KABUTEN CIANJIUR
TAHUN ANGGARAN 2019
NO UKURAN SAT INDEKS HARGA SATUAN HARGA BAHAN HARGA UPAH JUMLAH HARGA
A PEKERJAAN PERSIAPAN
Pek.Pembersihan Lahan m2
Bahan
Tenaga Kerja
Pekerja OH 0,1 80,000 8,000
1
Mandor OH 0,05 150,000 7,500
jumlah 15,500 15,500
Overhead & profit (10%) 1,550
Jumalah total 17,050
Pem.Bowplank m1
Bahan
Kayu Kaso 5/7 rasamala m3 0.012 3,100,000 37,200
Paku 4-7 Kg 2 13,000 26,000
Kayu papan borneo super m3 0.007 3,350,000 23,450
Tenaga Kerja
2 Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.005 150,000 750
Jumlah 86,650 20400 107,050
Overhead & profit (10%) 10,705
Jumlah total 117,755
Pem.Pagar Sementara m2
Bahan
Kayu dolken D8 cm lb 1.25 75,000 93750
Semen PC type 1 (50 Kg) m3 2.5 1,300 3250
Seng gelombang BJLS 30 lb 90 cm m1 1.2 35,000 42000
Pasir beton m3 0.005 250,000 1250
Batu pecah 2-3 cm m3 0.009 245,000 2205
Kayu albasia m3 0.072 1,700,000 122400
Paku 5-12 cm Kg 0.06 12,750 765
3
Meni besi lt 0.45 25,000 11250
Tenaga Kerja
Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.05 150,000 7500
Jumlah 276,870 27150 304,020
Overhead & profit (10%) 30,402
Jumlah total 334,422
Pem.Papan Proyek m2
Bahan
Multiplex lb 0.18 210,000 37800
Tiang Kayu 5/7 kls ll tinggi 3m m3 0.021 3,350,000 70350
Besi strip Kg 0.1 19,000 1900
Banner plastik m2 0.48 25,000 12000
Paku 4-7 cm Kg 0.125 13,000 1625
4 Tenaga Kerja
Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.05 115,000 5750
Mandor OH 0.05 150,000 7500
Jumlah 123,675 31750 170,050
Overhead & profit (10%) 17,005
Jumalah total 187,055
B PEKERJAAN TANAH
Pek.Galian Tanah 1m m3
Bahan
Tenaga Kerja
Pekerja
1 Mandor OH 0.75 80,000 60000
OH 0.025 150,000 3750
Jumlah 63750 63,750
Overhead & profit (10%) 6,375
Jumlah total 70,125
Pek.Pondasi Batu Kali 1: PC 4 PS m3
Bahan
Batu belah m3 1.2 250,000 300000
Semen portland Kg 163 1,300 211900
Pasir pasang m3 0.52 150,000 78000
Tenaga Kerja
2 Pekerja OH 1.5 80,000 120000
Tukang batu OH 0.75 105,000 78750
Kepala tukang OH 0.075 115,000 8625
Mandor OH 0.075 150,000 11250
Jumlah 589,900 808,525
Overhead & profit (10%) 80,853
Jumlah total 889,378
Pengurugan Tanah m3
Bahan
Tenaga Kerja
Pekerja OH 0.5 80,000 40000
3
Mandor OH 0.05 150,000 7500
Jumlah 47500 47,500
Overhead & profit (10%) 4,750
Jumlah total 52,250
C PEKERJAAN BETON
Pem.Beton Mutu Fc = 14.5 Mpa (KI75) m3
Bahan
Semen PC type 1 (50 Kg) Kg 326 1,300 423800
Pasir beton m3 0.52 250,000 130000
Batu pecah 2-3 cm m3 0.78 245,000 191100
Tenaga Kerja
1 Pekerja OH 1.65 80,000 132000
Tukang batu OH 0.275 105,000 28875
Kepala tukang OH 0.028 115,000 3220
Mandor OH 0.083 150,000 12450
Jumlah 744,900 921,445
Overhead & profit (10%) 92,145
Jumlah total 1,013,590
Pem.Bekisting Sloof 20x15 m2
Bahan
Kayu albasia m3 0.045 1,700,000 76500
Paku 5-12 cm Kg 0.3 12,750 3825
Minyak bekisting lt 0.1 2,500 250
Tenaga Kerja
2 Pekerja OH 0.52 80,000 41600
Tukang kayu OH 0.26 105,000 27300
