosongan Aanstampeng m3 1.000
Batu kali belah m3 1.2000 281,012.00
Pasir Urug m3 0.3000 181,500.00
Pekerja oh 0.7800 161,636.00
Tukang Batu oh 0.3900 160,500.00
Kepala Tukang Batu oh 0.0390 177,600.00
Mandor oh 0.0390 189,700.00
Jumlah
2 Pondasi Batu kali1:5 m3 1.000
Batu kali belah m3 1.100 281,012.00
Semen Portland kg 136.000 1,700.00
Pasir Pasang m3 0.544 242,000.00
Pekerja oh 1.500 161,636.00
Tukang Batu oh 0.750 160,500.00
Kepala Tukang Batu oh 0.075 177,600.00
Mandor oh 0.075 189,700.00
Jumlah
3 Pasangan Pondasi rollag batu bata 1:3 m3 1.000
Batu bata merah 5x11x22 cm bh 70.000 2,300.00
Semen Portland zak 0.287 71,610.00
Pasir pasang m3 0.040 242,000.00
Pekerja oh 0.300 161,636.00
Tukang Batu oh 0.100 160,500.00
Kepala Tukang Batu oh 0.010 177,600.00
Mandor oh 0.015 189,700.00
Jumlah 1 m2
Jumlah 1 m3 8.333 260,423.01
4 lapis ijuk m 1.000
lapis ijuk m 1.000 11,410.00
Pekerja OH 0.200 161,636.00
Mandor OH 0.040 189,700.00
Jumlah
IV. PEKERJAAN PASANGAN DINDING TEMBOK
1 Pasang Dinding Bata Ringan m2 1.000
Bata Ringan 60x20x t 10 cm bh 8.333 6,400.00
Perekat bata ringan mortar lv kg 2.500 1,700.00
Pekerja OH 0.300 161,636.00
Tukang Batu OH 0.100 160,500.00
Kepala Tukang Batu OH 0.010 177,600.00
Mandor OH 0.015 189,700.00
Jumlah
Jumlah 1 m3 8.330 126,745.63
2 Pasang Dinding Batu Palimanan m2 1.000
Batu Susun Palimanan m2 1.000 100,900.00
Semen Portland 50 kg zak 0.150 6,400.00
Pasir Pasang m3 0.030 242,000.00
Pekerja OH 0.300 161,636.00
Tukang Batu OH 0.100 161,636.00
Kepala Tukang Batu OH 0.010 160,500.00
Mandor OH 0.015 177,600.00
Jumlah
3 Pasang Dinding Bata 1:5 1/2 Bata m2 1.000
Batu Bata Merah bh 70.000 6,400.00
Semen Portland 50 kg zak 0.194 1,700.00
Pasir Pasang m3 0.045 242,000.00
Pekerja OH 0.300 161,636.00

12/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

Tukang Batu OH 0.100 160,500.00


Kepala Tukang Batu OH 0.010 177,600.00
Mandor OH 0.015 189,700.00
Jumlah
V. PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN
1 Plesteran Tebal 15mm Campuran 1 : 3 m2 1.000
Semen Portland 50 kg zak 0.156 1,700.00
Pasir pasang m3 0.023 242,000.00
Pekerja OH 0.300 161,636.00
Tukang Batu OH 0.150 160,500.00
Kepala Tukang Batu OH 0.015 177,600.00
Mandor OH 0.015 189,700.00
Jumlah
2 Plesteran Tebal 15mm Campuran 1 : 5 m2 1.000
Semen Portland 50 kg zak 0.104 1,700.00
Pasir pasang m3 0.026 242,000.00
Pekerja OH 0.300 161,636.00
Tukang Batu OH 0.150 160,500.00
Kepala Tukang Batu OH 0.015 177,600.00
Mandor OH 0.015 189,700.00
Jumlah
3 Benangan Sudut 1 : 2 m 1.000
Semen Portland zak 0.010 1,700.00
Pasir Pasang m3 0.013 242,000.00
Pekerja OH 0.080 161,636.00
Tukang Batu OH 0.040 160,500.00
Kepala Tukang Batu OH 0.040 177,600.00
Mandor OH 0.004 189,700.00
Jumlah
4 Acian Beton m2 1.000
Semen Portland zak 0.065 1,700.00
Pekerja OH 0.200 161,636.00
Tukang Batu OH 0.100 160,500.00
Kepala Tukang Batu OH 0.010 177,600.00
Mandor OH 0.010 189,700.00
Jumlah
VII. PEKERJAAN BETON
1 Beton Lantai Kerja 1:3:5 m3 1.000
Semen Portland 40 kg zak 5.750 57,288.00
Pasir beton m3 0.558 327,750.00
Batu pecah mesin 1/2 m3 0.541 190,600.00
Air (biaya air tawar) lt 215.000 50.00
Pekerja OH 1.200 161,636.00
Tukang Batu OH 0.200 160,500.00
Kepala Tukang Batu OH 0.020 177,600.00
Mandor OH 0.060 189,700.00
Jumlah
2 Beton Rabat beton 1:3:5 m3 1.000
Semen Portland 40 kg zak 6.900 57,288.00
Pasir beton m3 0.518 327,750.00
Batu pecah mesin 1/2 m3 0.533 190,600.00
Air (biaya air tawar) lt 215.000 50.00
Pekerja OH 1.650 161,636.00
Tukang Batu OH 0.275 160,500.00
Kepala Tukang Batu OH 0.028 177,600.00
Mandor OH 0.083 189,700.00
Jumlah
3 Beton K-225 m3 1.000
Semen Portland 40 kg zak 9.275 57,288.00
Pasir beton m3 0.436 327,750.00
Batu pecah mesin 1/2 m3 0.551 190,600.00
Air (biaya air tawar) lt 215.000 50.00
Pekerja OH 1.650 161,636.00
Tukang Batu OH 0.275 160,500.00
Kepala Tukang Batu OH 0.028 177,600.00
Mandor OH 0.083 189,700.00
Jumlah
4 Beton K-300 m3 1.000
Semen Portland 40 kg zak 10.325 57,288.00
Pasir beton m3 0.426 327,750.00
Batu pecah mesin 1/2 m3 0.537 190,600.00

13/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

Air (biaya air tawar) lt 215.000 50.00


Pekerja OH 1.650 161,636.00
Tukang Batu OH 0.275 160,500.00
Kepala Tukang Batu OH 0.028 177,600.00
Mandor OH 0.083 189,700.00
Jumlah
5 Pembesian Dengan Besi Ulir 39 kg 1.000
Besi beton ulir kg 1.050 11,400.00
Kawat beton (bendrat) kg 0.015 15,000.00
Pekerja OH 0.007 161,636.00
Tukang Besi OH 0.007 160,500.00
Kepala Tukang Besi OH 0.001 177,600.00
Mandor OH 0.000 189,700.00
Jumlah
6 Pembesian Dengan Besi Polos U-24 kg 1.000
Besi beton polos kg 1.050 11,200.00
Kawat beton (bendrat) kg 0.015 20,790.00
Pekerja OH 0.007 161,636.00
Tukang Besi OH 0.007 160,500.00
Kepala Tukang Besi OH 0.001 177,600.00
Mandor OH 0.000 189,700.00
Jumlah
7 Bekisting Untuk Sloof, Kolom, Ring Praktis m2 1.000
Kayu meranti papan (MC) m3 0.022 7,000,000.00
Kayu meranti usuk m3 0.002 1,613,400.00
Paku biasa 2"- 5" kg 0.300 19,100.00
Minyak Begesting ltr 0.100 2,800.00
Jumlah bahan
Pekerja OH 0.520 161,636.00
Tukang Kayu OH 0.260 160,500.00
Kepala Tukang Kayu OH 0.026 177,600.00
Mandor OH 0.026 189,700.00
Jumlah upah
Bahan Begesting 2x pakai 0.500 163,236.80
Upah bgesting 2 x pakai 1.000 135,330.52
Jumlah begesting 2 x pakai

