HARGA STANDAR KEGIATAN PEKERJAAN

PEMERINTAH KABUPATEN KUTAI TIMUR


TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8

I Ballast

1 Ballast Philips - TL 18 Watt buah 58,700 61,200 62,500 70,200

2 Ballast Philips - TL 36 Watt buah 58,700 61,200 62,500 70,200

II Baterry

Panasonic 9V /
1 Baterry pcs 20,400 21,700 21,700 24,200
6F22NT / 1S

2 Baterry Panasonic AA pcs 6,400 6,400 6,400 7,700

3 Baterry Panasonic AAA pcs 14,000 14,000 15,300 16,600

4 Baterry Panasonic Alkaline AA2 pcs 26,800 28,100 28,100 31,900

Panasonic Alkaline
5 Baterry pcs 26,800 28,100 28,100 31,900
AAA2
Panasonic D UM-
6 Baterry pcs 21,700 23,000 23,000 25,500
1U/2S

7 Baterry ABC Type R6, kecil buah 7,700 7,700 7,700 8,900

ABC Type R14,


8 Baterry buah 12,800 12,800 14,000 15,300
sedang

9 Baterry ABC Type R20, besar buah 14,000 14,000 15,300 16,600

Baterai Alkaline AA - 4
10 Baterry Pcs 11,500 11,500 12,800 14,000
Pcs
Baterai Alkaline 9V
11 Baterry buah 11,500 11,500 12,800 14,000
6LR61

III Fuse Box

1 Fuse Box 1 Grup buah 38,300 39,500 40,800 45,900

2 Fuse Box 2 Grup buah 71,400 75,300 76,500 84,200

IV Kabel

Kabel NYA, Standar 1 x 1,5 mm2 (@ 100


1 roll 331,600 347,000 353,300 392,900
SNI.04-02698, SPLN 42.1 meter)
Kabel NYA, Standar 1 x 2,5 mm2 (@ 100
2 roll 497,500 520,400 529,400 589,300
SNI.04-02698, SPLN 42.1 meter)
Kabel NYA, Standar 1 x 4 mm2 (@ 100
3 roll 969,400 1,012,800 1,031,900 1,149,300
SNI.04-02698, SPLN 42.1 meter)
Kabel NYA, Standar 1 x 6 mm2 (@ 100
4 roll 1,454,100 1,519,200 1,548,500 1,723,300
SNI.04-02698, SPLN 42.1 meter)

Halaman_235
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
Kabel NYA, Standar 1 x 10 mm2 (@ 100
5 roll 1,862,300 1,946,500 1,983,500 2,206,700
SNI.04-02698, SPLN 42.1 meter)
Kabel NYM, Standar 2 X 1,5 mm2 (@ 100
6 roll 8,214,600 8,584,500 8,749,100 9,733,800
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 2 X 2,5 mm2 (@ 100
7 roll 1,594,500 1,665,900 1,697,800 1,889,100
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 3 X 1,5 mm2 (@ 50
8 roll 1,505,200 1,572,800 1,603,400 1,783,200
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 3 X 2,5 mm2 (@ 50
9 roll 2,155,700 2,252,600 2,296,000 2,554,900
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 3 X 4 mm2 (@ 50
10 roll 2,806,200 2,932,500 2,988,600 3,325,400
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 4 X 2,5 mm2 (@ 50
11 roll 2,155,700 2,252,600 2,296,000 2,554,900
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 4 X 4 mm2 (@ 50
12 roll 2,678,700 2,799,900 2,853,400 3,174,900
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 4 X 6 mm2 (@ 50
13 roll 3,099,600 3,238,600 3,301,100 3,673,600
SNI.04-02698, SPLN 42.2 meter)
Kabel NYM, Standar 4 X 10 mm2 (@ 50
14 roll 3,660,900 3,825,400 3,899,400 4,338,200
SNI.04-02698, SPLN 42.2 meter)
Kabel NYY, Standar 2 X 1,5 mm2 (@ 50
15 roll 816,400 853,300 869,900 966,900
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 2 X 2,5 mm2 (@ 50
16 roll 1,103,400 1,153,100 1,174,800 1,307,400
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 3 X 1,5 mm2 (@ 50
17 roll 982,200 1,026,800 1,046,000 1,163,300
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 3 X 2,5 mm2 (@ 50
18 roll 1,415,900 1,479,600 1,507,700 1,677,400
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 3 X 4 mm2 (@ 50
19 roll 1,722,000 1,799,800 1,834,300 2,040,900
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 3 X 6 mm2 (@ 50
20 roll 2,155,700 2,252,600 2,296,000 2,554,900
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 42.5 mm2 (@ 50
21 roll 91,800 95,700 98,200 108,400
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar
22 4 x 35 mm Meter 216,800 227,000 230,900 256,400
SNI.04-02701, SPLN 43.1
Kabel NYY, Standar 44 mm2 (@ 50
23 roll 140,300 146,700 149,200 165,800
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 46 mm2 (@ 50
24 roll 178,600 186,200 190,100 211,700
SNI.04-02701, SPLN 43.1 meter)
Kabel NYY, Standar 410 mm2 (@ 50
25 roll 306,100 320,200 326,500 362,300
SNI.04-02701, SPLN 43.1 meter)

26 Kabel AAAC 70 mm (A3C) mtr 12,800 12,800 14,000 15,300

27 Kabel AAACS 70 mm (A3CS) mtr 19,100 20,400 20,400 23,000

28 Kabel AAAC 100 mm (A3C) mtr 21,700 23,000 23,000 25,500

29 Kabel AAACS 100 mm (A3CS) mtr 31,900 33,200 34,400 38,300

3 x 50 mm + 1 x 25
30 Kabel Twisted mtr 25,500 26,800 26,800 30,600
mm

Halaman_236
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
3 x 70 mm + 1 x 25
31 Kabel Twisted mtr 26,800 28,100 28,100 31,900
mm