Kepala tukang OH 0.026 115,000 2990
Mandor OH 0.026 150,000 3900
Jumlah 80,575 156,365
Overhead+profit (10%) 15,637
Jumlah total 172,002
Pem.Bekisting Kolom 15x15 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68000
Paku 5-12 cm Kg 0.4 12,750 5100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 m3 0.015 1,700,000 25500
Plywood 9 mm lb 0.35 105,000 36750
Kayu dolken D8 cm bt 2 75,000 150000
3
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 285,850 382,045
Overhead+Profit (10%) 38,205
Jumlah total 420,250
Pem.Bekisting Kolom 20x20 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 15-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 m3 0.021 1,700,000 35,700
Plywood 9 mm lb 0.35 105,000 36,750
Kayu dolken D8 cm bt 2 75,000 150,000
4
Pekerja
Pekerja OH 0.66 80,000 52,800
Tukang kayu OH 0.33 105,000 34,650
Kepala tukang OH 0.033 115,000 3,795
Mandor OH 0.033 150,000 4,950
Jumlah 296,050 392,245
Overhead + profit (10%) 39,225
Jumlah total 431,470
Pem.Bekisting Ringbalk 15x20 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 5-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 lb 0.015 1,700,000 25,500
Plywood 9 mm m3 0.35 105,000 36,750
Kayu dolken D8 cm bt 2 75,000 150,000
5
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 285,850 382,045
Overhead+Profit (10%) 38,205
Jumlah total 420,250
6 Pem.Bekisting Plat Lantai m3
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 5-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Plywood 9 mm m3 0.35 105,000 36,750
Kayu balok rasamal / kls ll m3 0.015 3,100,000 46,500
Kayu dolken D8 cm bt 6 75,000 450,000
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 606,850 703,045
Overhead+Profit (10%) 70,305
Jumlah total 773,350
Pem.Sloof 20x15 m3
Bahan
6 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x15 m2 1 172,002 172002
Jumlah 1185592 0 1185592
Pem.Kolom 15x15 m3
Bahan
7 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x15 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Kolom 15x15 m3
Bahan
8 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x20 m2 1 431,470 431470
Jumlah 1445060 0 1445060
Pem.Kolom 15x20 m3
Bahan
9 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting kolom 15x20 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Ringbalk 15x20 m3
Bahan
10 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting kolom 15x20 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Plat Beton m3
Bahan
10 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting Plat Lantai m2 1 773,350 773350
Jumlah 1786940 0 1786940
D PEKERJAAN DINDING
Pem.Dinding Bata Ringan tbl 7.5 cm m2
Bahan
Bata ringan tbl 10 cm m3 8.4 2,300 19320
Mortar siap pakai Kg 0.473 1,510 714.23
Tenaga Kerja
1 Pekerja OH 0.67 80,000 53,600
Tukang batu OH 1.3 105,000 136,500
1
2
Gpysum board Lb 0.364 64,000 23296
Paku skrup Kg 0.11 65,000 7150
Tenaga Kerja