14/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

8 Bekisting Plat Lantai m3 1.000


Kayu meranti usuk m3 0.0238 1,613,400.00
Paku biasa 2"- 5" kg 0.4000 19,100.00
Minyak Begesting ltr 0.2000 2,800.00
Balok Kayu Meranti m3 0.0150 5,000,000.00
Multiplek tebal 12 mm lbr 0.3500 193,600.00
Dolken Kayu Gelam 8-10/400 cm btg 6.0000 48,400.00
Jumlah bahan
Pekerja OH 0.660 161,636.00
Tukang Kayu OH 0.330 160,500.00
Kepala Tukang Kayu OH 0.033 177,600.00
Mandor OH 0.033 189,700.00
Jumlah upah
Bahan Begesting 2x pakai 0.500 479,758.92
Upah bgesting 2 x pakai 1.000 171,765.66
Jumlah begesting 2 x pakai
9 Beton Pondasi Tapak m3 1.000
Beton K225 m3 1.000 1,121,687.99
Bekisting m2 0.733 216,948.92
Pembesian Dengan Besi Polos U-24 kg 29.569 14,527.00
Jumlah
10 Beton Poer PC-3 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting m2 2.710 216,948.92
Besi beton ulir U39 kg 159.384 14,650.15
Jumlah
11 Beton Poer PC-4 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting m2 2.580 216,948.92
Besi beton ulir U39 kg 224.991 14,650.15
Jumlah
12 Beton Poer PC-5 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting m2 2.160 216,948.92
Besi beton ulir U39 kg 175.225 14,650.15
Jumlah
13 Pondasi strous dia 30 cm m3 1.000
Beton K300 m3 1.000 1,121,687.99
Besi beton polos U24 kg 89.000 14,527.00
Jumlah
14 Beton Sloof S-1 40/70 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 5.000 216,948.92
Besi beton polos U24 kg 49.193 14,527.00
Besi beton ulir U39 kg 89.143 14,650.15
Jumlah
15 Beton Sloof S-2 30/60 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 6.660 216,948.92
Besi beton polos U24 kg 64.494 14,527.00
Besi beton ulir U39 kg 86.667 14,650.15
Jumlah
16 Beton Sloof S-3 30/50 m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 6.660 216,948.92
Besi beton polos U24 kg 59.232 14,527.00
Besi beton ulir U39 kg 55.467 14,650.15
Jumlah
17 Beton Sloof S-4 15/20 m3 1.000
Beton K225 m3 1.000 1,121,687.99
Begesting 2x pakai m2 10.000 216,948.92
Besi beton polos U24 kg 355.060 14,527.00
Jumlah
18 Beton Kolom praktis 15/15 m3 1.000
Beton K225 m3 1.000 1,121,687.99
Begesting 2x pakai m2 13.333 216,948.92
Besi beton polos U24 kg 330.028 14,527.00
Jumlah
19 Beton Balok Latai dan ring balk 15/20 m3 1.000
Beton K225 m3 1.000 1,121,687.99
Begesting 2x pakai m2 10.000 216,948.92
Besi beton polos U24 kg 264.780 14,527.00
15/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

Jumlah

16/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

20 Beton plat lantai t= 15 cm m3 1.000


Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 6.667 411,645.12
Besi beton polos U24 kg 172.000 14,527.00
Besi beton ulir U39 kg 0.000 14,650.15
Jumlah

17/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

21 Beton plat lantai t= 12 cm m3 1.000


Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 8.333 411,645.12
Besi beton polos U24 kg 152.000 14,527.00
Besi beton ulir U39 kg 0.000 14,650.15
Jumlah
22 Beton plat lantai t= 10 cm m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 10.000 411,645.12
Besi beton polos U24 kg 132.000 14,527.00
Besi beton ulir U39 kg 0.000 14,650.15
Jumlah
23 Beton lisplank t= 15 cm m3 1.000
Beton K-225 m3 1.000 1,121,687.99
Begesting 2x pakai m2 0.914 411,645.12
Besi beton polos U24 kg 6.022 14,527.00
Jumlah
24 Beton plat dasar tandon t= 25 cm m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 3.000 216,948.92
Besi beton polos U24 kg 0.000 14,527.00
Besi beton ulir U39 kg 101.000 14,650.15
Jumlah
25 Beton plat dinding tandon t= 15 cm m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 13.333 411,645.12
Besi beton polos U24 kg 0.000 14,527.00
Besi beton ulir U39 kg 121.000 14,650.15
Jumlah
26 Beton plat tutup tandon t= 15 cm m3 1.000
Beton K300 m3 1.000 1,121,687.99
Begesting 2x pakai m2 6.667 411,645.12
Besi beton polos U24 kg 0.000 14,527.00
Besi beton ulir U39 kg 121.000 14,650.15
Jumlah
VIII. PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP

18/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

1 Pemasangan Genteng beton m2 1.000


genteng beton bh 10.000 7,100.00
Pekerja OH 0.150 161,636.00
Tukang OH 0.075 160,500.00
Kepala Tukang OH 0.008 177,600.00
Mandor OH 0.008 189,700.00
Jumlah
IX PEKERJAAN PELAPIS LANTAI DAN DINDING
1 Pemasangan Tegel Keramik Dinding 20x25cm m2 1.000
Semen PC 40 kg zak 0.233 57,288.00
Semen Berwarna Yiyitan kg 1.940 20,000.00
Pasir Pasang m3 0.018 242,000.00
Tegel Keramik Dinding 20x25 cm m2 1.060 57,300.00
Pekerja OH 0.900 161,636.00
Tukang Batu OH 0.450 160,500.00
Kepala Tukang Batu OH 0.045 177,600.00
Mandor OH 0.045 189,700.00
Jumlah
2 Pemasangan Keramik Lantai 20x20 cm m2 1.000
Semen PC 40 kg zak 0.233 57,288.00
Semen Berwarna Yiyitan kg 1.500 20,000.00
Pasir Pasang m3 0.045 242,000.00
Tegel Keramik 20x20 cm m2 1.068 60,900.00
Pekerja OH 0.700 161,636.00
Tukang Batu OH 0.350 160,500.00
Kepala Tukang Batu OH 0.035 177,600.00
Mandor OH 0.035 189,700.00
Jumlah
3 Pemasangan Lantai Keramik 40x40cm Polished m2 1.000
Keramik 40x40 cm Polished m2 1.050 62,000.00
Semen kg 11.380 1,700.00
Pasir Pasang m3 0.045 242,000.00
Semen Warna kg 1.620 20,000.00
Pekerja OH 0.700 161,636.00
Tukang Batu OH 0.350 160,500.00
Kepala Tukang Batu OH 0.035 177,600.00
Mandor OH 0.035 189,700.00
Jumlah

19/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

4 Pembongkaran Paving Block m2 1.000


Pekerja OH 0.100 161,636.00
Mandor OH 0.005 189,700.00
Jumlah
5 Pekerjaan Floor Hardener m2 1.000
Floor Hardener kg 3.000 8,000.00
Alat Bantu ls 1.000 14,600.00
Pekerja OH 0.120 20,000.00
Tukang Batu OH 0.120 161,636.00
Kepala Tukang Batu OH 0.012 160,500.00
Mandor OH 0.006 177,600.00
Jumlah
X PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pemasangan Kusen Aluminium 4 " m 1.000
Kusen Aluminium 4 " X 1 3/4" m' 1.050 96,300.00
Skrup/ripet buah 1.000 312.50
Sealent tube 4.000 1,950.00
Pekerja OH 0.150 161,636.00
Tukang besi OH 0.250 160,500.00
Kepala Tukang besi OH 0.022 177,600.00
Mandor OH 0.025 189,700.00
Jumlah
2 Pemasangan Kusen Aluminium 3 " m 1.000
Kusen Aluminium 3 " X 1 3/4" m' 1.050 96,300.00
Skrup/ripet buah 1.000 312.50
Sealent tube 4.000 1,950.00
Pekerja OH 0.150 161,636.00
Tukang besi OH 0.250 160,500.00
Kepala Tukang besi OH 0.022 177,600.00
Mandor OH 0.025 189,700.00
Jumlah
3 Frame Daun Pintu Aluminium 4,5x6,5 cm (ambang atas) m 1.000
Frame Daun Pintu Aluminium 4,5x6,5 m 1.050 55,900.00
Karet Kusen Aluminium m 1.000 4,000.00
Skrup/ Rivet bh 4.000 312.50
Pekerja OH 0.150 161,636.00
Tukang OH 0.250 160,500.00
Kepala Tukang OH 0.022 177,600.00
Mandor OH 0.025 189,700.00
Jumlah

20/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

4 Frame Daun Pintu Aluminium 4,5x11 cm (ambang bwh) m 1.000


Frame Daun Pintu Aluminium 4,5x11 cm (amb bwh) m 1.050 92,300.00
Karet Kusen Aluminium m 1.000 4,000.00
Skrup/ Rivet bh 4.000 312.50
Pekerja OH 0.150 161,636.00
Tukang OH 0.250 160,500.00
Kepala Tukang OH 0.022 177,600.00
Mandor OH 0.025 189,700.00
Jumlah
5 Frame Daun Jendela Aluminium m 1.000
Frame Daun Jendela Aluminium m 1.050 55,900.00
Karet Kusen Aluminium m 1.000 4,000.00
Skrup/ Rivet bh 4.000 312.50
Pekerja OH 0.150 161,636.00
Tukang OH 0.250 160,500.00
Kepala Tukang OH 0.022 177,600.00
Mandor OH 0.025 189,700.00
Jumlah
6 Ventilasi aluminium uk. 1"x3 " m 1.000
Vebtilasi aluminium 1 "x 3 " m 1.050 24,000.00
Skrup/ Rivet bh 4.000 312.50
Pekerja OH 0.150 161,636.00
Tukang OH 0.150 160,500.00
Kepala Tukang OH 0.010 177,600.00
Mandor OH 0.020 189,700.00
Jumlah
7 Pasang Kaca polos t= 5 mm m2 1.000
Kaca polos t= 5 mm m2 1.050 88,900.00
Pekerja OH 0.015 161,636.00
Tukang OH 0.150 160,500.00
Kepala Tukang OH 0.015 177,600.00
Mandor OH 0.008 189,700.00
Jumlah

