No.RAB : 1
Bidang : PEMBANGUNAN DESA
Kegiatan : GRAVEL PASANGAN BATU BATA DAN PENUTUP SALURAN
Pagu Anggaran : Rp. 28.391.500,-
Waktu Pelaksanaan : 25 Hari
Rincian Pendanaan : …………….
Volume Kegiatan : 53 m
Penerima manfaat : Laki-laki = 45 Orang
Perempuan= 175 Orang
ARTM = 75 Orang
VOLUME KEGIATAN
Type 1 Type 2
Panjang Saluran : 53 m'
Tinggi Pas.Batu Bata : 0.30 m'
diameter Gravel : 20 Cm
PDTI : ( Munawir )
PENUTUP SALURAN 0.25
#REF!
DAFTAR HARGA SATUAN BAHAN, ALAT & UPAH KONSTRUK
HARGA
No URAIAN BAHAN, ALAT & UPAH SATUAN
SATUAN
A BAHAN
HARGA
No URAIAN BAHAN, ALAT & UPAH SATUAN
SATUAN
B ALAT
C UPAH
1 Mandor OH 110,000
2 Tukang OH 100,000
3 Pekerja/Laden OH 80,000
4 Operator Terlatih OH 135,000
5 Operator KURANG Terlatih OH 85000
6 Pembantu Operator OH 80,000
7 Supir Truck OH 85000
8 Pembantu Supir OH 80000
Ongkos Angkut Khusus Lokasi Tidak terjangkau Truck
a Ongkos Angkut Semen zak 10,000
b Ongkos Angkut Pasir m3 80,000
c Ongkos Angkut Batu Bh 500
d Ongkos Angkut Gravel bh 5,000
D Lain - Lain
1 Papan Proyek 1Ls 150,000
2 Prasasti 1Ls 500,000
3 Plastik cor kg 110,000
4 Kawat Ayakan m3 20,000
5 Alat bantu lain2 Ls 250,000
6 Alat bantu Pengaspalan Set 350,000
7
8
9
10
URAIAN
BAHAN
Batu bata
Semen (50kg)
Plesteran 0.20 Pasangan 1/2 Bata Pasir Pasang
0.15 0.15 UPAH
Muka Tanah Pekerja
Tukang
0.30 Mandor
URAIAN
BAHAN
Semen (50kg)
Pasir
UPAH
Pekerja
Tukang
Mandor
1 M2 ACIAN
Luas Acian =
=(
=
URAIAN
BAHAN
Semen (50kg)
UPAH
Pekerja
Tukang
Mandor
0.30 a
0.30 1 M3 GALIAN TANAH BI
V Galian =
=(
0.15 0.15 =
b
UPAH
Pekerja
Mandor
URAIAN
BAHAN
Gravel 1/2 dia.
Semen
Upah
Mandor
ONGKOS ANGKUT MATERIAL Tukang
Hasil musyawarah ongkos angkut material sbb: Pekerja
Semen = Rp. 10,000 / Zak
Pasir = Rp. 80,000 / m3 REKAPITULASI KEBUTUHA
Batu = Rp. 500 / m3
Gravel = Rp. 5000 bh BAHAN
1 Gravel
HOK untuk angkut material adalah: 2 Batu Bata
1 Gravel = 53 bh 3 Pasir Pasang
Upah Pekerja adalah = 80,000 /hari 4 Semen 50 Kg
Produktifitas Pekerja= 80,000 / 5,000 = 16 zak /hari 5 Bambu
Kebutuhan Pekerja = 53 / 16 = 3.3 OH 6 Paku 7"
HOK untuk angkut material adalah:
1 Semen = 49 Zak ALAT
Upah Pekerja adalah = 80,000 /hari 1 Ember Aduk
Produktifitas Pekerja= 80,000 / 10,000 = 8 zak /hari 2 Benang
Kebutuhan Pekerja = 49 / 8.00 = 6.1 OH
