Anda di halaman 1dari 20

Rencana Anggaran Biaya (RAB)

PEKERJAAN : PEMBANGUNAN RUKO DI WAGOM FAKFAK


LOKASI : WAGOM FAKFAK

TAHUN ANGGARAN : 2021

JUMLAH HARGA
NO. JENIS PEKERJAAN
(RP)

A PEKERJAAN PERSIAPAN Rp. 15.071.532,00


B PEKERJAAN TANAH Rp. 43.742.336,78
C PEKERJAAN BETON Rp. 1.065.472.354,28
D PEKERJAAN DINDING DAN PLESTERAN Rp. 181.054.406,40
E PEKERJAAN KAYU Rp. 90.405.228,79
F PEKERJAAN PENUTUP ATAP Rp. 46.558.472,00
G PEKERJAAN LANGIT-LANGIT Rp. 72.225.234,50
H PEKERJAAN PENUTUP LANTAI DAN DINDING Rp. 359.053.565,04
I PEKERJAAN PENGECATAN Rp. 75.314.144,00
J PEKERJAAN SANITAIR Rp. 57.542.157,05
K PEKERJAAN BESI DAN ALUMINIUM Rp. 292.194.559,76
L PEKERJAAN KUNCI DAN KACA Rp. 5.867.603,61
M PEKERJAAN ELEKTRIKAL Rp. 16.917.400,00

JUMLAH Rp 2.321.418.994,23
PPN 10% Rp 232.141.899,42
TOTAL Rp 2.553.560.893,65
DIBULATKAN Rp 2.553.500.000,00

TERBILANG :
Dua Milyar Lima Ratus Lima Puluh Tiga Juta Lima Ratus Ribu Rupiah

Fakfak, 11 Januari 2021

...................................
Pelaksana
Rencana Anggaran Biaya (RAB)
PEKERJAAN : PEMBANGUNAN RUKO DI WAGOM FAKFAK
LOKASI : WAGOM FAKFAK

TAHUN : 2021

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

A PEKERJAAN PERSIAPAN Rp 15.071.532,00


1 Pengukuran dan Pasangan Bowplank 68,00 m' Rp 65.744,00 Rp 4.470.592,00
2 Pembuatan Gudang Semen dan Alat-alat 9,00 m2 Rp 955.660,00 Rp 8.600.940,00
3 Pembersihan Dan Perataan Lapangan 1,00 Ls Rp 1.000.000,00 Rp 1.000.000,00
4 Penyediaan Air dan Listrik Kerja 1,00 Ls Rp 1.000.000,00 Rp 1.000.000,00

B PEKERJAAN TANAH Rp 43.742.336,78


LANTAI 1
1 Galian Tanah Cadas 88,60 m3 Rp 159.000,00 Rp 14.087.400,00
2 Pasangan Pondasi Batu Belah camp. 1pc : 4pp 20,00 m3 Rp 1.120.400,00 Rp 22.408.000,00
3 Urugan Tanah Pilihan Dipadatkan 23,53 m3 Rp 307.940,00 Rp 7.246.936,78

C PEKERJAAN BETON Rp 1.065.472.354,28


LANTAI 1
1 Membuat Pondasi Foot plat Beton Bertulang - P 100x100x30cm
a. Beton camp. 1pc : 2ps : 3kr 12,96 m3 Rp 1.329.750,00 Rp 19.148.400,00
b. Besi 1.470,13 kg Rp 15.085,00 Rp 24.641.021,66
c. Bekisting 51,84 m2 Rp 189.730,00 Rp 10.928.448,00
2 Membuat Kolom Pedestal Beton Bertulang - K1 35/35 cm
a. Beton camp. 1pc : 2ps : 3kr 4,08 m3 Rp 1.329.750,00 Rp 6.031.746,00
b. Besi 733,62 kg Rp 15.085,00 Rp 12.296.226,93
c. Bekisting 54,43 m2 Rp 189.730,00 Rp 11.474.870,40
3 Membuat Sloof Beton Bertulang - S1 20/30 cm
a. Beton camp. 1pc : 2ps : 3kr 9,86 m3 Rp 1.329.750,00 Rp 14.560.762,50
b. Besi 1.719,88 kg Rp 15.085,00 Rp 28.827.098,74
c. Bekisting 98,55 m2 Rp 189.730,00 Rp 20.775.435,00
4 Membuat Sloof Beton Bertulang - S2 15/20 cm
a. Beton camp. 1pc : 2ps : 3kr 0,30 m3 Rp 1.329.750,00 Rp 448.790,63
b. Besi 54,31 kg Rp 15.085,00 Rp 910.229,82
c. Bekisting 4,05 m2 Rp 189.730,00 Rp 853.785,00
5 Membuat Kolom Beton Bertulang - K1 35/35 cm
a. Beton camp. 1pc : 2ps : 3kr 12,55 m3 Rp 1.329.750,00 Rp 18.535.651,20
b. Besi 2.212,72 kg Rp 15.085,00 Rp 37.087.650,09
c. Bekisting 83,64 m2 Rp 358.120,00 Rp 33.279.375,36
6 Membuat Kolom Beton Bertulang - K3 15/15 cm
a. Beton camp. 1pc : 2ps : 3kr 0,95 m3 Rp 1.329.750,00 Rp 1.403.218,69
b. Besi 217,17 kg Rp 15.085,00 Rp 3.640.006,64
c. Bekisting 25,33 m2 Rp 358.120,00 Rp 10.077.496,80
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

7 Membuat Kolom Beton Bertulang - K4 15/50 cm


a. Beton camp. 1pc : 2ps : 3kr 1,36 m3 Rp 1.329.750,00 Rp 2.004.598,13
b. Besi 192,11 kg Rp 15.085,00 Rp 3.219.998,24
c. Bekisting 23,52 m2 Rp 358.120,00 Rp 9.357.675,60
8 Membuat Balok Beton Bertulang - B1 25/40 cm
a. Beton camp. 1pc : 2ps : 3kr 14,94 m3 Rp 1.329.750,00 Rp 22.073.850,00
b. Besi 2.655,05 kg Rp 15.085,00 Rp 44.501.526,41
c. Bekisting 78,44 m2 Rp 364.120,00 Rp 31.733.058,00
9 Membuat Balok Beton Bertulang - B2 20/30 cm
a. Beton camp. 1pc : 2ps : 3kr 0,76 m3 Rp 1.329.750,00 Rp 1.116.990,00
b. Besi 132,26 kg Rp 15.085,00 Rp 2.216.779,32
c. Bekisting 10,08 m2 Rp 364.120,00 Rp 4.078.144,00
10 Membuat Balok Beton Bertulang - B3 15/20 cm
a. Beton camp. 1pc : 2ps : 3kr 0,30 m3 Rp 1.329.750,00 Rp 448.790,63
b. Besi 54,31 kg Rp 15.085,00 Rp 910.229,82
c. Bekisting 5,57 m2 Rp 364.120,00 Rp 2.252.992,50
11 Membuat Plat Lantai Beton Bertulang - Tebal 12 cm
a. Beton camp. 1pc : 2ps : 3kr 12,98 m3 Rp 1.329.750,00 Rp 19.178.319,38
b. Besi 5.527,77 kg Rp 15.085,00 Rp 92.651.580,64
c. Bekisting 54,08 m2 Rp 383.020,00 Rp 23.017.108,13
12 Membuat Plat Bordes dan Tangga Beton Bertulang
a. Beton camp. 1pc : 2ps : 3kr 2,47 m3 Rp 1.329.750,00 Rp 3.645.376,65
b. Besi 595,61 kg Rp 15.085,00 Rp 9.983.036,14
c. Bekisting 21,27 m2 Rp 337.410,00 Rp 7.974.685,35

LANTAI 2
1 Membuat Kolom Beton Bertulang - K2 35/35 cm
a. Beton camp. 1pc : 2ps : 3kr 11,90 m3 Rp 1.329.750,00 Rp 17.578.231,20
b. Besi 1.263,27 kg Rp 15.085,00 Rp 21.173.756,13
c. Bekisting 79,32 m2 Rp 358.120,00 Rp 31.560.399,36
2 Membuat Kolom Beton Bertulang - K3 15/15 cm
a. Beton camp. 1pc : 2ps : 3kr 0,95 m3 Rp 1.329.750,00 Rp 1.403.218,69
b. Besi 217,17 kg Rp 15.085,00 Rp 3.640.006,64
c. Bekisting 12,66 m2 Rp 358.120,00 Rp 5.038.748,40
3 Membuat Balok Beton Bertulang - B1 25/40 cm
a. Beton camp. 1pc : 2ps : 3kr 14,94 m3 Rp 1.329.750,00 Rp 22.073.850,00
b. Besi 2.655,05 kg Rp 15.085,00 Rp 44.501.526,41
c. Bekisting 78,44 m2 Rp 364.120,00 Rp 31.733.058,00
4 Membuat Ring Balok Beton Bertulang - RB 15/20 cm
a. Beton camp. 1pc : 2ps : 3kr 5,51 m3 Rp 1.329.750,00 Rp 8.148.043,13
b. Besi 982,06 kg Rp 15.085,00 Rp 16.460.341,35
c. Bekisting 50,55 m2 Rp 364.120,00 Rp 20.452.165,25
5 Membuat Plat Lantai Beton Bertulang - Tebal 12 cm
a. Beton camp. 1pc : 2ps : 3kr 12,98 m3 Rp 1.329.750,00 Rp 19.178.319,38
b. Besi 5.527,77 kg Rp 15.085,00 Rp 92.651.580,64
c. Bekisting 54,08 m2 Rp 383.020,00 Rp 23.017.108,13

