Pembangunan Gapura
PEKERJAAN : Pembangunan Gapura di Balai Bibit
LOKASI : DELI SERDANG
TAHUN 2022
........... .........
Ketua
RENCANA ANGGARAN BIAYA ( SWAKELOLA )
1 BAHAN
1.1 Semen Portland (PC) 74 Zak 60,000 4,440,000
1.2 Pasir Beton (PB) 4 M3 160,000 640,000
1.3 Kerikil (KR) 6 M3 175,000 1,050,000
1.4 Besi Beton Polos 489.1 Kg 15,000 7,337,000
1.5 Kawat Beton 7 Kg 20,000 140,000
1.6 Kayu Kelas III 0.51 M3 4,256,000 2,190,000
1.7 Paku 5 cm - 10 cm 5 Kg 22,000 110,000
1.8 Minyak Bekisting 2 Liter 17,000 34,000
1.9 Balok Kayu Kelas II 0.11 M3 5,320,000 598,000
1.10 Multipleks tebal 9 mm 3 Lbr 135,000 405,000
1.11 Kayu dolken dia. 8-10 cm, L = 4 M 15 Batang 73,000 1,095,000
1.12 Batu Andesit Alur Diagonal 15x30 11.94 M2 289,000 3,449,000
1.13 Pasir Pasang 1.18 M3 162,000 192,000
1.14 Semen Warna 26.75 Kg 7,000 187,000
1.15 Plamir 0.57 Kg 23,000 13,000
1.16 Cat dasar tembok 0.57 Kg 21,000 12,000
1.17 Cat Tembok Weathershield Pro Exterior 1.48 Kg 23,000 34,000
1.18 Granit Tile 60 x 60 cm Pholished 20.00 Bh 246,000 4,920,000
1.19 Relief Kolom Gapura 1.00 Ls 1,500,000 1,500,000
1.20 Teralis Besi Galvanis 1,5'' 1.00 Ls 1,900,000 1,900,000
1.21 Cetak Lambang A. Besar dan Nama Gampong Stainle 1.00 Ls 7,000,000 7,000,000
1.22 Batu Prasasti 1.00 Unit 300,000 300,000
1.23 Papan Nama Proyek 1.00 Unit 250,000 250,000
37,796,000
2 PERALATAN
2.1
2.2
-
3 UPAH
3.1 Pekerja 47 OH 82,000 3,854,000
3.2 Tukang 20 OH 102,000 2,040,000
3.3 Kepala Tukang/Ketua Kelompok 2 OH 123,000 246,000
3.4 Biaya penyusunan Rab Desain 1 Bh 1,500,000 1,500,000
7,640,000
TOTAL BIAYA 45,436,000
DI BULATKAN 45,436,000
........... .........
Ketua
DAFTAR ANALISA HARGA SATUAN
PEKERJAAN TANAH
PEKERJAAN PONDASI
PEKERJAAN PENGECATAN
Pt.t-38-2000-C (B.14) 1 m2 Mengecat Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Bahan : 0.260 Kg Cat Tembok Weathershield Pro Exterior @Rp. 115,000.00 Rp. 29,900.00
0.100 Kg Cat Dasar (Beton) @Rp. 23,000.00 Rp. 2,300.00
0.100 Kg Plamir @Rp. 27,500.00 Rp. 2,750.00
Jumlah Bahan Rp. 34,950.00
Jumlah Upah + Bahan Rp. 45,555.00
PEKERJAAN BETON
SNI. 7394:2008.6.4 1 m3 Lantai Kerja Beton Mutu K.100 (fc = 7,4 Mpa)
Bahan : 0.040 M3 Papan Kayu Klas III @Rp. 2,200,000.00 Rp. 88,000.00
0.400 kG Paku Kayu @Rp. 16,500.00 Rp. 6,600.00
0.015 m3 Kayu Klas II @Rp. 2,900,000.00 Rp. 43,500.00
2.000 Btg Dolken Kayu AE 8-10/400 Cm @Rp. 6,000.00 Rp. 12,000.00
0.350 Lbr Plywood/Triplek Tebal 9 mm @Rp. 144,000.00 Rp. 50,400.00
0.200 Ltr Residu / Teer/ Minyak Bekisting @Rp. 12,000.00 Rp. 2,400.00
Jumlah Bahan Rp. 202,900.00
Jumlah Upah + Bahan Rp. 310,810.00
Pemakaian 3 x Rp. 103,603.33
Bahan : 1.100 M2 Batu Andesit Alur Diagonal 15x30 @Rp. 400,000.00 Rp. 440,000.00