2 Pasir = 2 m3
Upah Pekerja adalah = 80,000 /hari
Produktifitas Pekerja= 80,000 / 80,000 = 1 m3 /hari UPAH
Kebutuhan Pekerja = 2 / 1.00 = 2.0 OH 1 Mandor
3 Batu = 2,226 Bh 2 Tukang
Upah Pekerja adalah = 80,000 /hari 3 Pekerja
Produktifitas Pekerja= 80,000 / 250 = 320 Bh /hari Pekerja anggkut semen
Kebutuhan Pekerja = ### / 320.00 = 7.0 OH Pekerja angkut Pasir
Pekerja angkut Batu
Pengukuran Tanggal:
Diukur oleh:
N DAN UPAH
an Volume dan Kebutuhan Bahan, Alat dan Upah ( Analisis DTRCK Kab.Cirebon )
31.80 m2
KOEFISIEN
LESTERAN 1 Pc : 3 Ps TEBAL 15 mm
(L.atas + 0,05 + 0,05) x Panjang Sal. x (Kn-Kr)
0.15 + 0.10 ) x 53 x 2
27 m 2
KOEFISIEN
CIAN
(L.atas + 0,05 + 0,05) x Panjang Sal x (Kn-Kr)
0.15 + 0.10 ) x 53 x 2
27 m2
KOEFISIEN
KOEFISIEN
= 0.750 x 4.77 = 3.58 OH
= 0.025 x 4.77 = 0.12 OH
sang Gravel
s Gravel = Panjang SPAL/Saluran
= 53 m'
KOEFISIEN
20 Cm = 1.000 x 53 = 53.00 bh
= 0.020 x 53 = 1.06 zak
= 0.012 x 53 = 0.64 OH
= 0.056 x 53 = 2.97 OH
= 0.120 x 53 = 6.36 OH
= 53 ~ 53 bh
= 2,226 ~ 2,226 bh
= 1.9 ~ 2 m3
= 15.0 ~ 49 zak
= 2.12 ~ 2 batang
= 1.06 ~ 1 Kg
= 1.1 ~ 1 bh
= 0.5 ~ 1 bh
= 1.9 ~ 2 OH
= 13.8 ~ 14 OH
= 32.7 ~ 33 OH
nggkut semen = 6.1
gkut Pasir = 2.0
gkut Batu = 7.0 +
15.0 OH
DAFTAR PERHITUNGAN BAHAN DAN UPAH
1 M2 PLESTERAN 1 Pc :
Luas Plesteran =
=(
=
URAIAN
BAHAN
Semen (50kg)
Pasir
UPAH
Pekerja
Tukang
Mandor
1 M2 ACIAN
Luas Acian =
=(
=
URAIAN
BAHAN
Semen (50kg)
UPAH
Pekerja
Tukang
Mandor
0.30 a
1 M3 GALIAN TANAH BI
V Galian =
=(
0.15 =
b
UPAH
Pekerja
Mandor
Upah
Mandor
Tukang
ONGKOS ANGKUT MATERIAL Pekerja
Hasil musyawarah ongkos angkut material sbb:
Semen = Rp. 10,000 / Zak REKAPITULASI KEBUTUHA
Pasir = Rp. 80,000 / m3
Batu = Rp. 500 / m3 BAHAN
Gravel = Rp. 5000 bh 1 Gravel
2 Batu Bata
HOK untuk angkut material adalah: 3 Pasir Pasang
1 Gravel = - bh 4 Semen 50 Kg
Upah Pekerja adalah = 80,000 /hari 5 Bambu
Produktifitas Pekerja= 80,000 / 5,000 = 16 zak /hari 6 Paku 7"
Kebutuhan Pekerja = - / 16 = - OH
1 Semen = - Zak ALAT
Upah Pekerja adalah = 80,000 /hari 1 Ember Aduk
Produktifitas Pekerja= 80,000 / 10,000 = 8 zak /hari 2 Benang
Kebutuhan Pekerja = - / 8.00 = - OH
2 Pasir = - m3
Upah Pekerja adalah = 80,000 /hari
Produktifitas Pekerja= 80,000 / 80,000 = 1 m3 /hari UPAH
