Anda di halaman 1dari 12

DAFTAR HARGA BAHAN

KABUTEN CIANJIUR
TAHUN ANGGARAN 2019

NO JENIS BAHAN-BAHAN SATUAN HARGA WILAYAH 2

1 Banner plastik m2 25,000


2 Batu belah Kg 250,000
3 Batu pecah 2-3 cm m3 245,000
4 Besi beton U.24 Kg 12,500
5 Besi strip Kg 19,000
6 Cat kayu Kg 70,000
7 Kawat beton Kg 18,000
8 Kayu albasia m3 1,700,000
9 Kayu dolken D 8 cm bt 75,000
10 Kayu Kaso 5/7 rasamala m3 3,100,000
11 Kayu papan borneo super m3 3,350,000
12 Kerikil maks 30 mm m3 245,000
13 Meni besi lt 25,000
14 Minyak bekisting lt 2,500
15 Multiplek lb 210,000
16 Paku 4-7 Kg 13,000
17 Paku 5-12 cm Kg 12,750
18 Pkau 8-12 Kg 12,500
19 Pasir beton m3 250,000
20 Pasir pasang m3 150,000
21 Plywood 9mm lb 105,000
22 Semen PC type 1 (50 kg) Kg 1,300
23 Semen portland Kg 1,300
24 Seng gelombang BJLS 30 lb 90 cm m1 35,000
25 Seng plat BJLS 30 lb 60 cm m1 46,500
26 Tiang kayu 5/7 kls ll tinggi 3m m3 3,350,000
27 Batako besar uk. 10x20x30 cm bh 2,300
28 Semen warna Kg 13,000
29 Keramik 20x20 cm m2 91,000
30 Balok kayu kamper samarinda m3 8,250,000
31 Lem kayu Kg 21,500
32 Papan kayu m3 3,100,000
33 Keramik 30x30 cm dus 70,000
34 Closet duduk standar putih unit 1,580,000
35 Wastafel TOTO lw 230 unit 1,450,000
36 Bak fiberglass 60x60 cm unit 320,000
37 Floor drain+aceessoris bh 27,800
38 Bak cuci piring stainles steel unit 288,000
39 Pipa PVC 3/4 btg 43,000
40 Pipa PVC 2,5 m 48,200
41 Cat manie Kg 45,000
42 Plamuur Kg 12,500
43 Cat dasar Kg 62,200
44 Cat penutup Kg 121,100
45 Kuas bh 9,000
46 Pengencer Kg 49,000
47 Ampelas lb 2,300
48 Kaca tebal 5 mm m2 120,000
49 Sealent Kg 28,300
50 Profil aluminium m2 85,000
51 Skrup pixer Kg 15,000
52 Kuas roll bh 35,000
53 Almunium strip m 98,500
54 Gpysum board lb 64,000
55 Paku skrup Kg 65,000
56 Pipa listrik btg 13,500
57 Kabel m 7,000
58 T dus bh 7,000
59 L bow bh 4,000
60 Lasdop bh 8,000
61 Klem bh 8,000
62 Mangkok listrik bh 2,000
63 Saklar bh 15,000
64 Fitting bh 10,000
65 Stop kontak bh 15,000
66 Pipa PVC 2 inch m 53,000
67 Genteng plentong bh 2,500
68 Genteng bubungan bh 6,800
69 Reng (3x4) bh 3,100,000
70 MCB bh 350,000
71 Kunci tanam biasa bh 68,000
72 Engsel pintu bh 23,000
73 Engsel kupu-kupu bh 15,000
74 Kkunci slot bh 13,000
ANALISA HARGA SATUAN
KABUTEN CIANJUR