21/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

8 Pasang Multiplek t= 12 mm m2 1.000


Multiplek t= 12 mm (122X244 cm lbr 0.350 193,600.00
Pekerja OH 0.0250 161,636.00
Tukang OH 0.0750 160,500.00
Kepala Tukang OH 0.0075 177,600.00
Mandor OH 0.0013 189,700.00
Jumlah
9 Pasang Plywood t=18 mm m2 1.000
plywood t= 18 mm (122X244 cm lbr 0.350 288,200.00
Pekerja OH 0.0250 161,636.00
Tukang OH 0.0750 160,500.00
Kepala Tukang OH 0.0075 177,600.00
Mandor OH 0.0013 189,700.00
Jumlah

22/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

10 Pintu aluminium Type P4 unit 1.000


Kusen aluminium silver 4 " m1 4.480 182,247.60
Frame daun pintu 4,5x6,5 cm m1 10.120 136,965.10
Frame daun pintu 4,5x11 cm m1 1.720 175,185.10
Multiplek t= 12 mm m2 0.970 85,417.01
HPL m2 1.940 36,314.16
Lever Handle set 1.000 244,900.00
Engsel steinlish stel 2.000 48,700.00
Lock case set 1.000 156,400.00
Jumlah

23/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

11 Pintu aluminium Type P6 unit 1.000


Kusen aluminium silver 4 " m1 7.660 182,247.60
Frame daun pintu 4,5x6,5 cm m1 5.050 136,965.10
Frame daun pintu 4,5x11 cm m1 0.850 175,185.10
Multiplek t= 12 mm m2 1.380 85,417.01
HPL m2 2.760 36,314.16
Frame Vision aluminium uk 20x70 cm m1 1.800 43,600.00
Kaca 5 mm vision m2 0.150 123,931.29
Jalusi aluminium 1"x3 " m1 5.100 80,340.40
Lever Handle set 1.000 244,900.00
Engsel steinlish stel 2.000 48,700.00
Lock case Cylinder set 1.000 156,400.00
Jumlah
12 Pintu aluminium Type P7 unit 1.000
Kusen aluminium silver 4 " m1 5.010 182,247.60
Frame daun pintu 4,5x6,5 cm m1 4.930 136,965.10
Frame daun pintu 4,5x11 cm m1 1.460 175,185.10
Multiplek t= 12 mm m2 0.990 85,417.01
HPL m2 1.990 36,314.16
Lever Handle set 1.000 244,900.00
Engsel steinlish stel 2.000 48,700.00
Lock case set 1.000 156,400.00
Jumlah
13 Pintu aluminium Type P8 unit 1.000
Kusen aluminium silver 4 " m1 4.260 182,247.60
Frame daun pintu 4,5x6,5 cm m1 6.280 136,965.10
Multiplek t= 12 mm m2 1.250 85,417.01
HPL m2 2.500 36,314.16
Handle HDL DKS set 1.000 166,800.00
Engsel steinlish stel 2.000 48,700.00
kunci tanam 2 slaag set 1.000 174,700.00
Jumlah
14 Pintu aluminium Type P9 unit 1.000
Kusen aluminium silver 4 " m1 6.000 182,247.60
Frame daun pintu 4,5x6,5 cm m1 5.800 136,965.10
Multiplek t= 12 mm m2 1.701 85,417.01
HPL m2 1.701 36,314.16
handle pintu alumunium set 1.000 166,800.00
Engsel steinlish stel 1.000 48,700.00
kunci tanam 2 slaag set 1.000 174,700.00
Jumlah
15 Pintu aluminium Type P9 kayu unit 1.000
Kusen aluminium silver 4 " m1 6.000 182,247.60
Frame daun pintu 4,5x6,5 cm m1 5.800 136,965.10
plywood t=18mm m2 1.701 118,527.01
HPL m2 1.701 36,314.16
handle pintu alumunium set 1.000 166,800.00
Engsel steinlish stel 1.000 48,700.00
kunci tanam 2 slaag set 1.000 174,700.00
Jumlah
16 pintu pvc m2 1.000
pintu pvc m2 1.000 324,000.00
pekerja oh 1.050 161,636.00
tukang oh 1.050 160,500.00
kepala tukang oh 0.100 177,600.00
mandor oh 0.005 189,700.00
Jumlah
17 Jendela aluminium Type J1 unit 1.000
Kusen aluminium silver 4 " m1 16.150 182,247.60
Grame daun jendela kaca m1 5.960 136,965.10
Kaca polos t= 5 mm m2 3.810 123,931.29
Sealent m1 24.600 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 2.000 54,100.00
Jumlah
18 Jendela aluminium Type J2 unit 1.000
Kusen aluminium silver 4 " m1 16.600 182,247.60
Grame daun jendela kaca m1 6.120 136,965.10
Kaca polos t= 5 mm m2 3.920 123,931.29
Sealent m1 22.100 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 2.000 54,100.00
24/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

Jumlah

25/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

19 Jendela aluminium Type J3 unit 1.000


Kusen aluminium silver 4 " m1 16.150 182,247.60
Frame daun jendela kaca m1 5.960 136,965.10
Jalusi aluminium 1"x3 " m1 14.400 80,340.40
Kaca polos t= 5 mm m2 1.880 123,931.29
Sealent m1 9.400 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 2.000 54,100.00
Jumlah
20 Jendela aluminium Type J4 unit 1.000
Kusen aluminium silver 4 " m1 16.600 182,247.60
Frame daun jendela kaca m1 6.120 136,965.10
Jalusi aluminium 1"x3 " m1 15.120 80,340.40
Kaca polos t= 5 mm m2 2.010 123,931.29
Sealent m1 11.300 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 2.000 54,100.00
Jumlah
21 Jendela aluminium Type J5 unit 1.000
Kusen aluminium silver 4 " m1 5.600 182,247.60
Frame daun jendela kaca m1 5.200 136,965.10
Jalusi aluminium 1"x3 " m1 80,340.40
Kaca polos t= 5 mm m2 1.205 123,931.29
Sealent m1 5.200 1,950.00
Casement 12 " set 1.000 45,800.00
Handle Lock CH 400 Dekson set 1.000 54,100.00
Jumlah
22 Jendela aluminium Type J6 unit 1.000
Kusen aluminium silver 4 " m1 31.800 182,247.60
Frame daun jendela kaca m1 11.580 136,965.10
Jalusi aluminium 1"x3 " m1 20.100 80,340.40
Kaca polos t= 5 mm m2 6.630 123,931.29
Sealent m1 38.100 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 3.000 54,100.00
Jumlah
23 Jendela aluminium Type J7 unit 1.000
Kusen aluminium silver 4 " m1 26.500 182,247.60
Frame daun jendela kaca m1 7.840 136,965.10
Jalusi aluminium 1"x3 " m1 16.800 80,340.40
Kaca polos t= 5 mm m2 5.400 123,931.29
Sealent m1 26.600 1,950.00
Cathment 12 " set 2.000 45,800.00
Handle Lock CH 400 Dekson set 2.000 54,100.00
Jumlah
24 Jendela aluminium Type BV unit 1.000
Kusen aluminium silver 4 " m1 2.000 182,247.60
Frame daun jendela kaca m1 1.520 136,965.10
Kaca polos t= 5 mm m2 1.100 123,931.29
Sealent m1 1.400 1,950.00
Cathment 12 " bh 2.000 45,800.00
Handle Lock CH 400 Dekson set 1.000 54,100.00
Jumlah