Kebutuhan Pekerja = - / 1.00 = - OH 1 Mandor
3 Batu = - m3 2 Tukang
Upah Pekerja adalah = 80,000 /hari 3 Pekerja
Produktifitas Pekerja= 80,000 / 500 = 160 m3 /hari Pekerja anggkut semen
Kebutuhan Pekerja = - / 160.00 = - OH Pekerja angkut Pasir
Pekerja angkut Batu
Pengukuran Tanggal:
Diukur oleh:
N DAN UPAH
an Volume dan Kebutuhan Bahan, Alat dan Upah ( Analisis DTRCK Kab.Cirebon )
- m3
KOEFISIEN
= 70 x - = - bh
14.37 Kg = 0.2874 x - = - zak
= 0.04 x - = - m3
= 0.3 x - = - OH
= 0.11 x - = - OH
= 0.015 x - = - OH
LESTERAN 1 Pc : 3 Ps TEBAL 15 mm
(L.atas + 0,05 + 0,05) x Panjang TPT x (Sebelah Kn atau Kr saja)
0.15 + 0.10 ) x - x 1
- m 2
KOEFISIEN
= 0.300 x - = - OH
= 0.165 x - = - OH
= 0.015 x - = - OH
CIAN
(L.atas + 0,05 + 0,05) x Panjang TPT x (Sebelah Kn atau Kr saja)
0.15 + 0.10 ) x - x 1
- m2
KOEFISIEN
= 0.200 x - = - OH
= 0.110 x - = - OH
= 0.010 x - = - OH
KOEFISIEN
= 0.750 x - = - OH
= 0.025 x - = - OH
sang Gravel
s Gravel = Panjang SPAL
= 0 m'
KOEFISIEN
20 Cm = 1.000 x 0 = - bh
= 0.020 x 0 = - zak
= 0.012 x 0 = - OH
= 0.056 x 0 = - OH
= 0.120 x 0 = - OH
= - ~ - bh
= - ~ - bh
= - ~ - m3
= - ~ - zak
= 0 ~ - batang
= 0 ~ - Kg
= - ~ - bh
= - ~ - bh
= - ~ - OH
= - ~ - OH
= - ~ - OH
nggkut semen = 0.0
gkut Pasir = 0.0
gkut Batu = 0.0 +
- OH
REKAPITULASI KEBUTUHAN BAHAN, ALAT DAN UPAH
Volume Kegiatan = 53 + - + = 53 m
2 Batamerah
= 2226 + 0 + = 2,226.0 ~ 2,226
3 Pasir Pasang
= 2 + 0 + = 2.0 ~ 2
= 12.00
4 Kaso 5/7 albasia panjang 3 m
= 6.00
5 Papan 3/20 albasia panjang 3 m
= 4.00
6 Triplex/Multiplex 9 mm
= 4.00
7 Paku Biasa 5 - 7 cm
= 37.00
8 Besi beton Ø 10 mm
= 4.00
9 Kawat Beton
12 Semen 50 Kg
= 33.60 + 49 + = 82.2 ~ 82
13 Bambu
= 2 + 0 + = 2.0 ~ 2
14 Paku
= 5.00 + 0 + = 5.0 ~ 5
ALAT
1 Ember aduk
= 1.06 + - + = 1.1 ~ 1
2 Benang
= 0.53 + - + = 0.5 ~ 1
UPAH
1 Mandor
= 2.63 + 2.0 + = 4.6 ~ 5
2 Tukang
= 8.05 + 14.0 + = 22.1 ~ 22
3 Pekerja
= 19.80 + 33.0 + = 52.8 ~ 53
Total Pekerja ~ 71
mbulatan
bh
bh
m3
zak
batang
Kg
bh
Rol
OH
OH
OH
OH
RENCANA ANGGARAN BIAYA
DESA CILEDUGKULON KECAMATAN CILEDUG
TAHUN ANGGARAN 2018
Bidang :
PEMBANGUNAN DESA
Kegiatan :
GRAVEL PASANGAN BATU BATA DAN PENUTUP SA
Pagu Anggaran :
Rp. 28.391.500,-
Waktu Pelaksanaan :
25 Hari
Rincian Pendanaan :
…………….