NO UKURAN SAT INDEKS HARGA SATUAN HARGA BAHAN HARGA UPAH JUMLAH HARGA

A PEKERJAAN PERSIAPAN
Pek.Pembersihan Lahan m2
Bahan
Tenaga Kerja
Pekerja OH 0,1 80,000 8,000
1
Mandor OH 0,05 150,000 7,500
jumlah 15,500 15,500
Overhead & profit (10%) 1,550
Jumalah total 17,050
Pem.Bowplank m1
Bahan
Kayu Kaso 5/7 rasamala m3 0.012 3,100,000 37,200
Paku 4-7 Kg 2 13,000 26,000
Kayu papan borneo super m3 0.007 3,350,000 23,450
Tenaga Kerja
2 Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.005 150,000 750
Jumlah 86,650 20400 107,050
Overhead & profit (10%) 10,705
Jumlah total 117,755
Pem.Pagar Sementara m2
Bahan
Kayu dolken D8 cm lb 1.25 75,000 93750
Semen PC type 1 (50 Kg) m3 2.5 1,300 3250
Seng gelombang BJLS 30 lb 90 cm m1 1.2 35,000 42000
Pasir beton m3 0.005 250,000 1250
Batu pecah 2-3 cm m3 0.009 245,000 2205
Kayu albasia m3 0.072 1,700,000 122400
Paku 5-12 cm Kg 0.06 12,750 765
3
Meni besi lt 0.45 25,000 11250
Tenaga Kerja
Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.05 150,000 7500
Jumlah 276,870 27150 304,020
Overhead & profit (10%) 30,402
Jumlah total 334,422
Pem.Papan Proyek m2
Bahan
Multiplex lb 0.18 210,000 37800
Tiang Kayu 5/7 kls ll tinggi 3m m3 0.021 3,350,000 70350
Besi strip Kg 0.1 19,000 1900
Banner plastik m2 0.48 25,000 12000
Paku 4-7 cm Kg 0.125 13,000 1625
4 Tenaga Kerja
Pekerja OH 0.1 80,000 8000
Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.05 115,000 5750
Mandor OH 0.05 150,000 7500
Jumlah 123,675 31750 170,050
Overhead & profit (10%) 17,005
Jumalah total 187,055
B PEKERJAAN TANAH
Pek.Galian Tanah 1m m3
Bahan
Tenaga Kerja
Pekerja
1 Mandor OH 0.75 80,000 60000
OH 0.025 150,000 3750
Jumlah 63750 63,750
Overhead & profit (10%) 6,375
Jumlah total 70,125
Pek.Pondasi Batu Kali 1: PC 4 PS m3
Bahan
Batu belah m3 1.2 250,000 300000
Semen portland Kg 163 1,300 211900
Pasir pasang m3 0.52 150,000 78000
Tenaga Kerja
2 Pekerja OH 1.5 80,000 120000
Tukang batu OH 0.75 105,000 78750
Kepala tukang OH 0.075 115,000 8625
Mandor OH 0.075 150,000 11250
Jumlah 589,900 808,525
Overhead & profit (10%) 80,853
Jumlah total 889,378
Pengurugan Tanah m3
Bahan
Tenaga Kerja
Pekerja OH 0.5 80,000 40000
3
Mandor OH 0.05 150,000 7500
Jumlah 47500 47,500
Overhead & profit (10%) 4,750
Jumlah total 52,250
C PEKERJAAN BETON
Pem.Beton Mutu Fc = 14.5 Mpa (KI75) m3
Bahan
Semen PC type 1 (50 Kg) Kg 326 1,300 423800
Pasir beton m3 0.52 250,000 130000
Batu pecah 2-3 cm m3 0.78 245,000 191100
Tenaga Kerja
1 Pekerja OH 1.65 80,000 132000
Tukang batu OH 0.275 105,000 28875
Kepala tukang OH 0.028 115,000 3220
Mandor OH 0.083 150,000 12450
Jumlah 744,900 921,445
Overhead & profit (10%) 92,145
Jumlah total 1,013,590
Pem.Bekisting Sloof 20x15 m2
Bahan
Kayu albasia m3 0.045 1,700,000 76500
Paku 5-12 cm Kg 0.3 12,750 3825
Minyak bekisting lt 0.1 2,500 250
Tenaga Kerja
2 Pekerja OH 0.52 80,000 41600
Tukang kayu OH 0.26 105,000 27300
Kepala tukang OH 0.026 115,000 2990
