VOLUME KEGIATAN
Type 1
Panjang : 100 m'
Tinggi T ≥ 50 cm : 0.5 m' Tinggi jadinya 0.70
Lebar Atas TPT : 0.25 m' (Sudah sam galian)
BONGKARAN
DATA PONDASI Pasangan Lama
Panjang : 40 m'
Lebar : 0.25 m'
Tinggi : 0.50 m'
sarana Jalan Desa ( Tembok Penahan Tanah )
m
DAFTAR HARGA SATUAN BAHAN, ALAT & UPAH KONSTRUK
HARGA
No URAIAN BAHAN, ALAT & UPAH SATUAN
SATUAN
A BAHAN
HARGA
No URAIAN BAHAN, ALAT & UPAH SATUAN
SATUAN
B ALAT
C UPAH
1 Mandor OH 120,000
2 Tukang OH 110,000
3 Pekerja/Laden OH 80,000
4 Operator Terlatih OH 140,000
5 Operator KURANG Terlatih OH 85,000
6 Pembantu Operator OH 80,000
7 Supir Truck OH 90,000
8 Pembantu Supir OH 80,000
Ongkos Angkut Khusus Lokasi Tidak terjangkau Truck
a Ongkos Angkut Semen zak 1
b Ongkos Angkut Pasir m3 2
c Ongkos Angkut Batu m3 3
d Ongkos Angkut Bgravel m4 4
D Lain - Lain
1 Papan Proyek 1Ls 250,000
2 Prasasti 1Ls 500,000
3 Plastik cor kg 42,000
4 Kawat Ayakan m3 30,000
5 Alat bantu lain2 Ls 265,000
6 Alat bantu Pengaspalan Set 385,000
7
8
9
10
No Sket Gambar Perhitungan Volume dan Kebutuhan Bahan, Alat dan Upah (Analisa DTRCK Kab.Cirebon)
URAIAN KOEFISIEN
0.25 BAHAN
Batu belah = 1.200 x 19.75 = 23.70 m3
Semen (50kg) 136 Kg = 2.720 x 19.75 = 53.72 Zak
Pasir = 0.544 x 19.75 = 10.74 m3
UPAH
Pekerja = 1.500 x 19.75 = 29.63 OH
cm
Tukang = 0.825 x 19.75 = 16.29 OH
Mandor = 0.075 x 19.75 = 1.48 OH
0.50
1 M2 PLESTERAN 1 Pc : 5 Ps TEBAL 15 mm
Luas Plesteran = (L.atas + 0,10+0,05) x Panjang TPT
0.70 m =( 0.25 + 0.15 ) x 100
= 40.00 m2
URAIAN KOEFISIEN
0.20
Plesteran Ban
Camp. 1Pc : 5 Ps BAHAN
10 10
Semen (50kg) 5.184 kg = 0.104 x 40.00 = 4.15 Zak
Suling-suli ng
Pasir = 0.026 x 40.00 = 1.04 m3
UPAH
0.30
Pasangan Batu Pekerja = 0.300 x 40.00 = 12.00 OH
Camp 1Pc : 5 Ps
Tukang = 0.165 x 40.00 = 6.60 OH
Mandor = 0.015 x 40.00 = 0.60 OH
DETAIL TPT
1 M2 ACIAN
Luas Acian = (L.atas + 0,1 +0,05 ) x Panjang TPT
=( 0.25 + 0.15 ) x 100
= 40.00 m2
URAIAN KOEFISIEN
BAHAN
Semen (50kg) 3.25 kg = 0.0650 x 40.00 = 2.60 zak
UPAH
Pekerja = 0.200 x 40.00 = 8.00 OH
Plesteran ad. 1pc : 5psr
0.25 Tukang = 0.110 x 40.00 = 4.40 OH
Mandor = 0.010 x 40.00 = 0.40 OH
0.05 0.10
0.20 a
1 M3 GALIAN TANAH BIASA SEDALAM 1 M
Vol. galian = (a x b x Panjang TPT
=( 0.20 x 0.30 )x 100
0.30 = 6.00 m3
b
UPAH KOEFISIEN
Pekerja = 0.750 x 6.00 = 4.50 OH
Mandor = 0.025 x 6.00 = 0.15 OH
BAHAN