26/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

XI PEKERJAAN SUN SCREEN, SECONDARY SKIN, RAILIING


1 PENGELASAN/FEBRIKASI DENGAN LAS LISTRIK CM 10.000
Kawat las listrik kg 0.400 34,100.00
Solar ltr 0.300 9,800.00
Minyak Pelumas ltr 0.040 5,600.00
Sewa Alat Welding Set (Min 5 jam) jam 0.170 440,000.00
Mandor OH 0.002 189,700.00
Tukang besi OH 0.020 160,500.00
Kepala Tukang besi OH 0.002 177,600.00
Pekerja OH 0.002 161,636.00
Jumlah
2 FEBRIKASI DAN PEMASANGAN PIPA BAJA (ELECTRODA) M1 1.000
Kawat las listrik kg 0.006 34,100.00
Solar ltr 0.005 9,800.00
Minyak Pelumas ltr 0.001 5,600.00
Sewa Alat Welding Set (Min 5 jam) jam 0.210 440,000.00
Mandor OH 0.002 189,700.00
Tukang besi OH 0.060 160,500.00
Kepala Tukang besi OH 0.006 177,600.00
Pekerja OH 0.028 161,636.00
Jumlah
3 FEBRIKASI DAN PEMASANGAN BAJA (ELECTRODA) KG 1.000
Pengelasan besi baja cm 0.200 95,871.87
Mandor OH 0.001 189,700.00
Tukang besi OH 0.001 160,500.00
Kepala Tukang besi OH 0.000 177,600.00
Pekerja OH 0.001 161,636.00
Jumlah
4 PEKERJAAN KONSTRUKSI BAJA RINGAN m2 1.000
reng r33-0.45 m 5.100 5,816.67
self drilling screw dia 6x20 mm bh 25.000 5,000.00
self drilling screw dia 4x16 mm bh 35.000 5,000.00
dynabolt dia 12-120 mm bh 1.000 7,400.00
c.100.75 m 2.800 14,600.00
alat bantu ls 1.000 14,600.00
Mandor OH 0.001 189,700.00
Tukang besi OH 0.176 160,500.00
Kepala Tukang besi OH 0.117 177,600.00
Pekerja OH 0.247 161,636.00
Jumlah
5 PEK BESI SIKU TERMASUK PEMASANGAN DAN ELECTRODA KG 1.000
Besi siku kg 1.050 5,816.67
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah
6 PEK BESI WF TERMASUK PEMASANGAN DAN ELECTRODA KG 1.000
Besi WF 200.100.5,5.7 kg 1.050 5,000.00
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah
7 PEK BESI KANAL C TERMASUK PEMASANGAN DAN ELECTRODA KG 1.000
Besi Kanal C 150.50.20.3,2 kg 1.050 7,400.00
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah
8 PEK BESI PLAT TERMASUK PEMASANGAN DAN ELECTRODA KG 1.000
Besi Plat kg 1.050 5,000.00
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah

27/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

9 PEK BESI TRACK STANK DIA 16 MM PEMASANGAN DAN ELECTRODA KG 1.000


Besi Track stank (besi beton) O 16 mm kg 1.050 11,400.00
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah
10 PEK BESI IKATAN ANGIN DIA 12 MM PEMASANGAN DAN ELECTRODA KG 1.000
Besi Ikatan angin (besi beton) O 12 mm kg 1.050 11,400.00
Pemasangan dan febrikasi besi siku kg 1.000 19,609.12
Jumlah
11 FEBRIKASI DAN PASANG PIPA BESI HOLLOW 20.20 M1 1.000
Besi Hollow 20x20x2 mm m1 1.050 15,000.00
Pemasangan dan febrikasi m1 0.250 108,252.87
Jumlah
12 FEBRIKASI DAN PASANG PIPA BESI HOLLOW 20.40 M1 1.000
Besi Hollow 20x40X2 MM m1 1.050 8,150.00
Pemasangan dan febrikasi m1 0.500 108,252.87
Jumlah
13 FEBRIKASI DAN PASANG PIPA BESI HOLLOW 40.40 M1 1.000
Besi Hollow 40x40X2,3 MM m1 1.050 10,766.67
Pemasangan dan febrikasi m1 0.900 108,252.87
Jumlah

28/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

XII PEKERJAAN PLAFOND


1 Pas. Plafond Kalsiboard 6 mm Rangka Hollow m2 1.000
Besi Hollow 40/40 m 0.750 108,732.58
Besi Hollow 20/20 m 2.000 42,813.22
Kalsiboard EG Uk. 240x120x6 mm lbr 0.382 75,000.00
Paku Asbes Skrup 4 bh 4.000 67.63
Pekerja OH 0.150 161,636.00
Tukang Kayu OH 0.250 160,500.00
Kepala Tukang Kayu OH 0.025 177,600.00
Mandor OH 0.075 189,700.00
Jumlah
2 Pas. Plafond Gypsumboard 9 mm Rangka Hollow m2 1.000
Besi Hollow 40/40 m 0.750 108,732.58
Besi Hollow 20/40 m 2.000 62,683.93
Gypsum Board Uk. 240x120x9 mm lbr 0.382 65,000.00
Paku Asbes Skrup 4 bh 4.000 67.63
Pekerja OH 0.150 161,636.00
Tukang Kayu OH 0.250 160,500.00
Kepala Tukang Kayu OH 0.025 177,600.00
Mandor OH 0.075 189,700.00
Jumlah
3 Pemasangan List Gypsum m1 1.000
Lis Gypsum m 1.050 15,000.00
Sekrup bh 4.000 67.63
Pekerja OH 0.050 161,636.00
Tukang Kayu OH 0.050 160,500.00
Kepala Tukang Kayu OH 0.005 177,600.00
Mandor OH 0.003 189,700.00
Jumlah
XIII PEKERJAAN CAT
1 Pengerjaan Cat Dinding Interior m2 1.000
Alkalin kg 0.120 163,900.00
Cat Tembok Interior klg 0.360 56,976.00
Pekerja OH 0.028 161,636.00
Tukang cat OH 0.042 160,500.00
Kepala Tukang cat OH 0.004 177,600.00
Mandor OH 0.003 189,700.00
Jumlah

29/76
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)

2 Pengerjaan Cat Dinding Exterior m2 1.000


Alkalin kg 0.120 163,900.00
Cat Tembok Exterior klg 0.360 42,644.00
Pekerja OH 0.028 161,636.00
Tukang cat OH 0.042 160,500.00
Kepala Tukang cat OH 0.004 177,600.00
Mandor OH 0.003 189,700.00
Jumlah
3 Pengerjaan Cat besi m2 1.000
Cat besi kg 0.100 59,500.00
Kuas bh 0.010 10,000.00
Pekerja OH 0.020 161,636.00
Tukang cat OH 0.200 160,500.00
Kepala Tukang cat OH 0.004 177,600.00
Mandor OH 0.003 189,700.00
Jumlah
4 Pengerjaan Cat Kayu m2 1.000
Cat Kayu kg 0.100 70,600.00
Kuas bh 0.010 10,000.00
Pekerja OH 0.020 161,636.00
Tukang cat OH 0.200 160,500.00
Kepala Tukang cat OH 0.004 177,600.00
Mandor OH 0.003 189,700.00
Jumlah
5 Pengerjaan Cat Plafond m2 1.000
Alkalin kg 0.120 163,900.00
Cat Tembok Exterior klg 0.360 42,644.00
Pekerja OH 0.028 161,636.00
Tukang cat OH 0.042 160,500.00
Kepala Tukang cat OH 0.004 177,600.00
Mandor OH 0.003 189,700.00
Jumlah
XV PEKERJAAN BONGKARAN
1 Pek. Bongkar finishing lantai m2 1.000
Pekerja OH 0.100 161,636.00
Mandor OH 0.005 189,700.00
Jumlah
XVI PEKERJAAN SANITASI
1 Memasang 1 buah Kloset duduk ls 1.000
Kloset duduk bh 1.000 1,311,000.00
perlengkapan ls 0.060 1,311,000.00
TOILET SPRAYER unit 1.000 85,890.00
Pekerja OH 3.300 161,636.00
Tukang Batu OH 1.100 160,500.00
Kepala Tukang OH 0.010 177,600.00
Mandor OH 0.160 189,700.00
Jumlah
2 KITCHEN SINK STAINLESS ls 1.000
KITCHEN SINK STAINLESS bh 1.000 705,100.00
water drain bh 1.000 50,000.00
Pekerja OH 0.030 161,636.00
Tukang Batu OH 0.300 160,500.00
Kepala Tukang OH 0.030 177,600.00
Mandor OH 0.015 189,700.00
Jumlah
3 bak kamar mandi 0,24 M3 ls 1.000
Bak fiber glass 0,4mx0,6m bh 1.000 800,000.00
perlengkapan ls 0.120 800,000.00
Pekerja OH 0.300 161,636.00
Tukang Batu OH 0.450 160,500.00
Kepala Tukang OH 0.045 177,600.00
Mandor OH 0.015 189,700.00
Jumlah

30/76
A HARGA SATUAN PEKERJAAN
BAHARUAN & PENYESUAIAN 2019

Jumlah
(Rp)

16,163.60
9,485.00
25,648.60

19,360.80
382.00
49,000.00
16,163.60
16,050.00
1,776.00
853.65
103,586.05

121,227.00
4,742.50
125,969.50

199,650.00
48,490.80
18,970.00
267,110.80

133,100.00
100,980.00
48,490.80
18,970.00
301,540.80

104,830.00
100,980.00
48,490.80
18,970.00
273,270.80

309,113.20
48,490.80
18,970.00
376,574.00

31/76
Jumlah
(Rp)

247,800.00
822.60
40,409.00
4,742.50
293,774.10

16,486.87
3,604.30
20,091.17

32,327.20
7,588.00
39,915.20

337,214.40
54,450.00
126,076.08
62,595.00
6,926.40
7,398.30
594,660.18

309,113.20
231,200.00
131,648.00
242,454.00
120,375.00
13,320.00
14,227.50
1,062,337.70

