Anda di halaman 1dari 10

PEMERINTAH KABUPATEN KEPULAUAN MERANTI

KECAMATAN RANGSANG BARAT


PEMERINTAH DESA PERMAI
Jl. H. M Ali Kode Pos 28752

DESAIN RAB dan GAMBAR RENCANA

BIDANG

PELAKSANAAN PEMBANGUNAN DESA

KEGIATAN
PEMB. DRAINASE BETON

: 235 M x 0.60 M x 0.60 M


LOKASI
JLN.PELITA DSN. PELAYAR

TAHUN ANGGARAN
2020
RENCANA ANGGARAN BIAYA ( RAB )
BELANJA MODAL

PROVINSI : RIAU BIDANG 02 : PEMBANGUNAN DESA


KABUPATEN : KEPULAUAN MERANTI SUB BIDANG 02.03 : PU DAN PENATAAN RUANG
KECAMATAN : RANGSANG BARAT JENIS KEGIATAN 02.03.14 : PEMB. DRAINASE PARIT BETON
DESA : PERMAI Ukuran/Dimensi : 235 M x 0.60 M x 0.60 M
LOKASI : Jl. PELITA Dsn. PELAYAR

Harga Satuan Jumlah Total (


N0 JENIS PEKERJAAN VOLUME SAT JUMLAH ( Rp. )
( Rp.) Rp. )
1 2 3 4 5 6 7

I BAHAN
1 Papan nama Kegiatan 1.0 Unit 150,000 150,000
2 Plakat/ Prasasti 1.0 Unit 550,000 550,000
3 Pasir Cor 23.0 M³ 310,000 7,130,000
4 Pasir Urug 12.00 M³ 310,000 3,720,000
5 Kerikil/Split 2/3 cm 33.0 M³ 450,000 14,850,000
6 Kayu Cerocok Ø 8 - 10 cm 1763.0 Btg 5,000 8,815,000
7 Minyak Bekisting 56.0 Ltr 18,000 1,008,000
8 Balok Kayu Kelas III 1.1 M³ 1,650,000 1,815,000
9 Besi Ø 6 Pjg 10 m 17.0 Btg 22,000 374,000
10 Besi Ø 8 Pjg 10 m 411.0 Btg 45,000 18,495,000
11 Semen @50 Kg 280.0 Zak 83,000 23,240,000
12 Kawat Beton 30.0 Kg 25,000 750,000
13 Paku 56.0 Kg 20,000 1,120,000
14 Plastik Alas Cor 169.0 M 6,000 1,014,000
15 Playwood Tebal 9mm 20.00 Lbr 120,000 2,400,000
16 Air Adukan Beton 46.00 Drum 30,000 1,380,000
17 Pipa PVC 3/4 Inchi 10.00 Btg 18,000 180,000
Jumlah (1) 86,991,000
II ALAT
1 Ember 4.0 Bh 18,000 72,000
2 Angkong 1.0 Bh 450,000 450,000
3 Concrete Mixer 29.0 Jam 57,000 1,653,000
4 Water Pump 16.0 Jam 45,000 720,000
5 Drum 1.0 Bh 400,000 400,000
6 Cangkul 2.0 Bh 70,000 140,000
7 Sekop 2.0 Bh 65,000 130,000
Jumlah (2) 3,565,000
III UPAH
1 Pekerja Lansir 1.00 Ls 21,751,000 21,751,000
2 Tukang 26.0 HOK 120,000 3,120,000
3 Pekerja 237.0 HOK 100,000 23,700,000
4 Jasa Desain Dan RAB 1.0 LS 1,401,000 1,401,000
Jumlah (3) 49,972,000
IV. HONORARIUM
1 PKA 1.00 Keg 200,000 200,000
2 Ketua TPK 1.00 Keg 200,000 200,000
3 Sekretaris TPK 1.00 Keg 150,000 150,000
4 Anggota TPK 1.00 Keg 150,000 150,000
5 Operasional TPK 1.00 Keg 1,000,000 1,000,000
Jumlah (4) 1,700,000
TOTAL ( 1 + 2 + 3 + 4) 142,228,000
TOTAL BIAYA + Swadaya 142,228,000

Permai, Desember 2019

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


KEPALA DESA PPKD TENAGA TEKNIS

AZMAN RAAD HAMADI, AMD MARLON SUMANJUNTAK, ST


RENCANA ANGGARAN BIAYA ( RAB )
UPAH KERJA & LANSIR

PROVINSI : RIAU BIDANG 02 : PEMBANGUNAN DESA


KABUPATEN : KEPULAUAN MERANTI SUB BIDANG 02.03 : PU DAN PENATAAN RUANG
KECAMATAN : RANGSANG BARAT JENIS KEGIATAN 02.03.14 : PEMB. DRAINASE PARIT BETON
DESA : PERMAI Ukuran/Dimensi : 235 M x 0.60 M x 0.60 M
LOKASI : Jl. PELITA Dsn. PELAYAR