Volume Kegiatan : 32 m
Penerima manfaat :
Laki-laki 45
Perempuan 175
ARTM 75
HARGA
NO URAIAN VOLUME SATUAN SATUAN
( Rp )
GRAVEL PASANGAN BATU BATA DAN PENUTUP SALURAN
A BELANJA PEGAWAI
Honor Tim Perencanaan
1. Honor Tim Perencanaan 1 orang 100,000
Honor TPK
1. Ketua 1 orang 50,000
2. Sekertaris 1 orang 25,000
3. Anggota 1 orang 20,000
Honor Tim Pendampingan
C Belanja Modal
Gravel ᶲ 20 '' 53 bh 40,000
Batamerah 2,226 bh 900
Pasir Pasang 2 m3 205,000
Semen 50 Kg 82 Zak 78,000
Batu pecah 2/3 2.70 m3 288,000
Pasir Beton 4.05 m3 230000
Kaso 5/7 albasia panjang 3 m 12 btg 50,000
Papan 3/20 albasia panjang 3 m 6 lbr 33,000
Triplex/Multiplex 9 mm 4 lbr 230,000
Besi beton Ø 10 mm 35 Btg 155,000
Kawat Beton 4 kg 23,000
Paku 7" 5 Kg 18,000
Orang
Orang
Orang
JUMLAH
( Rp )
100,000
50,000
25,000
20,000
50,000
30,000
15,000
3,000
150,000
-
20,000
30,000
70,000
75,000
700,000
100,000
2,120,000
2,003,400
410,000
6,396,000
777,600
931,500
600,000
198,000
920,000
5,425,000
92,000
90,000
550,000
2,200,000
4,240,000
28,391,500
1,402,800
107,000
26,881,700
( BBBBBBB )
GAMBAR RENCANA PRASARANA
KABUPATEN
Cirebon
KECAMATAN
Ciledug
DESA
Ciledugkulon
JENIS PRASARANA
GRAVEL PASANGAN BATU BATA DAN PENUT
LOKASI
RT. 04 RW. 002
JUDUL GAMBAR
PETA LOKASI KEGIATAN
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
( Aaaaaaaa )
Diperiksa dan Disetujui oleh :
( Munawir )
Menyetujui
Kepala Desa Ciledugkulon
( H. Wawan Kurniawan )
Lembar 01 Dari…..Lembar
GAMBAR RENCANA PRASARANA
TPT TYPE-1
GAMBAR RENCANA
KABUPATEN
Cirebon
KECAMATAN
Ciledug
DESA
Ciledugkulon
JENIS PRASARANA
GRAVEL PASANGAN BATU BATA DAN PENUT
LOKASI
RT. 04 RW. 002
JUDUL GAMBAR
Potongan Melintang
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
( Aaaaaaaa )
Diperiksa dan Disetujui oleh :
( Munawir )
MELINTANG Menyetujui
Kepala Desa Ciledugkulon
( H. Wawan Kurniawan )
Lembar 02 Dari…..Lembar
GAMBAR RENCANA PRASARANA
( Aaaaaaaa )
53 m Diperiksa dan Disetujui oleh :
( Munawir )
Menyetujui
DETAIL TPT Kepala Desa Ciledugkulon
MEMANJANG
( H. Wawan Kurniawan )
Lembar 03 Dari…..Lembar
GAMBAR RENCANA PRASARANA
GAMBAR RENCANA
TPT TYPE-2
KABUPATEN
Cirebon
KECAMATAN
Ciledug
DESA
Ciledugkulon
JENIS PRASARANA
GRAVEL PASANGAN BATU BATA DAN PENUT
LOKASI
RT. 04 RW. 002
JUDUL GAMBAR
Potongan Melintang