161,000.00
20,580.71
9,680.00
48,490.80
16,050.00
1,776.00
2,845.50
260,423.01
2,170,191.78

11,410.00
32,327.20
7,588.00
51,325.20

53,333.33
4,250.00
48,490.80
16,050.00
1,776.00
2,845.50
126,745.63
1,055,791.13

100,900.00
960.00
7,260.00
48,490.80
16,163.60
1,605.00
2,664.00
178,043.40

448,000.00
329.80
10,890.00
48,490.80

32/76
Jumlah
(Rp)
16,050.00
1,776.00
2,845.50
528,382.10

264.35
5,566.00
48,490.80
24,075.00
2,664.00
2,845.50
83,905.65

176.29
6,292.00
48,490.80
24,075.00
2,664.00
2,845.50
84,543.59

17.00
3,146.00
12,930.88
6,420.00
7,104.00
758.80
30,376.68

110.50
32,327.20
16,050.00
1,776.00
1,897.00
52,160.70

329,406.00
182,917.28
103,019.30
10,750.00
193,963.20
32,100.00
3,552.00
11,382.00
867,089.78

395,287.20
169,610.63
101,513.56
10,750.00
266,699.40
44,137.50
4,972.80
15,745.10
1,008,716.19

531,346.20
142,997.33
105,039.66
10,750.00
266,699.40
44,137.50
4,972.80
15,745.10
1,121,687.99

591,498.60
139,490.40
102,428.44

33/76
Jumlah
(Rp)
10,750.00
266,699.40
44,137.50
4,972.80
15,745.10
1,175,722.24

11,970.00
225.00
1,131.45
1,123.50
124.32
75.88
14,650.15

11,760.00
311.85
1,131.45
1,123.50
124.32
75.88
14,527.00

154,000.00
3,226.80
5,730.00
280.00
163,236.80
84,050.72
41,730.00
4,617.60
4,932.20
135,330.52
81,618.40
135,330.52
216,948.92

34/76
Jumlah
(Rp)

38,398.92
7,640.00
560.00
75,000.00
67,760.00
290,400.00
479,758.92
106,679.76
52,965.00
5,860.80
6,260.10
171,765.66
239,879.46
171,765.66
411,645.12

1,121,687.99
159,031.84
429,553.92
1,710,273.75

1,121,687.99
587,931.57
2,335,006.97
4,044,626.53

1,121,687.99
559,728.21
3,296,147.00
4,977,563.20

1,121,687.99
468,609.67
2,567,077.20
4,157,374.86

1,121,687.99
1,292,903.18
2,414,591.16

1,121,687.99
1,084,744.60
714,620.58
1,305,956.41
4,227,009.58

1,121,687.99
1,444,879.81
936,901.24
1,269,679.84
4,773,148.87

1,121,687.99
1,444,879.81
860,463.38
812,595.10
4,239,626.27

1,121,687.99
2,169,489.20
5,157,950.07
8,449,127.25

1,121,687.99
2,892,652.27
4,794,314.19
8,808,654.44

1,121,687.99
2,169,489.20
3,846,452.33
35/76
Jumlah
(Rp)
7,137,629.51

36/76
Jumlah
(Rp)

1,121,687.99
2,744,300.80
2,498,644.34
-
6,364,633.13

37/76
Jumlah
(Rp)

1,121,687.99
3,430,376.00
2,208,104.30
-
6,760,168.29

1,121,687.99
4,116,451.20
1,917,564.26
-
7,155,703.45

1,121,687.99
376,376.54
87,483.62
1,585,548.14

1,121,687.99
650,846.76
-
1,479,665.35
3,252,200.10

1,121,687.99
5,488,601.60
-
1,772,668.39
8,382,957.98

1,121,687.99
2,744,300.80
-
1,772,668.39
5,638,657.18

38/76
Jumlah
(Rp)

71,000.00
24,245.40
12,037.50
1,420.80
1,517.60
110,221.30

13,348.10
38,800.00
4,356.00
60,738.00
145,472.40
72,225.00
7,992.00
8,536.50
351,468.00

13,348.10
30,000.00
10,890.00
65,059.47
113,145.20
56,175.00
6,216.00
6,639.50
301,473.27

65,100.00
19,346.00
10,890.00
32,400.00
113,145.20
56,175.00
6,216.00
6,639.50
309,911.70

39/76
Jumlah
(Rp)

16,163.60
948.50
17,112.10

24,000.00
14,600.00
2,400.00
19,396.32
1,926.00
1,065.60
63,387.92

101,115.00
312.50
7,800.00
24,245.40
40,125.00
3,907.20
4,742.50
182,247.60

101,115.00
312.50
7,800.00
24,245.40
40,125.00
3,907.20
4,742.50
182,247.60

58,695.00
4,000.00
1,250.00
24,245.40
40,125.00
3,907.20
4,742.50
136,965.10

40/76
Jumlah
(Rp)

96,915.00
4,000.00
1,250.00
24,245.40
40,125.00
3,907.20
4,742.50
175,185.10

58,695.00
4,000.00
1,250.00
24,245.40
40,125.00
3,907.20
4,742.50
136,965.10

25,200.00
1,250.00
24,245.40
24,075.00
1,776.00
3,794.00
80,340.40

93,345.00
2,424.54
24,075.00
2,664.00
1,422.75
123,931.29

41/76
Jumlah
(Rp)

67,760.00
4,040.90
12,037.50
1,332.00
246.61
85,417.01

100,870.00
4,040.90
12,037.50
1,332.00
246.61
118,527.01

42/76
Jumlah
(Rp)

816,469.25
1,386,086.81
301,318.37
82,854.50
70,449.48
244,900.00
97,400.00
156,400.00
3,155,878.41

43/76
Jumlah
(Rp)

1,396,016.62
691,673.76
148,907.34
117,875.47
100,227.09
78,480.00
18,589.69
409,736.04
244,900.00
97,400.00
156,400.00
3,460,206.00

913,060.48
675,237.94
255,770.25
84,562.84
72,265.18
244,900.00
97,400.00
156,400.00
2,499,596.69

776,374.78
860,140.83
106,771.26
90,785.41
166,800.00
97,400.00
174,700.00
2,272,972.27

1,093,485.60
794,397.58
145,294.33
61,770.39
166,800.00
48,700.00
174,700.00
2,485,147.91

1,093,485.60
794,397.58
201,614.44
61,770.39
166,800.00
48,700.00
174,700.00
2,541,468.02

324,000.00
169,717.80
168,525.00
17,760.00
948.50
680,951.30

2,943,298.74
816,312.00
472,178.21
47,970.00
91,600.00
108,200.00
4,479,558.95

3,025,310.16
838,226.41
485,810.66
43,095.00
91,600.00
108,200.00
44/76
Jumlah
(Rp)
4,592,242.23

45/76
Jumlah
(Rp)

2,943,298.74
816,312.00
1,156,901.76
232,990.83
18,330.00
91,600.00
108,200.00
5,367,633.32

3,025,310.16
838,226.41
1,214,746.85
249,101.89
22,035.00
91,600.00
108,200.00
5,549,220.31

1,020,586.56
712,218.52
-
149,344.67
10,140.00
45,800.00
54,100.00
1,992,189.75

5,795,473.68
1,586,055.86
1,614,842.04
821,664.45
74,295.00
91,600.00
162,300.00
10,146,231.03

4,829,561.40
1,073,806.38
1,349,718.72
669,228.97
51,870.00
91,600.00
108,200.00
8,173,985.47

364,495.20
208,186.95
136,324.42
2,730.00
91,600.00
54,100.00
857,436.57

46/76
Jumlah
(Rp)

13,640.00
2,940.00
224.00
74,800.00
379.40
3,210.00
355.20
323.27
95,871.87

204.60
44.10
3.36
92,400.00
379.40
9,630.00
1,065.60
4,525.81
108,252.87

19,174.37
94.85
160.50
17.76
161.64
19,609.12

29,665.00
125,000.00
175,000.00
7,400.00
40,880.00
14,600.00
94.85
28,248.00
20,779.20
39,924.09
144,526.14

6,107.50
19,609.12
25,716.62

5,250.00
19,609.12
24,859.12

7,770.00
19,609.12
27,379.12

5,250.00
19,609.12
24,859.12

47/76
Jumlah
(Rp)

11,970.00
19,609.12
31,579.12

11,970.00
19,609.12
31,579.12

15,750.00
27,063.22
42,813.22

8,557.50
54,126.43
62,683.93

11,305.00
97,427.58
108,732.58

48/76
Jumlah
(Rp)

81,549.44
85,626.43
28,642.50
270.50
24,245.40
40,125.00
4,440.00
14,227.50
279,126.77

81,549.44
125,367.87
24,823.50
270.50
24,245.40
40,125.00
4,440.00
14,227.50
315,049.20

15,750.00
270.50
8,081.80
8,025.00
888.00
569.10
33,584.40

19,668.00
20,511.36
4,525.81
6,741.00
745.92
474.25
52,666.34

49/76
Jumlah
(Rp)

