KECAMATAN SALE
DESA UKIR
RENCANA PENGGUNAAN DANA
Kegiatan : Pembangunan Talud dan Hurug Jalan Pertanian RT 09 RW 02 Desa Ukir Kec. Sale Kab. Rembang
Harga Satuan
No Uraian Volume Satuan Jumlah
Rp.
1 2 3 4 5 6
I Pembelian Material -
Semen portland 616 Zak 58,000.00 35,728,000.00
Batu Belah 177 M3 221,000.00 39,117,000.00
Batu Pecah 1/2 0 M3 299,000.00 -
Sirtu (tak ayak) 157 M3 200,000.00 31,400,000.00
Pasir Pasang 78 M3 290,000.00 22,620,000.00
Kaso 4/6 3M 15 Btg 30,000.00 450,000.00
Papan 2/20 1,5M 15 btg 10,000.00 150,000.00
Paku 1 Kg 25,000.00 25,000.00
0 0 Lmbr 97,000.00 -
0 0 Kg 25,000.00 -
Sub Total I 129,490,000.00
II Tenaga
Pekerja 317.00 OH 90,000.00 28,530,000.00
Tukang Batu 126.00 OH 100,000.00 12,600,000.00
Sub Total II 41,130,000.00
Sub Total I dan II 170,620,000.00
Musdes Perencanaan
Snack 25 Dus 15,000.00 375,000.00
Makan 25 Dus 25,000.00 625,000.00
Musdes Pertanggung jawaban
Snack 25 Dus 15,000.00 375,000.00
Makan 25 Dus 25,000.00 625,000.00
biaya perjalanan dinas -
1 Ke Kecamatan 6 Kali 50,000.00 300,000.00
2 Ke Kabupaten 6 Kali 100,000.00 600,000.00
Sub Total III 4,380,000.00
Jumlah Total (I+II+III) 175,000,000.00
ANALISA HARGA SATUAN PEKERJAAN
4 A.4.4.2.5 Pemasangan 1 m2 Plesteran dgn campuran 1SP : 5PP tebal 15 mm Harga Satuan
Jumlah Harga
No. Uraian Kode Koefisien Satuan (Rp)
(Rp)
Pekerja L.01 0.3 OH 90,000 27,000.00
Tukang Batu L.02 0.15 OH 100,000 15,000.00
Semen portland 6.24 kg 1,450 9,048.00
Pasir Pasang 0.024 m3 290,000 6,960.00
Harga Satuan Pekerjaan 58,008.00
II Material 129,490,000.00
Semen portland 616.00 Zak 58,000.00 35,728,000.00
Batu Belah 177.00 M3 221,000.00 39,117,000.00
Sirtu (tak ayak) 157.00 M3 200,000.00 31,400,000.00
Pasir Pasang 78.00 M3 290,000.00 22,620,000.00
Kaso 4/6 3M 15.00 Btg 30,000.00 450,000.00
Papan 2/20 1,5M 15.00 btg 10,000.00 150,000.00
Paku 1.00 Kg 25,000.00 25,000.00
0 Lmbr 97,000.00 -
0 Kg 25,000.00 -
IV Operasional 4,380,000.00
Papan Proyek 1 Unit 150,000.00 150,000.00
Prasasti Kegiatan 1 Unit 350,000.00 350,000.00
ATK, Materai dan Fotocopy 1 Ls 480,000.00 480,000.00
Biaya Perencanaan 1 Ls 500,000.00 500,000.00
Perjalanan Dinas ke kecamatan 6 Kali 50,000.00 300,000.00
Perjalanan Dinas ke kabupaten 6 Kali 100,000.00 600,000.00
Snack 50 Dus 15,000.00 750,000.00
Makan 50 Dus 25,000.00 1,250,000.00
TOTAL 175,000,000.00
95,620,000.00
103,592,000.00
5,250,000.00 5.25
3,714,000.00 - 666,000.00
- 186,000.00
667,500.00
3,714,000
666,000.00 -
- 186,000.00
Harga Satuan Pekerjaan
TOTAL 171,052,904.00
145
Galian Talud P D L
145 x 0.5 x 0.6 = 43.5
43.5
Pas Lanjutan
P L T
= 145 x 0.45 x 1.6 = 104.4
Jumlah 104.4 M3
Plesteran Talud
p l
= 145 x 0.4 = 58
Jumlah 58 M2
Urug Jalan
145 x 2.5 x 0.2 = 72.5
145 x 0.25 x 1.6 = 58
130.5
120 galian
pasangan
p l d pas atas
10 0.35 0.35 0.35 0.35 0.3 0.325 0.3
32 0.35 0.35 0.35 0.3 0.3 0.3 0.3
5 0.4 0.5 0.45 0.3 0.5 0.4 0.3
57 0.5 0.5 0.5 0.5 0.5 0.5 0.3
17 0.5 0.4 0.45 0.5 0.35 0.425 0.3
30 0.35 0.35 0.35 0.35 0.3 0.325 0.3
0.35 0.325
0.35 0.3
0.45 0.4
0.5 0.5
0.45 0.425
0.35 0.325
ANALISA HITUNG
26.40 78.30
104.70 238
Tinggi rata2
0.325 1 0.5 0.75 1.05 0.75 0.35
0.325 0.5 0.5 0.5 0.8 0.5 0.3
0.375 0.5 2.1 1.3 1.6 1.3 0.4
0.4 2.1 2.1 2.1 2.4 2.1 0.5
0.375 2.1 1 1.55 1.85 1.55 0.45
0.325 1 0.5 0.75 1.05 0.75 0.35
PEMERINTAH KABUPATEN REMBANG
KECAMATAN SALE
DESA UKIR
GAMABAR TEKNIS
GAMBAR TEKNIS KEGIATAN PEMBANGUNAN TALUD
DAN HURUG JALAN PERTANIAN
TAHUN ANGGARAN 2022
2M 0.5 0.3
Desa : UKIR
Plester 1:5 dan acian
Pasangan Batu 1:5 Lokasi RT 09 RW 02 Dusun Ukir
Suling-suling 1.5 Desa Ukir
Hurugan Di gambar oleh:
SUDARTO
Di setujui,
KEPALA DESA UKIR
TEGUH HARTONO
NIP. 19720712 200701 1 021