SURVEI HARGA SATUAN BAHAN

KABUPATEN CIANJUR 2020

Nama Toko :
Penangung Jawab :

HARGA SATUAN HARGA SATUAN HARGA SATUAN


NO SATUAN TOKO / PEMASOK TRANSPORTASI/ONGKOS SAMPAI DILOKASI
Rp. Rp. Rp.
A Bahan Material
1 Semen PC (50) kg Zak 65,000.00
2 Pasir Pasang m3 230,000.00
3 Batu Belah m3 180,000.00
4 Pasir Urug m3 160,000.00
5 Buis Beton D'30 Bh 50,000.00
6 Batu Pecah Mesin 5/7 m3 210,000.00
7 Batu Pecah Mesin 2/3 m3 300,000.00
8 Batu Belah m3 175,000.00
9 Pasir Pasang m3 200,000.00
10 Batu pecah mesin 1/2 m3 300,000.00
11 Besi Kg 17,000.00
12 Wermes Lmb 300,000.00
13 Pasir Beton m3 260,000.00
14 Plastik Membran m2 2,500.00
15 Papan Bekisting bh 40,000.00
16 Kaso 5/7 btg 25,000.00
17 Paku Kg 20,000.00
18 Kawat Las Kg 20,000.00
19 Pipa PVC 4" M 80,000.00
20 Pipa Galvanis 3" M 130,000.00
21 Pipa Galvanis 2" M 110,000.00
22 Cat Besi Kg 100,000.00
23 Pipa PVC 8" m' 280,000.00
24 Sambungan Pipa 8" bh 200,000.00
25 Lem Pipa bh 15,000.00

B Alat Bantu
1 Cangkul Buah 75,000.00
2 Singkup Buah 80,000.00
3 Ember Cor Buah 10,000.00
4 Pengki Buah 14,500.00
5 Benang Buah 6,000.00
6 Concrete Mixer / Molen Hari 400,000.00
7 Mobilisasi Molen Ls 500,000.00
HARGA SATUAN UPAH
KABUPATEN CIANJUR 2020

UPAH
NO. JENIS PEKERJA / KEAHLIAN 1 HARI 8 JAM
(Rp)
1 Pekerja 80,000.00

2 Tukang 100,000.00

3 Kepala Tukang 140,000.00

4 Mandor 160,000.00

5 Operator Alat Berat 150,000.00

6 Pembantu Operator / Mekanik 100,000.00

7 Sopir Truk 150,000.00

8 Kenek Truk 100,000.00

11 Penjaga Malam 60,000.00


PERHITUNGAN VOLUME PEKERJAAN
DESA LOKASI
KECAMATAN KEGIATAN
KABUPATEN VOLUME
PROVINSI T.A

VOLUME
NO. JENIS PEKERJAAN SAT.
P L T VOL. VOL.

1 PEKERJAAN GALIAN PIPA DRAINASE PVC 8" M3 62.00 x x 0.30 0.50 = 9.30

2 PEKERJAAN RABAT BETON K-175 M3 77.00 x 1.30 x 0.10 = 10.01

3 PEKERJAAN PIPA DRAINASE M' 62.00 = 62.00

Cianjur, 27 Desember 2020


Dibuat Oleh :
Kader Teknik

........................
ANALISA HARGA/UPAH/MATERIAL
Rencana Anggaran Biaya (RAB)

DESA LOKASI
KECAMATAN KEGIATAN
KABUPATEN VOLUME
PROVINSI T.A

NO. KOEF. URAIAN VOLUME SATUAN HARGGA SATUAN JUMLAH HARGA

A ADMINISTRASI DAN PERENCANAAN

1 Perencanaan Swakelola 3%x0,6 1.00 Ls 900,000 900,000


2 Pelaporan dan Dokumentasi 1.0 ls 250,000 250,000
3 Papan proyek 1.0 bh 150,000 150,000
4 Prasasti 1.0 bh 300,000 300,000
5 Honor TPK
- Ketua 1.0 ls 200,000 200,000
- Sekretaris 1.0 ls 175,000 175,000
- Anggota 1.0 ls 150,000 150,000

Sub Total (A) 2,125,000

B PEKERJAAN PIPA DRAINASE


B.29.a Bongkar 1 m3 beton secara
1 konvensional 1.86 M3
3.60 Pekerja 6.70 Hok 80,000 535,680
Sub Total (1) 535,680

