Anda di halaman 1dari 5

DAFTAR RENCANA ANGGARAN BIAYA ( RAB )

PENGADAAN DAN PEMASANGAN PAGAR PENGAMAN JALAN : 100 METER

NO URAIAN JUMLAH
( Rp )

I PENGADAAN BAHAN 34,546,500.00

II PEKERJAAN BESI 16,302,425.278


Jumlah
50,848,925.28
PPN 10% 5,084,892.53
Jumlah 55,933,817.81
Dibulatkan

DAFTAR RENCANA ANGGARAN BIAYA ( RAB )


PENGADAAN DAN PEMASANGAN PAGAR PENGAMAN JALAN : 100 METER

NO URAIAN PEKERJAAN HARGA JUMLAH


VOLUME
SATUAN ( Rp ) ( Rp )
A. PENGADAAN BAHAN
1 Lempengan besi baja profit disain galvanis 25 bh 300,000.00 7,500,000.00
2 Tiang Penyangga besi SA 32 profit galvanis 51 bh 320,000.00 16,320,000.00
3 Besi pengikat baja profil disain bloking 51 bh 100,000.00 5,100,000.00
4 Mur baut Beam 16x25mm 208 bh 7,500.00 1,560,000.00
5 Mur Baut post 16x48mm 102 bh 9,000.00 918,000.00
6 Mur Baut 12x30mm 51 bh 1,000.00 51,000.00
7 Besi Angkur 30x30x3mm (panjang 300mm) 153 bh 7,500.00 1,147,500.00
8 Reflektor 27 bh 50,000.00 1,350,000.00
9 Terminal end ( slove beam ) 2 bh 300,000.00 600,000.00
JUMLAH 34,546,500.00

B. PEKERJAAN PONDASI
1 Cor Pondasi 1:2:3 24.48 M3 620,914.06 15,199,976.13
2 Galian Tanah 22.95 M3 16,917.00 388,245.15
3 Urugan Kembali 51 tiang 1,944.00 99,144.00
4 Pengelasan angkur tiang 153 bh 4,020.00 615,060.00
JUMLAH 16,302,425.28
Jumlah I, II, 50,848,925.28
PPN 10% 5,084,892.53
Jumlah 55,933,817.81
Dibulatkan

DAFTAR ANALISA SATUAN PEKERJAAN

1. 1 m3 Galian Tanah Keras/ M3


0.625 Pekerja @ Rp 23,000.00 Rp 14,375.00
0.062 Mandor @ Rp 41,000.00 Rp 2,542.00
Rp 16,917.00
2. 1m3 Urugan Tanah Kembali 1tiang
0.056 Pekerja @ Rp 23,000.00 Rp 1,288.00
0.016 Mandor @ Rp 41,000.00 Rp 656.00
1,944.00
3. 1m3 Urugan Pasir / M3
1.3 Pasir Urug @ Rp 42,800.00 Rp 55,640.00
0.6 Pekerja @ Rp 23,000.00 Rp 13,800.00
0.06 Mandor @ Rp 41,000.00 Rp 2,460.00
71,900.00
4. 1 m3 COR PONDASI 1:2:3 / M3
0.82 Batu pecah 2/3 @ Rp 159,000.00 Rp 130,380.00
6.19 PC 50 kg @ Rp 45,450.00 Rp 281,174.15
0.42331 Pasir u/ beton @ Rp 75,500.00 Rp 31,959.91
1 Pekerja @ Rp 23,000.00 Rp 23,000.00
0.1 Mandor @ Rp 41,000.00 Rp 4,100.00
6.0 Pekerja @ Rp 23,000.00 Rp 138,000.00
0.3 Mandor @ Rp 41,000.00 Rp 12,300.00
620,914.06
5. 1m2 Bekisting ( acuan )
0,04 m3 Kayu Tahun @ Rp 1,000,000.00 Rp 40,000.00
0,40 kg Paku @ Rp 12,000.00 Rp 4,800.00
0.5 Tukang @ Rp 34,000.00 Rp 17,000.00
0.05 Kepala Tukang @ Rp 35,000.00 Rp 1,750.00
0.2 Pekerja @ Rp 23,000.00 Rp 4,600.00
0.01 Mandor @ Rp 41,000.00 Rp 410.00
68,560.00
6. 1 m2 Plesteran dinding spesi IPC : 2 Ps -
0.147 zak PC 50 kg @ Rp 45,450.00 Rp 6,681.15
0.01 m3 Pasir pasang @ Rp 60,000.00 Rp 600.00

0.15 Tukang @ Rp 34,000.00 Rp 5,100.00


0.015 Kepala Tukang @ Rp 35,000.00 Rp 525.00
0.40 Pekerja @ Rp 23,000.00 Rp 9,200.00
0.02 Mandor @ Rp 41,000.00 Rp 820.00
22,926.15

7. 1m3 Pengelasan angkur 1titik


0.092 Pekerja @ Rp 23,000.00 Rp 2,116.00
0.056 Tukang @ Rp 34,000.00 Rp 1,904.00
4,020.00

DAFTAR HARGA BAHAN DAN SATUAN PEKERJAAN

No URAIAN SAT HARGA SATUAN


1 Tiang Penyangga besi SA 32 profit galvanis bh 320,000.00
2 Besi pengikat baja profil disain bloking bh 100,000.00
3 Lempengan besi baja profit disain galvanis m 300,000.00
4 Terminal end ( slove beam ) bh 300,000.00
5 Reflector bh 50,000.00
6 Mur baut Beam 16x25mm bh 7,500.00
7 Mur Baut post 16x48mm bh 9,000.00
8 Mur Baut 12x30mm bh 1,000.00
9 Besi Angkur 30x30x3 bh 7,500.00
7 Pasir urug m3 42,800.00
8 Pasir beton m3 75,500.00
9 Pasir pasang m3 60,000.00
10 Kayu tahun m3 1,000,000.00
11 Semen PC 50kg zak 45,450.00
12 Batu pecah 2/3 m3 159,000.00
13 Tukang Hr 34,000.00
14 Kepala Tukang Hr 35,000.00
15 Pekerja Hr 23,000.00
16 Mandor Hr 41,000.00

Kediri, 2008
CV. MULIA

HERU SUBAGIO
Direktur
52 m
PENGADAAN GUARD RAIL 44 METER

1 Pengadaan tiang Post 26 bh


2 Pengadaan blocking Post 26 bh
3 Pengadaan lempeng 12 BT
baja ( Beam )
4 Pengadaan Sleeve beam 4 bh
( terminal end )
5 Pengadaan Reflector 18 bh

6 Pengadaan mur baut beam 119 bh


7 Pengadaan mur tiang Pos 46 bh

Heru s Kediri
0.61 28
0.15 28
0.05 28

2.06 28
0.272 28
0.1 28

0.9 28

Anda mungkin juga menyukai