V Kapasitor

1 Kapasitor 22uF 250 Volt buah 34,400 35,700 37,000 40,800

VI Lampu

1 Lampu Hemat Listrik Philips 5 Watt buah 34,400 35,700 37,000 40,800

Philips, Essential 8
2 Lampu Hemat Listrik buah 45,900 48,500 48,500 54,800
watt
Philips, Esential 11
3 Lampu Hemat Listrik buah 48,500 51,000 51,000 57,400
watt
Philips, Essential 14
4 Lampu Hemat Listrik buah 58,700 61,200 62,500 70,200
watt
Philips, Essential 18
5 Lampu Hemat Listrik buah 61,200 63,800 65,100 72,700
watt
Philips, Essential 23
6 Lampu Hemat Listrik buah 70,200 72,700 75,300 82,900
watt

7 Lampu Hemat Listrik Philips, Genie 5 watt buah 47,200 49,700 49,700 56,100

8 Lampu Hemat Listrik Philips, Genie 8 watt buah 51,000 53,600 54,800 60,000

9 Lampu Hemat Listrik Philips, Genie 11 watt buah 53,600 56,100 57,400 63,800

10 Lampu Hemat Listrik Philips, Genie 18 watt buah 58,700 61,200 62,500 70,200

11 Lampu Hemat Listrik Tornado 5 Watt buah 58,700 61,200 62,500 70,200

12 Lampu Hemat Listrik Tornado 8 Watt buah 58,700 61,200 62,500 70,200

Philips, Tornado 12
13 Lampu Hemat Listrik buah 62,500 65,100 66,300 74,000
watt
Philips, Tornado 15
14 Lampu Hemat Listrik buah 67,600 70,200 71,400 80,400
watt
Philips, Tornado 20
15 Lampu Hemat Listrik buah 70,200 72,700 75,300 82,900
watt

16 Lampu TL Bundar 20 Watt buah 44,600 47,200 47,200 52,300

17 Lampu Mercury 80 Watt/22 buah 242,400 253,800 257,700 287,000

TL-D 10w/54/Cool
18 Lampu TL buah 11,500 11,500 12,800 14,000
Daylight
TL-D 18w/54/Cool
19 Lampu TL buah 17,900 19,100 19,100 21,700
Daylight
TL-D 36w/54/Cool
20 Lampu TL buah 20,400 21,700 21,700 24,200
Daylight

Halaman_237
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
TL-D 18w Brightboost
21 Lampu TL buah 34,400 35,700 37,000 40,800
83-84-86
TL-D 36w Brightboost
22 Lampu TL buah 39,500 40,800 42,100 47,200
83-84-86

23 Lampu TL TL-Ring 22w/CD buah 48,500 51,000 51,000 57,400

24 Lampu TL TL-Ring 32w/CD buah 53,600 56,100 57,400 63,800

VII MCB

1 MCB Broco 4a ecer buah 43,400 45,900 45,900 51,000

2 MCB Broco 6a ecer buah 42,100 43,400 44,600 49,700

3 MCB Broco 10a ecer buah 42,100 43,400 44,600 49,700

4 MCB Broco 16a ecer buah 42,100 43,400 44,600 49,700

MCB 32 A bh 43,500 47,850 56,550 73,950

VIII NSFB

NH Fuse 50 A bb 37,500 41,250 48,750 63,750

NFB 100 A bh 3,135,000 3,448,500 4,075,500 5,329,500

IX Klem Kabel

Imundex no.4 (Isi 100


1 Klem Kabel pak 11,500 11,500 12,800 14,000
pcs/kotak + Paku)
Imundex no.5 (Isi 100
2 Klem Kabel pak 11,500 11,500 12,800 14,000
pcs/kotak + Paku)
Imundex no.6 (Isi 100
3 Klem Kabel pak 12,800 12,800 14,000 15,300
pcs/kotak + Paku)
Imundex no.7 (Isi 100
4 Klem Kabel pak 12,800 12,800 14,000 15,300
pcs/kotak + Paku)
Imundex no.8 (Isi 100
5 Klem Kabel pak 15,300 16,600 16,600 17,900
pcs/kotak + Paku)
Imundex no.9 (Isi 100
6 Klem Kabel pak 15,300 16,600 16,600 17,900
pcs/kotak + Paku)
Imundex no.10 (Isi
7 Klem Kabel pak 17,900 19,100 19,100 21,700
100 pcs/kotak + Paku)
Imundex no.12 (Isi
8 Klem Kabel pak 24,200 25,500 25,500 29,300
100 pcs/kotak + Paku)
Imundex no.14 (Isi
9 Klem Kabel pak 29,300 30,600 30,600 34,400
100 pcs/kotak + Paku)

Halaman_238
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
Imundex no.17 (Isi
10 Klem Kabel pak 43,400 45,900 45,900 51,000
100 pcs/kotak + Paku)
Imundex no.19 (Isi
11 Klem Kabel pak 61,200 63,800 65,100 72,700
100 pcs/kotak + Paku)
Imundex no.22 (Isi
12 Klem Kabel pak 71,400 75,300 76,500 84,200
100 pcs/kotak + Paku)

X Saklar

Saklar Engkel, Single


1 Saklar pak 28,100 29,300 29,300 33,200
Switch, 250V, Cream
Saklar Seri, Double
2 Saklar pak 30,600 31,900 33,200 35,700
Switch, 250V, Cream
Saklar Engkel Outbow
3 Saklar dengan Stop Kontak, pak 39,500 40,800 42,100 47,200
250V, Cream
Saklar Engkel dengan
4 Saklar Stop Kontak, Single pak 39,500 40,800 42,100 47,200
Switch, 250V, Cream
Saklar Engkel, Single
5 Saklar pak 16,600 17,900 17,900 19,100
Switch, 250V, Black
Saklar Seri, Double
6 Saklar pak 21,700 23,000 23,000 25,500
Switch, 250V, Black
Saklar Engkel, Single
7 Saklar pak 23,000 24,200 24,200 26,800
Switch, 250V, Cream
Saklar Seri, Double
8 Saklar pak 28,100 29,300 29,300 33,200
Switch, 250V, Cream
Saklar Triple, Triple
9 Saklar pak 39,500 40,800 42,100 47,200
Switch, 250V, Cream
Saklar Engkel, Single
10 Saklar pak 23,000 24,200 24,200 26,800
Switch, 250V, Cream
Saklar Seri, Double
11 Saklar pak 28,100 29,300 29,300 33,200
Switch, 250V, Cream
Saklar AC Set Komplit
12 Saklar pak 144,100 150,500 153,100 170,900
Outbow, Cream

