DAFTAR HARGA SATUAN

MATERIAL BANGUNAN DAN UPAH

PEKERJAAN : PEKERJAAN RABAT BETON TEKSTUR JALAN DAN PARKIRAN CAPA RESORT MAUMERE
LOKASI : CAPA RESORT MAUMERE, JL. NAIROA - KEC. KANGAE - KAB. SIKKA
TAHUN : 2016

Harga Dasar Ongkos Angkut Jumlah Harga


No. Material / Bahan Bangunan Satuan Lokasi Material
Tanpa Pajak (Rp) (Rp) Tanpa Pajak (Rp)
1 2 3 4 5 6= 4+5 7
1 Batu Kerikil 2/3 M³ 300,000.00 90,000.00 390,000.00
2 Batu Kerikil 3/5 M³ 220,000.00 90,000.00 310,000.00
3 Pasir Urug M³ 60,000.00 90,000.00 150,000.00
4 Pasir Pasang M³ 75,000.00 90,000.00 165,000.00
5 Portland Cement (PC @ 40 Kg) Kg 52,000.00 500.00 52,500.00
6 Papan Bekisting M³ 2,750,000.00 50,000.00 2,800,000.00
7 Cat Eksterior ( Jotun Jotashield Primer 07 ) Kg 30,000.00 100.00 30,100.00
8 Minyak Bekisting Ltr 19,000.00 50.00 19,050.00
9 Thiner A Ltr 26,500.00 100.00 26,600.00
### Additive Beton Ltr 11,000.00 1,000.00 12,000.00
### Kwas Cat Biasa no. 2 Bh 4,000.00 10.00 4,010.00

DAFTAR HARGA SATUAN UPAH PEKERJA


Upah Dasar Jasa Total Harga
No Tenaga Kerja
Rp (Org/Hari) Kontraktor Rp (Org/Hari)
1 Pekerja 65,000.00 65,000.00
2 Tukang Batu 80,000.00 80,000.00
3 Tukang Cat 80,000.00 80,000.00
4 Kepala Tukang 85,000.00 85,000.00
5 Mandor 90,000.00 90,000.00

Maumere, 04 JuLi 2016

Dwieka Trimulya
ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN : PEKERJAAN RABAT BETON TEKSTUR JALAN DAN PARKIRAN CAPA RESORT MAUMERE
LOKASI : CAPA RESORT MAUMERE, JL. NAIROA - KEC. KANGAE - KAB. SIKKA
TAHUN : 2016

1 M2 Pembongkaran Paving Block R 4,810.00


Index Sat. Uraian Harga Satuan (Rp) Jumlah Harga (Rp)
I UPAH
0.065 O/h Pekerja Rp. 65,000.00 4,225.00
0.007 O/h Mandor Rp. 90,000.00 585.00
Jumlah R 4,810.00
TOTAL R 4,810.00

1 M² Cor Beton Tak Bertulang / Rabat, t = 8 cm (1:2:3) K 125 R 71,208.25


Index Sat. Uraian Harga Satuan (Rp) Jumlah Harga (Rp)
I BAHAN
0.076 m³ Kerikil 3/5 Rp. 310,000.00 23,622.00
0.082 Zak PC @ 40 Kg Rp. 52,500.00 4,278.75
0.076 m³ Pasir Pasang Rp. 165,000.00 12,540.00
Jumlah R 40,440.75
II UPAH
0.120 O/h Tukang Batu Rp. 80,000.00 9,600.00
0.018 O/h Kepala Tukang Rp. 85,000.00 1,487.50
0.300 O/h Pekerja Rp. 65,000.00 19,500.00
0.002 O/h Mandor Rp. 90,000.00 180.00
Jumlah R 30,767.50
TOTAL R 71,208.25

1 M² Plesteran Tekstur ( 1 : 3 ) Rp. 72,100.00


Index Sat. Uraian Harga Satuan (Rp) Jumlah Harga (Rp)
A BAHAN
0.520 Zak PC @ 40 Kg Rp. 52,500.00 Rp. 27,300.00
0.062 m³ Pasir Pasang Rp. 165,000.00 Rp. 10,230.00
Jumlah R 37,530.00
B UPAH
0.400 O/h Tukang Batu Rp. 80,000.00 Rp. 32,000.00
0.020 O/h Kepala Tukang Rp. 85,000.00 Rp. 1,700.00
0.012 O/h Pekerja Rp. 65,000.00 Rp. 780.00
0.001 O/h Mandor Rp. 90,000.00 Rp. 90.00
Jumlah R 34,570.00
TOTAL Rp. 72,100.00

