RENCANA ANGGARAN BIAYA

PEKERJAAN PASANG DINDING PENAHAN TANAH (TURAP)


PROYEK PERUMAHAN PURI DELTA TIGARAKSA

HARGA SATUAN JUMLAH


NO URAIAN PEKERJAAN VOL SAT
MATERIAL UPAH KERJA MATERIAL

PANJANG TURAP = 100 M

1 PASANG TURAP BATUKALI 100 m


Luas Potongan Turap 0.65 m2
Volume Pasangan 65 m3
Batu kali 78 m3 225,500 17,589,000
Semen 156 zak 39,000 6,084,000
Pasir 49.4 m3 100,100 4,944,940
Suling-suling PVC 1 1/2" 100 btg 75,000
Injuk bal
Upah Kerja 65 m3 150,000
JUMLAH 28,617,940

2 PONDASI SETEMPAT 34 bh 2.45 m3


Semen 14.03 zak 39,000 547,055
Pasir 1.66 m3 100,100 166,630
Split 2.55 m3 262,800 669,068
Besi O 12 - 15 cm 46.75 btg 125,500 5,867,125
Kawat Beton 5.63 kg 20,000 112,608
Upah Kerja 2.45 m3 450,000
JUMLAH 7,362,486

3 KOLOM 15 X 15 34 bh 0.99 m3
Semen 5.70 zak 39,000 222,241
Pasir 0.68 m3 100,100 67,694
Split 1.03 m3 262,800 271,809
Besi O 12 24.93 btg 125,500 3,129,133
Besi O 8 - 20 cm 12.48 btg 70,500 879,699
Kawat Beton 2.29 kg 20,000 45,747
Papan Cor 11.05 lbr 23,000 254,150
Upah Kerja 0.99 m3 550,000
JUMLAH 4,870,473

4 BALOK 15 X 15 P = 100 m 2.25 m3


Semen 12.89 zak 39,000 502,808
Pasir 1.53 m3 100,100 153,153
Split 2.34 m3 262,800 614,952
Besi O 12 36.67 btg 125,500 4,601,667
Besi O 8 - 20 cm 22.90 btg 70,500 1,614,450
Kawat Beton 5.175 kg 20,000 103,500
Papan Cor 25 lbr 23,000 575,000
Upah Kerja 2.25 m3 550,000
JUMLAH 8,165,529

5 GALIAN TANAH PONDASI 32.34 m3 75,000

JASA KOMTRAKTOR 10 %

TOTAL

HARGA PER M3 65 M3

HARGA PER M1 100 M1


JUMLAH JUMLAH HARGA SATUAN JASA 10 % HARGA
UPAH KERJA HARGA PEKERJAAN KONTRAKTOR DELTA

9,750,000
9,750,000 38,367,940 590,276 649,304 610,700

1,101,600
1,101,600 8,464,086 248,944 273,838 203,166

546,975
546,975 5,417,448 122,567 134,823 97,263
1,237,500
1,237,500 9,403,029 94,030 103,433 96,547

2,425,800

64,078,303

6,407,830

70,486,133

1,084,402

704,861
DAFTAR HARGA MATERIAL BULAN NOVEMBER 2018

NO JENIS MATERIAL SAT HARGA SATUAN

1 SEMEN 40 kg zak 39,000


2 BATUKALI m3 225,500
3 PASIR m3 100,100
4 SPLIT m3 262,800
5 BESI O 12 btg 125,500
6 BESI O 10 btg 95,500
7 BESI O 8 btg 70,500
8 KAWAT BETON kg 20,000
9 PAPAN COR lbr 23,000
10 PVC 1 1/2" AW btg 75,000
11 PAKU 5 kg 25,000
12 PAKU 7 kg 25,000