XI Skring Kas

1 Skring Kas 5 Group Biasa unit 68,900 71,400 74,000 81,600

XII Stater Neon

1 Stater Neon Philips buah 12,800 12,800 14,000 15,300

2 Stater Neon Biasa buah 7,700 7,700 7,700 8,900

Halaman_239
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
XIII Terminal

Stop Kontak Arde


1 Terminal Kuningan buah 26,800 28,100 28,100 31,900
Uticon 4 Lubang
Stop Kontak Arde
2 Terminal Kuningan buah 20,400 21,700 21,700 24,200
Uticon 3 Lubang
Stop Kontak Arde
3 Terminal Kuningan buah 15,300 16,600 16,600 17,900
Uticon 2 Lubang
Stop Kontak Arde
4 Terminal Kuningan buah 11,500 11,500 12,800 14,000
Uticon 1 Lubang
Stop Kontak Uticon 4
5 Terminal Kuningan Lubang+4Saklar+Kab buah 118,600 123,700 126,300 140,300
el

XIV Steker

1 Steker T Steker Arde Broco buah 28,100 29,300 29,300 33,200

XV Solder

1 Solder Sucker Beasr buah 58,700 61,200 62,500 70,200

2 Solder Tembak Kecil buah 165,800 173,500 176,000 196,400

XVI Rechargeable battery

Energizer,
1 Rechargeable battery Rechargeable battery, pcs 178,600 186,200 190,100 211,700
Alkaline, 9 Volt 1 pcs
Sanyo, Rechargeable
batteries, NiMH, AAA,
2 Rechargeable battery pcs 118,600 123,700 126,300 140,300
800mAh, 1.2 Volt, 2
pcs
Sanyo, Rechargeable
batteries, NiMH, AA,
3 Rechargeable battery pcs 140,300 146,700 149,200 165,800
2000mAh, 1.2 Volt, 2
pcs

Powerex, Travel
Charger 204W for 4
4 Rechargeable battery pcs AA rechargeable pcs 714,300 746,200 760,200 847,000
batteries + Battery AA
4 pcs, NiMH, 2700mAh

XVII Charger AKI

1 Charger AKI Coeppro 10 AHR buah 752,600 787,000 801,100 891,600

2 Charger AKI Coeppro 15 AHR buah 880,100 919,700 937,500 1,043,400

Halaman_240
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
3 Charger AKI Coeppro 20 AHR buah 1,007,700 1,053,600 1,072,700 1,193,900

XVIII Tiang Listrik

Tiang Beton 9 Meter


1 9 Meter mtr 8,010,500 8,371,500 8,530,900 9,492,700
Standar PLN
Tiang Beton 13 Meter
2 13 Meter mtr 13,801,600 14,422,800 14,698,300 16,355,200
Standar PLN
Tiang Beton 11 Meter
3 11 Meter Pc 11,696,900 12,223,700 12,457,100 13,860,200
Standar PLN
Tiang Besi 9 Meter
4 9 Meter mtr 6,301,300 6,584,400 6,710,700 7,467,100
Standar PLN
Tiang Besi 11 Meter
5 11 Meter Pc 6,964,600 7,278,300 7,417,400 8,252,900
Standar PLN
Tiang Lampu Jalan Besi
6 Galvanis Single Arm 13 13 Meter mtr 5,357,400 5,598,400 5,705,600 6,348,500
Meter
Tiang Lampu Jalan Besi
7 Galvanis Single Arm 9 9 Meter Pc 6,173,700 6,451,800 6,575,500 7,315,300
Meter
Tiang Lampu Jalan Besi
8 Galvanis Single Arm 11 11 Meter Pc 6,046,200 6,317,800 6,439,000 7,164,800
Meter
Tiang Lampu Jalan Besi
9 Galvanis Double Arm 9 9 Meter Pc 5,778,300 6,038,500 6,153,300 6,847,200
Meter
Tiang Lampu Jalan Besi
10 Galvanis Double Arm 11 11 Meter Pc 7,232,400 7,557,700 7,703,100 8,570,500
Meter

XIX Travo Distribusi

1 Travo Distribusi 3 Phase 50 kVA buah 75,092,200 78,471,200 79,973,800 88,984,300

2 Travo Distribusi 3 Phase 100 kVA buah 95,424,600 99,718,200 101,627,700 113,078,400

3 Travo Distribusi 3 Phase 150 kVA buah 121,701,200 127,177,200 129,612,200 144,216,100

4 Travo Distribusi 3 Phase 200 kVA buah 139,826,900 146,119,200 148,915,300 165,695,200

XX Solar Sel

Solar Sel Home System


1 set 9,196,800 9,610,100 9,795,000 10,898,400
(SHS) 50 Wp
Solar Sel Home System
2 set 14,720,000 15,382,000 15,676,600 17,443,300
(SHS) 100 Wp
Solar Sel Home System
3 set 17,602,700 18,394,900 18,746,900 20,859,200
(SHS) 200 Wp

Halaman_241
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
Lampu Sehen (Super
4 set 3,150,600 3,292,200 3,356,000 3,733,600
Hemat) Tenaga Surya
Lampu Jalan Tenaga
5 Surya (Tanpa Tiang set 15,638,400 16,342,500 16,655,000 18,531,300
Lampu)

XXI Kabel Twisted

1 Kabel Twisted 3 x 50 mtr 84,200 88,000 89,300 99,500

2 Kabel Twisted 3 x 25 mtr 49,700 52,300 53,600 58,700

XXII Isolator

1 Isolator Tampu 20 KV (CA 1-1) buah 867,400 906,900 923,500 1,028,100

2 Isolator Tarik 20 KV (CA 3) buah 1,237,300 1,293,400 1,317,700 1,465,600

XXIII Liannya

1 Cross Arm 1800 - uNP10 Pc 165,800 173,500 176,000 196,400

2 Arm Tie Type 750 Pipe 3/4 " Pc 216,800 227,000 230,900 256,400

3 Ball Clevis Pc 267,900 279,300 285,700 317,600

HV Band Strap / Cross


4 Set 165,800 173,500 176,000 196,400
Arm Clevis / Susp VEE
Socket Eye / Straight
5 Pc 267,900 279,300 285,700 317,600
Clevis Eye
Dead End Clamp (Strain
6 Set 216,800 227,000 230,900 256,400
clamp)

