Anda di halaman 1dari 4

DAFTAR HARGA UPAH KERJA DAN BAHAN

Pekerjaan : Pembangunan Sarana/Prasarana Pengendalian Banjir Pertemuan Batang Bangko dan Suliti Kabupaten Solok Selatan
Lokasi : Kab. Solok Selatan
Satua Kerja : SNVT PJSA WS. Batanghari Provinsi Sumatera Barat
Sumber Dana : APBN Tahun Anggaran 2021

No. Uraian Pekerjaan Satuan Harga (Rp.) KETERANGAN


I. UPAH :
1 Pekerja OH 85,000.00 12,142.86 Org/Jam
Pekerja Terlatih OH 150,000.00 21,428.57 Org/Jam
2 Tukang OH 90,000.00 12,857.14 Org/Jam
3 Kepala tukang OH 95,000.00 13,571.43 Org/Jam
4 Mandor OH 110,000.00 15,714.29 Org/Jam
5 Operator OH 200,000.00 28,571.43 Org/Jam
6 Pembantu Operator OH 85,000.00 12,142.86 Org/Jam
7 Sopir OH 150,000.00 21,428.57 Org/Jam
8 Mekanik OH 150,000.00 21,428.57 Org/Jam
9 Juru Ukur OH 150,000.00 21,428.57 Org/Jam
10 Pembantu Juru Ukur OH 85,000.00 12,142.86 Org/Jam
11 Drafter CAD OH 150,000.00 21,428.57 Org/Jam
12 Desian Engineer OH 150,000.00 21,428.57 Org/Jam
13 Tukang Fhoto OH 120,000.00 17,142.86 Org/Jam

II. BAHAN :
1 PC (portland cement) zak 60,000.00 1,200.00 /Kg
2 Pasir pasang / Pasir beton M3 200,000.00 142.86 /Kg
3 Kerikil beton M3 300,000.00 222.22 /Kg
4 Batu belah/batu kali M3 250,000.00
5 Pasir Urug M3 150,000.00
6 Tanah Timbun Pilihan m3 80,000.00
Tanah Timbun Biasa m3 22,200.00
7 Besi beton kg 11,500.00
8 Kawat Beton kg 20,000.00
9 Air M3 70,000.00 70.00 /Liter
10 Kayu Kelas II M3 2,700,000.00
11 Multiflek 4 mm Lbr 60,000.00
12 Multiflek 9 mm lbr 110,000.00
13 Multiflek 18mm Lbr 275,000.00
14 Paku kg 20,000.00
15 Asbes Gelompang Lbr 68,000.00
16 Plafon asbes 3mm Lbr 90,000.00
17 Paku Asbes kg 35,000.00
18 Jedela Kaca nako Bh 250,000.00
19 Minyak Bekisting Liter 20,000.00
20 Kayu Dolken Dia. 10 - 15 cm L = 4 m M' 35,000.00
21 Pipa PVC 2" M' 15,000.00
22 Ijuk kG 10,000.00
23 Rumput M2 15,000.00
24 Frame almunium Kg 22,000.00
25 Banner M2 30,000.00
26 Cat Kayu Kg 60,000.00
27 Elastic Filter t = 10 mm M2 65,000.00
28 Geobag Bh 50,000.00
29 Plamur Kg 40,000.00
30 Cat Dinding Kg 60,000.00
31 Lem Kayu Kg 25,000.00
32 Benang Geobag M 1,500.00
33 Geobag bh 100,000.00
34 Foto Printing Lbr 5,000.00
35 Foto Album Bh 70,000.00
36 Bahan Bakar Liter 12,500.00
No. Uraian Pekerjaan Satuan Harga (Rp.) KETERANGAN
37 Minyak Mesin Liter 30,000.00
38 Gemuk Lumas Liter 28,000.00
39 Transmission Liter 28,000.00
40 Pelumas Drive Liter 28,000.00
41 Filter Liter 270,000.00
42 Minyak Hidrolik Liter 45,000.00
Bronjong Pabrikasi 2 x 1 x 1 uk. 3 mm Buah 425,000.00
Bronjong Pabrikasi 2 x 1 x 0.5 uk. 3 mm Buah 370,000.00
Geotekstil M2 38,000.00
Baja Struktur Titik leleh 3500 kg/cm2 Kg 29,000.00
Kawat Las Doz 115,000.00
BRC kawat ukuran 1.2 m x 2.4 m kawat 6 mm unit 390,000.00 40 unit untuk pagar Direksi keet
Hollow Block tebal 15 Bh 1,200.00
.
III. PERALATAN
1 Excavator Hari #REF! Unit/Jam
2 Excavator Breaker Hari #REF! Unit/Jam
3 Bulldozer Hari #REF! Unit/Jam
4 Dump Truck Hari #REF! Unit/Jam
5 Vibratory Roller Hari #REF! Unit/Jam
6 Water Tanker Hari #REF! Unit/Jam
7 Concrete Mixer Hari #REF! Unit/Jam
8 Waterpass Hari 100,000.00 14,285.71 Unit/Jam
9 Theodholit Hari 150,000.00 21,428.57 Unit/Jam
10 Sewa Komputer Bulan 200,000.00
11 Sewa Scanner Ukuran A4 Bulan 89,999.00
12 Sewa Kamera Digital Hari 22,000.00
13 Triport Hari 50,000.00
14 Alat Panncang Hammer 0,5 ton Hari 150,000.00
15 Pompa disel 6 " Hari 275,000.00 39,285.71 Unit/Jam
Welding Set Hari 820,000.00 117,142.86 Unit/Jam
Crane 2 Ton Hari 315,000.00 45,000.00 Unit/Jam
Generator Set Hari 2,900,000.00 414,285.71 Unit/Jam