LANTAI 3
1 Membuat Kolom Beton Bertulang - K2 35/35 cm
a. Beton camp. 1pc : 2ps : 3kr 11,90 m3 Rp 1.329.750,00 Rp 17.578.231,20
b. Besi 1.263,27 kg Rp 15.085,00 Rp 21.173.756,13
c. Bekisting 79,32 m2 Rp 358.120,00 Rp 31.560.399,36
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

2 Membuat Kolom Beton Bertulang - K3 15/15 cm


a. Beton camp. 1pc : 2ps : 3kr 0,95 m3 Rp 1.329.750,00 Rp 1.403.218,69
b. Besi 217,17 kg Rp 15.085,00 Rp 3.640.006,64
c. Bekisting 12,66 m2 Rp 358.120,00 Rp 5.038.748,40
3 Membuat Ring Balok Beton Bertulang - RB 15/20 cm
a. Beton camp. 1pc : 2ps : 3kr 5,51 m3 Rp 1.329.750,00 Rp 8.148.043,13
b. Besi 982,06 kg Rp 15.085,00 Rp 16.460.341,35
c. Bekisting 50,55 m2 Rp 364.120,00 Rp 20.452.165,25
4 Membuat Plat Lantai Beton Bertulang - Tebal 12 cm
a. Beton camp. 1pc : 2ps : 3kr 5,51 m3 Rp 1.329.750,00 Rp 8.148.043,13
b. Besi 982,06 kg Rp 15.085,00 Rp 16.460.341,35
c. Bekisting 50,55 m2 Rp 383.020,00 Rp 21.513.754,63

D PEKERJAAN DINDING DAN PLESTERAN Rp 181.054.406,40


LANTAI 1
1 Memasang Dinding Bata Ringan (10x20x60)cm, camp. 1pc : 4psr 136,00 m2 Rp 234.494,00 Rp 31.891.184,00
2 Memasang Plesteran 1Pc : 4Pp tebal 15 mm 272,00 m2 Rp 76.632,00 Rp 20.843.904,00
3 Memasang Acian 272,00 m2 Rp 43.850,00 Rp 11.927.200,00

LANTAI 2
1 Memasang Dinding Bata Ringan (10x20x60)cm, camp. 1pc : 4psr 122,40 m2 Rp 234.494,00 Rp 28.702.065,60
2 Memasang Plesteran 1Pc : 4Pp tebal 15 mm 244,80 m2 Rp 76.632,00 Rp 18.759.513,60
3 Memasang Acian 244,80 m2 Rp 43.850,00 Rp 10.734.480,00

LANTAI 3
1 Memasang Dinding Bata Ringan (10x20x60)cm, camp. 1pc : 4psr 122,40 m2 Rp 234.494,00 Rp 28.702.065,60
2 Memasang Plesteran 1Pc : 4Pp tebal 15 mm 244,80 m2 Rp 76.632,00 Rp 18.759.513,60
3 Memasang Acian 244,80 m2 Rp 43.850,00 Rp 10.734.480,00

E PEKERJAAN KAYU Rp 90.405.228,79


LANTAI 1
1 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I 5/10 0,11 m3 Rp 8.165.125,00 Rp 883.466,53
2 Membuat dan Memasang Daun Pintu Panel Papan Kayu Kelas I 4,64 m2 Rp 771.500,00 Rp 3.581.303,00

LANTAI 2
1 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I 5/10 0,30 m3 Rp 8.165.125,00 Rp 2.449.537,50
2 Membuat dan Memasang Daun Pintu Panel Papan Kayu Kelas I 6,80 m2 Rp 771.500,00 Rp 5.246.200,00
3 Membuat dan Memasang Daun Jendela Kaca Kayu Kelas I 12,20 m2 Rp 753.900,00 Rp 9.197.580,00

LANTAI 3
1 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I 5/10 0,81 m3 Rp 8.165.125,00 Rp 6.613.751,25
2 Membuat dan Memasang Daun Pintu Panel Papan Kayu Kelas I 14,00 m2 Rp 771.500,00 Rp 10.801.000,00
3 Membuat dan Memasang Daun Jendela Kaca Kayu Kelas I 12,20 m2 Rp 753.900,00 Rp 9.197.580,00
4 Membuat dan Memasang Rangka Konstruksi Kuda-kuda Kayu Kelas I 5/10 4,34 m3 Rp 6.574.020,00 Rp 28.537.492,12
5 Memasang Rangka Konstruksi Gording Kayu Kelas II 5/10 3,58 m3 Rp 3.877.600,00 Rp 13.897.318,40
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

F PEKERJAAN PENUTUP ATAP Rp 46.558.472,00


2
1 Memasang Atap Zincalume Tebal 0.4 mm 380,00 m Rp 119.500,00 Rp 45.410.000,00
2 Memasang Nok Atap Zincalume Tebal 0.4 mm 21,60 m1 Rp 53.170,00 Rp 1.148.472,00

G PEKERJAAN LANGIT-LANGIT Rp 72.225.234,50


LANTAI 1
1 Memasang Langit-langit Kalsiboard Tebal 4.5 mm 240,00 m2 Rp 60.049,00 Rp 14.411.760,00
2 Memasang List Langit-langit Gypsum 208,00 m1 Rp 42.710,00 Rp 8.883.680,00

LANTAI 2
1 Memasang Langit-langit Kalsiboard Tebal 4.5 mm 240,00 m2 Rp 60.049,00 Rp 14.411.760,00
2 Memasang List Langit-langit Gypsum 208,00 m1 Rp 42.710,00 Rp 8.883.680,00

LANTAI 3
1 Memasang Langit-langit Kalsiboard Tebal 4.5 mm 250,50 m2 Rp 60.049,00 Rp 15.042.274,50
2 Memasang List Langit-langit Gypsum 248,00 m1 Rp 42.710,00 Rp 10.592.080,00

H PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 359.053.565,04


LANTAI 1
1 Membuat Lantai Beton camp. 1pc ; 2ps ; 3kr Tebal 10 cm 13,00 m3 Rp 1.329.750,00 Rp 17.292.002,51
2 Memasang Lantai Granit Tile (60x60)cm Polished ex. Granito 240,00 m2 Rp 443.780,00 Rp 106.507.200,00
3 Memasang Lantai Keramik Toilet (20x20)cm Unpolished ex. Asia Tile 7,32 m2 Rp 262.640,00 Rp 1.923.155,14
4 Memasang Dinding Keramik Toilet (20x30)cm Polished ex. Asia Tile 31,32 m2 Rp 307.809,90 Rp 9.640.606,13

LANTAI 2
1 Memasang Lantai Granit (60x60)cm Polished ex. Granito 239,00 m2 Rp 443.780,00 Rp 106.063.420,00

LANTAI 3
1 Memasang Lantai Granit (60x60)cm Polished ex. Granito 239,00 m2 Rp 443.780,00 Rp 106.063.420,00
2 Memasang Lantai Keramik Toilet (20x20)cm Unpolished ex. Asia Tile 7,32 m2 Rp 262.640,00 Rp 1.923.155,14
3 Memasang Dinding Keramik Toilet (20x30)cm Polished ex. Asia Tile 31,32 m2 Rp 307.809,90 Rp 9.640.606,13

I PEKERJAAN PENGECATAN Rp 75.314.144,00


LANTAI 1
1 Pengecatan Tembok Interior dan Eksterior 2 Lapis dengan Roll ex. Nippon Paint 244,80 m2 Rp 47.600,00 Rp 11.652.480,00
2 Pengecatan Langit-Langit 2 Lapis dengan Roll ex. Nippon Paint 240,00 m2 Rp 47.600,00 Rp 11.424.000,00
3 Pengecatan Penutup Permukaan Kayu 2 Lapis Kuas ex. Polibest 18,00 m2 Rp 57.886,00 Rp 1.041.948,00

LANTAI 2
1 Pengecatan Tembok Interior dan Eksterior 2 Lapis dengan Roll ex. Nippon Paint 244,80 m2 Rp 47.600,00 Rp 11.652.480,00
2 Pengecatan Langit-Langit 2 Lapis dengan Roll ex. Nippon Paint 240,00 m2 Rp 47.600,00 Rp 11.424.000,00
3 Pengecatan Penutup Permukaan Kayu 2 Lapis Kuas ex. Polibest 18,00 m2 Rp 57.886,00 Rp 1.041.948,00

LANTAI 3
1 Pengecatan Tembok Interior dan Eksterior 2 Lapis dengan Roll ex. Nippon Paint 294,80 m2 Rp 47.600,00 Rp 14.032.480,00
2 Pengecatan Langit-Langit 2 Lapis dengan Roll ex. Nippon Paint 240,00 m2 Rp 47.600,00 Rp 11.424.000,00
3 Pengecatan Penutup Permukaan Kayu 2 Lapis Kuas ex. Polibest 28,00 m2 Rp 57.886,00 Rp 1.620.808,00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