Hasil musyswarah ongkos angkut material sbb: 1 Batu Belah = 23.70 = 23.70 m3
Semen = 1 / sak 2 Pasir Pasang = 10.7 + 1.04 = 11.78 m3
Pasir = 2 / m3 3 Semen 50 Kg = 53.7 + 4.1 + 2.60 = 60.47 sak
Batu = 3 / m3 4 Bambu = 4 = 4.00 batang
5 Paku = 2 = 2.00 Kg
HOK untuk angkut material adalah:
1 Semen = 60 sak ALAT
Upah Pekerja adalah = 80,000 /hari 1 Ember aduk = 2.0 = 2.0 bh
Produktifitas Pekerja= 80,000 / 1 = 80,000.00 sak /hari 2 Benang = 1.0 = 1.0 bh
Pengukuran Tanggal:
Diukur oleh:
DAFTAR PERHITUNGAN BAHAN DAN UPAH
JENIS PEKERJAAN : Pembangunan/Rehabilitasi/Peningkatan Prasarana Jalan Desa ( Tembok Penahan TVOLUME KEGIATAN 0 m'
No Sket Gambar Perhitungan Volume dan Kebutuhan Bahan, Alat dan Upah (Analisa DTRCK Kab.Cirebon)
URAIAN KOEFISIEN
0 BAHAN
Batu belah = 1.200 x - = - m3
Semen (50kg) 136 Kg = 2.720 x - = - Zak
Pasir = 0.544 x - = - m3
UPAH
Pekerja = 1.500 x - = - OH
Tukang = 0.825 x - = - OH
Mandor = 0.075 x - = - OH
0.00
1 M2 PLESTERAN 1 Pc : 5 Ps TEBAL 15 mm
Luas Plesteran = (L.atas + 0,10+0,05) x Panjang TPT
- m =( - + 0.15 ) x 0
= - m2
URAIAN KOEFISIEN
-
Plesteran Ban
Camp. 1Pc : 5 Ps BAHAN
10 10
Semen (50kg) 5.184 kg = 0.104 x - = - Zak
Suling-suli ng
Pasir = 0.026 x - = - m3
UPAH
0.00
Pasangan Batu Pekerja = 0.300 x - = - OH
Camp 1Pc : 5 Ps
Tukang = 0.165 x - = - OH
Mandor = 0.015 x - = - OH
DETAIL TPT
1 M2 ACIAN
Luas Acian = (L.atas + 0,1 +0,05 ) x Panjang TPT
=( - + 0.15 ) x 0
= - m2
URAIAN KOEFISIEN
BAHAN
Semen (50kg) 3.25 kg = 0.0650 x - = - zak
UPAH
Pekerja = 0.200 x - = - OH
Plesteran ad. 1pc : 5psr
0 Tukang = 0.110 x - = - OH
Mandor = 0.010 x - = - OH
0.05 0.10
0.00 a
1 M3 GALIAN TANAH BIASA SEDALAM 1 M
Vol. galian = (a x b x Panjang TPT
=( - x - )x 0
0.00 = - m3
b
UPAH KOEFISIEN
Pekerja = 0.750 x - = - OH
Mandor = 0.025 x - = - OH
BAHAN
Hasil musyswarah ongkos angkut material sbb: 1 Batu Belah = - = - m3
Semen = 1 / sak 2 Pasir Pasang = - + - = - m3
Pasir = 2 / m3 3 Semen 50 Kg = - + - + - = - sak
Batu = 3 / m3 4 Bambu = 0 = - batang
5 Paku = 0 = - Kg
HOK untuk angkut material adalah:
1 Semen = - sak ALAT
Upah Pekerja adalah = 80,000 /hari 1 Ember aduk = - = - bh
Produktifitas Pekerja= 80,000 / 1 = 80,000.00 sak /hari 2 Benang = - = - bh
Pengukuran Tanggal:
Diukur oleh:
DAFTAR PERHITUNGAN BAHAN DAN UPAH
JENIS PEKERJAAN : Pembangunan/Rehabilitasi/Peningkatan Prasarana Jalan Desa ( Tembok PenahaVOLUME KEGIATAN 0 m'