7 Cut Out Switch 22 KV-100A + Bracket Set 2,627,700 2,746,300 2,798,600 3,113,600

8 Fuse Link 100 A Set 178,600 186,200 190,100 211,700

9 Suspension Clamp Set 433,700 452,800 461,800 514,100

10 Strain Clamp Set 216,800 227,000 230,900 256,400

Tombak Penangkal Petir


11 Set 5,472,200 5,718,300 5,828,000 6,484,900
Three Angle

12 Fiting Keramik 125 watt bh 10,600 11,660 13,780 18,020

13 Fiting Keramik 250 watt bh 3,300 3,630 4,290 5,610

14 Kabel NYM 3 x 2.5 mm2 m 10,650 11,715 13,845 18,105

Halaman_242
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
15 Saklar Tunggal bh 14,500 15,950 18,850 24,650

16 Pipa Conduit PVC klas D m 3,000 3,300 3,900 5,100

17 Rumah Lampu + Lampu TL 2 x 36 watt ( grill ) bh 410,100 451,110 533,130 697,170

18 Lampu Baret 40 watt bh 529,560 582,516 688,428 900,252

19 Lampu Down Light isi PL 2 x 9 watt bh 106,080 116,688 137,904 180,336

20 Lampu PL 2 x 9 watt bh 74,256 81,682 96,533 126,235

21 Stop Kontak 25A, 3 phase Brocco bh 187,500 206,250 243,750 318,750

22 Saklar Hotel bh 33,450 36,795 43,485 56,865

23 Saklar Tunggal Brocco bh 15,750 17,325 20,475 26,775

24 Saklar Double Brocco bh 21,750 23,925 28,275 36,975

25 PHB Induk uk. 80 x 60 x 40 bh 2,062,500 2,268,750 2,681,250 3,506,250

Kabel Scunt (sepatu


26 Cu 25, 35 mm bh 2,550 2,805 3,315 4,335
kabel)
Kabel Scunt (sepatu
27 Cu 50 mm bh 4,200 4,620 5,460 7,140
kabel)

28 Holder Fuse bh 24,750 27,225 32,175 42,075

29 Saklar bh 32,250 35,475 41,925 54,825

30 Kabel 10 m m 164,850 181,335 214,305 280,245

31 Lampu Indikator set 348,075 382,883 452,498 591,728

32 Plat Tembaga 0.5 m set 140,250 154,275 182,325 238,425

33 Pas. Ground bh 305,250 335,775 396,825 518,925

AW C uk. Dia 1/2"


34 Pipa PVC batang 21,700 22,900 22,900 26,300
(4m)
AW C uk. Dia 3/4"
35 Pipa PVC batang 32,000 33,200 34,300 37,800
(4m)

36 Pipa PVC AW C uk. Dia 1" (4m) batang 42,300 44,600 44,600 50,300

AW C uk. Dia 1 1/2"


37 Pipa PVC batang 83,500 86,900 89,200 99,500
(4m)

38 Pipa PVC AW C uk. Dia 2" (4m) batang 96,100 100,700 101,800 114,400

AW C uk. Dia 2 1/2"


39 Pipa PVC batang 132,700 138,400 141,900 156,700
(4m)

40 Pipa PVC AW C uk. Dia 3" (4m) batang 178,500 186,500 189,900 211,600

Halaman_243
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

HARGA SATUAN BAHAN MEKANIKAL ELEKTRIKAL


(Rupiah)
HARGA SATUAN
SPESIFIKASI /
NO. JENIS BARANG SATUAN
UKURAN
ZONA 1 ZONA 2 ZONA 3 ZONA 4

1 2 3 4 5 6 7 8
41 Pipa PVC AW C uk. Dia 4" (4m) batang 297,400 311,200 316,900 352,400

42 Pipa PVC AW C uk. Dia 6" (4m) batang 689,800 720,700 734,400 818,000

Halaman_244
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN ELEKTRICAL

Jenis Pekerjaan : Memasang Instalasi Penerangan & Stop Kontak


Kuantitas Pekerjaan : 1 Tiik
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.3714 150,000 55,710 165,000 61,281 162,000 60,167 168,000 62,395
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1065 160,000 17,040 176,000 18,744 173,000 18,425 179,000 19,064
Pembantu instalator OH 0.2306 150,000 34,590 165,000 38,049 162,000 37,357 168,000 38,741

II BAHAN
Fiting keramik 125 watt Bh ##### 10,600 290 11,660 319 14,310 392 18,020 494
NYM 3 x 2.5 mm2 m 10.000 10,650 106,500 11,715 117,150 14,378 143,775 18,105 181,050
Klem Bh 1.0000 750 750 825 825 1,013 1,013 1,275 1,275
Saklar Bh 0.0041 14,500 59 15,950 65 19,575 80 24,650 101
Pipa Conduit PVC klas D m 5.000 3,000 15,000 3,300 16,500 4,050 20,250 5,100 25,500
Jumlah Harga Per-satuan Pekerjaan 229,940 252,934 281,458 328,619

Jenis Pekerjaan : Memasang Lampu TL 2 x 36 watt (TKO)


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.3123 150,000 46,845 165,000 51,530 162,000 50,593 168,000 52,466
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1045 160,000 16,720 176,000 18,392 173,000 18,079 179,000 18,706
Pembantu instalator OH 0.2306 150,000 34,590 165,000 38,049 162,000 37,357 168,000 38,741

II BAHAN
Rumah lampu + lampu
Bh 1 410,100 410,100 451,110 451,110 553,635 553,635 697,170 697,170
TL 2 x 36 watt ( grill )
Jumlah Harga Per-satuan Pekerjaan 508,255 559,081 659,663 807,083