Mandor OH 0.026 150,000 3900
Jumlah 80,575 156,365
Overhead+profit (10%) 15,637
Jumlah total 172,002
Pem.Bekisting Kolom 15x15 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68000
Paku 5-12 cm Kg 0.4 12,750 5100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 m3 0.015 1,700,000 25500
Plywood 9 mm lb 0.35 105,000 36750
Kayu dolken D8 cm bt 2 75,000 150000
3
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 285,850 382,045
Overhead+Profit (10%) 38,205
Jumlah total 420,250
Pem.Bekisting Kolom 20x20 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 15-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 m3 0.021 1,700,000 35,700
Plywood 9 mm lb 0.35 105,000 36,750
Kayu dolken D8 cm bt 2 75,000 150,000
4
Pekerja
Pekerja OH 0.66 80,000 52,800
Tukang kayu OH 0.33 105,000 34,650
Kepala tukang OH 0.033 115,000 3,795
Mandor OH 0.033 150,000 4,950
Jumlah 296,050 392,245
Overhead + profit (10%) 39,225
Jumlah total 431,470
Pem.Bekisting Ringbalk 15x20 m2
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 5-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Balok kayu kelas 3 lb 0.015 1,700,000 25,500
Plywood 9 mm m3 0.35 105,000 36,750
Kayu dolken D8 cm bt 2 75,000 150,000
5
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 285,850 382,045
Overhead+Profit (10%) 38,205
Jumlah total 420,250
6 Pem.Bekisting Plat Lantai m3
Bahan
Kayu albasia m3 0.04 1,700,000 68,000
Paku 5-12 cm Kg 0.4 12,750 5,100
Minyak bekisting lt 0.2 2,500 500
Plywood 9 mm m3 0.35 105,000 36,750
Kayu balok rasamal / kls ll m3 0.015 3,100,000 46,500
Kayu dolken D8 cm bt 6 75,000 450,000
Tenaga Kerja
Pekerja OH 0.66 80,000 52800
Tukang kayu OH 0.33 105,000 34650
Kepala tukang OH 0.033 115,000 3795
Mandor OH 0.033 150,000 4950
Jumlah 606,850 703,045
Overhead+Profit (10%) 70,305
Jumlah total 773,350
Pem.Sloof 20x15 m3
Bahan
6 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x15 m2 1 172,002 172002
Jumlah 1185592 0 1185592
Pem.Kolom 15x15 m3
Bahan
7 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x15 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Kolom 15x15 m3
Bahan
8 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting sloof 20x20 m2 1 431,470 431470
Jumlah 1445060 0 1445060
Pem.Kolom 15x20 m3
Bahan
9 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting kolom 15x20 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Ringbalk 15x20 m3
Bahan
10 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting kolom 15x20 m2 1 420,250 420250
Jumlah 1433840 0 1433840
Pem.Plat Beton m3
Bahan
10 Beton mutu Fc = 14.5 Mpa (K175) m3 1 1,013,590 1013590
Bekisting Plat Lantai m2 1 773,350 773350
Jumlah 1786940 0 1786940
D PEKERJAAN DINDING
Pem.Dinding Bata Ringan tbl 7.5 cm m2
Bahan
Bata ringan tbl 10 cm m3 8.4 2,300 19320
Mortar siap pakai Kg 0.473 1,510 714.23
Tenaga Kerja
1 Pekerja OH 0.67 80,000 53,600
Tukang batu OH 1.3 105,000 136,500
1

