HARGA SATUAN
NO URAIAN UPAH SATUAN KET
(RP)
1 Pekerja Orang 100,000.00
2 Tukang Orang 131,000.00
3 Kepala Tukang Orang 157,000.00
4 Mandor Orang 118,000.00
HARGA SATUAN
NO URAIAN BAHAN SATUAN KET
(RP)
1 Air Liter 100.00
2 Batu Bata Buah 1,192.00
3 Batu Kali/Batu Belah (Sungai/Gunung) M3 207,075.00
4 Besi Beton Polos Kg 17,068.00
5 Besi Beton Ulir Kg 23,343.00
6 Baja Profil Kg 29,925.00
7 Beton Roster / Kerawang Bh 41,415.00
8 Kawat Beton Kg 25,100.00
9 Semen @ 40 Kg Zak 65,260.00
10 Semen @ 40 Kg per- Kg Kg 1,631.50
11 Semen Warna @ 50 Kg Zak 232,175.00
12 Semen Warna @ 50 Kg per- Kg Kg 4,643.50
13 Seng Spandek t = 0,3 mm M2 78,000.00
14 Nok Bubungan Seng Spandek M 42,500.00
15 Tanah Timbun M3 100,400.00
16 Pasir Urug M3 125,500.00
17 Pasir Pasang (lokal) M3 156,875.00
18 Pasir Beton/Kerikil (daratan) M3 564,750.00
19 Pasir Beton/Kerikil (daratan) Kg 418.33
20 Keramik 30 x 60 cm M2 155,000.00
21 Granit Tile 60 x 60 cm M2 326,300.00
22 Step Nosing Granit 10 x 60 cm Bh 45,000.00
23 Batu Alam Andesit M2 313,750.00
24 Kayu Kelas I M3 8,157,500.00
25 Kayu Kelas II M3 6,902,500.00
26 Kayu Kelas III M3 5,647,500.00
27 Papan Kayu Bouwplank 3/20 M3 5,647,500.00
28 Papan kayu Meuranti 3/20 M3 8,157,500.00
29 Kayu untuk Perancah M3 5,647,500.00
30 Dolken Kayu ø 8-10/4 m Btg 30,000.00
31 Multipleks 4 mm Lbr 94,125.00
32 Multipleks 9 mm Lbr 169,425.00
33 Gypsum Lbr 200,800.00
34 List Profil Gypsum M 16,315.00
35 Kloset Duduk Setara TOTO Bh 4,000,000.00
36 Wastafel Setara TOTO Bh 1,250,000.00
37 Shower Mandi Setara TOTO Bh 475,000.00
HARGA SATUAN
NO URAIAN BAHAN SATUAN KET
(RP)
38 Kran Air Bh 45,000.00
39 Sealtape Bh 4,000.00
40 Sealent Kg 32,500.00
41 Floor Drain Bh 55,000.00
42 Roof Drain Bh 60,000.00
43 Pipa PVC 1/2 Inc M 7,600.00
44 Pipa PVC 3/4 Inc M 9,100.00
45 Pipa PVC 1 Inc M 12,600.00
46 Pipa PVC 2 Inc M 19,000.00
47 Pipa PVC 3 Inc M 42,000.00
48 Pipa PVC 4 Inc M 51,000.00
49 Kuas cat Bh 31,375.00
50 Plamir Tembok Kg 27,610.00
51 Dempul Kayu Kg 25,100.00
52 Cat Kayu Dasar Kg 52,710.00
53 Cat Menie Kg 81,575.00
54 Cat Kayu Mengkilat Kg 81,575.00
55 Cat Dinding Tembok setara Jotun/Dulux Kg 175,700.00
56 Paku Kayu Kg 18,825.00
57 Paku Seng Kg 25,100.00
58 Paku Skrup Kg 31,500.00
59 Minyak Cat Liter 31,375.00
60 Minyak Bekisting Liter 9,450.00
61 Kertas Amplas Lbr 12,550.00
62 Thinner Kg 31,375.00
63 Residu Liter 9,450.00
DAFTAR ANALISA HARGA SATUAN
A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 7.4 Mpa (K 100),slump (12 ± 2) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 247 1,631.50 402,980.50
Pasir Beton kg 869 418.33 363,531.67
Kerikil (Maks 30 mm) kg 999 418.33 417,915.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,205,927.17
C PERALATAN
A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12.2 Mpa (K 150),slump (12 ± 2) cm, w/c = 0.72
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 299 1,631.50 487,818.50