J PEKERJAAN SANITAIR Rp 57.542.157,05


LANTAI 1
1 Membuat Bak Air KM/WC Finishing Keramik 4,00 unit Rp 1.690.579,19 Rp 6.762.316,78
2 Memasang Kloset Jongkok ex. INA 4,00 bh Rp 888.300,00 Rp 3.553.200,00
3 Memasang Kran 3/4 Stainless 4,00 bh Rp 63.395,00 Rp 253.580,00
4 Memasang Kran Washtafel Stainless 4,00 bh Rp 172.995,00 Rp 691.980,00
5 Memasang Floor Drain Stainless 4,00 bh Rp 62.400,00 Rp 249.600,00
6 Memasang Pipa Air PVC 4 inch 40,00 m' Rp 121.200,00 Rp 4.848.000,00
7 Memasang Pipa Air PVC 2 inch 40,00 m' Rp 63.280,00 Rp 2.531.200,00
8 Memasang Pipa Air PVC 3/4 inch 65,00 m' Rp 34.230,00 Rp 2.224.950,00

LANTAI 3
1 Membuat Bak Air KM/WC Finishing Keramik 4,00 unit Rp 1.690.579,19 Rp 6.762.316,78
2 Memasang Kloset Jongkok ex. INA 4,00 bh Rp 888.300,00 Rp 3.553.200,00
3 Memasang Washtafel Cuci Piring 4,00 bh Rp 844.504,00 Rp 3.378.016,00
4 Memasang Kran 3/4 Stainless 4,00 bh Rp 63.395,00 Rp 253.580,00
5 Memasang Kran Washtafel Stainless 4,00 bh Rp 172.995,00 Rp 691.980,00
6 Memasang Floor Drain Stainless 4,00 bh Rp 62.400,00 Rp 249.600,00
7 Memasang Pipa Air PVC 4 inch 78,00 m' Rp 121.200,00 Rp 9.453.600,00
8 Memasang Pipa Air PVC 2 inch 80,00 m' Rp 63.280,00 Rp 5.062.400,00
9 Memasang Pipa Air PVC 3/4 inch 100,00 m' Rp 34.230,00 Rp 3.423.000,00
10 Memasang Talang Datar Seng Plat BJLS 30 25,00 m' Rp 143.985,50 Rp 3.599.637,50

K PEKERJAAN BESI DAN ALUMINIUM Rp 292.194.559,76


LANTAI 1
1 Memasang Rangka Langit-langit Besi Hollow Galvalume Tebal 0.3 mm 240,00 m2 Rp 161.000,00 Rp 38.640.000,00
2 Memasang Pagar Railing Besi Stainless Steel 10,15 m2 Rp 1.295.000,00 Rp 13.144.250,00
3 Memasang Teralis Besi Stainless Steel 18,00 m' Rp 1.295.000,00 Rp 23.310.000,00
4 Memasang Rangka Besi Hollow 40x40x2.5 mm finishing cat 30,00 m2 Rp 945.000,00 Rp 28.350.000,00
5 Memasang Plat Besi Stainless Finish Hairline Tebal 1.2 mm 21,16 m2 Rp 781.654,53 Rp 16.539.809,76

LANTAI 2
1 Memasang Rangka Langit-langit Besi Hollow Galvalume Tebal 0.3 mm 240,00 m2 Rp 161.000,00 Rp 38.640.000,00
2 Memasang Pagar Railing Besi Stainless Steel 20,40 m2 Rp 1.295.000,00 Rp 26.418.000,00
3 Memasang Teralis Besi Stainless Steel 15,60 m' Rp 1.295.000,00 Rp 20.202.000,00

LANTAI 2
1 Memasang Rangka Langit-langit Besi Hollow Galvalume Tebal 0.3 mm 250,50 m2 Rp 161.000,00 Rp 40.330.500,00
2 Memasang Pagar Railing Besi Stainless Steel 20,40 m2 Rp 1.295.000,00 Rp 26.418.000,00
3 Memasang Teralis Besi Stainless Steel 15,60 m' Rp 1.295.000,00 Rp 20.202.000,00

L PEKERJAAN KUNCI DAN KACA Rp 5.867.603,61


LANTAI 1, 2 DAN 3
1 Memasang Kunci Tanam 2 Slag Stainless 6,00 bh Rp 311.650,00 Rp 1.869.900,00
2 Memasang Engsel Pintu 18,00 bh Rp 43.170,00 Rp 777.060,00
3 Memasang Engsel Jendela 24,00 bh Rp 40.475,00 Rp 971.400,00
4 Memasang Kunci Jendela 12,00 bh Rp 58.050,00 Rp 696.600,00
5 Memasang Kait Angin 24,00 bh Rp 49.270,00 Rp 1.182.480,00
6 Memasang Kaca tebal 5 mm 1,60 m2 Rp 231.150,00 Rp 370.163,61
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT
(RP) (RP)

M PEKERJAAN ELEKTRIKAL Rp 16.917.400,00


LANTAI 1
1 Memasang KWH Meter PLN Daya 3000 Volt Ampere 1,00 unit Rp 2.800.000,00 Rp 2.800.000,00
2 Memasang MCB 10A 1 Phasa 1,00 titik Rp 96.600,00 Rp 96.600,00
3 Memasang Lampu Pijar LED Bulb 27 Watt ex. Philips 12,00 titik Rp 269.700,00 Rp 3.236.400,00
4 Memasang Saklar Tunggal ex. Philips 2,00 titik Rp 213.400,00 Rp 426.800,00
5 Memasang Saklar Ganda ex. Philips 1,00 titik Rp 213.400,00 Rp 213.400,00
6 Memasang Stop Kontak ex. Philips 4,00 titik Rp 209.000,00 Rp 836.000,00

LANTAI 2
1 Memasang Lampu Pijar LED Bulb 27 Watt ex. Philips 8,00 titik Rp 269.700,00 Rp 2.157.600,00
2 Memasang Saklar Tunggal ex. Philips 2,00 titik Rp 213.400,00 Rp 426.800,00
3 Memasang Saklar Ganda ex. Philips 1,00 titik Rp 213.400,00 Rp 213.400,00
4 Memasang Stop Kontak ex. Philips 4,00 titik Rp 209.000,00 Rp 836.000,00

LANTAI 2
1 Memasang Lampu Pijar LED Bulb 27 Watt ex. Philips 14,00 titik Rp 269.700,00 Rp 3.775.800,00
2 Memasang Saklar Tunggal ex. Philips 3,00 titik Rp 213.400,00 Rp 640.200,00
3 Memasang Saklar Ganda ex. Philips 1,00 titik Rp 213.400,00 Rp 213.400,00
4 Memasang Stop Kontak ex. Philips 5,00 titik Rp 209.000,00 Rp 1.045.000,00
DAFTAR ANALISA PEKERJAAN

HARGA HARGA HARGA HARGA


NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)

I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)

1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER


1,2500 btg Bambu Sedang 16.100,00 20.125,00
1,2000 lbr Seng gelombang 3" - 5" 60.500,00 72.600,00
0,0720 m3 Kayu Matoa Usuk 5/7 2.000.000,00 144.000,00
0,0600 kg Paku biasa 2" - 5" 24.700,00 1.482,00
0,2000 oh Tukang Kayu 150.000,00 30.000,00
0,4000 oh Pekerja 100.000,00 40.000,00
0,0200 oh Kepala Tukang 150.000,00 3.000,00
0,0200 oh Mandor 150.000,00 3.000,00
Total : 76.000,00 238.207,00 314.207,00

2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK


0,0120 m3 Kayu putih 5/7 2.000.000,00 24.000,00
0,0200 kg Paku Biasa 2" - 5" 24.700,00 494,00
0,0070 m3 Kayu Papan putih 3/20 2.000.000,00 14.000,00
0,1000 oh Tukang Kayu 150.000,00 15.000,00
0,1000 oh Pekerja 100.000,00 10.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 27.250,00 38.494,00 65.744,00

3 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


0,2100 m3 Kayu Matoa 2.000.000,00 420.000,00
0,3000 kg Paku Biasa 2" - 5" 24.700,00 7.410,00
1,5000 lbr Seng gelombang BJLS 20 60.500,00 90.750,00
2,0000 oh Tukang Kayu 150.000,00 300.000,00
1,0000 oh Pekerja 100.000,00 100.000,00
0,2000 oh Kepala Tukang 150.000,00 30.000,00
0,0500 oh Mandor 150.000,00 7.500,00
Total : 437.500,00 518.160,00 955.660,00

4 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN


0,1000 oh Pekerja 100.000,00 10.000,00
0,0500 oh Mandor 150.000,00 7.500,00
Total : 17.500,00 17.500,00

5 1 M2 PEMBUATAN BEDENG BURUH


0,1860 m3 Kayu Matoa 2.000.000,00 372.000,00
0,3000 kg Paku Biasa 2" - 5" 24.700,00 7.410,00
1,5000 lbr Seng gelombang BJLS 20 60.500,00 90.750,00
1,3500 lbr Triplex 4 mm 97.300,00 131.355,00
2,0000 oh Tukang Kayu 150.000,00 300.000,00
1,0000 oh Pekerja 100.000,00 100.000,00
0,2000 oh Kepala Tukang 150.000,00 30.000,00
0,0500 oh Mandor 150.000,00 7.500,00
Total : 437.500,00 601.515,00 1.039.015,00