Kepala tukang OH 0.13 115,000 14,950


Mandor OH 0.003 150,000 450
Jumlah 20034.23 205,500 225,534
Overhead+Profit (10%) 22,553
Jumlah total 248,087
Pem.Plesteran 1 SP : 3 PP tbl 15 mm m2
Semen PC type 1 (50 kg) Kg 7.776 1,300 10108.8
Pasir pasang m3 0.023 150,000 3450
Tenaga Kerja
Pekerja OH 0.3 80,000 24000
2
Tukang batu OH 0.15 105,000 15750
Kepala tukang OH 0.015 115,000 1725
Mandor OH 0.015 150,000 2250
Jumlah 13558.8 43725 57,284
Overhead+Profit (10%) 5,728
Jumlah total 63,012
Pek.Acian m2
Bahan
Semen PC type 1 (50 kg) Kg 3.25 1,300 4225
Tenaga Kerja
Pekerja OH 0.2 80,000 16000
3 Tukang batu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.02 150,000 3000
Jumlah 4225 30650 34,875
Overhead+Profit (10%) 3,488
Jumlah total 38,363
Pek.Keramik Dinding m2
Bahan
Keramik 20x20 m2 1.05 91,000 95550
Semen PC type 1 (50 kg) Kg 9.3 1,300 12090
Pasir pasang m3 0.018 150,000 2700
Semen Warna Kg 1.94 13,000 25220
Tenaga Kerja
4
Pekerja OH 0.9 80,000 72000
Tukang batu OH 0.45 105,000 47250
Kepala tukang OH 0.45 115,000 51750
Mandor OH 0.45 150,000 67500
Jumlah 135560 238500 374,060
Overhead+Profit (10%) 37,406
Jumlah total 411,466
E PEKERJAAN KUSEN PINTU DAN JANDELA
Pek.Kusen Pintu & Jendela
Bahan
Balok kayu kamper samarinda m3 1.1 8,250,000 9075000
Paku 10 cm Kg 1.25 12,500 15625
Lem kayu Kg 1 21,500 21500
Tenaga Kerja
1 Pekerja OH 7 80,000 560000
Tukang kayu OH 2.1 105,000 220500
Kepala tukang OH 2.1 115,000 241500
Mandor OH 0.35 150,000 52500
Jumlah 9112125 1074500 10,186,625
Overhead+Profit (10%) 1,018,663
Jumlah total 11,205,288
Pek.Daun Pintu Panel
Bahan
Papan kayu m3 0.04 3,100,000 124000
Lem kayu Kg 0.5 21,500 10750
Tenaga Kerja
Pekerja OH 1 80,000 80000
2
Tukang kayu OH 3 105,000 315000
Kepala tukang OH 0.3 115,000 34500
Mandor OH 0.05 150,000 7500
Jumlah 134750 437000 571,750
Overhead+Profit (10%) 57,175
Jumlah total 628,925
Pek.Kaca 5 mm
Bahan
Kaca tebal 5 mm m2 1.1 120,000 132000
Sealent Kg 0.05 28,300 1415
Tenaga Kerja
Pekerja OH 0.015 80,000 1200
3
Tukang kayu OH 0.15 105,000 15750
3

Kepala tukang OH 0.015 115,000 1725


Mandor OH 0.0008 150,000 120
Jumlah 133415 18795 152,210
Overhead+Profit (10%) 15,221
Jumlah total 167,431
Pek.Kusen Pintu Aluminium
Bahan
Profil Aluminium m2 1.1 85,000 93500
Skrup pixer Kg 2 15,000 30000
Sealent Kg 0.06 28,300 1698
Tenaga Kerja
4 Pekerja OH 0.043 80,000 3440
Tukang Khusus Aluminium OH 0.043 105,000 4515
Kepala tukang OH 0.0043 115,000 494.5
Mandor OH 0.0021 150,000 315
Jumlah 125198 8764.5 133,963
Overhead+Profit (10%) 13,396
Jumlah total 147,359
Pek.Pintu Aluminium
Bahan
Profil Aluminium m 4.4 85,000 374000
Aluminium strip m 14.6 98,500 1438100
Tenaga Kerja
Pekerja OH 0.085 80,000 6800
5
Tukang Khusus OH 0.085 105,000 8925
Kepala tukang OH 0.0085 115,000 977.5
Mandor OH 0.0042 150,000 630
Jumlah 1812100 17332.5 1,829,433
Overhead+Profit (10%) 182,943
Jumlah total 2,012,376
PEKERJAAN LANTAI
Pem.Lantai Keramik 30x30 m2
Bahan
Keramik 30x30 cm dus 1.05 70,000 73500
Semen PC type 1 (50 kg) Kg 10 1,300 13000
Pasir pasang m3 0.045 150,000 6750
Semen warna Kg 0.5 13,000 6500
F1 Tenaga Kerja
Pekerja OH 0.7 80,000 56000
Tukang Khusus OH 0.35 105,000 36750
Kepala tukang OH 0.35 115,000 40250
Mandor OH 0.35 150,000 52500
Jumlah 99750 185500 285250
Overhead+Profit (10%) 28,525
Jumlah total 313,775
Pem.Lantai Keramik 20x20 m2
Bahan
Keramik 20x20 dus 1.05 91,000 95550
Semen PC type 1 (50 kg) Kg 10.4 1,300 13520
Pasir pasang m3 0.045 150,000 6750
Semen warna Kg 0.5 13,000 6500
Tenaga Kerja
2
Pekerja OH 0.7 80,000 56000
Tukang batu OH 0.35 105,000 36750
Kepala tukang OH 0.35 115,000 40250
Mandor OH 0.35 150,000 52500
Jumlah 122320 185500 307,820
Overhead+Profit (10%) 30,782
Jumlah total 338,602
G PEKERJAAN LANGIT - LANGIT
Pek.Rangka Plafond m2
Bahan
Kayu Kaso 5/7 rasamala kls ll m3 0.0154 3,100,000 47740
Paku 5 - 12 cm Kg 0.2 12,750 2550
Tenaga Kerja
Pekerja OH 0.15 80,000 12000
1
Tukang Kayu OH 0.3 105,000 31500
Kepala tukang OH 0.03 115,000 3450
Mandor OH 0.075 150,000 11250
Jumlah 50290 58200 108,490
Overhead+Profit (10%) 10,849
Jumlah total 119,339
Pem.Plafond Gypsum m2
Bahan

