X PEKERJAAN BONGKARAN :
1 Bongkar dinding 1/2 batu M2pekerja 0.2org/hr
mandor 0.01org/hr
2 Bongkar dinding 1/2 batu M3pekerja 2org/hr
mandor 0.1org/hr
3 Bongkar batu kali M3pekerja 1.5org/hr
(tebal < 50 cm) mandor 0.075org/hr
4 Bongkar batu kali M3pekerja 3org/hr
(tebal < 50 cm) mandor 0.15org/hr
5 Bongkar beton M3tukang 1.2org/hr
kepala tukang 0.12org/hr
pekerja 6org/hr
mandor 0.3org/hr
6Bongkar beton bertulang M3tukang 1.6org/hr
kepala tukang 0.16org/hr
pekerja 8org/hr
mandor 0.4org/hr
7Bongkar lantai M2pekerja 0.1org/hr
mandor 0.01org/hr
8Bongkar plesteran M2pekerja 0.05org/hr
mandor 0.0025org/hr
9Bongkar atas genteng M2pekerja 0.02org/hr
mandor 0.01org/hr
1
0Bongkar karpusan atap genteng M2pekerja 0.03org/hr
mandor 0.015org/hr
11Bongkar atap seng/asbes M2tk. Besi 0.05org/hr
pekerja 0.01org/hr
1
2Bongkar kaso & reng kayu M2tk. Kayu 0.025org/hr
(kayu tidak dipakai lagi) ke. Tk. Kayu 0.0025org/hr
pekerja 0.1org/hr
mandor 0.005org/hr
1
3Bongkar rangka atap kuda-2 kayuM3tukang kayu 1org/hr
kepala tukang 0.2org/hr
1
4Bongkar plafond + rangka M2pekerja 0.04org/hr
mandor 0.02org/hr
1Bongkar lisplank M' pekerja 0.03org/hr
5
mandor 0.015org/hr
1
6Bongkar kusen pintu M3tukang 1org/hr
kepala tukang 0.1org/hr
1
7Bongkar daun pintu M2pekerja 0.02org/hr
mandor 0.001org/hr
1
8Bongkar kaca M2pekerja 0.03org/hr
mandor 0.003org/hr
1
9Bongkar rabat beton M2pekerja 0.05org/hr
mandor 0.0025org/hr
2
0Bongkar bak air teraso BHpekerja 0.3org/hr
mandor 0.015org/hr