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
( Aaaaaaaa )
Diperiksa dan Disetujui oleh :
( Munawir )
Menyetujui
Kepala Desa Ciledugkulon
Plesteran Ban t. 5 cm
Camp. 1PC : 5 Ps KABUPATEN
Cirebon
KECAMATAN
Ciledug
DESA
Ciledugkulon
JENIS PRASARANA
GRAVEL PASANGAN BATU BATA DAN PENUT
0.00
LOKASI
0.00
RT. 04 RW. 002
Muka Tanah JUDUL GAMBAR
Potongan Memanjang
Digambar Oleh
0.00 Pelaksana Kegiatan
(Kader Teknik)
( Aaaaaaaa )
#REF! m Diperiksa dan Disetujui oleh :
( Munawir )
Menyetujui
DETAIL TPT Kepala Desa Ciledugkulon
MEMANJANG
( H. Wawan Kurniawan )
Lembar 05 Dari…..Lembar
ANA
n
ANA
AN PENUTUP SALURAN
02
AR
GIATAN
eh
atan
k)
)
ujui oleh :
ugkulon
awan )
Lembar
ANA
n
ANA
AN PENUTUP SALURAN
02
AR
ng
eh
atan
k)
)
ujui oleh :
ugkulon
awan )
Lembar
ANA
n
ANA
AN PENUTUP SALURAN
02
AR
njang
eh
atan
k)
)
ujui oleh :
ugkulon
awan )
Lembar
ANA
n
ANA
AN PENUTUP SALURAN
02
AR
ng
eh
atan
k)
)
ujui oleh :
ugkulon
awan )
Lembar
ANA
n
ANA
AN PENUTUP SALURAN
02
AR
njang
eh
atan
k)
)
ujui oleh :
ugkulon
awan )
Lembar
B A
B A
Plesteran 1: 5
Plesteran 1: 5
0.1
0.05 Urugan Pasir
0.15 0.25 0.15 0.15 0.25
POTONGAN A - A POTONGAN B - B
PROGRAM
PEMBANGUNAN &
PEMBERDAYAAN
MASYARAKAT DESA
PEKERJAAN : SALURAN
DRAINASE
VOLUME : 150 M
LOKASI : BLOK KEBUN KELAPA
0.2
JUDUL GAMBAR
)
POTONGAN B - B (
DOKUMEN PERENCANAAN
SKETSA
Urugan Pasir
2 Bekisting Alas = p
Tanggal Survey :
Kecamatan
VOLUME PEKERJAAN Desa
Lokasi
DUIKER Pakucu
PERHITUNGAN
6.40 m3
Ʃ= 11.13
= 4.77 m2
x l = 53 x 0.6 = 6.36 m2
Layer
4.77 m3
Dibuat Oleh :
Kaur Program, TPK dan PDTI
: Ciledug
: Cileduglor
: Pakucu
VOLUME
Volume =
6.40 m3
Volume =
0.32 m3
Volume =
2.70 m3
32.00
m3
Volume
12.00 m2
m2
Volume
Ø. 10 = 35.00 btg
Ø. 10 = 259.14 kg
btg
Volume
5.00 m3
Volume :
1 bh
P3MD Kabupaten Cirebon
5. Pekerjaan Pembesian
Besi Beton Ø 10 mm
Volume = 259.14 Kg
* Bahan Besi beton Ø 10 mm = 1.0500 x 259.14 =
Kawat Beton = 0.0150 x 259.14 =
6. Pekerjaan Pengecoran
Volume = 1 bh
Volume : P 4 M X L 0.8 M
Pekerja Tukang
= 1.00 m3
3.240 m3 = 4.00 m3
1.469 m3 = 2.00 m3
7.344 sak = 8.00 sak
1.000 = 1.00 bh
1.00
1.00
0.10
4.00
2.00
8.00
1.00
12.000
1.00
1.00
33.60
0.53
0.10
4.73 1.00 4.00 2.00 41.60 12.00
Multiplek 9 mm Paku 4-7 Bambu Besi 8mm Besi 12mm Kawat Beton Batu Pecah 2/3 Pasir Beton
6.000
3.60
2.70
4.05