Jenis Pekerjaan : Memasang Lampu Baret 40 watt


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1045 150,000 15,675 165,000 17,243 162,000 16,929 168,000 17,556
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1050 160,000 16,800 176,000 18,480 173,000 18,165 179,000 18,795
Pembantu instalator OH 0.2274 150,000 34,110 165,000 37,521 162,000 36,839 168,000 38,203

II BAHAN
Lampu baret 40 watt Bh 1 529,560 529,560 582,516 582,516 714,906 714,906 900,252 900,252
Jumlah Harga Per-satuan Pekerjaan 596,145 655,760 786,839 974,806

Halaman_245
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN ELEKTRICAL

Jenis Pekerjaan : Memasang Lampu Down Light isi PL 2 x 9 watt


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1045 150,000 15,675 165,000 17,243 162,000 16,929 168,000 17,556
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1050 160,000 16,800 176,000 18,480 173,000 18,165 179,000 18,795
Pembantu instalator OH 0.2321 150,000 34,815 165,000 38,297 162,000 37,600 168,000 38,993

II BAHAN
Lampu down light isi PL
Bh 1 106,080 106,080 116,688 116,688 143,208 143,208 180,336 180,336
2 x 9 watt
Jumlah Harga Per-satuan Pekerjaan 173,370 190,707 215,902 255,680

Jenis Pekerjaan : Memasang Lampu PL 2 x 9 watt


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1045 150,000 15,675 165,000 17,243 162,000 16,929 168,000 17,556
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1050 160,000 16,800 176,000 18,480 173,000 18,165 179,000 18,795
Pembantu instalator OH 0.2321 150,000 34,815 165,000 38,297 162,000 37,600 168,000 38,993

II BAHAN
Lampu PL 2 x 9 watt Bh 1 74,256 74,256 81,682 81,682 100,246 100,246 126,235 126,235
Jumlah Harga Per-satuan Pekerjaan 141,546 155,701 172,940 201,579

Jenis Pekerjaan : Memasang Stop kontak 3 (phase)


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1052 150,000 15,780 165,000 17,358 162,000 17,042 168,000 17,674
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1055 160,000 16,880 176,000 18,568 173,000 18,252 179,000 18,885
Pembantu instalator OH 0.2326 150,000 34,890 165,000 38,379 162,000 37,681 168,000 39,077

II BAHAN
Stop kontak 25A, 3
Bh 1 187,500 187,500 206,250 206,250 253,125 253,125 318,750 318,750
phase Brocco
Jumlah Harga Per-satuan Pekerjaan 255,050 280,555 326,100 394,385

Halaman_246
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN ELEKTRICAL

Jenis Pekerjaan : Memasang Saklar hotel Brocco


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1052 150,000 15,780 165,000 17,358 162,000 17,042 168,000 17,674
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1055 160,000 16,880 176,000 18,568 173,000 18,252 179,000 18,885
Pembantu instalator OH 0.2326 150,000 34,890 165,000 38,379 162,000 37,681 168,000 39,077

II BAHAN
Saklar hotel Bh 1 33,450 33,450 36,795 36,795 45,158 45,158 56,865 56,865
Jumlah Harga Per-satuan Pekerjaan 101,000 111,100 118,133 132,500

Jenis Pekerjaan : Memasang Saklar tunggal


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1052 150,000 15,780 165,000 17,358 162,000 17,042 168,000 17,674
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1055 160,000 16,880 176,000 18,568 173,000 18,252 179,000 18,885
Pembantu instalator OH 0.2336 150,000 35,040 165,000 38,544 162,000 37,843 168,000 39,245

II BAHAN
Saklar tunggal Brocco Bh 1 15,750 15,750 17,325 17,325 21,263 21,263 26,775 26,775
Jumlah Harga Per-satuan Pekerjaan 83,450 91,795 94,400 102,578

Jenis Pekerjaan : Memasang Saklar dobel


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.1052 150,000 15,780 165,000 17,358 162,000 17,042 168,000 17,674
Mandor OH 175,000 - 193,000 - 189,000 - 196,000 -
Tukang Listrik OH 0.1055 160,000 16,880 176,000 18,568 173,000 18,252 179,000 18,885
Pembantu instalator OH 0.2336 150,000 35,040 165,000 38,544 162,000 37,843 168,000 39,245

II BAHAN
Saklar double Brocco Bh 1 21,750 21,750 23,925 23,925 29,363 29,363 36,975 36,975
Jumlah Harga Per-satuan Pekerjaan 89,450 98,395 102,500 112,778

Halaman_247
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN ELEKTRICAL

Jenis Pekerjaan : Memasang Box Panel pembagi


Kuantitas Pekerjaan : 1 Buah
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH ##### 150,000 75,000 165,000 82,500 162,000 81,000 168,000 84,000
Mandor OH 0.0500 175,000 8,750 193,000 9,650 189,000 9,450 196,000 9,800
Tukang Listrik OH 0.0500 160,000 8,000 176,000 8,800 173,000 8,650 179,000 8,950

II BAHAN
PHB induk uk. 80 x 60 x
bh 1 2,062,500 2,062,500 2,268,750 2,268,750 2,784,375 2,784,375 3,506,250 3,506,250
40
NFB 100 A bh 1 3,135,000 3,135,000 3,448,500 3,448,500 4,232,250 4,232,250 5,329,500 5,329,500
Kabel scunt (sepatu
bh 4 2,550 10,200 2,805 11,220 3,443 13,770 4,335 17,340
kabel) Cu 25, 35 mm
Kabel scunt (sepatu
bh 8 4,200 33,600 4,620 36,960 5,670 45,360 7,140 57,120
kabel) Cu 50 mm
MCB 32 A bh 1 43,500 43,500 47,850 47,850 58,725 58,725 73,950 73,950
NH Fuse 50 A bb 6 37,500 225,000 41,250 247,500 50,625 303,750 63,750 382,500
Holder fuse bh 6 24,750 148,500 27,225 163,350 33,413 200,475 42,075 252,450
Fiting keramik 250 watt bh 1 3,300 3,300 3,630 3,630 4,455 4,455 5,610 5,610
Saklar bh 1 32,250 32,250 35,475 35,475 43,538 43,538 54,825 54,825
Kabel 10 m m 4 164,850 659,400 181,335 725,340 222,548 890,190 280,245 1,120,980
Lampu indikator set 1 348,075 348,075 382,883 382,883 469,901 469,901 591,728 591,728
Plat tembaga 0.5 m set 1 140,250 140,250 154,275 154,275 189,338 189,338 238,425 238,425
Pas. Ground bh 1 305,250 305,250 335,775 335,775 412,088 412,088 518,925 518,925
Jumlah Harga Per-satuan Pekerjaan 7,238,575 7,962,458 9,747,314 12,252,353