2
Gpysum board Lb 0.364 64,000 23296
Paku skrup Kg 0.11 65,000 7150
Tenaga Kerja
Pekerja OH 0.1 80,000 8000
2
Tukang Kayu OH 0.05 105,000 5250
Kepala Tukang OH 0.005 115,000 575
Mandor OH 0.005 150,000 750
Jumlah 30446 14575 45,021
Overhead+Profit (10%) 4,502
Jumlah total 49523
H PEKERJAAN CAT
Pengecetan Bidang Kayu m2
Bahan
Cat manie Kg 0.2 45,000 9000
Plamuur Kg 0.15 12,500 1875
Cat dasar Kg 0.17 62,200 10574
Cat penutup Kg 0.26 121,100 31486
Kuas bh 0.01 9,000 90
Pengencer Kg 0.03 49,000 1470
1 Ampelas lb 0.2 2,300 460
Tenaga Kerja
Pekerja OH 0.07 80,000 5600
Tukang Cat OH 0.009 105,000 945
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.003 150,000 450
Jumlah 54955 7685 62,640
Overhead+Profit (10%) 6,264
Jumlah total 68,904
Pengecetan Bidang Tembok m2
Bahan
Plamuur Kg 0.15 12,500 1875
Cat dasar Kg 0.17 62,200 10574
Cat penutup Kg 0.26 121,100 31486
Kuas bh 0.01 9,000 90
Ampelas lb 0.2 2,300 460
2 Tenaga Kerja
Pekerja OH 0.02 80,000 1600
Tukang Cat OH 0.063 105,000 6615
Kepala Tukang OH 0.0063 115,000 724.5
Mandor OH 0.003 150,000 450
Jumlah 44485 9389.5 53,875
Overhead+Profit (10%) 5,387
Jumlah total 59,262
3 Pengecetan Bidang Plafond m2
Bahan
Cat plafond Kg 0.26 121,100 31486
Kuas roll bh 0.01 35,000 350
Tenaga Kerja
Pekerja OH 0.02 80,000 1600
Tukang Cat OH 0.063 105,000 6615
Kepala Tukang OH 0.0063 115,000 724.5
Mandor OH 0.003 150,000 450
Jumlah 31836 9389.5 41,226
Overhead+Profit (10%) 4,123
Jumlah total 45,349
I PEKERJAAN LISTRIK
Pem. 1 Bh MCB
Bahan
Pipa listrik 5/8 btg 3 13,500 40500
Kabel m 24 7,000 168000
T dus bh 3 7,000 21000
L bow bh 4 4,000 16000
Lasdop bh 3 8,000 24000
Klem bh 24 8,000 192000
1
Mongkok bh 1 2,000 2000
Saklar bh 2 15,000 30000
Fitting bh 3 10,000 30000
Tenaga Kerja
Upah 25% 523,500 130875
Jumlah 523500 130875 654,375
Overhead+Profit (10%) 65,438
Jumlah total 719,813
Pem. 1 Bh MCB
Bahan
Pipa listrik 5/8 btg 3 13,500 40500
Kabel m 24 7,000 168000
T dus bh 3 7,000 21000
L bow bh 4 4,000 16000
2 Klem bh 24 8,000 192000
MCB bh 1 350,000 350000
Tenaga Kerja
Upah 25% 787,500 196875
Jumlah 787500 196875 984,375
Overhead+Profit (10%) 98,438
Jumlah total 1,082,813
Pem. 1 Bh Stopkontak
Bahan
Kabel m 20 7,000 140000
Stop kontak bh 1 15,000 15000
3 Tenaga Kerja
Upah 25% 155,000 38750
Jumlah 155000 38750 193,750
Overhead+Profit (10%) 19,375
Jumlah total 213,125
J PEKERJAAN SANITASI
Pem. 1 Bh Closet Duduk
Bahan
Closet duduk standar putih unit 1 1,580,000 1580000
Semen portlad Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500
Tenaga Kerja
1 Pekerja OH 1 80,000 80000
Tukang batu OH 1.5 105,000 157500
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.16 150,000 24000
Jumlah 1589300 278750 1,868,050
Overhead+Profit (10%) 186,805
Jumlah total 2,054,855
Pem. 1 Bh Wastafel
Bahan
Wastafel unit 1 1,450,000 1450000
Semen portland Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500
Tenaga Kerja
2 Pekerja OH 1.2 80,000 96000
Tukang batu OH 1.45 105,000 152250
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.006 150,000 900
Jumlah 1459300 266400 1,725,700
Overhead+Profit (10%) 172,570
Jumlah total 1,898,270
Pem. 1 Bh Bak Air Fiberglass
Bahan
Bak fiberglass 60x60 cm unit 1 320,000 320000
Tenaga Kerja
Pekerja OH 0.3 80,000 24000
3 Tukang batu OH 0.45 105,000 47250
Kepala Tukang OH 0.045 115,000 5175
Mandor OH 0.015 150,000 2250
Jumlah 320000 78675 398,675
Overhead+Profit (10%) 39,868
Jumlah total 438,543
Pem. 1 Bh Floor Drain bh
Bahan
Floor drain bh 1 27,800 27800
Tenaga Kerja
Pekerja OH 0.01 80,000 800
4 Tukang Kayu OH 0.1 105,000 10500
Kepala Tukang OH 0.01 115,000 1150
Mandor OH 0.005 150,000 750
Jumlah 27800 13200 41000
Overhead+Profit (10%) 4100
Jumlah total 45100
Pem. 1 Bh Bak Cuci Piring Stainles Steel unit
Bahan
Bak cuci piring stainless stel unit 1 288,000 288000
Semen portland Kg 6 1,300 7800
Pasir pasang m3 0.01 150,000 1500