Indramayu, ……………..2021
#REF!

#REF!
#REF!
ANALISA HARGA SATUAN PEKERJAAN ITEM BARU

Jenis Pekerjaan : Beton K. 175


Satuan : #REF!
Analisa : Permen No.28/PRT/M/2016 - B.05.b
HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS
( Rp.) ( Rp )
I TENAGA KERJA
Pekerja OH 1.32300 85,000.00 112,455.00
Tukang OH 0.18900 90,000.00 17,010.00
Kepala tukang OH 0.01900 95,000.00 1,805.00
Mandor OH 0.13200 110,000.00 14,520.00

II BAHAN
Semen Kg 326.00000 1,200.00 391,200.00
Pasir Kg 760.00000 142.86 108,571.43
Kerikil Kg 1,029.00000 222.22 228,666.67
Air Ltr 215.00000 70.00 15,050.00

III ALAT
Molen Kap. 0,3 m3 Hari 0.25000 0.00 0.00

JUMLAH 889,278.10
OVERHEAD DAN PROFIT ( 10 % ) 88,927.81
TOTAL JUMLAH 978,205.90

Jenis Pekerjaan : Pemasangan 1 m 2 acian


Satuan : M3
Analisa : Permen No.28/PRT/M/2016 - A.4.4.2.27
HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS
( Rp.) ( Rp )
I TENAGA KERJA
1 Pekerja OH 0.20000 85,000.00 17,000.00
2 Tukang OH 0.10000 90,000.00 9,000.00
3 Kepala tukang OH 0.01000 95,000.00 950.00
4 Mandor OH 0.01000 110,000.00 1,100.00

II BAHAN
2 Semen Kg 3.25000 1,200.00 3,900.00

III ALAT

JUMLAH 31,950.00
OVERHEAD DAN PROFIT ( 10 % ) 3,195.00
TOTAL JUMLAH 35,145.00
Jenis Pekerjaan : Pasangan Bronjong Pabrikasi 2 x 1 x 1
Satuan : M3
Analisa : Permen No.28/PRT/M/2016 - P.06.b.4
HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS
( Rp.) ( Rp )
I TENAGA KERJA
1 Pekerja (isi batu dan pasang) OH 0.60000 150,000.00 90,000.00
2 Mandor OH 0.06000 110,000.00 6,600.00

II BAHAN
1 Batu / Batu Belah m3 2.60000 250,000.00 650,000.00
2 Kawat Bronjong 2 x 1 x 1 uk. 3 mm Buah 1.00000 425,000.00 425,000.00
III ALAT

JUMLAH 1,171,600.00
OVERHEAD DAN PROFIT ( 10 % ) 117,160.00
TOTAL JUMLAH 1,288,760.00

Jenis Pekerjaan : Pasangan Bronjong Pabrikasi 2 x 1 x 0.5


Satuan : M3
Analisa : Permen No.28/PRT/M/2016 - P.06.b.4
HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS
( Rp.) ( Rp )
I TENAGA KERJA
1 Pekerja (isi batu dan pasang) OH 0.30000 150,000.00 45,000.00
2 Mandor OH 0.03000 110,000.00 3,300.00

II BAHAN
1 Batu / Batu Belah m3 1.30000 250,000.00 325,000.00
2 Kawat Bronjong 2 x 1 x 0.5 uk. 3 mm Buah 1.00000 370,000.00 370,000.00
III ALAT

JUMLAH 743,300.00
OVERHEAD DAN PROFIT ( 10 % ) 74,330.00
TOTAL JUMLAH 817,630.00

Jenis Pekerjaan : Pemasangan Geotekstil


Satuan : M2
Analisa : Permen No.28/PRT/M/2016 - P.09.b
HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS
( Rp.) ( Rp )
I TENAGA KERJA
1 Pekerja OH 0.16000 85,000.00 13,600.00
2 Tukang OH 0.03200 90,000.00 2,880.00
3 Mandor OH 0.01600 110,000.00 1,760.00

II BAHAN
1 Geotekstil m2 1.08000 38,000.00 41,040.00
III ALAT

JUMLAH 59,280.00
OVERHEAD DAN PROFIT ( 10 % ) 5,928.00
TOTAL JUMLAH 65,208.00