A.2.3.1.1. Penggalian 1 m3 tanah biasa


2 9.30 M3
sedalam 1 m
0.75 Pekerja 6.98 Hok 80,000 558,000
Sub Total (2) 558,000
A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200
3 62.00 M'
mm
Pemasangan Pipa
1.00 Pipa PVC Ø 200 mm 62.00 m' 500,000 31,000,000
Lem Pipa 1.00 Kaleng 50,000 50,000
0,189 Pekerja 11.72 Hok 80,000 937,440
0,095 Tukang Batu 5.89 Hok 105,000 618,450
Sub Total (3) 32,605,890
A.5.1.1 15. Pemasangan 1 buah bak kontrol
4 3 Bh
pasangan bata 30x30 tinggi 35 cm
40 Bata merah 120.00 Bh 800 96,000
0.88 Semen portland 2.64 Zak 65,000 171,600
0.07 Pasir pasang 0.21 M3 230,000 48,300
0.06 Pasir beton 0.18 M3 260,000 46,800
0.07 Kerikil/Splite 0.21 M3 300,000 63,000
0.33755 Baja tulangan/Besi 8 1.01 Btg 60,000 60,759
2.16 Pekerja 6.48 Hok 80,000 518,400
0.72 Tukang batu 2.16 Hok 105,000 226,800
Sub Total (4) 1,231,659
TOTAL B 34,931,229
C PEKERJAAN RABAT BETON K-175
1 PEKERJAAN RABAT BETON K-175 10.01 M3

1 m² bekisting lantai beton biasa


B.21.c menggunakan papan kayu menggunakan 15.40 m2
papan kayu 3/20 cm (TP)

Papan 3/20 cm kayu


0.014 9.06 Lbr 40,000 362,208
kelas II
0.003 Kaso 5/7 3.28 Btg 25,000 82,005
0.30 Paku 5-10 cm 4.62 kg 20,000 92,400
0.30 Pekerja 4.62 Hok 80,000 369,600
0.15 Tukang kayu 2.31 Hok 105,000 242,550
Sub Total (1) 1,148,763
2 Cor Beton
B.02 1 m³ beton mutu, f’c = 7,4 MPa (K100), slump (12±2) cm, w/c = 0,87
NO. KOEF. URAIAN VOLUME SATUAN HARGGA SATUAN JUMLAH HARGA

4.94 Semen PC (50) kg 49.45 Zak 65,000 3,214,211


0.62 Pasir beton 6.22 M3 260,000 1,616,215
0.74 Split Pecah mesin 2/3 7.41 M3 300,000 2,222,220
Plastik Membran 115.50 M2 2,000 231,000
1.32 Pekerja 13.24 Hok 80,000 1,059,458
0.19 Tukang batu 1.89 Hok 105,000 198,648
0.25 Concrete Mixer / Molen 2.50 Hari 400,000 1,001,000
Mobilisasi dan Demobilisasi Molen 1.00 Ls 500,000 500,000
Sub Total (2) 10,042,752
TOTAL C 11,191,515

D PERALATAN

1 Cangkul 4.00 Bh 75,000 300,000


2 Singkup 2.00 Bh 80,000 160,000
3 Ember Cor 8.00 Bh 10,000 80,000
4 Pengki 4.00 Bh 14,500 58,000
5 Benang 2.00 Bh 6,000 12,000

Sub Total (C) 610,000

TOTAL BIAYA (A+B+C) 48,856,909

Cianjur, 27 Desember 2020

Mengetahui Dibuat Oleh :


kepala Desa Kader Teknik

..................
RENCANA ANGGARAN BIAYA (RAB)

DESA 0 LOKASI 0
KECAMATAN 0 KEGIATAN 0
KABUPATEN 0 VOLUME 0
PROVINSI 0 T.A 0

JUMLAH
H A R G A SATUAN JUMLAH TOTAL
VOL.
NO. U R A I A N VOL. SAT. TOTAL (Rp.) PEMBULATAN
PMBLTN
(Rp.) (Rp.)

