RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBUATAN PAGAR


LOKASI : DELI SERDANG
TAHUN : 2021

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Satuan Volume
Upah Bahan Upah+Bahan Upah Bahan Upah+Bahan
1 2 3 4 5 6 7 8 9 10

I PEKERJAAN PENDAHULUAN
1 Survey dan Pengukuran Ls 1.00 1,000,000.00 - 1,000,000.00 1,000,000.00 - 1,000,000.00
2 Rambu-Rambu dan SMK 3 Ls 1.00 - 1,000,000.00 1,000,000.00 - 1,000,000.00 1,000,000.00
3 Mobilisasi dan Demobilisasi Ls 1.00 4,000,000.00 1,000,000.00 5,000,000.00 4,000,000.00 1,000,000.00 5,000,000.00
Jumlah I 7,000,000.00

II SIPIL
A PEKERJAAN PAGAR
1 Pembongkaran Pondasi Untuk Kolom m3 0.68 429,828.00 - 429,828.00 292,283.04 - 292,283.04
2 pengecoran Kolom danBalok Penyokong Pagar Camp. 1:2:3 m3 1.90 359,605.40 846,360.00 1,205,965.40 683,250.26 2,291,334.26 2,974,584.52
3 Pembesian Kolom dan Balok Penyokong Kg 180.35 3,555.23 17,730.00 21,285.23 641,185.73 3,197,605.50 3,838,791.23
4 Bekisting Kolom dan Balok Penyokong m2 38.08 236,105.10 145,400.00 381,505.10 8,990,882.21 5,536,832.00 14,527,714.21
5 Pemasangan Batu Bata m2 142.00 92,498.00 99,360.38 191,858.38 13,134,716.00 14,109,173.96 27,243,889.96
6 Pengecoran Ring Balok dan Sloof m3 2.13 359,605.40 846,360.00 1,205,965.40 765,959.50 1,802,746.80 2,568,706.30
7 Pembesian Ring Balok dan Sloof Kg 469.23 3,875.15 17,730.00 21,605.15 1,818,336.63 8,319,447.90 10,137,784.53
8 Bekisting Ring Balok dan Sloof m2 28.40 236,105.10 145,400.00 381,505.10 6,705,384.84 4,129,360.00 10,834,744.84
9 Plesteran dinding halus m2 152.65 111,373.50 12,354.38 123,727.88 17,001,164.78 1,885,896.11 18,887,060.88
10 Pengecatan dinding belakang m2 152.65 23,406.95 28,470.00 51,876.95 3,573,070.92 4,345,945.50 7,919,016.42
Jumlah A 99,224,575.93
B PEKERJAAN PIPA
1 Pengantian pipa pcv 1" m 30.00 3,400.00 11,100.00 14,500.00 102,000.00 333,000.00 435,000.00
Jumlah B 435,000.00
Jumlah A+B 99,659,575.93
Jumlah II 99,659,575.93

III PEKERJAAN LAIN - LAIN


1 Pembersihan Akhir Ls 1.00 2,000,000.00 - 2,000,000.00 2,000,000.00 - 2,000,000.00
2 Photo dokumentasi dan administrasi Ls 1.00 1,000,000.00 500,000.00 1,500,000.00 1,000,000.00 500,000.00 1,500,000.00
Jumlah III 3,500,000.00