TIME SCHEDULLE

PROGRAM : GEDUNG DAN BANGUNAN


KEGIATAN : PEMBANGUNAN GEDUNG ASRAMA BERLANTAI 5 LPMP SUMBAR
PEKERJAAN : PEMBANGUNAN GEDUNG KELAS dan ASRAMA BLOK B TAHAP I (STRUKTUR)
LOKASI : KOMPLEK PERGURUAN TINGGI AIR TAWAR PADANG
TAHUN : 2015

Bulan Ke - 1 Bulan Ke - 2 Bulan Ke - 3 Bulan Ke - 4 Bulan Ke - 5 Bulan Ke - 6 Bulan Ke - 7


NO. URAIAN PEKERJAAN BIAYA BOBOT Minggu Ke - Minggu Ke - Minggu Ke - Minggu Ke - Minggu Ke - Minggu Ke - Minggu Ke - Persentase
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

I PEKERJAAN STRUKTUR BAWAH 100%


I.1 PEKERJAAN PONDASI KSLL Rp 2,813,187,601.97 27.70% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 090%

II PEKERJAAN STRUKTUR ATAS 080%

II.1 PEKERJAAN STRUKTUR LANTAI 1 (SATU) Rp 1,456,758,540.50 14.34% 2.05% 2.05% 2.05% 2.05% 2.05% 2.05% 2.05% 070%

II.2 PEKERJAAN LANTAI 2 (DUA) Rp 1,288,339,371.75 12.69% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 060%

II.3 PEKERJAAN LANTAI 3 (TIGA) Rp 1,289,375,978.15 12.70% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 1.81% 050%
II.4 PEKERJAAN LANTAI 4 (EMPAT) Rp 1,145,633,245.05 11.28% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 040%
II.5 PEKERJAAN STRUKTUR LANTAI 5 (LIMA) Rp 1,340,987,328.51 13.20% 2.20% 2.20% 2.20% 2.20% 2.20% 2.20% 030%
II.6 PEKERJAAN STRUKTUR LANTAI DACK Rp 442,299,254.12 4.36% 1.09% 1.09% 1.09% 1.09% 020%
II.7 PEKERJAAN STRUKTUR ATAP Rp 378,876,109.43 3.73% 1.87% 1.87% 010%
000%

JUMLAH TOTAL (Tanpa PPN) Rp 10,155,457,429.48 100%


BOBOT RENCANA 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 5.13% 5.13% 5.13% 2.05% 3.86% 3.86% 3.86% 3.63% 3.63% 3.63% 3.63% 3.69% 3.69% 3.69% 4.08% 4.08% 4.08% 3.29% 3.29% 3.29% 2.95% 1.87%
BOBOT KOMULATIF Rp - 3.1% 6.2% 9.2% 12.3% 15.4% 18.5% 23.6% 28.7% 33.8% 35.9% 39.8% 43.6% 47.5% 51.1% 54.7% 58.4% 62.0% 65.7% 69.4% 73.1% 77.1% 81.2% 85.3% 88.6% 91.9% 95.2% 98.1% 100.0%
BOBOT REALISASI
BOBOT REALISASI KOMULATIF

Padang, April 2015

Konsultan Perencana
PT. NATURAL SUMATERA CONSULTANT

Ir. CHANDRA SURYA


Direktur