Anda di halaman 1dari 2

ANALISA SALURAN BUIS BETON

Pek. Pasangan Buis Beton O dia. 30 cm 44.00 M¹ Jumlah (%)


1.000 Buis Beton O dia. 30 cm 44.000 Bh 62,000 2,728,000
0.01250 Semen 40 kg 0.550 sak 56,500 31,075
0.01300 Pasir Pasang 0.572 m3 100,000 57,200 2,816,275 74.2
Tenaga
0.01080 Ketua Kelompok 0.475 Hok 65,000 30,888
0.10800 Kepala Tukang 4.752 Hok 60,000 285,120
0.10800 Tukang 4.752 Hok 55,000 261,360
0.21600 Pekerja 9.504 Hok 42,500 403,920 981,288 25.8
Sub Total (9) 3,797,563 3,797,563

Pek. Pasangan Buis Beton O dia.40 cm 74.00 M¹ Jumlah (%)


1.000 Buis Beton O dia. 30 cm 74.000 Bh 91,000 6,734,000
0.01250 Semen 40 kg 0.925 sak 56,500 52,263
0.01300 Pasir Pasang 0.962 m3 100,000 96,200 6,882,463 74.5
Tenaga
0.32000 Pekerja 23.680 Hok 42,500 1,006,400
0.16000 Tukang 11.840 Hok 55,000 651,200
0.14000 Kepala Tukang 10.360 Hok 60,000 621,600
0.01600 Ketua Kelompok 1.184 Hok 65,000 76,960 2,356,160 25.5
Sub Total (9) 9,238,623 9,238,623
ANALISA SALURAN BUIS BETON

Pek. Pasangan Buis Beton O dia.20 cm 35.00 M¹ Jumlah (%)


1.000 Buis Beton O dia. 20 cm 35.000 Bh 47,000 1,645,000
0.01250 Semen 40 kg 0.438 sak 56,500 24,719
0.01300 Pasir Pasang 0.455 m3 100,000 45,500 1,715,219 74.8
Tenaga
0.16000 Pekerja 5.600 Hok 42,500 238,000
0.08000 Tukang 2.800 Hok 55,000 154,000
0.08000 Kepala Tukang 2.800 Hok 60,000 168,000
0.00800 Ketua Kelompok 0.280 Hok 65,000 18,200 578,200 25.2
Sub Total (9) 2,293,419 2,293,419

ANALISA KABUPATEN SITUBONDO

Pek. Pasangan Buis Beton O dia.20 cm 35.00 M¹ Jumlah (%)


1.000 Buis Beton O dia. 20 cm 35.000 Bh 47,000 1,645,000
0.01250 Semen 40 kg 0.438 sak 56,500 24,719
0.01300 Pasir Pasang 0.455 m3 100,000 45,500 1,715,219 85.6
Tenaga -
0.08000 Pekerja 2.800 Hok 42,500 119,000
0.04000 Tukang 1.400 Hok 55,000 77,000
0.04000 Kepala Tukang 1.400 Hok 60,000 84,000
0.00400 Ketua Kelompok 0.140 Hok 65,000 9,100 289,100 14.4
Sub Total (9) 2,004,319 2,004,319