II PEKERJAAN TANAH (SNI 2835 : 2008)

1 1 M3 GALIAN TANAH CADAS DALAM 1 METER


1,5000 oh Pekerja 100.000,00 150.000,00
0,0600 oh Mandor 150.000,00 9.000,00
Total : 159.000,00 159.000,00

2 1 M3 URUGAN PASIR
1,2000 m3 Pasir Urug 350.000,00 420.000,00
0,3000 oh Pekerja 100.000,00 30.000,00
0,0100 oh Mandor 150.000,00 1.500,00
Total : 31.500,00 420.000,00 451.500,00

3 1 M3 URUGAN TANAH PILIHAN DIPADATKAN


1,2000 m3 Tanah Urug 208.700,00 250.440,00
0,5000 oh Pekerja 100.000,00 50.000,00
0,0500 oh Mandor 150.000,00 7.500,00
Total : 57.500,00 250.440,00 307.940,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
III PEKERJAAN PONDASI (SNI 2836 : 2008)

1 1 M3 BATU KALI CAMP. 1 PC : 4 PS


1,2000 m3 Batu Kali / Batu Belah 15/20 300.000,00 360.000,00
163,0000 kg Semen Portland 1.800,00 293.400,00
0,5200 m3 Pasir Pasang 350.000,00 182.000,00
1,5000 oh Pekerja 100.000,00 150.000,00
0,7500 oh Tukang Batu 150.000,00 112.500,00
0,0750 oh Kepala Tukang 150.000,00 11.250,00
0,0750 oh Mandor 150.000,00 11.250,00
Total : 285.000,00 835.400,00 1.120.400,00

2 1 M3 PASANGAN BATU KOSONG


1,2000 m3 Batu Kali / Batu Bulat 15/20 15/20 300.000,00 360.000,00
0,4320 m3 Pasir Urug 350.000,00 151.200,00
0,7800 oh Pekerja 100.000,00 78.000,00
0,3900 oh Tukang Batu 150.000,00 58.500,00
0,0390 oh Kepala Tukang 150.000,00 5.850,00
0,0390 oh Mandor 150.000,00 5.850,00
Total : 148.200,00 511.200,00 659.400,00

IV PEKERJAAN DINDING (SNI 6897 : 2008)

1 1 M2 PASANGAN BATA RINGAN 10 X 20 X 60 CAMP. 1 PC : 4 PS


8,3330 bh Bata Ringan 10 x 20 x 60 cm 18.000,00 149.994,00
11,5000 kg Semen Portland 1.800,00 20.700,00
0,0430 m3 Pasir Pasang 350.000,00 15.050,00
0,3000 oh Pekerja 100.000,00 30.000,00
0,1000 oh Tukang Batu 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0150 oh Mandor 150.000,00 2.250,00
Total : 48.750,00 185.744,00 234.494,00

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

1 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM


6,2400 kg Semen Portland 1.800,00 11.232,00
0,0240 m3 Pasir Pasang 350.000,00 8.400,00
0,3000 oh Pekerja 100.000,00 30.000,00
0,1500 oh Tukang Batu 150.000,00 22.500,00
0,0150 oh Kepala Tukang 150.000,00 2.250,00
0,0150 oh Mandor 150.000,00 2.250,00
Total : 57.000,00 19.632,00 76.632,00

2 1 M2 PEKERJAAN ACIAN
3,2500 kg Semen Portland 40 Kg 1.800,00 5.850,00
0,2000 oh Pekerja 100.000,00 20.000,00
0,1000 oh Tukang Labur/Cat 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0100 oh Mandor 150.000,00 1.500,00
Total : 38.000,00 5.850,00 43.850,00

VI PEKERJAAN KAYU (SNI 3434 : 2008)

1
MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I (KAYU BESI)
1,1000 m3 Balok Kayu Besi 3.500.000,00 3.850.000,00
1,2500 Kg Paku 10 Cm 31.700,00 39.625,00
1,0000 Kg Lem Kayu 58.000,00 58.000,00
7,0000 oh Pekerja 100.000,00 700.000,00
21,0000 oh Tukang Kayu 150.000,00 3.150.000,00
2,1000 oh Kepala Tukang 150.000,00 315.000,00
0,3500 oh Mandor 150.000,00 52.500,00
Total : 4.217.500,00 3.947.625,00 8.165.125,00

2
MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II (KAYU BESI)
0,0400 m3 Papan Kayu Besi 3.500.000,00 140.000,00
0,5000 Kg Lem Kayu 58.000,00 29.000,00
1,0000 oh Pekerja 100.000,00 100.000,00
3,0000 oh Tukang Kayu 150.000,00 450.000,00
0,3000 oh Kepala Tukang 150.000,00 45.000,00
0,0500 oh Mandor 150.000,00 7.500,00
Total : 602.500,00 169.000,00 771.500,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
3
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II (KAYU BESI)
0,0240 m3 Papan Kayu Besi 3.500.000,00 84.000,00
1,0000 m2 Kaca rayben 5 mm 170.500,00 170.500,00
0,3000 Kg Lem Kayu 58.000,00 17.400,00
0,8000 oh Pekerja 100.000,00 80.000,00
2,4000 oh Tukang Kayu 150.000,00 360.000,00
0,2400 oh Kepala Tukang 150.000,00 36.000,00
0,0400 oh Mandor 150.000,00 6.000,00
Total : 482.000,00 271.900,00 753.900,00

4
MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I,II,III BENTANG 6 M'
1,1000 m3 Balok Kayu Besi 3.500.000,00 3.850.000,00
15,0000 Kg Besi Strip Tebal 5 cm 9.100,00 136.500,00
5,6000 Kg Paku 12 Cm 31.700,00 177.520,00
4,0000 oh Pekerja 100.000,00 400.000,00
12,0000 oh Tukang Kayu 150.000,00 1.800.000,00
1,2000 oh Kepala Tukang 150.000,00 180.000,00
0,2000 oh Mandor 150.000,00 30.000,00
Total : 2.410.000,00 4.164.020,00 6.574.020,00

5 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II


1,1000 m3 Balok Kayu Matoa 2.000.000,00 2.200.000,00
15,0000 Kg Besi Strip Tebal 5 cm 9.100,00 136.500,00
3,0000 Kg Paku 12 Cm 31.700,00 95.100,00
2,4000 oh Pekerja 100.000,00 240.000,00
7,2000 oh Tukang Kayu 150.000,00 1.080.000,00
0,7200 oh Kepala Tukang 150.000,00 108.000,00
0,1200 oh Mandor 150.000,00 18.000,00
Total : 1.446.000,00 2.431.600,00 3.877.600,00

6 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II


0,0110 m3 Papan Kayu Besi 3.500.000,00 38.500,00
0,0500 Kg Paku 5 Cm dan 7 Cm 31.700,00 1.585,00
0,1000 oh Pekerja 100.000,00 10.000,00
0,2000 oh Tukang Kayu 150.000,00 30.000,00
0,0200 oh Kepala Tukang 150.000,00 3.000,00
0,0050 oh Mandor 150.000,00 750,00
Total : 43.750,00 40.085,00 83.835,00

7 MEMASANG 1 M3 PAGAR KAYU KELAS I 5/10


1,1000 m3 Balok Kayu Besi 3.500.000,00 3.850.000,00
5,6000 Kg Paku 12 Cm 31.700,00 177.520,00
4,0000 oh Pekerja 100.000,00 400.000,00
12,0000 oh Tukang Kayu 150.000,00 1.800.000,00
1,2000 oh Kepala Tukang 150.000,00 180.000,00
0,2000 oh Mandor 150.000,00 30.000,00
Total : 2.410.000,00 4.027.520,00 6.437.520,00

VII PEKERJAAN BETON ( SNI 7394:2008)

1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR
218,0000 kg Semen Portland 1.800,00 392.400,00
0,5200 m3 Pasir Beton 350.000,00 182.000,00
0,8700 m3 Koral Beton 500.000,00 435.000,00
1,6500 oh Pekerja 100.000,00 165.000,00
0,2500 oh Tukang Batu 150.000,00 37.500,00
0,0250 oh Kepala Tukang 150.000,00 3.750,00
0,0800 oh Mandor 150.000,00 12.000,00
Total : 218.250,00 1.009.400,00 1.227.650,00

2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR
280,0000 kg Semen Portland 1.800,00 504.000,00
0,4500 m3 Pasir Beton 350.000,00 157.500,00
0,9000 m3 Koral Beton 500.000,00 450.000,00
1,6500 oh Pekerja 100.000,00 165.000,00
0,2500 oh Tukang Batu 150.000,00 37.500,00
0,0250 oh Kepala Tukang 150.000,00 3.750,00
0,0800 oh Mandor 150.000,00 12.000,00
Total : 218.250,00 1.111.500,00 1.329.750,00