Maumere, 04 JuLi 2016

Dwieka Trimulya
RENCANA ANGGARAN & BIAYA

PEKERJAAN : PEKERJAAN RABAT BETON TEKSTUR JALAN DAN PARKIRAN CAPA RESORT MAUMERE
LOKASI : CAPA RESORT MAUMERE, JL. NAIROA - KEC. KANGAE - KAB. SIKKA
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


No. URAIAN PEKERJAAN SAT. VOLUME
BAHAN (Rp) UPAH (Rp) BAHAN (Rp) UPAH (Rp)
I PEKERJAAN PERSIAPAN
1 Pembongkaran Paving Block M² 446.230 0.000 4,810.00 0.00 2,146,366.30
2 Pengukuran & Pemasangan Bowplank & Uitzet Ls 1.000 0.000 1,500,000.00 0.00 1,500,000.00
JUMLAH I 0.00 3,646,366.30
II PEKERJAAN BETON BERTULANG
1 Cor Rabat Beton, t = 8 cm ( K 175 ) M² 446.230 40,440.750 30,767.50 18,045,875.87 13,729,381.53
JUMLAH II 18,045,875.87 13,729,381.53
III PEKERJAAN PLESTERAN TEKSTUR
1 Plesteran tekstur ( 1 Pc : 3 Ps ) M² 446.230 37,530.000 34,570.00 16,747,011.90 15,426,171.10
JUMLAH III 16,747,011.90 15,426,171.10
IV PEKERJAAN LAIN-LAIN
1 Pembersihan Kembali Ls 1.000 0.000 1,000,000.00 0.00 1,000,000.00
2 Perbaikan Saluran Air Ls 1.000 0.000 1,500,000.00 0.00 1,500,000.00
JUMLAH V 0.00 2,500,000.00
JUMLAH TOTAL BAHAN I s/d V 34,792,887.77
JUMLAH TOTAL UPAH I s/d V 35,301,918.93
JUMLAH TOTAL UPAH & BAHAN I s/d V 70,094,806.70

Mengetahui Maumere, 04 JuLi 2016


Direktur PT. Petrada Widya Radhasa Dibuat Oleh

Januarius G. Goleng Dwieka Trimulya


446.22857142857
REKAPITULASI RENCANA ANGGARAN & BIAYA

PEKERJAAN : PEKERJAAN RABAT BETON TEKSTUR JALAN DAN PARKIRAN CAPA RESORT MAUMERE
LOKASI : CAPA RESORT MAUMERE, JL. NAIROA - KEC. KANGAE - KAB. SIKKA
TAHUN : 2016

No. URAIAN PEKERJAAN HARGA

I PEKERJAAN PERSIAPAN Rp. 3,646,366.30


II PEKERJAAN BETON BERTULANG Rp. 31,775,257.40
III PEKERJAAN PLESTERAN TEKSTUR Rp. 32,173,183.00
IV PEKERJAAN LAIN-LAIN Rp. 2,500,000.00
JUMLAH I s/d XIII Rp. 70,094,806.70
DIBULATKAN Rp. 70,000,000.00

TERBILANG # DELAPAN PULUH DUA JUTA ENAM RATUS LIMA PULUH EMPAT RIBU RUPIAH #

Mengetahui, Maumere, 04 JuLi 2016


Direktur Utama PT. Petrada Widya Radhasa

Melchias M. Mekeng Dwieka Trimulya

CATATAN :
1. DALAM PEKERJAAN INI YANG BERLAKU ADALAH BORONGAN UPAH PEKERJAAN SEBESAR : RP.34.000.000,-
2. BAHAN / MATERIAL KERJA DITANGGUNG OLEH OWNER
3. PELAKSANAAN PEKERJAAN TELAH DIMULAI SEJAK TANGGAL 06 JULI 2016
4. SETELAH HARGA UPAH BORONGAN DISETUJUI, KAMI MENGHARAPKAN BANTUAN DANA AWAL PEKERJAAN
SEBESAR RP. 15.000.000,00