5
Tenaga Kerja
5 Pekerja OH 1.2 80,000 96000
Tukang batu OH 1.45 105,000 152250
Kepala Tukang OH 0.15 115,000 17250
Mandor OH 0.006 150,000 900
Jumlah 297300 266400 563700
Overhead+Profit (10%) 53370
Jumlah total 617070
Pem. Pipa PVC tipe AW D 3/4 m
Bahan
Pipa PVC 3/4 m 1.2 43,000 51600
Tenaga Kerja
Pekerja OH 0.036 80,000 2880
6 Tukang batu OH 0.06 105,000 6300
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.002 150,000 300
Jumlah 51600 10170 61770
Overhead+Profit (10%) 6177
Jumlah total 67947
Pem. Pipa PVC tipe AW D 2" m
Bahan
Pipa PVC 2 inch m 1.2 53,000 63600
Tenaga Kerja
Pekerja OH 0.036 80,000 2880
7 Tukang batu OH 0.06 105,000 6300
Kepala Tukang OH 0.006 115,000 690
Mandor OH 0.002 150,000 300
Jumlah 63600 10170 73770
Overhead+Profit (10%) 7377
Jumlah total 81147
K PEKERJAAN AKSESORIS
Pem. 1 Buah Kunci Tanam Biasa bh
Bahan
Kunci tanam biasa bh 1 68,000 68000
Tenaga Kerja
Pekerja OH 0.01 80,000 800
1 Tukang kayu OH 0.5 105,000 52500
Kepala Tukang OH 0.05 115,000 5750
Mandor OH 0.005 150,000 750
Jumlah 68000 59800 127800
Overhead+Profit (10%) 12780
Jumlah total 140580
Pem. 1 Buah Engsel Pintu bh
Bahan
Engsel pintu bh 1 23,000 23000
Tenaga Kerja
Pekerja OH 0.015 80,000 1200
2 Tukang kayu OH 0.15 105,000 15750
Kepala tukang OH 0.015 115,000 1725
Mandor OH 0.0008 150,000 120
Jumlah 23000 18795 41795
Overhead+Profit (10%) 4180
Jumlah total 45975
Pem. 1 Buah Engsel Jendela Kupu-Kupu bh
Bahan
Engsel kupu-kupu bh 1 15,000 15000
Tenaga Kerja
Pekerja OH 0.01 80,000 800
3 Tukang kayu OH 0.1 105,000 10500
Kepala tukang OH 0.01 115,000 1150
Mandor OH 0.0005 150,000 75
Jumlah 15000 12525 27525
Overhead+Profit (10%) 2752
Jumlah total 30277
Pem. 1 Buah Kunci Slot bh
Bahan
Kunci slot bh 1 13,000 13000
Tenaga Kerja
4
Pekerja OH 0.02 80,000 1600
Tukang kayu OH 0.2 105,000 21000
Kepala tukang OH 0.02 115,000 2300
Mandor OH 0.001 150,000 150
Jumlah 13000 25050 38050
Overhead+Profit (10%) 3805
Jumlah total 41855
REKAPITULASI HARGA SATUAN
PEKERJAAN RUMAH TINGGAL

