DAFTAR HARGA UPAH DAN BAHAN

HARGA SATUAN
NO URAIAN UPAH SATUAN KET
(RP)
1 Pekerja Orang 100,000.00
2 Tukang Orang 131,000.00
3 Kepala Tukang Orang 157,000.00
4 Mandor Orang 118,000.00

HARGA SATUAN
NO URAIAN BAHAN SATUAN KET
(RP)
1 Air Liter 100.00
2 Batu Bata Buah 1,192.00
3 Batu Kali/Batu Belah (Sungai/Gunung) M3 207,075.00
4 Besi Beton Polos Kg 17,068.00
5 Besi Beton Ulir Kg 23,343.00
6 Baja Profil Kg 29,925.00
7 Beton Roster / Kerawang Bh 41,415.00
8 Kawat Beton Kg 25,100.00
9 Semen @ 40 Kg Zak 65,260.00
10 Semen @ 40 Kg per- Kg Kg 1,631.50
11 Semen Warna @ 50 Kg Zak 232,175.00
12 Semen Warna @ 50 Kg per- Kg Kg 4,643.50
13 Seng Spandek t = 0,3 mm M2 78,000.00
14 Nok Bubungan Seng Spandek M 42,500.00
15 Tanah Timbun M3 100,400.00
16 Pasir Urug M3 125,500.00
17 Pasir Pasang (lokal) M3 156,875.00
18 Pasir Beton/Kerikil (daratan) M3 564,750.00
19 Pasir Beton/Kerikil (daratan) Kg 418.33
20 Keramik 30 x 60 cm M2 155,000.00
21 Granit Tile 60 x 60 cm M2 326,300.00
22 Step Nosing Granit 10 x 60 cm Bh 45,000.00
23 Batu Alam Andesit M2 313,750.00
24 Kayu Kelas I M3 8,157,500.00
25 Kayu Kelas II M3 6,902,500.00
26 Kayu Kelas III M3 5,647,500.00
27 Papan Kayu Bouwplank 3/20 M3 5,647,500.00
28 Papan kayu Meuranti 3/20 M3 8,157,500.00
29 Kayu untuk Perancah M3 5,647,500.00
30 Dolken Kayu ø 8-10/4 m Btg 30,000.00
31 Multipleks 4 mm Lbr 94,125.00
32 Multipleks 9 mm Lbr 169,425.00
33 Gypsum Lbr 200,800.00
34 List Profil Gypsum M 16,315.00
35 Kloset Duduk Setara TOTO Bh 4,000,000.00
36 Wastafel Setara TOTO Bh 1,250,000.00
37 Shower Mandi Setara TOTO Bh 475,000.00
HARGA SATUAN
NO URAIAN BAHAN SATUAN KET
(RP)
38 Kran Air Bh 45,000.00
39 Sealtape Bh 4,000.00
40 Sealent Kg 32,500.00
41 Floor Drain Bh 55,000.00
42 Roof Drain Bh 60,000.00
43 Pipa PVC 1/2 Inc M 7,600.00
44 Pipa PVC 3/4 Inc M 9,100.00
45 Pipa PVC 1 Inc M 12,600.00
46 Pipa PVC 2 Inc M 19,000.00
47 Pipa PVC 3 Inc M 42,000.00
48 Pipa PVC 4 Inc M 51,000.00
49 Kuas cat Bh 31,375.00
50 Plamir Tembok Kg 27,610.00
51 Dempul Kayu Kg 25,100.00
52 Cat Kayu Dasar Kg 52,710.00
53 Cat Menie Kg 81,575.00
54 Cat Kayu Mengkilat Kg 81,575.00
55 Cat Dinding Tembok setara Jotun/Dulux Kg 175,700.00
56 Paku Kayu Kg 18,825.00
57 Paku Seng Kg 25,100.00
58 Paku Skrup Kg 31,500.00
59 Minyak Cat Liter 31,375.00
60 Minyak Bekisting Liter 9,450.00
61 Kertas Amplas Lbr 12,550.00
62 Thinner Kg 31,375.00
63 Residu Liter 9,450.00
DAFTAR ANALISA HARGA SATUAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A. 2.2.1.9 Pembersihan 1 m2 Lapangan dan Perataan


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Mandor OH 0.050 118,000.00 5,900.00
Jumlah Tenaga Kerja 15,900.00
B BAHAN

Jumlah Harga Bahan 0.00


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 15,900.00
E Overhead & Profit (10%) 10% x D 1,590.00
F Harga Satuan Pekerjaan (D+E) 17,490.00