19,668.00
15,351.84
4,525.81
6,741.00
745.92
474.25
47,506.82

5,950.00
100.00
3,232.72
32,100.00
745.92
474.25
42,602.89

7,060.00
100.00
3,232.72
32,100.00
745.92
474.25
43,712.89

19,668.00
15,351.84
4,525.81
6,741.00
745.92
474.25
47,506.82

16,163.60
948.50
17,112.10

1,311,000.00
78,660.00
85,890.00
533,398.80
176,550.00
1,776.00
30,352.00
2,217,626.80

705,100.00
50,000.00
4,849.08
48,150.00
5,328.00
2,845.50
816,272.58

800,000.00
96,000.00
48,490.80
72,225.00
7,992.00
2,845.50
1,027,553.30

50/76
ANALISA HARGA SATUAN PEKERJAAN MEKANIKAL DAN ELEKTRICAL
DATA PEMBAHARUAN & PENYESUAIAN 2019-2020

A. PEKERJAAN ELECTRICAL
Harga Satuan
No Uraian Pekerjaan Vol. Satuan
(Rp)
1 2 3 4 5
1 Inst. Penerangan, NYM 3x2,5 mm² (o) PVC HI dia. 20mm
a Kabel NYM 3 x 2.5 mm2 9.0 m 11,400
b Pipa Conduit 20 HI 9.0 m 4,567
c Klem Pipa Conduit 10.0 bh 2,053
d T.Doost 2.0 bh 2,200
e Socket Conduit 3.0 bh 6,560
f Fisher 21.0 bh 1,000
g Lasdop 3.0 bh 500
J Upah Instalasi Kabel + Pipa 1.0 ls 131,200
Jumlah Total
2 Inst. Stop kontak, NYM 3x2,5 mm² (o) PVC HI dia. 20mm
a Kabel NYM 3 x 2.5 mm2 10.0 m 11,400
b Pipa Conduit 20 HI 10.0 m 4,567
c Klem Pipa Conduit 11.0 bh 2,053
d T.Doost 1.0 bh 2,200
e Socket Conduit 3.0 bh 6,560
f Fisher 21.0 bh 1,000
g Lasdop 3.0 bh 500
J Upah Instalasi Kabel + Pipa 1.0 ls 131,200
TOTAL
3 Instalasi antar tiang lampu taman kabel NYFGBY4x2,5mm2
a Kabel NFGBY 4 x 2.5 mm2 20.0 m' 33,800
g Lasdop 4.0 bh 500
J Upah gelar kabel 1.0 ls 3,000
TOTAL Rp.
4 Galian Kabel lewat Taman/Paving & urug kembali
a Galian & Uruk kembali 1.0 m' 23,400
b Batu Bata 11.0 bh 2,300
c Pasir 0.0 m3 242,000
TOTAL
5 Lampu SL 50 WATT
a Lampu SL 50 WATT 1.0 bh 110,500
b Upah Pasang 0.1 OH 131,200
Jumlah Total
6 Lampu SL 18 WATT
a Lampu SL 18 WATT 1.0 bh 58,500
b Upah Pasang 0.1 OH 131,200
Jumlah Total
7 Lampu SL 11 WATT
a Lampu SL 11 WATT 1.0 bh 30,000
b Upah Pasang 0.1 OH 131,200
Jumlah Total
8 Exhause Fan Toilet 100 cfm /50 Watt
a Exhause Fan Toilet 100 cfm /50 Watt 1.0 bh 585,000
b Upah Pasang 0.2 OH 131,200
Jumlah Total
9 Lampu Down Light 15 Watt
a Lampu Down Light 15 watt 1.0 bh 91,680
b Upah Pasang 0.1 OH 131,200
Jumlah Total

51/76
10 Lampu Taman SL 1 x18 watt (termasuk tiang lampu dan pondasi)
a Lampu SL 18 WATT 1.0 bh 58,500
Tiang + Pondasi 1.0 ls 1,040,000
b Upah Pasang 0.1 OH 131,200
Jumlah Total
11 Fiting lampu E 27
a Fiting lampu E 27 1.0 bh 10,000
b Upah Pasang 0.1 OH 131,200
Jumlah Total
12 Stop Kontak 1 Phase, 200 VA
a Stop Kontak 1 Phase, 200 VA 1.0 bh 13,000
b Upah Pasang 0.1 OH 131,200
Jumlah Total
13 Saklar Tunggal
a Saklar Tunggal 1.0 bh 32,500
b Upah Pasang 0.1 OH 131,200
Jumlah Total
14 Saklar Ganda
a Saklar Ganda 1.0 bh 58,500
b Upah Pasang 0.1 OH 131,200
Jumlah Total
15 '-Kabel NYFGBY 4 X 25mm2 BC 25mm2
a Kabel NYFGBY 4 X 50mm2 BC 25mm2 1.0 m' 84,500
g Spatu Kabel dia.25 4.0 bh 8,450
J Upah Pasang 0.0 ls 131,200
TOTAL Rp.
15 '-Kabel NYY 4 X 4mm2 + BC 4mm2
a Kabel NYY 4 X 4mm2 + BC 4mm2 1.0 m' 58,500
g Spatu Kabel dia.50 4.0 bh 8,450
J Upah Pasang 0.0 ls 131,200
TOTAL Rp.
15 '-Kabel NYY 4 X 10mm2 + BC 10mm2
a '-Kabel NYY 4 X 10mm2 + BC 10mm2 1.0 m' 71,500
g Spatu Kabel dia.50 4.0 bh 8,450
J Upah Pasang 0.0 ls 131,200
TOTAL Rp.
16 MCB 1 Phase 10 A/4,5 KA
a MCB 1 Phase 10 A/4,5 KA 1.0 bh 122,600
b Upah Pasang 0.1 OH 131,200
TOTAL Rp.
17 Grounding
a Grounding System 1.0 titik 2,000,000
Upah Pasang 0.1 OH 131,200
TOTAL Rp.
18 pompa 230 watt
a pompa 230 watt 1.0 unit 931,868
b Upah Pasang 0.1 OH 131,200
TOTAL Rp.
B. PEKERJAAN MEKANIKAL
Harga Satuan
No Uraian Pekerjaan Vol. Satuan
(Rp)
1 2 3 4 5
PIPA PVC Class AW
1 Pipa Ø 100 mm / 4” (PVC "AW" )
Pipa Ø 100 mm / 4” (PVC "AW" ) 1.00 M 34,675.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 118,080.00
Sub Total
2 Pipa Ø 80 mm / 3" (PVC "AW" )
Pipa Ø 80 mm / 3" (PVC "AW" ) 1.00 M 53,950.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 118,080.00
Sub Total

52/76
3 Pipa Ø 65 mm / 2 ½” (PVC "AW" )
Pipa Ø 65 mm / 2 ½” (PVC "AW" ) 1.00 M 35,360.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 104,960.00
Sub Total
4 pipa Ø 50 mm / 2” (PVC "AW" )
pipa Ø 50 mm / 2” (PVC "AW" ) 1.00 M 17,925.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
5 Ø 50 mm / 2” PIPA PVC "D" ( pipa Ventilasi )
Pipa PVC 1.00 M 17,925.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
6 Floor drain Ø 50
Floor drain Ø 50 1.00 M 195,000.00
Material Bantu 1.00 ls 2,080.50
Upah Pasang 1.00 M 52,480.00
Sub Total
7 kran
kran air 1.00 unit 93,600.00
Upah Pasang 1.00 unit 52,480.00
Sub Total
8 Clean Out Ø 50
Clean Out Ø 50 1.00 M 195,000.00
Material Bantu 1.00 ls 2,080.50
Upah Pasang 1.00 M 52,480.00
Sub Total
9 Clean Out Ø 100
Clean Out Ø 100 1.00 M 48,555.56
Material Bantu 1.00 ls 2,080.50
Upah Pasang 1.00 M 52,480.00
Sub Total
PIPA PPR PN - 10
10 Pipa Ø 40 mm / 1½
Pipa Ø 40 mm / 1½ 1.00 M 6,325.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
11 Pipa Ø 32 mm / 1¼"
Pipa Ø 32 mm / 1¼" 1.00 M 4,975.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total

53/76
12 Pipa.Ø 25 mm / 1"
Pipa.Ø 25 mm / 1" 1.00 M 4,600.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
13 Pipa Ø 20 mm / 1/4"
Pipa Ø 20 mm / 1/4" 1.00 M 3,425.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
14 Pipa 3/4"
Pipa 3/4" 1.00 M 4,975.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
15 Pipa Ø 15 mm / 1/2"
Pipa Ø 15 mm / 1/2" 1.00 M 2,568.75
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total
16 Memasang Talang U
Pekerja 0.1500 OH 161,636.00
Tukang 0.3000 OH 160,500.00
Kepala tukang 0.0300 OH 177,600.00
Mandor 0.0080 OH 189,700.00
seng plat 1.05 m' 31,600.00
paku 1 cm - 2,5 cm 0.01 kg 19,100.00
besi strip 0.5 kg 14,133.02
Sub Total
17 pipa vent 50mm
pipa vent 50mm 1.00 M 6,875.00
Fitting 1.00 ls 15,875.00
Support 1.00 ls 6,875.00
Material Bantu 1.00 ls 2,080.50
Alat Kerja 1.0 ls 14,600.00
Upah Pasang 1.00 M 52,480.00
Sub Total

