HARGA SATUAN
NO. URAIAN SATUAN
(RP)
HARGA SATUAN
NO. URAIAN SATUAN
(RP)
HARGA SATUAN
NO. URAIAN SATUAN
(RP)
E BAHAN ATAP
1 Rangka Atap Baja Ringan (Kaso-kaso+Reng) m2 162,000.00
2 Rangka Atap Baja Ringan m2 162,000.00
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(RP)
F BAHAN PLAFOND
1 Hollow Galvanis untuk Plafond 40x40mm, t = 0,4 mm m1 10,200.00
2 Sekrup Gypsum/GRC kg 32,000.00
3 GRC 1200x2400, t= 4 mm lbr 52,000.00
4 Gypsumboard 120 x 240 t = 9 mm lbr 54,000.00
5 Semen Compound Adhesive, @20kg kg 3,200.00
6 Joint Tape @75 m roll 38,000.00
7 Metal Furing CST 300x0.5 mm m1 5,600.00
8 Tie Rod M4 m1 2,000.00
9 Shadowline t=0,4mm m1 4,500.00
H BAHAN FINISHING/PENGECATAN/LABURAN
1 Cat Dasar Jotun kg 32,000.00
2 Cat Dinding Interior Jotun Jotaplast kg 36,000.00
3 Cat Dinding Exterior Jotun Toughshield kg 48,000.00
4 Cat kayu/besi ex. Seiv kg 45,000.00
5 Coating Kayu Ultran Lasur kg 96,000.00
6 Vernis ltr 60,000.00
7 Plamir ex. Nippon Matex kg 14,200.00
8 Terpentin/Pengencer ex. ND ltr 18,000.00
9 Kwas 4" bh 18,000.00
10 Roll Cat bh 24,000.00
11 Ampelas lbr 4,000.00
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(RP)
HARGA SATUAN
NO. URAIAN SATUAN
(RP)
N MEKANIKAL,ELEKTRIKAL
1 NYM 3 x 2.5 mm2 + Conduit m' 19,600.00
2 NYM 3 x 2.5 mm2 m' 15,100.00
3 NYM 3 x 4 mm2 m' 23,250.00
4 NYY 1 x 95 mm2 m' 159,100.00
5 NYY 1 x 150 mm2 m' 245,450.00
6 NYY 3 x 4 mm2 m' 26,750.00
7 NYY 3 X 10 mm2 m' 60,400.00
8 NYY 4 x 2.5 mm2 m' 34,000.00
9 NYY 4 x 4 mm2 m' 47,450.00
10 NYY 4 x 6 mm2 m' 61,850.00
11 NYY 4 x 10 mm2 m' 88,650.00
12 NYY 4 x 16 mm2 m' 120,200.00
13 NYY 4 x 25 mm2 m' 184,900.00
14 NYY 4 x 35 mm2 m' 251,750.00
15 NYY 4 x 50 mm2 m' 334,250.00
16 NYY 4 x 70 mm2 m' 474,100.00
17 NYY 4 x 95 mm2 m' 652,900.00
18 NYY 4 x 120 mm2 m' 820,450.00
19 NYY 4 x 150 mm2 m' 1,009,450.00
20 NYY 4 x 185 mm2 m' 1,259,050.00
21 NYY 4 x 240 mm2 m' 1,657,950.00
22 NYFGbY 3 x 10 mm2 m' 70,150.00
23 NYFGbY 4 x 6 mm2 m' 61,850.00
24 N2XSEFGby 3x185 mm2 m' 1,683,500.00
25 N2XSY 1X95 mm2 m' 242,200.00
26 BC 2 x 35 mm2 m' 62,850.00
27 Kabel Tray U W200xH100 m' 215,400.00
28 Kabel Tray U W250xH100 m' 242,250.00
29 Kabel Tray U W300xH100 m' 269,100.00
30 Inside Riser Tray W200xH100 m' 285,000.00
31 Inside Riser Tray W250xH100 m' 320,000.00
32 Inside Riser Tray W300xH100 m' 347,000.00
33 Outside Riser Tray W200xH100 m' 235,000.00
34 Outside Riser Tray W250xH100 m' 248,000.00
35 Outside Riser Tray W300xH100 m' 302,000.00
36 CrossTray W200xH100 m' 492,000.00
37 CrossTray W250xH100 m' 524,000.00
38 CrossTray W300xH100 m' 578,000.00
39 Pas Titi Instalasi Lampu NYM 3x2,5 mm2+ PVC Conduit dia 20 mm ttk 170,000.00