3 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


10,5000 kg Besi Beton (Polos/ Ulir) 12.200,00 128.100,00
0,1500 kg Kawat Beton 24.000,00 3.600,00
0,0700 oh Pekerja 100.000,00 7.000,00
0,0700 oh Tukang Besi 150.000,00 10.500,00
0,0070 oh Kepala Tukang 150.000,00 1.050,00
0,0040 oh Mandor 150.000,00 600,00
Total : 19.150,00 131.700,00 15.085,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)

4 1 M2 PASANG BEKISTING UNTUK PONDASI


0,0400 m3 Kayu Bekisting 2.000.000,00 80.000,00
0,3000 kg Paku Biasa 5' - 10' 31.700,00 9.510,00
0,1000 ltr Minyak Bekisting 14.200,00 1.420,00
0,5200 oh Pekerja 100.000,00 52.000,00
0,2600 oh Tukang Kayu 150.000,00 39.000,00
0,0260 oh Kepala Tukang 150.000,00 3.900,00
0,0260 oh Mandor 150.000,00 3.900,00
Total : 98.800,00 90.930,00 189.730,00

5 1 M2 PASANG BEKISTING UNTUK SLOOF


0,0400 m3 Kayu Bekisting 2.000.000,00 80.000,00
0,3000 kg Paku Biasa 5' - 10' 31.700,00 9.510,00
0,1000 ltr Minyak Bekisting 14.200,00 1.420,00
0,5200 oh Pekerja 100.000,00 52.000,00
0,2600 oh Tukang Kayu 150.000,00 39.000,00
0,0260 oh Kepala Tukang 150.000,00 3.900,00
0,0260 oh Mandor 150.000,00 3.900,00
Total : 98.800,00 90.930,00 189.730,00

6 1 M2 PASANG BEKISTING UNTUK KOLOM


0,0400 m3 Kayu Bekisting 2.000.000,00 80.000,00
0,4000 kg Paku Biasa 5' - 12' 31.700,00 12.680,00
0,2000 ltr Minyak Bekisting 14.200,00 2.840,00
0,0150 m3 Kayu Usuk 4/6 2.000.000,00 30.000,00
0,3500 lbr Plywood 9 mm 164.000,00 57.400,00
2,0000 btg Dolken Kayu 8" - 10"/4 m 24.900,00 49.800,00
0,6600 oh Pekerja 100.000,00 66.000,00
0,3300 oh Tukang Kayu 150.000,00 49.500,00
0,0330 oh Kepala Tukang 150.000,00 4.950,00
0,0330 oh Mandor 150.000,00 4.950,00
Total : 125.400,00 232.720,00 358.120,00

7 1 M2 PASANG BEKISTING UNTUK BALOK


0,0400 m3 Kayu Bekisting 2.000.000,00 80.000,00
0,4000 kg Paku Biasa 5' - 12' 31.700,00 12.680,00
0,2000 ltr Minyak Bekisting 14.200,00 2.840,00
0,0180 m3 Kayu Usuk 4/6 2.000.000,00 36.000,00
0,3500 lbr Plywood 9 mm 164.000,00 57.400,00
2,0000 btg Dolken Kayu 8" - 10"/4m 24.900,00 49.800,00
0,6600 oh Pekerja 100.000,00 66.000,00
0,3300 oh Tukang Kayu 150.000,00 49.500,00
0,0330 oh Kepala Tukang 150.000,00 4.950,00
0,0330 oh Mandor 150.000,00 4.950,00
Total : 125.400,00 238.720,00 364.120,00

8 1 M2 PASANG BEKISTING UNTUK LANTAI


0,0400 m3 Kayu Bekisting 2.000.000,00 80.000,00
0,4000 kg Paku Biasa 5' - 12' 31.700,00 12.680,00
0,2000 ltr Minyak Bekisting 14.200,00 2.840,00
0,0150 m3 Kayu Usuk 4/6 2.000.000,00 30.000,00
0,3500 lbr Plywood 9 mm 164.000,00 57.400,00
3,0000 btg Dolken Kayu 8" - 10"/4m 24.900,00 74.700,00
0,6600 oh Pekerja 100.000,00 66.000,00
0,3300 oh Tukang Kayu 150.000,00 49.500,00
0,0330 oh Kepala Tukang 150.000,00 4.950,00
0,0330 oh Mandor 150.000,00 4.950,00
Total : 125.400,00 257.620,00 383.020,00

9 1 M2 PASANG BEKISTING UNTUK DINDING


0,0300 M3 Kayu Bekisting 2.000.000,00 60.000,00
0,4000 Kg Paku Biasa 5' - 12' 31.700,00 12.680,00
0,2000 Ltr Minyak Bekisting 14.200,00 2.840,00
3
0,0200 M Kayu Usuk 4/6 2.000.000,00 40.000,00
0,3500 Lbr Plywood 9 mm 164.000,00 57.400,00
3,0000 Btng Dolken Kayu 8" - 10"/4m 24.900,00 74.700,00
4,0000 Bh Formite/penjaga jarak bekisting/spacer 6.700,00 26.800,00
0,6600 Oh Pekerja 100.000,00 66.000,00
0,3300 Oh Tukang Kayu 150.000,00 49.500,00
0,0330 Oh Kepala Tukang 150.000,00 4.950,00
0,0330 Oh Mandor 150.000,00 4.950,00
Total : 125.400,00 274.420,00 399.820,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
10 1 M2 PASANG BEKISTING UNTUK TANGGA
0,0300 m3 Kayu Bekisting 2.000.000,00 60.000,00
0,4000 kg Paku Biasa 5' - 12' 31.700,00 12.680,00
0,1500 ltr Minyak Bekisting 14.200,00 2.130,00
0,0150 m3 Kayu Usuk 4/6 2.000.000,00 30.000,00
0,3500 lbr Plywood 9 mm 164.000,00 57.400,00
2,0000 btg Dolken Kayu 8" - 10"/4m 24.900,00 49.800,00
0,6600 oh Pekerja 100.000,00 66.000,00
0,3300 oh Tukang Kayu 150.000,00 49.500,00
0,0330 oh Kepala Tukang 150.000,00 4.950,00
0,0330 oh Mandor 150.000,00 4.950,00
Total : 125.400,00 212.010,00 337.410,00

11 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKISTING)


0,3200 m3 Kayu Bekisting 2.000.000,00 640.000,00
3,2000 kg Paku Biasa 5' - 12' 31.700,00 101.440,00
1,6000 ltr Minyak Bekisting 14.200,00 22.720,00
157,5000 kg Besi Beton 12.200,00 1.921.500,00
2,2500 kg Kawat Beton 24.000,00 54.000,00
336,0000 kg Semen Portland 1.800,00 604.800,00
0,5400 m3 Pasir Beton 350.000,00 189.000,00
0,8100 m3 Koral Beton 500.000,00 405.000,00
0,1200 m3 Kayu Kelas II balok 2.000.000,00 240.000,00
2,8000 lbr Plywood 9 mm 164.000,00 459.200,00
32,0000 btg Dolken Kayu 8" /4 m 24.900,00 796.800,00
5,3000 oh Pekerja 100.000,00 530.000,00
0,2750 oh Tukang Batu 150.000,00 41.250,00
1,3000 oh Tukang Kayu 150.000,00 195.000,00
1,0500 oh Tukang Besi 150.000,00 157.500,00
0,2650 oh Kepala Tukang 150.000,00 39.750,00
0,2650 oh Mandor 150.000,00 39.750,00
Total : 1.003.250,00 5.434.460,00 6.437.710,00

12 1 M1 MEMBUAT BALOK PENGUAT BETON BERTULANG (11 X 11 CM)


0,0020 m3 Kayu Bekisting 2.000.000,00 4.000,00
0,0100 kg Paku Biasa 5' - 12' 31.700,00 317,00
3,0000 kg Besi Beton 12.200,00 36.600,00
0,0450 kg Kawat Beton 24.000,00 1.080,00
4,0000 kg Semen Portland 1.800,00 7.200,00
0,0060 m3 Pasir Beton 350.000,00 2.100,00
0,0090 m3 Koral Beton 500.000,00 4.500,00
0,1800 oh Pekerja 100.000,00 18.000,00
0,0200 oh Tukang Batu 150.000,00 3.000,00
0,0200 oh Tukang Kayu 150.000,00 3.000,00
0,0200 oh Tukang Besi 150.000,00 3.000,00
0,0060 oh Kepala Tukang 150.000,00 900,00
0,0090 oh Mandor 150.000,00 1.350,00
Total : 29.250,00 55.797,00 85.047,00

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)

1 1 M2 PEMASANGAN ATAP SPANDECK ZINCALUME


1,1000 m2 Atap Spandek Zincalume 0.4 mm 85.000,00 93.500,00
6,0000 bh Screw Cteks 12 x 4 - 50 1.300,00 7.800,00
2,0000 bh Screw Cteks 10 x 16 - 16 900,00 1.800,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,0800 oh Tukang Kayu 150.000,00 12.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0060 oh Mandor 150.000,00 900,00
Total : 16.400,00 103.100,00 119.500,00

2 1 M1 PEMASANGAN NOK ZINCALUME


1,1000 m Nok Zincalume tebal 0,4 mm 29.200,00 32.120,00
6,0000 bh Screw Cteks 10 x 16 - 16 900,00 5.400,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,0800 oh Tukang Kayu 150.000,00 12.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0010 oh Mandor 150.000,00 150,00
Total : 15.650,00 37.520,00 53.170,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)