11.750 Kg Semen PC @Rp. 1,425.00 Rp. 16,743.75
0.035 M3 Pasir Pasang @Rp. 75,000.00 Rp. 2,625.00
Jumlah Bahan Rp. 459,368.75
Jumlah Upah + Bahan Rp. 573,818.75
Bahan : 26.500 Buah Keramik 20 x 20 Cm Texture (Standar) @Rp. 3,080.00 Rp. 81,620.00
10.400 Kg Semen PC @Rp. 1,425.00 Rp. 14,820.00
0.045 M3 Pasir Pasang @Rp. 75,000.00 Rp. 3,375.00
1.620 Kg Semen Putih @Rp. 2,660.00 Rp. 4,309.20
Jumlah Bahan Rp. 104,124.20
Jumlah Upah + Bahan Rp. 218,574.20
Bahan : 2.778 Buah Granit Top Gres 60 x 60 RED @Rp. 76,000.00 Rp. 211,111.11
9.300 Kg Semen PC @Rp. 1,425.00 Rp. 13,252.50
0.018 M3 Pasir Pasang @Rp. 75,000.00 Rp. 1,350.00
1.940 Kg Semen Putih @Rp. 2,660.00 Rp. 5,160.40
Jumlah Bahan Rp. 230,874.01
Jumlah Upah + Bahan Rp. 378,024.01
Dibuat Oleh :
TIM PENGELOLA KEGIATAN
(TPK) GAMPONG
.........
Ketua
ANALISA HARGA SATUAN PEKERJAAN
PENGUKURAN/PEMASANGAN BOUWPLANK
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 0.1000 1.400
2 Tukang Kayu OH 0.1000 1.400
3 Kepala Tukang OH 0.0100 0.140
4 Mandor OH 0.0050 0.070
14.00
B. BAHAN
1 Kayu 5 x 7 cm (Klas III) M3 0.012 0.168
2 Paku 2" -3" Kg 0.200 2.800
3 Kayu Papan 2/30 (Klas III) M3 0.007 0.098
PEKERJAAN TANAH
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
2.64 1 Pekerja OH 0.7500 1.977
2 Mandor OH 0.0250 0.066
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
0.88 1 Pekerja OH 0.2500 0.220
2 Mandor OH 0.0833 0.073
PEKERJAAN PASANGAN
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 0.2000 1.138
2 Tukang OH 0.1000 0.569
5.69 3 Kepala Tukang OH 0.0100 0.057
4 Mandor OH 0.0100 0.057
B. BAHAN
1 Semen Portland (PC) Kg 3.250 18.493
Jenis Pekerjaan : Pasangan Dinding Batu Alam
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.58.a
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 0.7000 7.595
2 Tukang OH 0.3500 3.798
3 Kepala Tukang OH 0.0350 0.380
4 Mandor OH 0.0350 0.380
10.85
B. BAHAN
1 Batu Andesit Alur Diagonal 15x30 M2 1.100 11.935
2 Semen Portland (PC) Kg 11.750 127.488
3 Pasir Pasang M3 0.035 0.380
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 0.7000 12.481
2 Tukang OH 0.3500 6.241
3 Kepala Tukang OH 0.0350 0.624
4 Mandor OH 0.0350 0.624
17.83
B. BAHAN
1 Granit Tile 60 x 60 cm Pholished Bh 3.000 53.490
2 Semen Portland (PC) Kg 10.000 178.300
3 Pasir Pasang M3 0.045 0.802
4 Semen Warna Kg 1.500 26.745
PEKERJAAN BETON
Jenis Pekerjaan : Membuat Beton Mutu F'c = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.1
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 1.6500 0.279
2 Tukang OH 0.2750 0.046
3 Kepala Tukang OH 0.0280 0.005
4 Mandor OH 0.0830 0.014
0.17
B. BAHAN
1 Semen Portland (PC) Kg 247.00 41.743
2 Pasir Beton (PB) Kg 869.00 146.861
3 Kerikil (KR) Kg 999.00 168.831