Pekerja OH 0.1 80,000 8000
2
Tukang Kayu OH 0.05 105,000 5250
Kepala Tukang OH 0.005 115,000 575
Mandor OH 0.005 150,000 750
Jumlah 30446 14575 45,021
Overhead+Profit (10%) 4,502
Jumlah total 49523
H PEKERJAAN CAT
Pengecetan Bidang Kayu m2
Bahan
Cat manie Kg 0.2 45,000 9000
Plamuur Kg 0.15 12,500 1875
Cat dasar Kg 0.17 62,200 10574
Cat penutup Kg 0.26 121,100 31486
Kuas bh 0.01 9,000 90
Pengencer Kg 0.03 49,000 1470
1 Ampelas lb 0.2 2,300 460
Tenaga Kerja
Pekerja OH 0.07 80,000 5600
Tukang Cat OH 0.009 105,000 945
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.003 150,000 450
Jumlah 54955 7685 62,640
Overhead+Profit (10%) 6,264
Jumlah total 68,904
Pengecetan Bidang Tembok m2
Bahan
Plamuur Kg 0.15 12,500 1875
Cat dasar Kg 0.17 62,200 10574
Cat penutup Kg 0.26 121,100 31486
Kuas bh 0.01 9,000 90
Ampelas lb 0.2 2,300 460
2 Tenaga Kerja
Pekerja OH 0.02 80,000 1600
Tukang Cat OH 0.063 105,000 6615
Kepala Tukang OH 0.0063 115,000 724.5
Mandor OH 0.003 150,000 450
Jumlah 44485 9389.5 53,875
Overhead+Profit (10%) 5,387
Jumlah total 59,262
3 Pengecetan Bidang Plafond m2
Bahan
Cat plafond Kg 0.26 121,100 31486
Kuas roll bh 0.01 35,000 350
Tenaga Kerja
Pekerja OH 0.02 80,000 1600
Tukang Cat OH 0.063 105,000 6615
Kepala Tukang OH 0.0063 115,000 724.5
Mandor OH 0.003 150,000 450
Jumlah 31836 9389.5 41,226
Overhead+Profit (10%) 4,123
Jumlah total 45,349
I PEKERJAAN LISTRIK
Pem. 1 Bh MCB
Bahan
Pipa listrik 5/8 btg 3 13,500 40500
Kabel m 24 7,000 168000
T dus bh 3 7,000 21000
L bow bh 4 4,000 16000
Lasdop bh 3 8,000 24000
Klem bh 24 8,000 192000
1
Mongkok bh 1 2,000 2000
Saklar bh 2 15,000 30000
Fitting bh 3 10,000 30000
Tenaga Kerja
Upah 25% 523,500 130875
Jumlah 523500 130875 654,375
Overhead+Profit (10%) 65,438
Jumlah total 719,813
Pem. 1 Bh MCB
Bahan
Pipa listrik 5/8 btg 3 13,500 40500
Kabel m 24 7,000 168000
T dus bh 3 7,000 21000
L bow bh 4 4,000 16000
2 Klem bh 24 8,000 192000
MCB bh 1 350,000 350000
Tenaga Kerja
Upah 25% 787,500 196875
Jumlah 787500 196875 984,375
Overhead+Profit (10%) 98,438
Jumlah total 1,082,813
Pem. 1 Bh Stopkontak
Bahan
Kabel m 20 7,000 140000
Stop kontak bh 1 15,000 15000
3 Tenaga Kerja
Upah 25% 155,000 38750
Jumlah 155000 38750 193,750
Overhead+Profit (10%) 19,375
Jumlah total 213,125
J PEKERJAAN SANITASI
Pem. 1 Bh Closet Duduk
Bahan
Closet duduk standar putih unit 1 1,580,000 1580000
Semen portlad Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500
Tenaga Kerja
1 Pekerja OH 1 80,000 80000
Tukang batu OH 1.5 105,000 157500
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.16 150,000 24000
Jumlah 1589300 278750 1,868,050
Overhead+Profit (10%) 186,805
Jumlah total 2,054,855
Pem. 1 Bh Wastafel
Bahan
Wastafel unit 1 1,450,000 1450000
Semen portland Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500
Tenaga Kerja
2 Pekerja OH 1.2 80,000 96000
Tukang batu OH 1.45 105,000 152250