Harga Satuan Jumlah Total


N0 JENIS PEKERJAAN VOLUME SAT JUMLAH ( Rp. )
( Rp.) ( Rp. )

I BAHAN
1 Mobilisasi Alat 1.0 Ls 250,000 250,000
2 Demobilisasi Alat 1.0 Ls 300,000 300,000
3 Pasir Cor 23.0 M³ 160,000 3,680,000
4 Pasir Urug 12.00 M³ 160,000 1,920,000
5 Kerikil/Split 2/3 cm 33.0 M³ 200,000 6,600,000
6 Kayu Cerocok Ø 8 - 10 cm 1763.0 Btg 1,000 1,763,000
7 Balok Kayu Kelas III 1.1 M³ 150,000 165,000
8 Besi Ø 6 Pjg 10 m 17.0 Btg 4,000 68,000
9 Besi Ø 8 Pjg 10 m 411.0 Btg 6,000 2,466,000
10 Semen @50 Kg 280.0 Zak 10,000 2,800,000
11 Plastik Alas Cor 169.0 M2 1,000 169,000
12 Playwood Tebal 9mm 20.00 Lbr 30,000 600,000
13 Air Adukan Beton 46.00 Drum 20,000 920,000
14 Pipa PVC 3/4 Inchi 10.00 Btg 5,000 50,000
Jumlah 21,751,000
HOK PEKERJA LANSIR 217.51
III UPAH
1 Tukang 26.0 HOK 120,000 3,120,000
2 Pekerja 237.0 HOK 100,000 23,700,000
3 Jasa Desain Dan RAB 1.0 LS 1,401,000 1,401,000
Jumlah 28,221,000
TOTAL ( 1 + 2 + 3 ) 49,972,000
TOTAL BIAYA + Swadaya 49,972,000
Permai, Desember 2019

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


KEPALA DESA PPKD TENAGA TEKNIS

AZMAN RAAD HAMADI, AMD MARLON SUMANJUNTAK, ST


Kabupaten : KEPULAUAN MERANTI Jenis Prasarana : Drainase Beton & Saluran Pembuangan
Kecamatan : RANGSANG BARAT Take Of Sheet Lokasi : Jl. PELITA Dsn. PELAYAR
DESA : PERMAI Volume : 235 M x 0.60 M x 0.60 M

PEKERJAAN GALIAN
(P) (T) (L)
= ( 235 x 0.60 x 0.60 )
= 84.6 M³ = 141 M² 115.15

PEK KAYU CEROCOK Ø 8-10 CM PANJANG 2 M


N = 235 : 0.2
0.75 m
= 1175.0 ≈ 1175
N = 0.60 : 0.2
= 3.0
JUMLAH = 1175 x 3
= 3525 Batang
235.00
Galian ( karena panjang cerocok adalah 4 M, Maka : = 3525
2
= 1763 Btg
Volume Urugan Pasir
Panjang = 235.0
Lebar = 1.00
Tebal = 0.07 x 1.0 x 235 )
16.00 M³
Luas = 235 M2

V3 10/10
Tebal Penampang Beton = 0.10
Ø8 - 8 cm 10

Ø8 - 15 cm
0.40 0.60
V1 V1
10
V2
PEMBESIAN BALOK PENOPANG

Ø 6 (begel) L = ( 10 x 2 )+( 10 x 2 )+( 3 x 2 )


0.60 = 20 + 20 + 5
0.40
= 45 Cm
10 10

Kebutuhan 1 Balok = 0.40


+ 1
0.15
10 cm = 3.66667 ~ 4 Buah

45 x 4 = 180 ~ 1.80 M
4 Ø 8 mm
235
+ 1 = 95.0 ~ 95 Balok
Ø 6 - 15 cm 2.5
10 cm
Kebutuhan besi Ø 6 = 1.80 x 95
= 171
= 171
10 cm 10
2.5 cm
= 17.1 ~ 17 Btg - Pjg 10 M

10 cm 10cm Ø8 L¹ = 4 x 0.6 = 2 M x 95
= 228
10
10 cm Pembesian Ø 8 MEMANJANG = 23 Btg - 10 M
Dinding Kanan&Kiri
1.20 = 6 L² = ( 6 + 3 )x 235.0
0.20 = 9 x 235.0
Lantai = 2115
0.60 = 3.0 10
0.20 = 211.5 ~ 212 Btg - 10 M

