Anda di halaman 1dari 4

RENCANA ANGGARAN BIAYA

(RAB)
PEKERJAAN : PEMBANGUNAN JALAN LINGKUNGAN DI KAMPUNG TOMAGE

LOKASI : DISTRIK TOMAGE

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT.
(RP) (RP)

A PEKERJAAN PERSIAPAN Rp 23,500,000.00


1 Pembersihan Dan Perataan 1.00 Ls Rp 2,000,000.00 Rp 2,000,000.00
2 Penyediaan Air Kerja 1.00 Ls Rp 1,500,000.00 Rp 1,500,000.00
3 Penyediaan urugan/timbunan 50.00 M 3
Rp 400,000.00 Rp 20,000,000.00

B PEKERJAAN COR BETON JALAN Rp 195,795,469.28


1 Membuat Jalan Beton Camp. 1pc : 2ps : 3kr Tebal 20 cm 75.00 M3 Rp 2,570,606.26 Rp 192,795,469.28
2 Memasang Bekisting Papan 1.00 M 3
Rp 3,000,000.00 Rp 3,000,000.00

JUMLAH Rp 219,295,469.28
PPN 10% Rp 21,929,546.93
TOTAL Rp 241,225,016.20
DIBULATKAN Rp 241,200,000.00
TERBILANG :
Dua Ratus Empat Puluh Satu Juta Dua Ratus Ribu Rupiah
DAFTAR ANALISA PEKERJAAN

HARGA HARGA HARGA HARGA


NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)

I PEKERJAAN TANAH (SNI 2835 : 2008)


1 1 M3 URUGAN TANAH PILIHAN DIPADATKAN
1.2000 m3 Tanah Urug 220,465.35 264,558.42
0.5000 oh Pekerja 100,000.00 50,000.00
0.0500 oh Mandor 150,000.00 7,500.00
Total : 57,500.00 264,558.42 322,058.42

II PEKERJAAN PONDASI (SNI 2836 : 2008)


1 1 M3 BATU KALI CAMP. 1 PC : 4 PS
1.2000 m3 Batu Kali / Batu Bulat 15/20 737,334.12 884,800.94
163.0000 kg Semen Portland 3,411.09 556,008.29
0.5200 m3 Pasir Pasang 345,000.00 179,400.00
1.5000 oh Pekerja 100,000.00 150,000.00
0.7500 oh Tukang Batu 150,000.00 112,500.00
0.0750 oh Kepala Tukang 150,000.00 11,250.00
0.0750 oh Mandor 150,000.00 11,250.00
Total : 285,000.00 1,620,209.22 1,905,209.22
III PEKERJAAN BETON ( SNI 7394:2008)
1 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR
280.0000 kg Semen Portland 3,411.09 955,106.26
0.4500 m3 Pasir Beton 345,000.00 155,250.00
0.9000 m3 Koral Beton 1,380,000.00 1,242,000.00
1.6500 oh Pekerja 100,000.00 165,000.00
0.2500 oh Tukang Batu 150,000.00 37,500.00
0.0250 oh Kepala Tukang 150,000.00 3,750.00
0.0800 oh Mandor 150,000.00 12,000.00
Total : 218,250.00 2,352,356.26 2,570,606.26

2 1 M2 PASANG BEKISTING UNTUK SLOOF


0.0400 m3 Kayu Bekisting 1,725,000.00 69,000.00
0.3000 kg Paku Biasa 5' - 10' 28,750.00 8,625.00
0.1000 ltr Minyak Bekisting 18,372.11 1,837.21
0.5200 oh Pekerja 100,000.00 52,000.00
0.2600 oh Tukang Kayu 150,000.00 39,000.00
0.0260 oh Kepala Tukang 150,000.00 3,900.00
0.0260 oh Mandor 150,000.00 3,900.00
Total : 98,800.00 79,462.21 178,262.21
DAFTAR HARGA SATUAN BAHAN

HARGA
NO NAMA BARANG SATUAN
(Rp)

1 Papan Cor/Papan Kayu Putih m3 Rp. 1,725,000.00


2 Paku 5 biasa kg Rp. 28,750.00
3 Batu Pecah 2-3 m3 Rp. 1,380,000.00
4 Pasir Lokal m3 Rp. 345,000.00
5 Tanah urug m3 Rp. 220,465.35
6 Semen Tonasa 40 kg kg Rp. 3,411.09
DAFTAR HARGA SATUAN UPAH

HARGA
NO NAMA BARANG SATUAN
(Rp)

1 Mandor Hari Rp 150,000.00


2 Kepala Tukang Hari Rp 150,000.00
3 Tukang Batu Hari Rp 150,000.00
4 Tukang kayu Hari Rp 150,000.00
5 Tukang gali/buruh/ pekerja Hari Rp 100,000.00
6 Pekerja Hari Rp 100,000.00

Anda mungkin juga menyukai