1 1 M1 PASANG LIST LANGIT-LANGIT GIPSUM


1,0500 m1 List Gipsum 26.000,00 27.300,00
0,1000 kg Paku list SQ 17.100,00 1.710,00
0,0500 oh Pekerja 100.000,00 5.000,00
0,0500 oh Tukang Kayu 150.000,00 7.500,00
0,0050 oh Kepala Tukang 150.000,00 750,00
0,0030 oh Mandor 150.000,00 450,00
Total : 13.700,00 29.010,00 42.710,00

2 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM


0,1100 kg Paku Sekrup 900,00 99,00
0,3640 lbr Kalsiboard 4.5 mm 112.500,00 40.950,00
0,1000 oh Pekerja 100.000,00 10.000,00
0,0500 oh Tukang Kayu 150.000,00 7.500,00
0,0050 oh Kepala Tukang 150.000,00 750,00
0,0050 oh Mandor 150.000,00 750,00
Total : 19.000,00 41.049,00 60.049,00

X PEKERJAAN SANITASI ( SNI 2002 )

1 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


1,0000 bh Kloset jongkok porselen 300.000,00 300.000,00
6,0000 kg Semen Portland 1.800,00 10.800,00
0,0100 m3 Pasir Pasang 350.000,00 3.500,00
1,0000 oh Pekerja 100.000,00 100.000,00
1,5000 oh Tukang batu 150.000,00 225.000,00
1,5000 oh Kepala Tukang 150.000,00 225.000,00
0,1600 oh Mandor 150.000,00 24.000,00
Total : 574.000,00 314.300,00 888.300,00

2 MEMASANG 1 BUAH WASHTAFEL CUCI PIRING


1,0000 bh Washtafel cuci piring 419.200,00 419.200,00
12% x harga wast Perlengkapan 50.304,00
1,2000 oh Pekerja 100.000,00 120.000,00
1,4500 oh Tukang batu 150.000,00 217.500,00
0,1500 oh Kepala Tukang 150.000,00 22.500,00
0,1000 oh Mandor 150.000,00 15.000,00
Total : 375.000,00 469.504,00 844.504,00

3 MEMASANG 1 M1 PIPA GALVANIS f 1"


1,2000 m1 Pipa galvanis 55.600,00 66.720,00
35% x harga pipa Perlengkapan - 19.460,00
0,0540 oh Pekerja 100.000,00 5.400,00
0,0900 oh Tukang Pipa 150.000,00 13.500,00
0,0090 oh Kepala Tukang 150.000,00 1.350,00
0,0270 oh Mandor 150.000,00 4.050,00
Total : 24.300,00 86.180,00 110.480,00

4 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"


1,2000 m1 Pipa PVC 13.200,00 15.840,00
35% x harga pipa Perlengkapan 4.620,00
0,0360 oh Pekerja 100.000,00 3.600,00
0,0600 oh Tukang Pipa 150.000,00 9.000,00
0,0060 oh Kepala Tukang 150.000,00 900,00
0,0018 oh Mandor 150.000,00 270,00
Total : 13.770,00 20.460,00 34.230,00

5 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"


1,2000 m1 Pipa PVC 27.500,00 33.000,00
35% x harga pipa Perlengkapan 9.625,00
0,0540 oh Pekerja 100.000,00 5.400,00
0,0900 oh Tukang Pipa 150.000,00 13.500,00
0,0090 oh Kepala Tukang 150.000,00 1.350,00
0,0027 oh Mandor 150.000,00 405,00
Total : 20.655,00 42.625,00 63.280,00

6 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"


1,2000 m1 Pipa PVC 58.200,00 69.840,00
35% x harga pipa Perlengkapan 20.370,00
0,0810 oh Pekerja 100.000,00 8.100,00
0,1350 oh Tukang Pipa 150.000,00 20.250,00
0,0135 oh Kepala Tukang 150.000,00 2.025,00
0,0041 oh Mandor 150.000,00 615,00
Total : 30.990,00 90.210,00 121.200,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
7 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"
1,0000 bh Kran air Stainlless 44.900,00 44.900,00
0,0250 bh Seal tape 9.800,00 245,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,1000 oh Tukang Pipa 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 18.250,00 45.145,00 63.395,00

8 MEMBUAT 1 UNIT SEPTIKTANK KAPASITAS 4 M3 TERMASUK RESAPAN


4,4100 m³ Pekerjaan Galian Tanah Cadas 159.000,00 701.190,00
1,2635 m³ Pasir Urugan 451.500,00 570.470,25
0,3610 m³ Pasangan Batu Kosong 659.400,00 238.043,40
0,6000 m³ Pasang Beton Tumbuk camp. 1Pc : 3Ps : 5Kr 1.227.650,00 736.590,00
10,0000 m² Pasangan Bata Ringan 1Pc : 4Ps 234.494,00 2.344.940,00
12,0000 m² Pasangan Plesteran 1Pc : 4Ps 76.632,00 919.584,00
1,4700 m³ Urugan Kembali 53.000,00 77.910,00
0,5808 m³ Plat Beton Bertulang Penutup Septictank tebal = 12cm 6.437.710,00 3.739.021,97
1,5000 m' Pasang Pipa Gip 3 inch 171.100,00 256.650,00
1,0000 ls Pasang Handle 500.000,00 200.000,00
Total : - 9.784.399,62 9.784.399,62

9 MEMBUAT 1 UNIT SEPTIKTANK KAPASITAS 2 M3 TERMASUK RESAPAN


2,3100 m³ Pekerjaan Galian Tanah Cadas 159.000,00 367.290,00
0,5985 m³ Pasir Urugan 451.500,00 270.222,75
0,1710 m³ Pasangan Batu Kosong 659.400,00 112.757,40
0,3000 m³ Pasang Beton Tumbuk camp. 1Pc : 3Ps : 5Kr 1.227.650,00 368.295,00
6,0000 m² Pasangan Bata Ringan 1Pc : 4Ps 234.494,00 1.406.964,00
6,0000 m² Pasangan Plesteran 1Pc : 4Ps 76.632,00 459.792,00
0,7700 m³ Urugan Kembali 53.000,00 40.810,00
0,3168 m³ Plat Beton Bertulang Penutup Septictank tebal = 12cm 6.437.710,00 2.039.466,53
1,5000 m' Pasang Pipa Gip 171.100,00 256.650,00
1,0000 ls Pasang Handle 500.000,00 200.000,00
Total : - 5.522.247,68 5.522.247,68

10 MEMBUAT 1 UNIT BAK AIR KM/WC FINISHING KERAMIK


3,6000 m² Pasangan Bata Ringan 1Pc : 4Ps Uk. 10x20x60 cm 234.494,00 844.178,40
2,1000 m² Pasang Keramik 20x30 cm 307.809,90 646.400,79
1,0000 ls Pasang Pipa Outlet Serta Penutup 200.000,00 200.000,00
Total : - 1.690.579,19 1.690.579,19

11 MEMASANG 1 BUAH KRAN CUCI PIRING f 0,75" ATAU 0,5"


1,0000 bh Kran Cuci Piring 154.500,00 154.500,00
0,0250 bh Seal tape 9.800,00 245,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,1000 oh Tukang Pipa 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 18.250,00 154.745,00 172.995,00

12 MEMASANG 1 BUAH GATE VALVE 3 INCH


1,0000 bh Gate Valve 3 inch 1.214.500,00 1.214.500,00
0,0250 bh Seal tape 9.800,00 245,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,1000 oh Tukang Pipa 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 18.250,00 1.214.745,00 1.232.995,00

13 MEMASANG 1 BUAH GATE VALVE 1 INCH


1,0000 bh Gate Valve 1 inch 143.300,00 143.300,00
0,0250 bh Seal tape 9.800,00 245,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,1000 oh Tukang Pipa 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 18.250,00 143.545,00 161.795,00

XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)


1 MEMBUAT 10 CM PENGELASAN DENGAN LAS LISTRIK
0 0,400 kg Kawat Las 67.800,00 27.120,00
0 0,300 ltr Solar 13.000,00 3.900,00
0 0,040 ltr Minyak Pelumas 14.200,00 568,00
0 0,040 OH Pekerja 100.000,00 4.000,00
0 0,020 OH Tukang Besi 150.000,00 3.000,00
0 0,002 OH Kepala Tukang 150.000,00 300,00
0 0,002 OH Mandor 150.000,00 300,00
0 0,170 Jam Sewa Alat (Las Listrik) 75.000,00 12.750,00
Total : 20.350,00 31.588,00 51.938,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
2 1 M1 PASANG TALANG DATAR, SENG BJLS 28
1,0500 lbr Seng plat 25.400,00 26.670,00
0,0150 kg Paku biasa 0,5" - 1" 24.700,00 370,50
0,0190 m3 Kayu papan matoa 2.000.000,00 38.000,00
0,1500 oh Pekerja 100.000,00 15.000,00
0,4000 oh Tukang besi 150.000,00 60.000,00
0,0250 oh Kepala Tukang 150.000,00 3.750,00
0,0013 oh Mandor 150.000,00 195,00
Total : 78.945,00 65.040,50 143.985,50