Halaman_248
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN MEKANIKAL

PEKERJAAN INSTALSI AIR BERSIH & PEMBUANGAN

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 1/2 "
Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.036 150,000 5,400 165,000 5,940 162,000 5,832 168,000 6,048
Mandor OH 0.0018 175,000 315 193,000 347 189,000 340 196,000 353
Tukang pasang pipa OH 0.060 160,000 9,600 176,000 10,560 173,000 10,380 179,000 10,740
Kepala tukang pipa OH 0.006 165,000 990 182,000 1,092 178,000 1,068 185,000 1,110

II BAHAN
Pipa PVC m 1.2000 5,425 6,510 5,725 6,870 5,725 6,870 6,575 7,890
Perlengkapan 35 % harga
- 0.3500 2,279 - 2,405 - 2,405 - 2,762
pipa
Jumlah Harga Per-satuan Pekerjaan 25,094 27,214 26,895 28,902

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 3/4 "
Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.036 150,000 5,400 165,000 5,940 162,000 5,832 168,000 6,048
Mandor OH 0.0018 175,000 315 193,000 347 189,000 340 196,000 353
Tukang pasang pipa OH 0.060 160,000 9,600 176,000 10,560 173,000 10,380 179,000 10,740
Kepala tukang pipa OH 0.006 165,000 990 182,000 1,092 178,000 1,068 185,000 1,110

II BAHAN
Pipa PVC m 1.2000 8,000 9,600 8,300 9,960 8,575 10,290 9,450 11,340
Perlengkapan 35 % harga
- 0.3500 3,360 - 3,486 - 3,602 - 3,969
pipa
Jumlah Harga Per-satuan Pekerjaan 29,265 31,385 31,512 33,560

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 1 "


Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.036 150,000 5,400 165,000 5,940 162,000 5,832 168,000 6,048
Mandor OH 0.0018 175,000 315 193,000 347 189,000 340 196,000 353
Tukang pasang pipa OH 0.060 160,000 9,600 176,000 10,560 173,000 10,380 179,000 10,740
Kepala tukang pipa OH 0.006 165,000 990 182,000 1,092 178,000 1,068 185,000 1,110

II BAHAN
Pipa PVC m 1.2000 10,575 12,690 11,150 13,380 11,150 13,380 12,575 15,090
Perlengkapan 35 % harga
- 0.3500 4,442 - 4,683 - 4,683 - 5,282
pipa
Jumlah Harga Per-satuan Pekerjaan 33,437 36,002 35,683 38,622

Halaman _249
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN MEKANIKAL

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 1 1/2 "
Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.036 150,000 5,400 165,000 5,940 162,000 5,832 168,000 6,048
Mandor OH 0.0018 175,000 315 193,000 347 189,000 340 196,000 353
Tukang pasang pipa OH 0.060 160,000 9,600 176,000 10,560 173,000 10,380 179,000 10,740
Kepala tukang pipa OH 0.006 165,000 990 182,000 1,092 178,000 1,068 185,000 1,110

II BAHAN
Pipa PVC m 1.2000 20,875 25,050 21,725 26,070 22,300 26,760 24,875 29,850
Perlengkapan 35 % harga
- 0.3500 8,768 - 9,125 - 9,366 - 10,448
pipa
Jumlah Harga Per-satuan Pekerjaan 50,123 53,134 53,746 58,548

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 2 "


Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.054 150,000 8,100 165,000 8,910 162,000 8,748 168,000 9,072
Mandor OH 0.0027 175,000 473 193,000 521 189,000 510 196,000 529
Tukang pasang pipa OH 0.090 160,000 14,400 176,000 15,840 173,000 15,570 179,000 16,110
Kepala tukang pipa OH 0.009 165,000 1,485 182,000 1,638 178,000 1,602 185,000 1,665

II BAHAN
Pipa PVC m 1.2000 24,025 28,830 25,175 30,210 25,450 30,540 28,600 34,320
Perlengkapan 35 % harga
- 0.3500 10,091 - 10,574 - 10,689 - 12,012
pipa
Jumlah Harga Per-satuan Pekerjaan 63,378 67,693 67,659 73,708

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 2 1/2 "
Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.054 150,000 8,100 165,000 8,910 162,000 8,748 168,000 9,072
Mandor OH 0.0027 175,000 473 193,000 521 189,000 510 196,000 529
Tukang pasang pipa OH 0.090 160,000 14,400 176,000 15,840 173,000 15,570 179,000 16,110
Kepala tukang pipa OH 0.009 165,000 1,485 182,000 1,638 178,000 1,602 185,000 1,665

II BAHAN
Pipa PVC m 1.2000 33,175 39,810 34,600 41,520 35,475 42,570 39,175 47,010
Perlengkapan 35 % harga
- 0.3500 13,934 - 14,532 - 14,900 - 16,454
pipa
Jumlah Harga Per-satuan Pekerjaan 78,201 82,961 83,900 90,840

Halaman _250
HARGA STANDAR KEGIATAN PEKERJAAN
PEMERINTAH KABUPATEN KUTAI TIMUR
TAHUN 2015

PEKERJAAN MEKANIKAL

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 3 "


Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.0810 150,000 12,150 165,000 13,365 162,000 13,122 168,000 13,608
Mandor OH 0.0041 175,000 718 193,000 791 189,000 775 196,000 804
Tukang pasang pipa OH 0.1350 160,000 21,600 176,000 23,760 173,000 23,355 179,000 24,165
Kepala tukang pipa OH 0.0135 165,000 2,228 182,000 2,457 178,000 2,403 185,000 2,498