4 Air Liter 215.00 36.335
Jenis Pekerjaan : Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA KERJA
1 Pekerja OH 1.6500 1.892
2 Tukang OH 0.2750 0.315
3 Kepala Tukang OH 0.0280 0.032
4 Mandor OH 0.0830 0.095
1.15
B. BAHAN
1 Semen Portland (PC) Kg 326.00 373.739
2 Pasir Beton (PB) Kg 760.00 871.293
3 Kerikil (KR) Kg 1,029.00 1,179.684
4 Air Liter 215.00 246.484
Jenis Pekerjaan : Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, W/c = 0,61
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.6
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 1.6500 6.181
2 Tukang OH 0.2750 1.030
3 Kepala Tukang OH 0.0280 0.105
4 Mandor OH 0.0830 0.311
3.75
B. BAHAN
1 Semen Portland (PC) Kg 352.00 1,318.680
2 Pasir Beton (PB) Kg 731.00 2,738.509
3 Kerikil (KR) Kg 1,031.00 3,862.384
4 Air Liter 215.00 805.444
Jenis Pekerjaan : Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 1.6500 4.026
2 Tukang OH 0.2750 0.671
3 Kepala Tukang OH 0.0280 0.068
4 Mandor OH 0.0830 0.203
2.44
B. BAHAN
1 Semen Portland (PC) Kg 371.00 905.240
2 Pasir Beton (PB) Kg 698.00 1,703.120
3 Kerikil (KR) Kg 1,047.00 2,554.680
4 Air Liter 215.00 524.600
Jenis Pekerjaan : Pembesian 1 Kg Dengan Besi Polos
Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.17
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 0.0700 32.588
2 Tukang OH 0.0700 32.588
3 Kepala Tukang OH 0.0070 3.259
4 Mandor OH 0.0400 18.622
465.55
B. BAHAN
1 Besi Beton Polos Kg 10.500 4,888.251
2 Kawat Beton Kg 0.150 69.832
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 0.5200 5.583
2 Tukang OH 0.2600 2.791
3 Kepala Tukang OH 0.0260 0.279
4 Mandor OH 0.0260 0.279
10.74
B. BAHAN
1 Kayu Kelas III M3 0.040 0.429
2 Paku 5 cm - 10 cm Kg 0.300 3.221
3 Minyak Bekisting Liter 0.100 1.074
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 0.6600 9.895
2 Tukang OH 0.3300 4.948
3 Kepala Tukang OH 0.0330 0.495
4 Mandor OH 0.0330 0.495
B. BAHAN
14.99
1 Kayu Kelas III M3 0.0400 0.600
2 Paku 5 cm - 10 cm Kg 0.4000 5.997
3 Minyak Bekisting Liter 0.2000 2.999
4 Balok Kayu Kelas II M3 0.0150 0.225
5 Mutipleks tebal 9 mm Lbr 0.3500 5.248
6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 2.0000 29.986
REKAPITULASI PEKERJAAN BETON
PEKERJAAN PENGECATAN
Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
Jumlah Kebutuhan
Volume No Uraian Satuan Koefisien
bahan dan upah
A. TENAGA
1 Pekerja OH 0.0200 0.114
2 Tukang OH 0.0630 0.358
3 Kepala Tukang OH 0.0063 0.036
4 Mandor OH 0.0025 0.014
5.69
B. BAHAN
1 Plamir Kg 0.1000 0.569
2 Cat dasar tembok Kg 0.1000 0.569
3 Cat Tembok Weathershield Pro Exterior Kg 0.2600 1.479
DAFTAR HARGA UPAH ,BAHAN DAN PERALATAN
A. UPAH PEKERJA
B. HARGA BAHAN
C. HARGA PERALATAN
.........