3 MEMBUAT 1 M2 PLAT BESI STAINLESS TEBAL 1.2 MM


1,100 m2 Besi Plat Stainless Finish Hairline tbl 1.2 mm 447.467,75 492.214,53
0,050 Kg Kawat Las 67.800,00 3.390,00
1,050 OH Pekerja 100.000,00 105.000,00
1,050 OH Tukang besi 150.000,00 157.500,00
0,105 OH Kepala Tukang 150.000,00 15.750,00
0,052 OH Mandor 150.000,00 7.800,00
Total : 286.050,00 495.604,53 781.654,53

4 MEMBUAT 1 UNIT TANGGA HOLLOW GALVANIS 40X40X2 MM - L 60 T 50


80,787 kg Besi Hollow Galvanis 40x40x2 mm 27.383,33 2.212.208,22
54,400 cm Pengelasan 10 cm dengan Las Listrik 51.938,00 2.825.427,20
4,448 m2 Pengecatan 2 Lapis Cat Besi 43.167,00 192.006,82
1,000 ls Ongkos Kerja 500.000,00 500.000,00
Total : 500.000,00 5.229.642,24 5.729.642,24

5 1 M2 PASANG RANGKA BESI HOLLOW 1X40.40.3 UKURAN (60X60) CM


4,0000 m' Rangka Holow Galvalum 40.40.3mm 18.000,00 72.000,00
100%xrangka ls Assesoris (perkuatan, las,dll) - 18.000,00
0,2000 oh Pekerja 100.000,00 20.000,00
0,3000 oh Tukang Kayu 150.000,00 45.000,00
0,0300 oh Kepala Tukang 150.000,00 4.500,00
0,0100 oh Mandor 150.000,00 1.500,00
Total : 71.000,00 90.000,00 161.000,00

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)

1 1 BH PASANG KUNCI TANAM


1,0000 bh Kunci tanam biasa 233.400,00 233.400,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,5000 oh Tukang besi 150.000,00 75.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0050 oh Mandor 150.000,00 750,00
Total : 78.250,00 233.400,00 311.650,00

2 1 PS PASANG ENGSEL PINTU


1,0000 ps Engsel pintu 16.800,00 16.800,00
0,0150 oh Pekerja 100.000,00 1.500,00
0,1500 oh Tukang besi 150.000,00 22.500,00
0,0150 oh Kepala Tukang 150.000,00 2.250,00
0,0008 oh Mandor 150.000,00 120,00
Total : 26.370,00 16.800,00 43.170,00

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU


1,0000 ps Engsel jendela 22.900,00 22.900,00
0,0100 oh Pekerja 100.000,00 1.000,00
0,1000 oh Tukang besi 150.000,00 15.000,00
0,0100 oh Kepala Tukang 150.000,00 1.500,00
0,0005 oh Mandor 150.000,00 75,00
Total : 17.575,00 22.900,00 40.475,00

4 1 BH PASANG KAIT ANGIN


1,0000 ps Kait angin 22.900,00 22.900,00
0,0150 oh Pekerja 100.000,00 1.500,00
0,1500 oh Tukang besi 150.000,00 22.500,00
0,0150 oh Kepala Tukang 150.000,00 2.250,00
0,0008 oh Mandor 150.000,00 120,00
Total : 26.370,00 22.900,00 49.270,00

5 1 BH PASANG KUNCI JENDELA


1,0000 bh Kunci slot 22.900,00 22.900,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,2000 oh Tukang besi 150.000,00 30.000,00
0,0200 oh Kepala Tukang 150.000,00 3.000,00
0,0010 oh Mandor 150.000,00 150,00
Total : 35.150,00 22.900,00 58.050,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
6 1 M2 MEMASANG KACA TEBAL 5 MM
1,1000 m2 Kaca tebal 5 mm 170.500,00 187.550,00
0,1600 OH Pekerja 100.000,00 16.000,00
0,1600 OH Tukang Kayu 150.000,00 24.000,00
0,0160 OH Kepala Tukang 150.000,00 2.400,00
0,0080 OH Mandor 150.000,00 1.200,00
Total : 43.600,00 187.550,00 231.150,00

XIII PEK. PENUTUP LANTAI DAN DINDING (SNI 7395:2008)

1 1 M2 PASANG LANTAI GRANIT 60 X 60 CM


3,1000 bh Granit 60 x 60 cm 80.645,16 250.000,00
9,6000 kg Semen Portland 1.800,00 17.280,00
0,0450 m3 Pasir Pasang 350.000,00 15.750,00
1,5000 kg Semen warna/semen grouting 18.500,00 27.750,00
0,7000 oh Pekerja 100.000,00 70.000,00
0,3500 oh Tukang batu 150.000,00 52.500,00
0,0350 oh Kepala Tukang 150.000,00 5.250,00
0,0350 oh Mandor 150.000,00 5.250,00
Total : 133.000,00 310.780,00 443.780,00

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM


26,5000 bh Keramik 20 x 20 cm 2.460,38 65.200,00
10,4000 kg Semen Portland 1.800,00 18.720,00
0,0450 m3 Pasir Pasang 350.000,00 15.750,00
1,6200 kg Semen warna/semen grouting 18.500,00 29.970,00
0,7000 oh Pekerja 100.000,00 70.000,00
0,3500 oh Tukang batu 150.000,00 52.500,00
0,0350 oh Kepala Tukang 150.000,00 5.250,00
0,0350 oh Mandor 150.000,00 5.250,00
Total : 133.000,00 129.640,00 262.640,00

3 1 M2 PASANG DINDING KERAMIK 20 X 30 CM


17,0833 bh Keramik 20 x 30 cm 4.558,82 77.879,90
9,3000 kg Semen Portland 1.800,00 16.740,00
0,0180 m3 Pasir Pasang 350.000,00 6.300,00
1,9400 kg Semen warna/semen grouting 18.500,00 35.890,00
0,9000 oh Pekerja 100.000,00 90.000,00
0,4500 oh Tukang batu 150.000,00 67.500,00
0,0450 oh Kepala Tukang 150.000,00 6.750,00
0,0450 oh Mandor 150.000,00 6.750,00
Total : 171.000,00 136.809,90 307.809,90

4 1 M2 PASANG BATU ALAM


# 13,8889 bh Batu Alam 11.649,59 161.799,87
9,3000 kg Semen Portland 1.800,00 16.740,00
0,0180 m3 Pasir Pasang 350.000,00 6.300,00
0,9000 oh Pekerja 100.000,00 90.000,00
0,4500 oh Tukang batu 150.000,00 67.500,00
0,0450 oh Kepala Tukang 150.000,00 6.750,00
0,0450 oh Mandor 150.000,00 6.750,00
Total : 171.000,00 184.839,87 355.839,87

XIV PEKERJAAN PENGECATAN (SNI 2002)

1 1 M2 PENGECATAN BIDANG KAYU BARU


1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0,2000 kg Cat meni 63.500,00 12.700,00
0,1500 kg Dempul 51.400,00 7.710,00
0,1700 kg Cat dasar 63.500,00 10.795,00
0,2600 kg Cat Penutup 2x 65.600,00 17.056,00
0,0700 oh Pekerja 100.000,00 7.000,00
0,0090 oh Tukang cat 150.000,00 1.350,00
0,0060 oh Kepala Tukang 150.000,00 900,00
0,0025 oh Mandor 150.000,00 375,00
Total : 9.625,00 48.261,00 57.886,00

2 1 M2 PENGECATAN WATERPROOF TEMBOK BARU


(1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0,1000 kg Cat dasar 55.800,00 5.580,00
0,2600 kg Cat Penutup 55.800,00 14.508,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,0630 oh Tukang cat 150.000,00 9.450,00
0,0063 oh Kepala Tukang 150.000,00 945,00
0,0025 oh Mandor 150.000,00 375,00
Total : 12.770,00 20.088,00 32.858,00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
3 1 M2 PENGECATAN TEMBOK (1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0,1000 kg Plamir 10.900,00 1.090,00
0,1000 kg Cat dasar 24.100,00 2.410,00
0,2600 kg Cat Penutup Exterior 2x 120.500,00 31.330,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,0630 oh Tukang cat 150.000,00 9.450,00
0,0063 oh Kepala Tukang 150.000,00 945,00
0,0025 oh Mandor 150.000,00 375,00
Total : 12.770,00 34.830,00 47.600,00

4 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


0,1000 kg Meni besi 63.500,00 6.350,00
0,0100 lbr Kuas 31.700,00 317,00
0,0200 oh Pekerja 100.000,00 2.000,00
0,2000 oh Tukang cat 150.000,00 30.000,00
0,0200 oh Kepala Tukang 150.000,00 3.000,00
0,0100 oh Mandor 150.000,00 1.500,00
Total : 36.500,00 6.667,00 43.167,00

XV PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
3,0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 21.200,00 63.600,00
1,0000 bt Pipa Clipsal 20 mm hitam 36.100,00 36.100,00
1,0000 bh Tee dos clipsal 20 mm hitam 9.800,00 9.800,00
bj Klem clipsal 20 mm hitam 5.400,00 -
1,0000 bj Sock clipsal 20 mm hitam 3.600,00 3.600,00
1,0000 bj Inbow dos plastik clipsal E 157 P 9.800,00 9.800,00
1,0000 ttk Biaya pasang 50.000,00 50.000,00
Total : 50.000,00 122.900,00 172.900,00