54/76
KTRICAL
19-2020

Harga
(Rp)
6
38,001
102,600
41,100
20,530
4,400
19,680
21,000
1,500
131,200
38,001
357,830
114,000
45,667
22,583
2,200
19,680
21,000
1,500
131,200
357,830
681,000
676,000
2,000
3,000
681,000
51,120
23,400
25,300
2,420
51,120
117,060
110,500
6,560
117,060
65,060
58,500
6,560
65,060
36,560
30,000
6,560
36,560
611,240
585,000
26,240
611,240
98,240
91,680
6,560
98,240

55/76
1,105,060
58,500
1,040,000
6,560
1,105,060
16,560
10,000
6,560
16,560
19,560
13,000
6,560
19,560
39,060
32,500
6,560
39,060
65,060
58,500
6,560
65,060
123,548
84,500
33,800
5,248
123,548
97,548
58,500
33,800
5,248
97,548
110,548
71,500
33,800
5,248
110,548

122,600
6,560
129,160

2,000,000
6,560
2,006,560

931,868
6,560
938,428

Harga
(Rp)
6

192,186
34,675
15,875
6,875
2,081
14,600
118,080
192,186
211,461
53,950
15,875
6,875
2,081
14,600
118,080
211,461

56/76
179,751
35,360
15,875
6,875
2,081
14,600
104,960
179,751
109,836
17,925
15,875
6,875
2,081
14,600
52,480
109,836
109,836
17,925
15,875
6,875
2,081
14,600
52,480
109,836
249,561
195,000
2,081
52,480
249,561
146,080
93,600
52,480
146,080
249,561
195,000
2,081
52,480
249,561
103,116
48,556
2,081
52,480
103,116

98,236
6,325
15,875
6,875
2,081
14,600
52,480
98,236
96,886
4,975
15,875
6,875
2,081
14,600
52,480
96,886

57/76
96,511
4,600
15,875
6,875
2,081
14,600
52,480
96,511
95,336
3,425
15,875
6,875
2,081
14,600
52,480
95,336
96,886
4,975
15,875
6,875
2,081
14,600
52,480
96,886
94,479
2,569
15,875
6,875
2,081
14,600
52,480
94,479

24,245
48,150
5,328
1,518
14,840
191
7,067
101,338
98,786
6,875
15,875
6,875
2,081
14,600
52,480
98,786

58/76
DAFTAR HARGA SATUAN BAHAN DAN UPAH
Update Periode 2019-2020 Region 1
Region 2
Region 3
Region 4
Kode Region I ###
Harga
No Uraian Pekerjaan Satuan
(Rp) Sumber/Referensi

1 2 3 4 5
Elektrikal

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


1 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYFGBY 4 X 50mm2 BC 25mm2 84,500.00 BARANG/JASA TAHUN ANGGARAN 2026

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


2 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYY 4 X 6mm2 + BC 6mm2 54,600.00 BARANG/JASA TAHUN ANGGARAN 2027

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


3 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYM 3 x 2.5 mm2 11,400.00 BARANG/JASA TAHUN ANGGARAN 2028

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


4 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYM 2 x 2,5 mm2 10,400.00 BARANG/JASA TAHUN ANGGARAN 2029

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


5 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NFGBY 4 x 2.5 mm2 33,800.00 BARANG/JASA TAHUN ANGGARAN 2030

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


6 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYY 4 X 4mm2 + BC 4mm2 58,500.00 BARANG/JASA TAHUN ANGGARAN 2031

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


7 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel NYY 4 X 10mm2 + BC 10mm2 71,500.00 BARANG/JASA TAHUN ANGGARAN 2032

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


8 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel try lantai 1 ukuran 100mm x 300mm 250,000.00 BARANG/JASA TAHUN ANGGARAN 2033

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


9 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Kabel try Riser ukuran 100mm x 300mm 250,000.00 BARANG/JASA TAHUN ANGGARAN 2034

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


10 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCCB 3 Phase 160 A36KA 450,000.00 BARANG/JASA TAHUN ANGGARAN 2035

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


11 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCCB 3 Phase 40 A/18KA 550,000.00 BARANG/JASA TAHUN ANGGARAN 2036

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


12 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCCB 3 Phase 30 A/18KA 550,000.00 BARANG/JASA TAHUN ANGGARAN 2037

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


13 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCCB 3 Phase 20 A/18KA 550,000.00 BARANG/JASA TAHUN ANGGARAN 2038

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


14 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCB 1 Phase 16 A/4,5 KA 65,000.00 BARANG/JASA TAHUN ANGGARAN 2039

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


15 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCB 1 Phase 10 A/4,5 KA 122,600.00 BARANG/JASA TAHUN ANGGARAN 2040

59/76
KEPUTUSAN WALI KOTA BANDUNG NOMOR :
16 unit 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
MCB 3 Phase 40 A/18 KA 350,000.00 BARANG/JASA TAHUN ANGGARAN 2041

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


17 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Amper meter 250,000.00 BARANG/JASA TAHUN ANGGARAN 2042

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


18 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Volt meter 250,000.00 BARANG/JASA TAHUN ANGGARAN 2043

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


19 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
VSS 250,000.00 BARANG/JASA TAHUN ANGGARAN 2044

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


20 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Fuse 2 A 25,000.00 BARANG/JASA TAHUN ANGGARAN 2045

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


21 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu Indikator 75,000.00 BARANG/JASA TAHUN ANGGARAN 2046

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


22 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Cu Bar 350,000.00 BARANG/JASA TAHUN ANGGARAN 2047

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


23 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Box Panel LVMDP+ Wiring 1,250,000.00 BARANG/JASA TAHUN ANGGARAN 2048

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


24 unit 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Juction Box Telepon 10 pair 205,000.00 BARANG/JASA TAHUN ANGGARAN 2049

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


25 unit 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
PABX 1 Line 10 Extantion 6,500,000.00 BARANG/JASA TAHUN ANGGARAN 2050

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


26 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Outlet Telepon 65,000.00 BARANG/JASA TAHUN ANGGARAN 2051

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


27 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Pesawat telephone 250,000.00 BARANG/JASA TAHUN ANGGARAN 2052

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


28 titik 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Instalasi outlet telepon dengan kabel ITC 2 x 2 x d.0,6 mm 265,000.00 BARANG/JASA TAHUN ANGGARAN 2053
29 dalam conduit PVC HI dia. 20 mm

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


30 ttk 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Instalasi AC 1Phase/220 Volt 275,000.00 BARANG/JASA TAHUN ANGGARAN 2055

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


31 ttk 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Instalasi pipa drain AC.pipa PVC Ø 25mm2 / ¾ 15,000.00 BARANG/JASA TAHUN ANGGARAN 2056

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


32 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Stop Kontak 1 Phase, 200 VA 45,500.00 BARANG/JASA TAHUN ANGGARAN 2057
0
KEPUTUSAN WALI KOTA BANDUNG NOMOR :
33 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Saklar Tungg 32,500.00 BARANG/JASA TAHUN ANGGARAN 2058

60/76
KEPUTUSAN WALI KOTA BANDUNG NOMOR :
34 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Saklar Ganda 58,500.00 BARANG/JASA TAHUN ANGGARAN 2059

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


35 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu SL 50 WATT 110,500.00 BARANG/JASA TAHUN ANGGARAN 2060

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


36 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu SL 18 WATT 58,500.00 BARANG/JASA TAHUN ANGGARAN 2061

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


37 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu SL 11 WATT 45,500.00 BARANG/JASA TAHUN ANGGARAN 2062

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


38 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu Down Light 15 Watt 91,680.00 BARANG/JASA TAHUN ANGGARAN 2063

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


39 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Lampu Taman SL 1 x18 watt (termasuk tiang lampu dan pondasi) 2,730,000.00 BARANG/JASA TAHUN ANGGARAN 2064

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


40 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Fiting lampu E 27 17,000.00 BARANG/JASA TAHUN ANGGARAN 2065

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


41 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Exhause Fan Toilet 100 cfm /50 Watt 585,000.00 BARANG/JASA TAHUN ANGGARAN 2066

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


42 Unit 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
TB-SS 205,000.00 BARANG/JASA TAHUN ANGGARAN 2067

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


43 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Power Amplifier 160 Watt 12,500,000.00 BARANG/JASA TAHUN ANGGARAN 2068

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


44 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Paging Mic. Call 8,500,000.00 BARANG/JASA TAHUN ANGGARAN 2069