Kebutuhan besi Ø 8 = L¹ + L²
= 23 + 212
= 235 Btg - 10 m

Ø8 L =( 50 x 2 )+( 45.0 x 1 ) + ( 2.5 x 2 )


2.5 cm = 100 + 45 + 5
= 150 cm ~ 1.5 M

0.50 0.50 m Kebutuhan : Kebutuhan Besi Dalam Kg


235.0 Total Besi x 0.395 /1m (Berat Besi Ø 8)
= 1175 Potongan
0.2 = 411 Btg x 0.395
= 162.35 Kg
1.50 x 1175
1763 M
0.45 Kebutuhan besi Ø 8 1763
= 176 Btg - 10 M
10
Kabupaten : KEPULAUAN MERANTI Jenis Prasarana : Drainase Beton & Saluran Pembuangan
Kecamatan : RANGSANG BARAT Take Of Sheet Lokasi : Jl. PELITA Dsn. PELAYAR
Desa : PERMAI Volume : 235 M x 0.60 M x 0.60 M

ADUKAN BETON K - 175


Kayu 4/6
V1 =( 0.60 x 0.10 x 235 ) x 2 = 28.2 M³
V3 V2 0.60 0.10 235 ) = 14.1 M³
Papan 2/20 =( x x
V3 =( 0.10 x 0.10 x 0.40 ) x 95 = 0.38 ~ 0 M³
V1 Total Volume Beton = 43.00 M³
V1

V2
1 M³ Cor Beton Adukan K - 175

6.52 Zak Semen x 43 = 280.36 Dipakai 280 Zak


0.54 M³ Pasir x 43 = 23.22 Dipakai 23 M³
0.76 M³ Kerikil x 43 = 32.68 Dipakai 33 M³
0.02 M³ Papan Mall x 43 = 0.86 Dipakai 1 M³
215 Ltr Air Adukan x 43 = 9245 9245 Ltr
0.4 Kg Paku x 43 = 17.2 Dipakai 17 Kg

SNI 2013
1 M² Bekiesting Untuk Dinding Parit Beton
Data Perencanaan
Sisi 1 Sisi 2 Panjang = 235 M
Tinggi = 0.60
Sisi = 2x
By2 By1 Total Volume = 282
Estimasi Pemakaian 6x Pakai
= 56.4 M2

a5 a5

Volume yg di perlukan BAHAN MATERIAL LOKAL


= Oyong Sagu/Kulit Batang Sagu
0.400 Kg Paku 5 cm -12 cm x 56.4 = 23 Perhitungan
0.200 Ltr Minyak bekisting x 56.4 = 11.00 1 Btg Kulit Sagu
0.020 M³ Balok kayu kelas III x 56.4 = 1.10 Panjang = M
0.350 Lbr Multipleks tebal 9 mm x 56.4 = 20.00 Lebar = M
SNI 2013 Luas = M2

Luas Permukaan Lantai Darinase


= 141 M2
Analisa SNI 2013 Setiap 1 KgBeton
Pembesian
Bertulang
Polos/Ulir
Vol 1993.694 Pemakaian Oyong/Kulit Batang Sagu
10.500 kg Besi beton (polos/ulir) = = Btg
0.015 kg Kawat beton = 29.91 Kg 1 Gerobak Isi Oyong Sagu = 100 Btg
0.007 OH Pekerja = 14.00 HOK = 0 Gerobak
0.007 OH Tukang besi = 14.00 HOK
Penggunaan Pipa PVC 3/4 Inchi
Panjang Dinding Drainase =
Panjang = 235.00
Rekapitulasi Bahan Dan Tenaga Kerja Lebar = 0.40
Panjang Pipa 1 dinding = 0.40
Semen @ 50 Kg = 280 zak semen Jumlah Titik = 78 x 2
Pasir Cor = 23 M3 = 157 Titik
Kerikil / Split 2/3 cm = 33 M3 Total Panjang = 63 M
Balok kayu kelas III = 1.10 M3 = 10
Multiplek 9mm = 20.0 Lbr
Paku = 17 Kg
Besi Ø 6 Pjg 10 M = 17 Batang 0.222 2.664 45.5544
Besi Ø 8 Pjg 10 M = 411 Batang 0.395 4.74 1948.14
Kawat = 30 Kg
Kulit Batang Sagu/Oyong = 0 Gerobak
Kayu Cerocok ø5-8 cm Pjg. 3 m = 1763 Btg
Total Kg Besi 1993.7 Kg
Dibagi 10 Kg 199.37 Kg