Pasir Beton kg 799 418.33 334,248.33
Kerikil (Maks 30 mm) kg 1,017 418.33 425,445.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,269,011.83
C PERALATAN
A. 4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa (K 100),slump (3 - 6) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.200 100,000.00 120,000.00
Tukang batu OH 0.200 131,000.00 26,200.00
Kepala Tukang OH 0.020 157,000.00 3,140.00
Mandor OH 0.060 118,000.00 7,080.00
Jumlah Tenaga Kerja 156,420.00
B BAHAN
Semen Portland kg 230 1,631.50 375,245.00
Pasir Beton kg 893 418.33 373,571.67
Kerikil (Maks 30 mm) kg 1,027 418.33 429,628.33
Air Liter 200 100.00 20,000.00
Jumlah Harga Bahan 1,198,445.00
C PERALATAN
A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 352 1,631.50 574,288.00
Pasir Beton kg 731 418.33 305,801.67
Kerikil (Maks 30 mm) kg 1,031 418.33 431,301.67
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,332,891.33
C PERALATAN
A. 4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0.58
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 371 1,631.50 605,286.50
Pasir Beton kg 698 418.33 291,996.67
Kerikil (Maks 30 mm) kg 1,047 418.33 437,995.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,356,778.17
C PERALATAN
A. 4.4.1.7 Pemasangan 1 m2 dinding bata merah (5 x11x 22) cm tebal 1/2 batu campuran 1SP : 2PP
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 46,440.00
B BAHAN
Bata Merah bh 70.000 1,192.00 83,440.00
Semen Portland kg 18.950 1,631.50 30,916.93
Pasir Pasang m3 0.038 156,875.00 5,961.25
Jumlah Harga Bahan 120,318.18
C PERALATAN
A. 4.5.1.7 Pemasangan 1 m2 Langit-langit Gypsum Board ukuran (120 x 240) cm, tebal 9 mm
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang Kayu OH 0.050 131,000.00 6,550.00
Kepala Tukang OH 0.005 157,000.00 785.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 17,925.00
B BAHAN
Gypsum Board Lembar 0.364 200,800.00 73,091.20
Paku Skrup kg 0.110 31,500.00 3,465.00
Jumlah Harga Bahan 76,556.20
C PERALATAN
A. 4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.070 100,000.00 7,000.00
Tukang Cat OH 0.009 131,000.00 1,179.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,475.00
B BAHAN
Cat Menie kg 0.200 81,575.00 16,315.00
Plamur kg 0.150 27,610.00 4,141.50
Cat Dasar kg 0.170 52,710.00 8,960.70
Cat Penutup kg 0.260 175,700.00 45,682.00
Kuas Bh 0.010 31,375.00 313.75
Pengencer/Thinner kg 0.030 31,375.00 941.25
Amplas Lbr 0.200 12,550.00 2,510.00
Jumlah Harga Bahan 78,864.20
C PERALATAN
A. 4.7.1.12 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.028 100,000.00 2,800.00
Tukang Cat OH 0.042 131,000.00 5,502.00
Kepala Tukang OH 0.0042 157,000.00 659.40
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,315.40
B BAHAN
Cat Dasar kg 0.120 52,710.00 6,325.20
Cat Penutup kg 0.180 175,700.00 31,626.00
Jumlah Harga Bahan 37,951.20
C PERALATAN