3 KOLOM 15 X 15 34 bh 0.99 m3
Semen 5.70 zak 39,000 222,241
Pasir 0.68 m3 100,100 67,694
Split 1.03 m3 262,800 271,809
Besi O 12 24.93 btg 125,500 3,129,133
Besi O 8 - 20 cm 12.48 btg 70,500 879,699
Kawat Beton 2.29 kg 20,000 45,747
Papan Cor 11.05 lbr 23,000 254,150
Upah Kerja 0.99 m3 550,000
JUMLAH 4,870,473
JASA KOMTRAKTOR 10 %
TOTAL
HARGA PER M3 65 M3
9,750,000
9,750,000 38,367,940 590,276 649,304 610,700
1,101,600
1,101,600 8,464,086 248,944 273,838 203,166
546,975
546,975 5,417,448 122,567 134,823 97,263
1,237,500
1,237,500 9,403,029 94,030 103,433 96,547
2,425,800
64,078,303
6,407,830
70,486,133
1,084,402
704,861
DAFTAR HARGA MATERIAL BULAN NOVEMBER 2018