Permai, Desember 2019

Diketahui Oleh : Diperiksa Oleh : Di Validasi Oleh Dbuat Oleh :


KEPALA DESA PPKD TA ID/PDTI TENGA TEKNIS

AZMAN RAAD HAMADI, AMD ACHMAD AMBARI,ST MARLON SUMANJUNTAK, ST


PERHITUNGAN KEBUTUHAN TENAGA KERJA/BAHAN/ALAT
ANALISA HARGA SATUAN (AHS 2013)

JENIS KEGIATAN : DRAINASE BETON


KABUPATEN : KEPULAUAN MERANTI
KECAMATAN : RANGSANG BARAT Volume : : 235 M x 0.60 M x 0.60 M
DESA : PERMAI Lokasi : : Jl. PELITA Dsn. PELAYAR

Volume
NO URAIAN KERJA Satuan Koefisien Volume Harga Jumlah
Kebutuhan
(1) (2) (3) (4) (5) (6) (7) (8)

1 Divisi 1. Umum
1.1 Umum Ls 1.00
a. Mobilisasi Peralatan Ls 1.00 250,000 250,000
b. Papan Nama Ls 1.0000 1.00 150,000 150,000
c. Demobilisasi Peralatan Ls 1.00 300,000 300,000
d. Prasasti Ls 1.0000 1.00 550,000 550,000
e. Desain dan RAB Ls 1.0000 1,401,000 1,401,000
Jumlah 2,651,000
2 Divisi 3. Pekerjaan Tanah M3 16.00
2.1 Pembersihan Gali Parit M2 115.15
a. Tenaga Kerja
Pekerja HOK 0.2500 29.00 100,000 2,900,000

Jumlah 2,900,000
3 Pekerjaan Pondasi Tapak M2 115.15
3.1 Pekerjaan Cerocok Btg 1,762.50
a. Tenaga Kerja
Pekerja HOK 0.070 123.0 100,000 12,300,000
b. Bahan -
Kayu Cerocok 8-10 cm Btg 1.000 1,763.0 6,000 10,578,000
Sub Total1 22,878,000
4 Divisi7. Pekerjaan Struktur 235.00
4.1 Cor Beton Dalam 1 M3 (SNI K-175) 43.00
56.40
282.00
a. Tenaga Kerja
Pekerja HOK 1.6500 71.00 100,000 7,100,000
Tukang HOK 0.2750 12.00 120,000 1,440,000
b. Bahan
Semen Zak 6.5200 280.00 93,000 26,040,000
Pasir Beton M3 0.5400 23.00 470,000 10,810,000
Kerikil M3 0.7600 33.00 650,000 21,450,000
Minyak Bekisting Ltr 0.2000 56.00 18,000 1,008,000
Pasir Urug M3 0.0500 12.00 470,000 5,640,000
Balok Kayu Kelas III M3 0.0200 1.10 1,800,000 1,980,000
Paku Kg 0.4000 56.00 20,000 1,120,000
Plastik Alas Cor M2 1.2000 169.00 7,000 1,183,000
Air Adukan Beton Drum 1.080 46.00 50,000 2,300,000
Multiplex 9mm Lbr 1.0000 20.00 150,000 3,000,000
Pipa PVC 3/4 Inchi Btg 1.0000 10.00 23,000 230,000
c. Alat
Concrete Mixer Jam 0.6827 29.00 57,000 1,653,000
Water Pump Jam 0.3620 16.00 45,000 720,000
Ember Bh 1.0000 4.00 18,000 72,000
Gerobak Sorong Bh 1.0000 1.00 450,000 450,000
Drum Bh 1.00 400,000 400,000
Cangkul Bh 2.00 65,000 130,000
Sekop Bh 2.00 70,000 140,000
Jumlah 86,866,000
Volume
NO URAIAN KERJA Satuan Koefisien Volume Harga Jumlah
Kebutuhan
(1) (2) (3) (4) (5) (6) (7) (8)
4.2 Pekerjaan Pembesian 1 Kg Dia. 6 17.00
Dia. 8 411.00
Total Volume Besi Kg 1,993.69
a. Tenaga Kerja
Pekerja HOK 0.0070 14.00 100,000 1,400,000
Tukang HOK 0.0070 14.00 120,000 1,680,000
b. Bahan -
Besi dia 6 Btg 1.0000 17.00 26,000 442,000
Besi dia 8 Btg 1.0000 411.00 51,000 20,961,000
Kawat Beton Kg 0.0150 30.00 25,000 750,000
Jumlah 25,233,000
Sub Total 140,528,000
TOTAL BIAYA 140,528,000
DIBULATKAN 140,528,000