2 1 TITIK PASANG LAMPU LED 27 W


1,0000 titik Instalasi 172.900,00 172.900,00
1,0000 bh Lampu Pijar 96.800,00 96.800,00
Total : 269.700,00 269.700,00

3 1 TITIK PASANG LAMPU PIJAR LED 19 W


1,0000 titik Instalasi 172.900,00 172.900,00
1,0000 bh Lampu Pijar 79.100,00 79.100,00
Total : 252.000,00 252.000,00

4 1 TITIK SAKLAR TUNGGAL


1,0000 titik Instalasi 172.900,00 172.900,00
1,0000 bh Saklar tunggal 40.500,00 40.500,00
Total : 213.400,00 213.400,00

5 1 TITIK SAKLAR SERI (GANDA)


1,0000 titik Instalasi 172.900,00 172.900,00
1,0000 bh Saklar ganda 40.500,00 40.500,00
Total : 213.400,00 213.400,00

6 1 TITIK STOP KONTAK TERMASUK INSTALASI


1,0000 titik Instalasi 172.900,00 172.900,00
1,0000 bh Stop Kontak 36.100,00 36.100,00
Total : 209.000,00 209.000,00
DAFTAR HARGA SATUAN BAHAN

HARGA
NO NAMA BARANG SATUAN
(Rp)

1 Cat Meni Besi/dasar (Polibest) Kaleng 0,8 kg kg Rp. 63.500,00


2 Cat kayu+Besi/dasar (polibest) kaleng 0.8 kg kg Rp. 65.600,00
3 Cat menie besi (Avian) Kaleng 1 kg kg Rp. 63.500,00
4 Cat menie kayu (polibest) 0,8 kg kg Rp. 63.500,00
5 Cat tembok Paragon 5 Kg kg Rp. 24.100,00
6 Cat tembok (Nippon) Interior / Warna kg Rp. 120.500,00
7 Dempul kayu (polibest) 0,8 Kg kg Rp. 51.400,00
8 Kuas Besar 4 inch bh Rp. 31.700,00
9 Plamir tembok 5 kg kg Rp. 10.900,00
10 Cat Waterprof Aquaproof 1 kg kg Rp. 55.800,00
11 Minyak Solar B-0 ( 1 KL ) PBBKB 100% (7,5%) Ltr Rp. 13.000,00
12 Atap Zincalume 0.4 mm Spandek m2 Rp. 85.000,00
13 Besi strip 1kg kg Rp. 9.100,00
14 Formite/Penjaga Jarak Berkisting/Spacer bh Rp. 6.700,00
15 Seng BJLS 0,20 gelombang lbr Rp. 60.500,00
16 Seng Plat BJLS 30 lebar 28 cm lbr Rp. 25.400,00
17 Nok Zincalum Spandek bh Rp. 29.200,00
18 Engsel kupu-kupu jendela biasa ps Rp. 22.900,00
19 Engsel kupu-kupu pintu biasa ps Rp. 16.800,00
20 Kaca 5 mm bening 153x122 m2 m2 Rp. 170.500,00
21 Kait angin biasa ps Rp. 22.900,00
22 Kunci slot sedang bh Rp. 22.900,00
23 Kunci tanam 2 slag Bagus bh Rp. 233.400,00
24 Bambu sedang Ukuran 4 m btg Rp. 16.100,00
25 Kayu Besi 5 x 10, panjang 4 m' m3 Rp. 3.500.000,00
26 Papan Kayu besi 2,5 x 25, panjang 4 m' m3 Rp. 3.500.000,00
27 Papan Cor/Papan Kayu Putih m3 Rp. 2.000.000,00
28 Kayu Matoa 5 x 10, panjang 4 m' m3 Rp. 2.000.000,00
29 Kayu Matoa 5 x 5, panjang 4 m' m3 Rp. 2.000.000,00
30 Papan Kayu Matoa 2,5 x 25, panjang 4 m' m3 Rp. 2.000.000,00
31 Kayu dolken (pekerjaan sementara) btg Rp. 24.900,00
32 Lem Kayu (fox) kg Rp. 58.000,00
33 List Gypsum standar m1 Rp. 26.000,00
34 Minyak bekisting ltr Rp. 14.200,00
35 Multipleks 9 mm lbr Rp. 164.000,00
36 Kalsiboard 4,5 mm lbr Rp. 112.500,00
37 Granito 60 x 60 polos m2 Rp. 250.000,00
38 Keramik 20 x 20 kelas I warna tua m2 Rp. 65.200,00
39 Keramik 20 x 30 kelas I warna muda m2 Rp. 77.500,00
40 Batu alam ex. Cladding Kombinasi m2 Rp. 161.800,00
41 Floor drain stainless bh Rp. 62.400,00
42 Kloset porselin jongkok Ina (standar) bh Rp. 300.000,00
43 Kran air 3/4 biasa dari besi Stainless bh Rp. 44.900,00
44 Kran cuci piring bh Rp. 154.500,00
45 Seal tape Besar bh Rp. 9.800,00
46 Washtafel cuci piring 1 lubang bh Rp. 419.200,00
47 Profil Tank 2200 Liter bh Rp. 3.832.500,00
48 Paku 5 biasa kg Rp. 24.700,00
49 Paku 7 biasa kg Rp. 31.700,00
50 Paku 10 biasa kg Rp. 31.700,00
51 Paku list SQ kg Rp. 17.100,00
52 Paku skrup 1/2" bh Rp. 900,00
53 Paku skrup 2" bh Rp. 1.300,00
54 Bata Ringan/ Bataco 10 x 20 x 60 bj Rp. 18.000,00
55 Batu gunung/ belah m3 Rp. 300.000,00
HARGA
NO NAMA BARANG SATUAN
(Rp)
56 Batu Pecah 2-3 m3 Rp. 500.000,00
57 Pasir kasar m3 Rp. 350.000,00
58 Tanah urug m3 Rp. 208.700,00
59 Pipa Galvanis 1" MA m1 Rp. 55.600,00
60 Pipa Galvanis 3" MA m1 Rp. 171.100,00
61 Pipa Winlon AW 2 m1 Rp. 27.500,00
62 Pipa Winlon AW 3/4 m1 Rp. 13.200,00
63 Pipa Winlon AW 4 m1 Rp. 58.200,00
64 Gate Valve 3 inch bh Rp. 1.214.500,00
65 Stop Kran 1 Inch bh Rp. 143.300,00
66 Pompa Air Shimizu Pc-260BIT JET Pump + Tabung unit Rp. 1.713.400,00
67 Semen Tonasa 40 kg kg Rp. 1.800,00
68 Semen warna/semen grouting kg Rp. 18.500,00
69 Besi beton kg Rp. 12.200,00
70 Besi Holous 40 x 40 btg Rp. 164.300,00
71 Kawat beton RRT 1 Kg kg Rp. 24.000,00
72 Kawat Las 1kg kg Rp. 67.800,00
73 Hollow 4x4x0.3cm Galvalume m1 Rp. 18.000,00
74 Rangka Teralis Besi Stainless Steel m2 Rp. 1.295.000,00
75 Rangka Teralis Besi Hollow Galvanis m2 Rp. 945.000,00
76 Plat Besi Stainless Finish Hairline Tebal 1.2 mm m2 Rp. 315.900,00
77 Saklar ganda philip bh Rp. 40.500,00
78 Saklar Tunggal philip bh Rp. 40.500,00
79 Stop kontak philip bh Rp. 36.100,00
80 Kabel NYM 3 x 2.5 mm ex. Supreme m1 Rp. 21.200,00
81 Pipa clipsal 20 mm bt Rp. 36.100,00
82 Sock clipsal 20 mm bj Rp. 3.600,00
83 Tee dos clipsal 20 mm bh Rp. 9.800,00
84 Klem clipsal 0,5 " bj Rp. 5.400,00
85 Inbow dos plastik clipsal E 157 P bj Rp. 9.800,00
86 Lampu LED Bulb 27W Philips bh Rp. 96.800,00
87 Lampu LED Bulb 19W Philips bh Rp. 79.100,00
88 MCB 10A 1 Phasa bh Rp. 96.600,00
DAFTAR HARGA SATUAN UPAH

HARGA
NO NAMA BARANG SATUAN
(Rp)

1 Mandor Hari Rp 150.000,00


2 Kepala Tukang Hari Rp 150.000,00
3 Tukang Politur Hari Rp 150.000,00
4 Tukang Batu Hari Rp 150.000,00
5 Tukang kayu Hari Rp 150.000,00
6 Tukang Besi Hari Rp 150.000,00
7 Tukang cat Hari Rp 150.000,00
8 Tukang gali/buruh/ pekerja Hari Rp 150.000,00
9 Tukang Listrik Hari Rp 150.000,00
10 Tukang Pipa/ Tukang Ledeng Hari Rp 150.000,00
11 Pekerja Hari Rp 100.000,00

Anda mungkin juga menyukai