40 Pas Titi Instalasi Stop Kon+ PVC Conduit dia. 20 mm ttk 312,000.00
41 Inside Riser Tray W300xH100 bh 344,000.00
42 Pas. Lampu Fitting Roset E27 + Bohlam LED 12 Watt bh 54,000.00
43 Pas. Lampu Tl-Balk 1x36 Watt bh 82,000.00
44 Pas. Lampu LED Baret 20 Watt bh 215,000.00
45 Pas. Lampu Exit 8 Watt bh 174,000.00
46 Kabel Ladder W200xH100 bh 427,000.00
47 Kabel Ladder W300xH100 bh 446,000.00
48 Pas. Saklar Seri bh 24,000.00
49 Pas. Saklar Tunggal bh 16,000.00
50 Stop Kontak 16 A bh 28,000.00
51 Penangkal Petir Elektrostatis bh 15,250,000.00
52 Arester Lightning protection radius 50 meter bh 6,120,000.00
53 Grounding System max. 2 ohm bh 3,150,000.00
54 Genset 1x200 kVA set 415,000,000.00
55 Panel Kontrol Generator set 88,000,000.00
56 Tanki Solar 1000 liter set 12,500,000.00
57 Transformer Type Oil Imersed 630 kVA set 88,000,000.00
58 Panel Utama Tegangan Menengah (PUTM) set 67,000,000.00
59 Panel Utama Tegangan Rendah (PUTR) set 96,000,000.00
60 Panel Capasitor Bank 10x15 kVAR set 86,000,000.00
61 Copper Rod, kabel BC, clamp rod, Bar CU, Bak kontrol 300x300x300mm set 1,750,000.00
62 Down Conduktor 1 X 7 0mm2 + accessories set 80,000.00
63 Tiang pipa penangkal petir set 70,000.00
64 bak control set 350,000.00
65 PP Hunian Lt. 5-9 set 17,500,000.00
66 P kWh-Meter Kamar Hunian + Box MCB set 4,200,000.00
67 PP Service Lt. 5-9 set 6,400,000.00
68 PP Pompa Booster set 4,700,000.00
69 PP Pompa Presurized fan set 5,400,000.00
70 PP Lift Penumpang 1 set 6,800,000.00
71 PP Lift Barang set 7,400,000.00
72 Panel ATS 500 KVA unit 112,000,000.00
MATV
1 LNB bh 520,000.00
2 PRE AMP bh 460,000.00
3 Power Divider bh 4,850,000.00
4 Demodulator bh 1,150,000.00
5 Modulator bh 480,000.00
6 Active Combiner bh 815,000.00
7 Coaxial 75 ohm m 15,000.00
8 Termination & supporting material lot 492,000.00
9 Splitter 4 way bh 110,000.00
10 Terminal Box Splitter TV bh 245,000.00
11 TV outlet bh 45,000.00
12 Instalasi TV outlet ttk 210,000.00
CCTV
1 DVR bh 3,000,000.00
2 Battery & Charger 4 jam bh 1,965,000.00
3 Dome pan tilt Camera bh 3,550,000.00
4 Stop Kontak 1 fasa bh 48,000.00
5 kabel RG11 + Conduit HI dia 25 mm2 Instalasi camera CCTV ttk 380,000.00
6 NYM 3x2.5 + Conduit HI dia 25 mm2 Instalasi stop kontak 1 fasa ttk 520,000.00
TATA SUARA
1 Power Amplifier bh 2,700,000.00
2 Mixer bh 3,100,000.00
3 Mic bh 1,600,000.00
4 Rak sound system bh 1,800,000.00
5 Terminal box sound system (TBSS) bh 260,000.00
6 NYMHY 3x2.5 mm2 + Conduit dia. 20 mm m 15,100.00
7 Wall Speaker 10 Watt bh 540,000.00
8 JB-SS bh 620,000.00
9 Steel box Speaker 6 watt bh 115,000.00
10 NYMHY 2x1.5 mm2 + Conduit dia. 20 mm2 Instalasi kabel speaker ttk 64,000.00