Ketua
TABEL PEMBESIAN CETAKAN BEKISITNG
INPUT 30 x 30 cm
Kolom 30 x 30 cm
Pajang Kolom/M3 = 11.1111
INPUT 25 x 25 cm
Kolom 25 x 25 cm
Pajang Kolom/M3 = 16.0000
INPUT 20 x 20 cm
Kolom 20 x 20 cm
Pajang Kolom/M3 = 25.0000
INPUT 15 x 15 cm
Kolom 15 x 15 cm
Pajang Kolom /M3 = 44.4444
INPUT 13 x 13 cm
Kolom 13 x 13 cm
Pajang Kolom /M3 = 59.1716
1 of 5
TABEL PEMBESIAN CETAKAN BEKISITNG
INPUT 20 x 30 cm
Sloof 20 x 30 cm
Pajang Kolom/M3 = 16.6667
INPUT 20 x 25 cm
Sloof 20 x 25 cm
Pajang Kolom/M3 = 20.0000
INPUT 18 x 25 cm
Sloof 18 x 25 cm
Pajang Kolom /M3 = 22.2222
INPUT 15 x 20 cm
Sloof 15 x 20 cm
Pajang Kolom /M3 = 33.3333
INPUT 15 x 25 cm
Sloof 15 x 25 cm
Pajang Kolom /M3 = 26.6667
1 of 5
TABEL PEMBESIAN CETAKAN BEKISITNG
1 of 5
TABEL PEMBESIAN CETAKAN BEKISITNG
INPUT 18 x 20 cm
Ring Balok 18 x 20 cm
Pajang Kolom/M3 = 27.7778
INPUT 15 x 15 cm
Ring Balok 15 x 15 cm
Pajang Kolom/M3 = 44.4444
INPUT 15 x 18 cm
Ring Balok 15 x 18 cm
Pajang Kolom/M3 = 37.0370
INPUT 13 x 20 cm
Ring Balok 13 x 20 cm
Pajang Kolom/M3 = 38.4615
1 of 5
TABEL PEMBESIAN CETAKAN BEKISITNG
INPUT 13 x 15 cm
Balok Latai 13 x 15 cm
Pajang Kolom/M3 = 51.2821
INPUT 13 x 13 cm
Balok Latai 13 x 13 cm
Pajang Kolom/M3 = 59.1716
1 of 5
TABEL PEMBESIAN CETAKAN BEKISITNG
Pjg
Tebal Jarak Total
Bahan Ø 1 Kg/m' Besi/ Banyak Pjg Total Kg/M3
/M3 (Spasi) Besi
Btg
Besi 14 1.208 1.00 0.90 0.12 30.000 108.000 130.501 130.501
1x
Sisi Luas/M3
Pakai
2.000
Bekisting 2 2.000
INPUT 80 x 80 cm
Pondasi Tapak 80 x 80 cm
Pajang Kolom/M3 = 1.5625
Pjg
Tebal Jarak Total
Bahan Ø 1 Kg/m' Besi/ Banyak Pjg Total Kg/M3
/M3 (Spasi) Besi
Btg
Besi 14 1.208 1.56 0.70 0.1 28.000 121.100 146.330 146.330
1x
Sisi Luas/M3
Pakai
2.500
Bekisting 2 2.500
1 of 5
ENGINEERING ESTIMATE ( EE )
PEMBANGUNAN RUMAH TYPE
45 BANDA ACEH
Rumah Type 40
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT ANALISA SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan Bowplank m' #REF! #REF! #REF!