II BAHAN
Pipa PVC m 1.2000 44,625 53,550 46,625 55,950 47,475 56,970 52,900 63,480
Perlengkapan 35 % harga
- 0.3500 18,743 - 19,583 - 19,940 - 22,218
pipa
Jumlah Harga Per-satuan Pekerjaan 108,988 115,906 116,564 126,772

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 4 "


Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.0810 150,000 12,150 165,000 13,365 162,000 13,122 168,000 13,608
Mandor OH 0.0041 175,000 718 193,000 791 189,000 775 196,000 804
Tukang pasang pipa OH 0.1350 160,000 21,600 176,000 23,760 173,000 23,355 179,000 24,165
Kepala tukang pipa OH 0.0135 165,000 2,228 182,000 2,457 178,000 2,403 185,000 2,498

II BAHAN
Pipa PVC m 1.2000 74,350 89,220 77,800 93,360 79,225 95,070 88,100 105,720
Perlengkapan 35 % harga
- 0.3500 31,227 - 32,676 - 33,275 - 37,002
pipa
Jumlah Harga Per-satuan Pekerjaan 157,142 166,409 167,999 183,796

Jenis Pekerjaan : Memasang Instalasi Pipa PVC type AW dia. 6 "


Kuantitas Pekerjaan : 1 Meter
Produksi Harian/Jam : Harian

Zone I Zone II Zone III Zone IV


No Uraian Satuan Indeks Harga Jumlah Harga Jumlah Harga Jumlah Harga Jumlah
Satuan Harga Satuan Harga Satuan Harga Satuan Harga

I UPAH
Pekerja OH 0.0810 150,000 12,150 165,000 13,365 162,000 13,122 168,000 13,608
Mandor OH 0.0041 175,000 718 193,000 791 189,000 775 196,000 804
Tukang pasang pipa OH 0.1350 160,000 21,600 176,000 23,760 173,000 23,355 179,000 24,165
Kepala tukang pipa OH 0.0135 165,000 2,228 182,000 2,457 178,000 2,403 185,000 2,498

II BAHAN
Pipa PVC m 1.2000 172,450 206,940 180,175 216,210 183,600 220,320 204,500 245,400
Perlengkapan 35 % harga
- 0.3500 72,429 - 75,674 - 77,112 - 85,890
pipa
Jumlah Harga Per-satuan Pekerjaan 316,064 332,257 337,087 372,364

Halaman _251
RESUME ANALISA TEKNIS
HARGA SATUAN PEKERJAAN MEKANIKAL & ELEKTRIKAL

NO URAIAN KOEF. SAT. HARGA SAT. JUMLAH

IL : PEK. INSTALASI PENERANGAN dan STOP KONTAK


1 Ttk - Instalasi Penerangan & Stop Kontak
Fiting keramik 125 watt 0.0274 bh 2,200 60
NYM 3 x 2.5 mm2 10 m 7,100 71,000
Klem 1 bh 500 500
Saklar 0.0041 bh 14,500 59
Pipa Conduit PVC klas D 5 m 2,000 10,000
Pekerja 0.3714 hr 33,000 12,256
Tukang listrik 0.1065 hr 55,000 5,858
Pembantu instalator 0.2306 hr 33,000 7,610
JUMLAH 107,343
DIBULATKAN 107,300
1Bh - Lampu TL 2 x 36 watt (TKO)
Rumah lampu + lampu TL 2 x 36 watt ( grill ) 1 bh 273,400 273,400
Pekerja 0.3123 hr 33,000 10,306
Tukang listrik 0.1045 hr 55,000 5,748
Pembantu instalatir 0.2326 hr 33,000 7,676
JUMLAH 297,129
DIBULATKAN 297,100
1Bh - Lampu Baret 40 watt
Lampu baret 40 watt 1 bh 353,040 353,040
Pekerja 0.1045 hr 33,000 3,449
Tukang listrik 0.105 hr 55,000 5,775
Pembantu instalatir 0.2274 hr 33,000 7,504
JUMLAH 369,768
DIBULATKAN 369,800
1Bh - Lampu Down Light isi PL 2 x 9 watt
Lampu down light isi PL 2 x 9 watt 1 bh 70,720 70,720
Pekerja 0.1045 hr 33,000 3,449
Tukang listrik 0.105 hr 55,000 5,775
Pembantu instalatir 0.2321 hr 33,000 7,659
JUMLAH 87,603
DIBULATKAN 87,600
1Bh - Lampu PL 2 x 9 watt
lampu PL 2 x 9 watt 1 bh 49,504 49,504
Pekerja 0.1045 hr 33,000 3,449
Tukang listrik 0.105 hr 55,000 5,775
Pembantu instalatir 0.2321 hr 33,000 7,659
JUMLAH 66,387
DIBULATKAN 66,400
1Bh - Stop kontak 3 (phase)
Stop kontak 25A, 3 phase Brocco 1 bh 125,000 125,000
Pekerja 0.1052 hr 33,000 3,472
Tukang listrik 0.1055 hr 55,000 5,803
Pembantu instalatir 0.2336 hr 33,000 7,709
JUMLAH 141,983
DIBULATKAN 142,000
1Bh - Saklar hotel Brocco
Saklar hotel 1 bh 22,300 22,300
Pekerja 0.1052 hr 33,000 3,472
Tukang listrik 0.1055 hr 55,000 5,803
Pembantu instalatir 0.2336 hr 33,000 7,709
JUMLAH 39,283
DIBULATKAN 39,300
1Bh - Saklar tunggal Brocco
Saklar tunggal 1 bh 10,500 10,500
Pekerja 0.1052 hr 33,000 3,472
Tukang listrik 0.1055 hr 55,000 5,803
Pembantu instalatir 0.2336 hr 33,000 7,709
JUMLAH 27,483
DIBULATKAN 27,500
1Bh - Saklar double Brocco
Saklar double 1 bh 14,500 14,500
Pekerja 0.1052 hr 33,000 3,472
Tukang listrik 0.1055 hr 55,000 5,803
Pembantu instalatir 0.2336 hr 33,000 7,709
JUMLAH 31,483
DIBULATKAN 31,500