NO URAIAN PEKERJAAN SAT HARGA SATUAN


A PEKERJAAN PERSIAPAN
1 Pek.Pembersihan Lahan m2 17,050
2 Pem.Bowplank m1 117,755
3 Pem.Pagar Sementara m2 334,422
4 Pem.Papan Proyek m2 187,055
B PEKERJAAN TANAH
1 Pek.Galian Tanah 1m m3 70,125
2 Pek.Pondasi Batu Kali 1: PC 4 PS m3 889,378
3 Pengurugan Tanah m3 52,250
C PEKERJAAN BETON
1 Pem.Sloof 20x15 m3 1,185,592
2 Pem.Kolom 15x15 m3 1,433,840
3 Pem.Kolom 15x15 m3 1,445,060
4 Pem.Kolom 15x20 m3 1,433,840
5 Pem.Ringbalk 15x20 m3 1,433,840
6 Pem.Plat Beton m3 1,786,940
D PEKERJAAN DINDING
1 Pem.Dinding Bata Ringan tbl 7.5 cm m2 248,087
2 Pem.Plesteran 1 SP : 3 PP tbl 15 mm m2 63,012
3 Pek.Acian m2 38,363
4 Pek.Keramik Dinding m2 411,466
E PEKERJAAN KUSEN PINTU & JENDELA
1 Pek.Kusen Pintu & Jendela m3 11,205,288
2 Pek.Daun Pintu Panel m2 628,925
3 Pek.Kaca 5 mm m2 167,431
4 Pek.Kusen Pintu Aluminium m3 147,359
5 Pek.Pintu Aluminium m2 2,012,376
F PEKERJAAN LANTAI
1 Pem.Lantai Keramik 30x30 m2 313,775
2 Pem.Lantai Keramik 20x20 m2 338,602
G PEKERJAAN LANGIT-LANGIT
1 Pek.Rangka Plafond m2 119,339
2 Pem.Plafond Gypsum m2 49523