2 Administrasi/P3k dan Keamanan Ls Taksir 3,500,000.00 -
4 Quality Kontrol Ls Taksir 3,250,000.00 -
5 Direksi keet Ls Taksir 7,500,000.00 -
6 Barak Kerja + Gudang Ls Taksir 2,500,000.00 -
7 Pagar pengaman proyek m' Taksir 85,000.00 -
Jumlah #REF!
B PEKERJAAN TANAH
1 Galian pondasi 62.540 m3 #REF! #REF! #REF!
2 Urugan kembali bekas galian 15.640 m3 #REF! #REF! #REF!
3 Pasir urug bawah lantai dan pondasi 12.500 m3 #REF! #REF! #REF!
4 Timbunan tanah bawah lantai m3 #REF! #REF! #REF!
Jumlah #REF!
C PEKERJAAN PASANGAN
1 Aanstamping 7.530 m3 #REF! #REF! #REF!
2 Pondasi batu gunung/batu kali 29.440 m3 #REF! #REF! #REF!
3 Pasangan bata 1 PC : 2 PS Trasraam 48.590 m2 #REF! #REF! #REF!
4 Plasteran 1 PC : 2 PS Trasraam 97.180 m2 #REF! #REF! #REF!
5 Pasangan bata 1 PC : 4 PS 241.130 m2 #REF! #REF! #REF!
6 Plasteran 1 PC : 4 PS 482.260 m2 #REF! #REF! #REF!
Jumlah #REF!
D PEKERJAAN BETON BERTULANG
1 Sloof 18/25 3.880 m3 #REF! #REF! #REF!
2 Kolom 20/30 0.840 m3 #REF! #REF! #REF!
3 Kolom praktis 1.730 m3 #REF! #REF! #REF!
4 Ring balok 13/15 cm 1.680 m3 #REF! #REF! #REF!
5 Balok latai 13/15 cm 0.290 m3 #REF! #REF! #REF!
6 Balok plat dag 13/15 cm 0.210 m3 #REF! #REF! #REF!
7 Plat dag dan meja beton T=10 cm 2.010 m3 #REF! #REF! #REF!
Jumlah #REF!
E PEKERJAAN KOSEN, KAYU DAN KACA
1 Kayu kusen 1.225 m3 #REF! #REF! #REF!
2 Pintu panel + kaca 80 x 210 cm 2.000 unit Taksir -
3 Pintu panel 80 x 210 cm 8.000 unit Taksir -
4 Pintu fiber 70 x 210 cm 2.000 unit Taksir -
5 Jendela 50 x 115 cm 4.000 unit Taksir -
6 Jendela 60 x 115 cm 10.000 unit Taksir -
7 Jendela 60 x 160 cm 4.000 unit Taksir -
8 Krepyak 1.010 m2 Taksir -
9 Kaca mati 0.770 m2 Taksir -
Jumlah #REF!
F PEKERJAAN LANTAI & PELAPIS DINDING
1 Beton tumbuk t = 7 cm 6.388 m3 #REF! #REF! #REF!
2 Lantai keramik 40 x 40 cm 66.000 m2 #REF! #REF! #REF!
3 Lantai keramik 40 x 40 cm anti slip 21.000 m2 #REF! #REF! #REF!
4 Lantai keramik 20 x 20 cm anti slip 5.670 m2 #REF! #REF! #REF!
Basement Hal. 31 of 40
1 2 3 4 5 6 7
5 Dinding keramik 20 x 25 cm 39.670 m2 #REF! #REF! #REF!
6 Plin keramik 75.000 m' -
7 Bon-bon keramik 50.000 m' -
Jumlah #REF!