A ADMINISTRASI DAN PERENCANAAN


a. PERENCANAAN TEKNIS
1 Perencanaan Swakelola 3%x0,6 1.00 1.00 Ls 900,000 900,000 900,000
2 Pelaporan dan Dokumentasi 1.00 1.00 ls 250,000 250,000 250,000
3 Papan proyek 1.00 1.00 bh 150,000 150,000 150,000
4 Prasasti 1.00 1.00 bh 300,000 300,000 300,000
5 Honor TPK
- Ketua 1.00 1.00 ls 200,000 200,000 200,000
- Sekretaris 1.00 1.00 ls 175,000 175,000 175,000
- Anggota 1.00 1.00 ls 150,000 150,000 150,000
Sub Total Adminisrasi dan Perencanaan (A) 2,125,000 2,125,000
B UPAH
a. BIAYA UPAH
1 Pekerja 49.73 50.00 Hok 80,000 3,978,578 4,000,000
2 Tukang 12.25 12.00 Hok 105,000 1,286,448 1,260,000
Sub Total Upah (B) 5,265,027 5,260,000
C BELANJA MODAL
a. PENGADAAN BAHAN MATERIAL
1 Pipa PVC Ø 200 mm 62.00 62.00 m' 500,000 31,000,000 31,000,000
2 Lem Pipa 1.00 1.00 Kaleng 50,000 50,000 50,000
3 Bata merah 120.00 120.00 Bh 800 96,000 96,000
4 Semen portland 52.09 50.00 Zak 65,000 3,385,811 3,250,000
5 Pasir pasang 0.21 0.00 M3 230,000 48,300 -
6 Pasir beton 6.40 6.00 M3 260,000 1,663,015 1,560,000
7 Kerikil/Splite 7.62 8.00 M3 300,000 2,285,220 2,400,000
8 Baja tulangan/Besi 8 1.01 1.00 Btg 60,000 60,759 60,000
9 Papan 3/20 cm kayu 9.06 9.00 Lbr 40,000 362,208 360,000
kelas II
10 Kaso 5/7 3.28 3.00 Btg 25,000 82,005 75,000
11 Paku 5-10 cm 4.62 5.00 kg 20,000 92,400 100,000
12 Plastik Membran 115.50 116.00 M2 2,000 231,000 232,000
13 Concrete Mixer / Molen 2.50 3.00 Hari 400,000 1,001,000 1,200,000
14 Mobilisasi dan Demobilisasi Molen 1.00 1.00 Ls 500,000 500,000 500,000
Sub Total Belanja Alat (C) 40,857,718 40,883,000

D PERALATAN

a. PENGADAAN PERALATAN
1 Cangkul 4.00 4.00 Bh 75,000 300,000 300,000
2 Singkup 2.00 2.00 Bh 80,000 160,000 160,000
3 Ember Cor 8.00 8.00 Bh 10,000 80,000 80,000
4 Pengki 4.00 4.00 Bh 14,500 58,000 58,000
5 Benang 2.00 2.00 Bh 6,000 12,000 12,000
Sub Total Peralatan (D) 610,000 610,000
TOTAL BIAYA (A+B+C+D+E) 48,856,909 48,878,000

Cianjur, 27 Desember 2020


Mengetahui Dibuat Oleh :
kepala Desa Kader Teknik

.........................
REKAPITULASI RENCANA ANGGARAN BIAYA

LOKASI 0
KEGIATAN 0
VOLUME 0
T.A 0
DESA 0
KECAMATAN 0
KABUPATEN 0
PROVINSI 0

NO URAIAN PEKERJAAN VOLUM SATUAN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A BIAYA UMUM 1.00 LS 2,125,000.00 2,125,000.00

B PEKERJAAN PIPA DRAINASE 34,931,229.49

1 B.29.a Bongkar 1 m3 beton secara konvensional 1.86 M3 288,000.00 535,680.00


###

2 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m 9.30 M3 60,000.00 558,000.00


###

3 A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200 mm 62.00 M' 525,901.45 32,605,890.00

A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata


4 3.00 Bh 410,553.16 1,231,659.49
30x30 tinggi 35 cm

B PEKERJAAN RABAT BETON K-175 11,191,515.45

1 m² bekisting lantai beton biasa menggunakan papan kayu


1 15.40 m2 74,595.00 1148763
menggunakan papan kayu 3/20 cm (TP)

1 m³ beton mutu, f’c = 7,4 MPa (K100), slump (12±2) cm,


2 10.01 M3 10042752.45
w/c = 0,87

C PERALATAN 1.00 LS 610,000.00 610,000.00


###

TOTAL BIAYA (A+B+C) 48,856,908.80


###

Cianjur, 27 Desember 2020


Dibuat Oleh :
Mengetahui Kader Teknik
Kepala Desa

..........................

Mengetahui
Pendamping Desa Teknik Infrastruktur

ERIK MUSTIADI