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.006 150,000 900
Jumlah 1459300 266400 1,725,700
Overhead+Profit (10%) 172,570
Jumlah total 1,898,270
Pem. 1 Bh Bak Air Fiberglass
Bahan
Bak fiberglass 60x60 cm unit 1 320,000 320000
Tenaga Kerja
Pekerja OH 0.3 80,000 24000
3 Tukang batu OH 0.45 105,000 47250
Kepala Tukang OH 0.045 115,000 5175
Mandor OH 0.015 150,000 2250
Jumlah 320000 78675 398,675
Overhead+Profit (10%) 39,868
Jumlah total 438,543
Pem. 1 Bh Floor Drain bh
Bahan
Floor drain bh 1 27,800 27800
Tenaga Kerja
Pekerja OH 0.01 80,000 800
4 Tukang Kayu OH 0.1 105,000 10500
Kepala Tukang OH 0.01 115,000 1150
Mandor OH 0.005 150,000 750
Jumlah 27800 13200 41000
Overhead+Profit (10%) 4100
Jumlah total 45100
Pem. 1 Bh Bak Cuci Piring Stainles Steel unit
Bahan
Bak cuci piring stainless stel unit 1 288,000 288000
Semen portland Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500
5
Tenaga Kerja
5 Pekerja OH 1.2 80,000 96000
Tukang batu OH 1.45 105,000 152250
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.006 150,000 900
Jumlah 297300 266400 563700
Overhead+Profit (10%) 53370
Jumlah total 617070
Pem. Pipa PVC tipe AW D 3/4 m
Bahan
Pipa PVC 3/4 m 1.2 43,000 51600
Tenaga Kerja
Pekerja OH 0.036 80,000 2880
6 Tukang batu OH 0.06 105,000 6300
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.002 150,000 300
Jumlah 51600 10170 61770
Overhead+Profit (10%) 6177
Jumlah total 67947
Pem. Pipa PVC tipe AW D 2" m
Bahan
Pipa PVC 2 inch m 1.2 53,000 63600
Tenaga Kerja
Pekerja OH 0.036 80,000 2880
7 Tukang batu OH 0.06 105,000 6300
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.002 150,000 300
Jumlah 63600 10170 73770
Overhead+Profit (10%) 7377
Jumlah total 81147
K PEKERJAAN AKSESORIS
Pem. 1 Buah Kunci Tanam Biasa bh
Bahan
Kunci tanam biasa bh 1 68,000 68000
Tenaga Kerja
Pekerja OH 0.01 80,000 800
1 Tukang kayu OH 0.5 105,000 52500
Kepala Tukang OH 0.05 115,000 5750
Mandor OH 0.005 150,000 750
Jumlah 68000 59800 127800
Overhead+Profit (10%) 12780
Jumlah total 140580
Pem. 1 Buah Engsel Pintu bh
Bahan
Engsel pintu bh 1 23,000 23000
Tenaga Kerja
Pekerja OH 0.015 80,000 1200
2 Tukang kayu OH 0.15 105,000 15750
Kepala tukang OH 0.015 115,000 1725
Mandor OH 0.0008 150,000 120
Jumlah 23000 18795 41795
Overhead+Profit (10%) 4180
Jumlah total 45975
Pem. 1 Buah Engsel Jendela Kupu-Kupu bh
Bahan
Engsel kupu-kupu bh 1 15,000 15000
Tenaga Kerja
Pekerja OH 0.01 80,000 800
3 Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.0005 150,000 75
Jumlah 15000 12525 27525
Overhead+Profit (10%) 2752
Jumlah total 30277
Pem. 1 Buah Kunci Slot bh
Bahan
Kunci slot bh 1 13,000 13000
Tenaga Kerja
4
Pekerja OH 0.02 80,000 1600
Tukang kayu OH 0.2 105,000 21000
Kepala tukang OH 0.02 115,000 2300
Mandor OH 0.001 150,000 150
Jumlah 13000 25050 38050
Overhead+Profit (10%) 3805
Jumlah total 41855
REKAPITULASI HARGA SATUAN
PEKERJAAN RUMAH TINGGAL