No Sket Gambar Perhitungan Volume dan Kebutuhan Bahan, Alat dan Upah (Analisa DTRCK Kab.Cirebon)
URAIAN KOEFISIEN
0 BAHAN
Batu belah = 1.200 x - = - m3
Semen (50kg) 136 Kg = 2.720 x - = - Zak
Pasir = 0.544 x - = - m3
UPAH
Pekerja = 1.500 x - = - OH
Tukang = 0.825 x - = - OH
Mandor = 0.075 x - = - OH
0.00
1 M2 PLESTERAN 1 Pc : 5 Ps TEBAL 15 mm
Luas Plesteran = (L.atas + 0,10+0,05) x Panjang TPT
- m =( - + 0.15 ) x 0
= - m2
URAIAN KOEFISIEN
-
Plesteran Ban
Camp. 1Pc : 5 Ps BAHAN
10 10
Semen (50kg) 5.184 kg = 0.104 x - = - Zak
Suling-suli ng
Pasir = 0.026 x - = - m3
UPAH
0.00
Pasangan Batu Pekerja = 0.300 x - = - OH
Camp 1Pc : 5 Ps
Tukang = 0.165 x - = - OH
Mandor = 0.015 x - = - OH
DETAIL TPT
1 M2 ACIAN
Luas Acian = (L.atas + 0,1 +0,1 ) x Panjang TPT
=( - + 0.15 ) x 0
= - m2
URAIAN KOEFISIEN
BAHAN
Semen (50kg) 3.25 kg = 0.0650 x - = - zak
UPAH
Pekerja = 0.200 x - = - OH
Tukang = 0.110 x - = - OH
Plesteran ad. 1pc : 5psr
0 Mandor = 0.010 x - = - OH
0.00 a 0.05 0.10
1 M3 GALIAN TANAH BIASA SEDALAM 1 M
Vol. galian = (a x b x Panjang TPT
=( - x - )x 0
0.00 = - m3
b
UPAH KOEFISIEN
Pekerja = 0.750 x - = - OH
Mandor = 0.025 x - = - OH
BAHAN
Hasil musyswarah ongkos angkut material sbb: 1 Batu Belah = - = - m3
Semen = 1 / sak 2 Pasir Pasang = - + - = - m3
Pasir = 2 / m3 3 Semen 50 Kg = - + - + - = - sak
Batu = 3 / m3 4 Bambu = 0 = - batang
5 Paku = 0 = - Kg
HOK untuk angkut material adalah:
1 Semen = - sak ALAT
Upah Pekerja adalah = 80,000 /hari 1 Ember aduk = - = - bh
Produktifitas Pekerja= 80,000 / 1 = 80,000 sak /hari 2 Benang = - = - bh
Pengukuran Tanggal:
Diukur oleh:
DAFTAR PERHITUNGAN BAHAN DAN UPAH
JENIS PEKERJAAN : Bongkar Saluran pas Batu bata VOLUME KEGIATAN 40 m'
No Sket Gambar Perhitungan Volume dan Kebutuhan Bahan, Alat dan Upah ( Analisis DTRCK Kab.Cirebon )
UPAH
1 Mandor = 1.67 OH
2 Pekerja = 33.34 OH
Pengukuran Tanggal:
Diukur oleh:
REKAPITULASI KEBUTUHAN BAHAN, ALAT DAN UPAH
1 Batu Belah
= 23.70 + = 23.7 ~ 24 m3
2 Pasir Pasang
= 11.78 + = 11.8 ~ 12 m3
3 Semen 50 Kg
= 60.47 + = 60.5 ~ 60 zak
4 Bambu
= 4.00 + = 4.0 ~ 4 batang
5 Paku
= 2.00 + = 2.0 ~ 2 Kg
ALAT
1 Ember aduk
= 2.00 + = 2.0 ~ 2 bh
2 Benang
= 1.00 + = 1.0 ~ 1 Rol
UPAH
1 Mandor
= 2.63 + +
1.67
= 4.30 ~ 4 OH
2 Tukang
= 27.29 + + = 27.29 ~ 27 OH
= 54.13 + + = 87.46 87 OH
3 Pekerja 33.34
Pekerja anggkut semen = 0.00 + + = 0.00 -