11 Equalizer bh 3,400,000.00
FIRE ALARM
1 MCFA. Kapasitas 20 Zone bh 15,400,000.00
2 Rectifier bh 450,000.00
3 Power surge arrester bh 2,700,000.00
4 Battery & Charger 4 jam bh 1,500,000.00
5 Grounding untuk MCFA dan Surge Arrester (R<0.5 Ohm) lot 500,000.00
6 TB-FA bh 285,000.00
7 Smoke Detector bh 345,000.00
8 Rate of rise detector bh 85,000.00
9 Manual Push button bh 140,000.00
10 Indikator Lamp bh 43,000.00
11 Bell alarm bh 180,000.00
12 End of line resistor bh 42,000.00
13 Instalasi peralatan Alarm NYA 2x1.5 mm2 di Conduit dia.20 mm
14 - Instalasi Rate of rise detector ttk 82,000.00
15 - Instalasi Smoke detector ttk 114,000.00
16 - Instalasi Manual Push button ttk 140,000.00
17 - Instalasi Indikator Lamp ttk 140,000.00
18 - Instalasi Bell alarm ttk 140,000.00
19 - Instalasi End of line resistor ttk 140,000.00
Ventilasi
1 Exhaust fan 840 cmh unit 1,830,000.00
2 Exhaust fan 1080 cmh unit 2,584,000.00
3 AC 1 PK unit 4,750,000.00
4 AC 2 PK unit 8,620,000.00
Pipa Galvanis
1 -Dia. 2-1/2" m 120,000.00
2 -Dia. 2'' m 86,000.00
3 -Dia. 3/4" m 32,000.00
Pipa PVC
1 -Dia. 4" m 74,000.00
2 -Dia. 3" m 52,000.00
3 -Dia. 2'' m 24,000.00
4 -Dia. 1" m 12,000.00
5 -Dia. 3/4" m 9,000.00
Header
1 -Dia. 4" m 210,000.00
2 -Dia. 3" m 150,000.00
Gate Valve
1 -Dia. 2-1/2" bh 940,000.00
Check Valve
1 -Dia. 2-1/2" bh 3,100,000.00
Flexsible Joint
1 -Dia. 2-1/2" bh 500,000.00
Strainer
1 -Dia. 2-1/2" bh 750,000.00
Foot Valve
1 -Dia. 3" bh 1,050,000.00
Float Valve
1 -Dia. 2'' bh 700,000.00
2 Meter Air bh 120,000.00
PLUMBING HYDRANT
1 Pompa Diesel Hydrant unit 348,600,000.00
2 Pompa Elektrik Hydrant unit 289,200,000.00
3 Pompa Jockey Hydrant unit 26,000,000.00
4 Pipa BSH 40
5 -Dia. 8" m 350,000.00
6 -Dia. 6" m 243,000.00
7 -Dia. 4" m 128,000.00
8 -Dia. 3" m 96,000.00
9 -Dia. 2-1/2" m 75,000.00
10 -Dia. 11/2" m 31,000.00
11 -Dia. 1" m 21,000.00
12 Outdoor Hydrant Box set 4,600,000.00
13 Pillar Hydrant set 3,200,000.00
14 Siamese connection set 4,320,000.00
15 Indoor Hydrant Box set 6,871,000.00
16 Sprinkler bh 28,000.00
17 Fire Extinguisher / APAR 3,5 kg bh 375,000.00
18 Fire Extinguisher / APAR 25 kg bh 3,120,000.00
PEKERJAAN LIFT
Pengadaan dan pemasangan Lift penumpang set 1,642,000,000.00
Kapasitas : 1150 Kg
Kecepatan : 105
Tipe : Traksi
Home Engine/ Frame Engine (included)
ARD bh 41,000,000.00
Pengadaan dan pemasangan Lift Barang set 1,575,000,000.00
Kapasitas : 1000 Kg
Kecepatan : 90
Tipe : Traksi
Home Engine/ Frame Engine (included)
ARD bh 41,000,000.00
Pengadaan dan pemasangan Lift Barang Untuk Proyek selama 5 bln set 117,000,000.00
Kapasitas : 1000 Kg
Kecepatan : 90
Tipe : Traksi
Home Engine/ Frame Engine (included)