Permai, Desember 2019

Diketahui Oleh : Di Vaidasi Oleh Dbuat Oleh :


KEPALA DESA PDTI TENGA TEKNIS

AZMAN ACHMAD AMBARI,ST MARLON SUMANJUNTAK, ST


HARGA SATUAN UPAH / BAHAN / ALAT
BULAN : JANUARI TAHUN 2019

KECAMATAN : RANGSANG BARAT


DESA : PERMAI

UPAH PAJAK HARGA HARGA


No. J E N I S SATUAN
LANSIR SUPLIER/TOKO ( Rp )
A BAHAN
1 Batu Kerikil M³ 200,000 450,000 650,000
2 Besi Beton 10 mm Btg 7,000 75,000 82,000
3 Besi Beton 8 mm Btg 6,000 45,000 51,000
4 Besi Beton 6 mm Btg 4,000 22,000 26,000
5 Besi Beton 10 mm Kg 11,000
6 Besi Beton 8 mm Kg 11,000
7 Besi Beton 6 mm Kg 10,000
8 Kawat Beton Kg 25,000 25,000
9 Kayu Klas II M³ 150,000 1,650,000 1,800,000
10 Kayu Bekisting M³ 150,000 1,650,000 1,800,000
11 Kayu Cerocok 8 - 10 cm pjg 2 m Btg 1,000 5,000 6,000
12 Paku Kg 20,000 20,000
13 Pasir Cor M³ 160,000 310,000 470,000
14 Pasir Pasang M³ 160,000 310,000 470,000
15 Pasir Urug M³ 160,000 310,000 470,000
16 Semen Zak 10,000 83,000 93,000
17 Plastik Alas cor M 1,000 6,000 7,000
18 Pipa PVC 3/4 Inchi Btg 5,000 18,000 23,000
19 Playwood Tebal 9mm Lbr 30,000 120,000 150,000
20 Plakat / Prasasti Unit 300,000 300,000
21 Minyak Bekisting Ltr - 18,000 18,000
22 Air Adukan Beton Drum 20,000 30,000 50,000
23 Kulit Batang Sagu/Oyong Sagu Btg 600 600 1,200
24 Papan Nama Kegiatan Ls 130,000 150,000

B ALAT
1 Ember Buah 18,000
2 Gerobak Buah 450,000
3 Papan Nama Kegiatan Unit 150,000
4 Concrete Mixer/Molen Jam 57,000
5 Water Pump/Pompa Air Jam 45,000
6 Drum Bh 400,000
7 Gunting Besi Bh 300,000
8 Cangkul Bh 65,000
9 Sekop Bh 70,000

C UPAH
1 Tukang HOK 120,000
2 Pekerja HOK 100,000

Permai, Desember 2019

Diketahui Oleh : Dibuat Oleh :


KEPALA DESA PPKD

AZMAN RAAD HAMADI, AMD


JADWAL PELAKSANAAN PEKERJAAN
APBDes TAHUN ANGGARAN 2020 DESA : PERMAI
: PEMB. DRAINASE PARIT BETON VOLUME : 235 M x 0.60 M x 0.60 M

JADWAL PELAKSANAAN

Bobot BULAN I BULAN II


No Item Pekerjaan
(%)
Minggu Ke- Minggu Ke-
1 2 3 4 1 2 3 4
1 Divisi 1. Umum 0.14 0.10 0.04

2 Divisi 3. Pekerjaan Tanah


Pembersihan Gali Parit 0.37 0.37

3 Pekerjaan Cerocok 5.26 3 2.26

4 Divisi7. Pekerjaan Struktur


Pekerjaan Pembesian 16.76 5 5.00 6.00 0.76

Pekerjaan Beton K125 77.47 10 20 20.00 15.00 12.47

Jumlah 100.00
Waktu Pelaksanaan
Rencana 0.47 18.00 27.26 26.00 15.76 12.47 0.00 0.04
Kumulatif Rencana 0.47 18.47 45.74 71.74 87.50 99.97 99.97 100.0
Realisasi
Kumulatif Realisasi
Jumlah Hari Rencana 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
Jumlah Hari Kumulatif 7.00 14.0 21.0 28.0 35.0 42.0 49.0 56.0

Permai, Desember 2019

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


KEPALA DESA PDTI TENAGA TEKNIS

AZMAN ACHMAD AMBARI,ST MARLON SUMANJUNTAK, ST

Anda mungkin juga menyukai