SCOPE OF WORK
PEMBANGUNAN JALAN BETON GUDANG SLAB AREA PPC
HPSOE PTKS
NO DESKRIPSI PEKERJAAN SPESIFIKASI UNIT JUMLAH HARGA SATUAN HARGA
IDR IDR
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bowplank Theodolit, Kaso 5/7 + Papan 2/20 m ( 870,00)
2 Pembersihan Area, Clearing & Grubbing Buldozer Ls ( 1,00)
3 Direksi Keet, Container 20', Kondisi 80% Sewa Pakai, Kondisi 80% UM ( 4,00)
Mobilisasi dan Demobilisasi Alat, tenaga kerja &
4 Umum Ls ( 1,00)
material
V PEKERJAN AKHIR
1 Testing beton Curing time: 7, 14 & 28 (1 set 3 sample) sets ( 10,00)
2 Test CBR Standard titik ( 10,00)
3 Finishing & perapihan seluruh pekerjaan Standard Ls ( 1,00)
4 As-built drawing and documentation Standard/See bestek Ls ( 1,00)
ROUNDED (IDR) ( -)