Nama Toko :
Penangung Jawab :
B Alat Bantu
1 Cangkul Buah 75,000.00
2 Singkup Buah 80,000.00
3 Ember Cor Buah 10,000.00
4 Pengki Buah 14,500.00
5 Benang Buah 6,000.00
6 Concrete Mixer / Molen Hari 400,000.00
7 Mobilisasi Molen Ls 500,000.00
HARGA SATUAN UPAH
KABUPATEN CIANJUR 2020
UPAH
NO. JENIS PEKERJA / KEAHLIAN 1 HARI 8 JAM
(Rp)
1 Pekerja 80,000.00
2 Tukang 100,000.00
4 Mandor 160,000.00
VOLUME
NO. JENIS PEKERJAAN SAT.
P L T VOL. VOL.
1 PEKERJAAN GALIAN PIPA DRAINASE PVC 8" M3 62.00 x x 0.30 0.50 = 9.30
........................
ANALISA HARGA/UPAH/MATERIAL
Rencana Anggaran Biaya (RAB)
DESA LOKASI
KECAMATAN KEGIATAN
KABUPATEN VOLUME
PROVINSI T.A
D PERALATAN
..................
RENCANA ANGGARAN BIAYA (RAB)
DESA 0 LOKASI 0
KECAMATAN 0 KEGIATAN 0
KABUPATEN 0 VOLUME 0
PROVINSI 0 T.A 0
JUMLAH
H A R G A SATUAN JUMLAH TOTAL
VOL.
NO. U R A I A N VOL. SAT. TOTAL (Rp.) PEMBULATAN
PMBLTN
(Rp.) (Rp.)
D PERALATAN
a. PENGADAAN PERALATAN
1 Cangkul 4.00 4.00 Bh 75,000 300,000 300,000
2 Singkup 2.00 2.00 Bh 80,000 160,000 160,000
3 Ember Cor 8.00 8.00 Bh 10,000 80,000 80,000
4 Pengki 4.00 4.00 Bh 14,500 58,000 58,000
5 Benang 2.00 2.00 Bh 6,000 12,000 12,000
Sub Total Peralatan (D) 610,000 610,000
TOTAL BIAYA (A+B+C+D+E) 48,856,909 48,878,000
.........................
REKAPITULASI RENCANA ANGGARAN BIAYA
LOKASI 0
KEGIATAN 0
VOLUME 0
T.A 0
DESA 0
KECAMATAN 0
KABUPATEN 0
PROVINSI 0
NO URAIAN PEKERJAAN VOLUM SATUAN HARGA SATUAN (RP) JUMLAH HARGA (RP)
3 A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200 mm 62.00 M' 525,901.45 32,605,890.00
..........................
Mengetahui
Pendamping Desa Teknik Infrastruktur
ERIK MUSTIADI