Pekerja angkut Pasir = 0.00 + + = 0.00 -
Pekerja angkut Batu = 0.00 + + = 0.00 -
Rincian Pendanaan :
HARGA
JUMLAH
NO URAIAN VOLUME SATUAN SATUAN
( Rp ) ( Rp )
Pembangunan/Rehabilitasi/Peningkatan Prasarana Jalan Desa ( Tembok Penahan Tanah )
01 Belanja Modal Honor Tim yang Melaksanakan Kegiatan
Honorarium TPK
Ketua 1 Keg 395,000 395,000
Sekertaris 1 Keg 237,000 237,000
Seksi Teknis 1 Keg 158,000 158,000
02 Belanja Modal Upah Tenaga Kerja
Mandor Lapangan 4 OH 120,000 480,000
Tukang/Buruh Terlatih 27 OH 110,000 2,970,000
Pekerja/Buruh Tak Terlatih 87 OH 80,000 6,960,000
03 Belanja Modal Bahan Baku -
Batu Belah 24 m3 345,000 8,280,000
Pasir Pasang 12 m3 223,000 2,676,000
Semen 50 Kg 60 zak 65,000 3,900,000
Bambu 4 Batang 19,500 78,000
Paku 7" 2 Kg 23,000 46,000
Ember 2 Bh 25,000 50,000
Benang 1 Rol 3,500 3,500
Papan Proyek 1 Paket 250,000 250,000
Prasasti 1 Paket 500,000 500,000
04 Belanja Modal Sewa Peralatan
Sewa Gerobak 4 1Bh/Hari 17,500 70,000
05 Belanja Modal Administrasi Kegiatan
ATK (Materai,Kwitansi,Pulpen,dll) 1 Ls 100,000 100,000
Cetak Pengadaan (Fotocopy & Jilid) 1 paket 150,000 150,000
KABUPATEN
Pasaleman
KECAMATAN
Cirebon
DESA
Tonjong
JENIS PRASARANA
Pembangunan/Rehabilitasi/Peningkatan Prasarana Jalan Desa ( Te
LOKASI
Dusun Getrak
JUDUL GAMBAR
PETA LOKASI KEGIATAN
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
(………………….)
Diperiksa dan Disetujui oleh :
( Dadang Iskandar )
Menyetujui
Kuwu Desa Tonjong
(………………….)
Lembar 01 Dari…..Lembar
GAMBAR RENCANA PRASARANA
TPT TYPE-1
GAMBAR RENCANA
0.25 m KABUPATEN
Pasaleman
KECAMATAN
Cirebon
DESA
5 Cm Tonjong
Cm
JENIS PRASARANA
Pembangunan/Rehabilitasi/Peningkatan Prasarana Jalan Desa ( Te
0.50 m LOKASI
Dusun Getrak
0.70 m
JUDUL GAMBAR
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
Plesteran Ban
0.20 m
Camp. 1Pc : 5 Ps
10 10
(………………….)
Suling-suling
Diperiksa dan Disetujui oleh :
0.30 m
Pasangan Batu
Camp 1Pc : 5 Ps
( Dadang Iskandar )
Menyetujui
DETAIL TPT Kuwu Desa Tonjong
MELINTANG (………………….)
Lembar 02 Dari…..Lembar
GAMBAR RENCANA PRASARANA
Digambar Oleh
0.20 Pelaksana Kegiatan
(Kader Teknik)
(………………….)
100 Diperiksa dan Disetujui oleh :
( Dadang Iskandar )
Menyetujui
DETAIL TPT Kuwu Desa Tonjong
MEMANJANG
(………………….)
Lembar 03 Dari…..Lembar
RENCANA ANGGARAN BIAYA
DESA TONJONG KECAMATAN PASALEMAN
KABUPATEN CIREBON
DOKUMEN PERENCANAAN
Volume : 100 m
012