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


45 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
DVD/CD/MP3/Radio Tuner 2,500,000.00 BARANG/JASA TAHUN ANGGARAN 2070

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


46 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Horn Speaker 15 Watt 350,000.00 BARANG/JASA TAHUN ANGGARAN 2071

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


47 ttk 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Instalasi Horn Speaker Kabel NYMHY 2 x 1.5 mm² 265,000.00 BARANG/JASA TAHUN ANGGARAN 2072
dalam conduit PVC HI dia. 20 mm ###
Penyambungan ###

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


1 ls 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Pemasangan Listrik Dengan Daya 79 kVA 295,500,000.00 BARANG/JASA TAHUN ANGGARAN 2075

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


2 ls 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Penyambungan Telepon (dengan 3 sambungan ) 6,500,000.00 BARANG/JASA TAHUN ANGGARAN 2076

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


3 ls 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Pemasangan /Sambungan PDAM Dia.Pipa 2" 12,000,000.00 BARANG/JASA TAHUN ANGGARAN 2077

61/76
KEPUTUSAN WALI KOTA BANDUNG NOMOR :
027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Material Bantu BARANG/JASA TAHUN ANGGARAN 2078

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


1 m' 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Pipa Conduit 20 HI 4,566.67 BARANG/JASA TAHUN ANGGARAN 2079

KEPUTUSAN WALI KOTA BANDUNG NOMOR :


2 bh 027/Kep. 806-BPKA/2019 TENTANG
STANDARISASI HARGA TERTINGGI SATUAN
Klem Pipa Conduit 2,053.00 BARANG/JASA TAHUN ANGGARAN 2080

https://www.google.com/amp/s/
3 bh m.tokopedia.com/amp/s3-satriasecure/
hitam-t-dos-dus-doos-terminal-listrik-
T.Doost 2,200.00 cabang-3-t-dost-tdos-t-dus

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
4 bh TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Socket Conduit 6,560.00 TAHUN ANGGARAN 2076

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
5 bh TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Fisher 1,000.00 TAHUN ANGGARAN 2076

https://m.tokopedia.com/suksesabaditlo/
lasdop-4mm-kuning?
whid=2465830&xClientId=amp-
6 bh
m8AlP5UaxRr4G25uBLUiSMcqiFbgPD
QQH3AApJ_7tIpqUL5cbE-8PgY0x52Jo-
8z&cid=amp-
m8AlP5UaxRr4G25uBLUiSMcqiFbgPD
QQH3AApJ_7tIpqUL5cbE-8PgY0x52Jo-
Lasdop 500.00 8z&amp=true

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
7 bh TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Batu Bata 2,300.00 TAHUN ANGGARAN 2076

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
8 m3 TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pasir 242,000.00 TAHUN ANGGARAN 2077

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
9 bh TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Spatu Kabel dia.50 8,450.00 TAHUN ANGGARAN 2078
Upah ###

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
1 ls TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Upah Instalasi Kabel + Pipa 2,067,000.00 TAHUN ANGGARAN 2078

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
2 OH TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Upah Pasang 131,200.00 TAHUN ANGGARAN 2079

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
3 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Galian & Uruk kembali 23,400.00 TAHUN ANGGARAN 2080

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
4 ls TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Tiang + Pondasi 1,040,000.00 TAHUN ANGGARAN 2081
Mekanik ###
PIPA PPR PN - 10 ###

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
1 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa Ø 15 mm / 1/2" 2,568.75 TAHUN ANGGARAN 2081

62/76
KEPUTUSAN WALI KOTA BANDUNG
NOMOR : 027/Kep. 806-BPKA/2019
2 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa Ø 20 mm / 1/4" 3,425.00 TAHUN ANGGARAN 2082

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
3 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa.Ø 25 mm / 1" 4,600.00 TAHUN ANGGARAN 2083

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
4 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa Ø 32 mm / 3/4" 4,975.00 TAHUN ANGGARAN 2084

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
5 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa Ø 40 mm / 1½ 6,325.00 TAHUN ANGGARAN 2085
PIPA PVC Class AW ###

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
6 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pipa Ø 100 mm / 4” (PVC "AW" ) 34,675.00 TAHUN ANGGARAN 2085

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
7 m' TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
pipa Ø 50 mm / 2” (PVC "AW" ) 17,925.00 TAHUN ANGGARAN 2088

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
8 bh TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Clean Out Ø 100 48,555.56 TAHUN ANGGARAN 2093

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
9 ls TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Fitting 15,875.00 TAHUN ANGGARAN 2095

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
10 ls TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Support 6,875.00 TAHUN ANGGARAN 2096

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
11 ls TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Alat Kerja 14,600.00 TAHUN ANGGARAN 2097

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
12 M TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Upah Pasang 131,200.00 TAHUN ANGGARAN 2098

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
13 unit TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Pompa Air Sanyo c/w assesoris 931,868.00 TAHUN ANGGARAN 2105

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
14 unit TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Conecting Sleeve 250,000.00 TAHUN ANGGARAN 2109

KEPUTUSAN WALI KOTA BANDUNG


NOMOR : 027/Kep. 806-BPKA/2019
15 ttk TENTANG STANDARISASI HARGA
TERTINGGI SATUAN BARANG/JASA
Grounding System 2,000,000.00 TAHUN ANGGARAN 2112

63/76
pondasi tapak

P
PELAT 0.7
PEDESTAL 0.15
LC 0.7
P URUG 0.7

bekisting
PELAT 0.56
PEDESTAL 0.33
0.89
besi jumlah
4d10 4
10 - 100 16
8 - 150 5

pondasi rollag
SLOOF DAN RINGBALK
SLOOF
BETON
P L T VOL
40 0.15 0.2 1.2

RINGBALK
BETON
P L T VOL
40 0.15 0.2 1.2

KOLOM
BETON
P L T VOL
0.15 0.15 41.6 0.936

LISTPLANK
KEBUTUHAN CAT
Err:509
kusen pintu

daun pintu

kusen jendela

daun jendela
L T VPOND TGAL VGAL VURUG
0.7 0.2 0.098 0.9 0.441 0.257125
0.15 0.55 0.012375
0.7 0.05 0.0245
0.7 0.1 0.049
0.183875

w/m L Total
0.61 1.5 3.66
0.61 3 29.28
0.39 1.56 2.96088
35.90088

P L T
3 1.645 0.655
LC 3 1.645 0.05
URUG 3 1.645 0.1
SIRTU 3 0.945 0.2
ROLLAG 1 0.25 0.25 0.6
ROLLAG 2 0.21 0.21 0.675
ROLLAG 3 0.21 0.21 0.425

LUAS T
48.258 0.1

TUL jumlah w/m L Total BEKIS


7D10 7 0.61 59.2 252.784 12
8-150 268 0.39 1.66 173.2874

426.0714

TUL jumlah w/m L Total BEKIS


4D10 4 0.61 59.2 144.448 12
8-150 268 0.39 1.66 173.2874

317.7354

TUL jumlah w/m L Total BEKIS


4D10 4 0.61 57.2 139.568 12
8-150 278 0.39 1.56 169.338

308.906

BETON
P L T VOL TUL jumlah w/m L
0.15 0.5 5.3 0.3975 8-150 5 0.39 5.3
2.9 1.15 0.15 0.50025 8-150 36 0.39 0.15
1.7955 8-150 9 0.39 2.95
8-150 21 0.39 1.175

LUAS CAT
Err:509 Err:509 luas sisi Err:509
UNIT 4 0.2295 2 1.836
4 0.214929 4 3.438864
4 0.09018 2 0.72144
UNIT 4 1.701 2 13.608
4 0.102202 2 0.817614
4 0.03224 2 0.25792
UNIT 4 0.313477 2 2.507818
4 0.15 6 3.6
4 0.135 4 2.16
UNIT 4 0.50904 2 4.072318
5 0.0734 6 2.201994
6 0.06682 4 1.603689
7 5 0
14.26412 22.56154
VGAL VRUG
3.232425 1.839165
0.24675
0.4935
0.567
0.0375
0.0297675
0.0187425
1.39326

VGAL TOTAL VURUG


4.825800229 4.8258
Total BEKIS
10.335 2
2.1255 3
10.3545 5
9.62325
32.43825
0.2
P L T VPOND TGAL VGAL

BATU KALI 0.6 40 0.6 9.6 0.9 21.6


AANS 0.6 40 0.2 4.8
P URUG 0.6 40 0.1 2.4
16.8
VURUG

4.8
JL1 PKL1 PK2
A 1.95 1.89 1.575
4.5 5.16 5.85 9 7.8
14.85 5.16 2.325 7.11 3.9
3.6 10.95 7.11 8.7
7.05
22.95 10.32 19.125 30.27 20.4
143.6577
3 3
3 3
3 3

22.95 20.64 38.25 53.49 20.4


233.4566

BATU ALAM
P L T
0.15 0.15 2.5 3
7.05
10.05

HOLLOW
P L T
10