Halaman_252
RESUME ANALISA TEKNIS
HARGA SATUAN PEKERJAAN MEKANIKAL & ELEKTRIKAL

NO URAIAN KOEF. SAT. HARGA SAT. JUMLAH

1 unit - Pasang Box Panel pembagi


PHB induk uk. 80 x 60 x 40 1 bh 1,375,000 1,375,000
NFB 100 A 1 bh 2,090,000 2,090,000
Kabel scunt (sepatu kabel) Cu 25, 35 mm 4 bh 1,700 6,800
Kabel scunt (sepatu kabel) Cu 50 mm 8 bh 2,800 22,400
MCB 32 A 1 bh 29,000 29,000
NH Fuse 50 A 6 bb 25,000 150,000
Holder fuse 6 bh 16,500 99,000
Fiting keramik 250 watt 1 bh 2,200 2,200
Saklar 1 bh 21,500 21,500
Kabel 10 m 4 m 109,900 439,600
Lampu indikator 1 set 232,050 232,050
Plat tembaga 0.5 m 1 set 93,500 93,500
Pas. Ground 1 bh 203,500 203,500
Pekerja 0.5 hr 33,000 16,500
Mandor 0.05 hr 71,500 3,575
Instalatur/ Tukang listrik 0.5 hr 55,000 27,500
JUMLAH 4,812,125
DIBULATKAN 4,812,100
IA PEK. INSTALSI AIR BERSIH & PEMBUANGAN
1 M' - Instalasi Pipa PVC type AW dia. 1/2 "
Pipa PVC 1.2 m 3,400 4,080
Perlengkapan 35 % harga pipa 0.35 - 1,190 417
Pekerja 0.036 hr 33,000 1,188
mandor 0.0018 hr 71,500 129
Tukang pasang pipa 0.06 hr 49,500 2,970
Kepala tukang pipa 0.006 hr 60,500 363
JUMLAH 9,146
DIBULATKAN 9,100
1 M' - Instalasi Pipa PVC type AW dia. 3/4 "
Pipa PVC 1.2 m 5,100 6,120
Perlengkapan 35 % harga pipa 0.35 - 1,785 625
Pekerja 0.036 hr 33,000 1,188
mandor 0.0018 hr 71,500 129
Tukang pasang pipa 0.06 hr 49,500 2,970
Kepala tukang pipa 0.006 hr 60,500 363
JUMLAH 11,394
DIBULATKAN 11,400
1 M' - Instalasi Pipa PVC type AW dia. 1 "
Pipa PVC 1.2 m 7,200 8,640
Perlengkapan 35 % harga pipa 0.35 - 2,520 882
Pekerja 0.036 hr 33,000 1,188
mandor 0.0018 hr 71,500 129
Tukang pasang pipa 0.06 hr 49,500 2,970
Kepala tukang pipa 0.006 hr 60,500 363
JUMLAH 14,172
DIBULATKAN 14,200
1 M' - Instalasi Pipa PVC type AW dia. 1 1/2 "
Pipa PVC 1.2 m 11,000 13,200
Perlengkapan 35 % harga pipa 0.35 - 3,850 1,348
Pekerja 0.036 hr 33,000 1,188
mandor 0.0018 hr 71,500 129
Tukang pasang pipa 0.06 hr 49,500 2,970
Kepala tukang pipa 0.006 hr 60,500 363
JUMLAH 19,197
DIBULATKAN 19,200
1 M' - Instalasi Pipa PVC type AW dia. 2 "
Pipa PVC 1.2 m 14,200 17,040
Perlengkapan 35 % harga pipa 0.35 - 4,970 1,740
Pekerja 0.054 hr 33,000 1,782
mandor 0.0027 hr 71,500 193
Tukang pasang pipa 0.09 hr 49,500 4,455
Kepala tukang pipa 0.009 hr 60,500 545
JUMLAH 25,754
DIBULATKAN 25,800
1 M' - Instalasi Pipa PVC type AW dia. 2 1/2 "
Pipa PVC 1.2 m 21,000 25,200

Halaman_253
RESUME ANALISA TEKNIS
HARGA SATUAN PEKERJAAN MEKANIKAL & ELEKTRIKAL

NO URAIAN KOEF. SAT. HARGA SAT. JUMLAH

Perlengkapan 35 % harga pipa 0.35 - 7,350 2,573


Pekerja 0.054 hr 33,000 1,782
mandor 0.0027 hr 71,500 193
Tukang pasang pipa 0.09 hr 49,500 4,455
Kepala tukang pipa 0.009 hr 60,500 545
JUMLAH 34,747
DIBULATKAN 34,700
1 M' - Instalasi Pipa PVC type AW dia. 3 "
Pipa PVC 1.2 m 28,000 33,600
Perlengkapan 35 % harga pipa 0.35 - 9,800 3,430
Pekerja 0.081 hr 33,000 2,673
mandor 0.0041 hr 71,500 293
Tukang pasang pipa 0.135 hr 49,500 6,683
Kepala tukang pipa 0.0135 hr 60,500 817
JUMLAH 47,495
DIBULATKAN 47,500
1 M' - Instalasi Pipa PVC type AW dia. 4 "
Pipa PVC 1.2 m 46,425 55,710
Perlengkapan 35 % harga pipa 0.35 - 16,249 5,687
Pekerja 0.081 hr 33,000 2,673
mandor 0.0041 hr 71,500 293
Tukang pasang pipa 0.135 hr 49,500 6,683
Kepala tukang pipa 0.0135 hr 60,500 817
JUMLAH 71,862
DIBULATKAN 71,900
1 M' - Instalasi Pipa PVC type AW dia. 6 "
Pipa PVC 1.2 m 105,950 127,140
Perlengkapan 35 % harga pipa 0.35 - 37,083 12,979
Pekerja 0.081 hr 33,000 2,673
mandor 0.0041 hr 71,500 293
Tukang pasang pipa 0.135 hr 49,500 6,683
Kepala tukang pipa 0.0135 hr 60,500 817
JUMLAH 150,584
DIBULATKAN 150,600

Halaman_254