Basement Hal. 32 of 40
1 2 3 4 5 6 7
G PEKERJAAN INSTALASI LISTRIK
1 Pemasukan arus listrik 1.000 unit Taksir -
2 Box Zekering 1.000 unit Taksir 350,000.00 350,000.00
3 Lampu hemat energi 15 watt 15.000 bh Taksir 280,000.00 4,200,000.00
4 Lampu hemat energi 10 watt 2.000 bh Taksir 140,000.00 280,000.00
5 Titik lampu + instalasi 17.000 bh Taksir 120,000.00 2,040,000.00
6 Saklar tunggal 6.000 bh Taksir 43.00 258.00
7 Saklar ganda 4.000 bh Taksir 32,000.00 128,000.00
8 Stop kontak 10.000 bh Taksir 38,000.00 380,000.00
Jumlah 7,378,258.00
H PEKERJAAN ATAP, RANGKA DAN PLAFOND
1 Rangka Baja Ringan 163.110 m2 Taksir 135,000.00 22,019,850.00
2 Atap Genteng Metal 163.110 m2 #REF! #REF! #REF!
3 Talang 14.000 m2 Taksir 250,000.00 3,500,000.00
4 Rabung genteng Bulat 51.200 m' #REF! #REF! #REF!
5 Papan Lisplank 2,5/30cm 57.100 m2 #REF! #REF! #REF!
6 Plafond triplek 134.900 m2 #REF! #REF! #REF!
7 Profil kayu 5/5 178.720 m' Taksir 6,500.00 1,161,680.00
8 Profil kayu 2/3 61.600 m' Taksir -
Jumlah #REF!
I PEKERJAAN PENGECATAN
1 Cat tembok dan plafon 665.750 m2 #REF! #REF! #REF!
2 Cat minyak listplank m2 #REF! #REF! #REF!
3 Cat plafond Rider m2 #REF! #REF! #REF!
Jumlah #REF!
J PEKERJAAN SANITAIR
1 Kloset jongkok 2.000 bh Taksir -
2 Titk air + kran 4.000 bh Taksir -
3 Tutup bak 2.000 bh Taksir -
4 Floor drain 2.000 bh Taksir -
5 Wastafel stainless steel 2.000 bh Taksir -
6 Pipa air kotor 2" 1.000 Pkt Taksir -
7 Pipa air kotor 3" 1.000 Pkt Taksir -
8 Pipa air bersih 1" 1.000 Pkt Taksir -
9 Septictank + resapan 2.000 unit Taksir -
Jumlah -
K PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Kunci pintu double 2 slag Bh Taksir 180,000.00 -
2 Kunci pintu 2 slag Bh Taksir 150,000.00 -
3 Engsel pintu Psg Taksir 9,000.00 -
4 Engsel jendela Psg Taksir 7,000.00 -
5 Grendel jendela Bh Taksir 8,100.00 -
6 Hak angin Bh Taksir 10,800.00 -
7 Tarikan jendela Bh Taksir 13,000.00 -
Jumlah -
L PEKERJAAN LAIN-LAIN
1 Reiling Tangga Galvanis + Fiber m' Taksir 550,000.00 -
2 Alumunium komposit panel m2 Taksir 500,000.00 -
3 Tolak angin motif Aceh Tamiang pkt Taksir 9,000,000.00 -
4 Kusen Ventilasi Kayu 25x35 cm bh Taksir 85,000.00 -
5 Crepyak alumunium m2 Taksir 550,000.00 -
6 Relief Pkt Taksir 6,000,000.00 -
Basement Hal. 33 of 40
1 2 3 4 5 6 7
Jumlah -
Basement Hal. 34 of 40
REKAPITULASI ENGINEERING ESTIMATE (EE)
PEMBANGUNAN RUMAH TYPE 40
#REF!
Terbilang : Tiga milyar delapan ratus delapan belas juta lima ratus sembilan puluh satu ribu rupiah
#REF!
#REF!
#REF!
#REF!
#REF!
DAFTAR HARGA UPAH, BAHAN DAN PERALATAN
HARGA Retribusi
A. UPAH SATUAN Pajak PPn PPh HARGA
SATUAN Daerah
1 Mandor Org/Hari 110,000 2,200 113,000
2 Kepala Tukang Org/Hari 120,000 2,400 123,000
3 Tukang Org/Hari 100,000 2,000 102,000
4 Pekerja Org/Hari 80,000 1,600 82,000