A. 2.2.1.4 Pengukuran dan Pemasangan 1m' Bouwplank


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang kayu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 25,260.00
B BAHAN
Kayu Balok 5/7 m3 0.012 5,647,500.00 67,770.00
Paku 2"-3" Kg 0.020 18,825.00 376.50
Kayu Papan 3/20 m3 0.007 5,647,500.00 39,532.50
Jumlah Harga Bahan 107,679.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 132,939.00
E Overhead & Profit (10%) 10% x D 13,293.90
F Harga Satuan Pekerjaan (D+E) 146,232.90

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A. 2.3.1.1 Penggalian 1 m3 Tanah Biasa sedalam 1 m


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.750 100,000.00 75,000.00
Mandor OH 0.025 118,000.00 2,950.00
Jumlah Tenaga Kerja 77,950.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 77,950.00
E Overhead & Profit (10%) 10% x D 7,795.00
F Harga Satuan Pekerjaan (D+E) 85,745.00
A. 2.3.1.2 Penggalian 1 m3 Tanah Biasa sedalam 2 m
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.900 100,000.00 90,000.00
Mandor OH 0.045 118,000.00 5,310.00
Jumlah Tenaga Kerja 95,310.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 95,310.00
E Overhead & Profit (10%) 10% x D 9,531.00
F Harga Satuan Pekerjaan (D+E) 104,841.00

A. 2.3.1.9 Pengurugan kembali 1 m3 galian tanah


Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koofisien pekerjaan galian
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.500 100,000.00 50,000.00
Mandor OH 0.050 118,000.00 5,900.00
Jumlah Tenaga Kerja 55,900.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 55,900.00
E Overhead & Profit (10%) 10% x D 5,590.00
F Harga Satuan Pekerjaan (D+E) 61,490.00

A. 2.3.1.11 Pengurugan 1 m3 dengan pasir urug


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Mandor OH 0.010 118,000.00 1,180.00
Jumlah Tenaga Kerja 31,180.00
B BAHAN
Pasir Urug m3 1.200 125,500.00 150,600.00
Jumlah Harga Bahan 150,600.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 181,780.00
E Overhead & Profit (10%) 10% x D 18,178.00
F Harga Satuan Pekerjaan (D+E) 199,958.00

A. 2.3.1.11a Pengurugan 1 m3 Tanah Timbun


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Mandor OH 0.010 118,000.00 1,180.00
Jumlah Tenaga Kerja 31,180.00
B BAHAN
Tanah Timbun m3 1.200 100,400.00 120,480.00
Jumlah Harga Bahan 120,480.00
C PERALATAN
Jumlah Harga Alat
D Jumlah (A + B + C) 151,660.00
E Overhead & Profit (10%) 10% x D 15,166.00
F Harga Satuan Pekerjaan (D+E) 166,826.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A. 3.2.1.2 Pemasangan 1m3 pondasi batu belah campuran 1SP : 4PP


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.500 100,000.00 150,000.00
Tukang batu OH 0.750 131,000.00 98,250.00
Kepala Tukang OH 0.075 157,000.00 11,775.00
Mandor OH 0.075 118,000.00 8,850.00
Jumlah Tenaga Kerja 268,875.00
B BAHAN
Batu Belah/ Kali m3 1.200 207,075.00 248,490.00
Semen Portland Kg 163.000 1,631.50 265,934.50
Pasir Pasang m3 0.520 156,875.00 81,575.00
Jumlah Harga Bahan 595,999.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 864,874.50
E Overhead & Profit (10%) 10% x D 86,487.45
F Harga Satuan Pekerjaan (D+E) 951,361.95

A. 3.2.1.9 Pemasangan 1m3 batu kosong (Aanstamping)


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.780 100,000.00 78,000.00
Tukang batu OH 0.390 131,000.00 51,090.00
Kepala Tukang OH 0.039 157,000.00 6,123.00
Mandor OH 0.039 118,000.00 4,602.00
Jumlah Tenaga Kerja 139,815.00
B BAHAN
Batu Belah/ Kali m3 1.200 207,075.00 248,490.00
Pasir Urug m3 0.432 125,500.00 54,216.00
Jumlah Harga Bahan 302,706.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 442,521.00
E Overhead & Profit (10%) 10% x D 44,252.10
F Harga Satuan Pekerjaan (D+E) 486,773.10

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Catatan : Bobot isi pasir = 1400 kg/m3 , Bobot isi kerikil = 1350 kg/m3

A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 7.4 Mpa (K 100),slump (12 ± 2) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 247 1,631.50 402,980.50
Pasir Beton kg 869 418.33 363,531.67
Kerikil (Maks 30 mm) kg 999 418.33 417,915.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,205,927.17
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,421,142.17
E Overhead & Profit (10%) 10% x D 142,114.22
F Harga Satuan Pekerjaan (D+E) 1,563,256.38
A. 4.1.1.2 Membuat 1 m3 beton mutu f'c = 9.8 Mpa (K 125),slump (12 ± 2) cm, w/c = 0.78
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 276 1,631.50 450,294.00
Pasir Beton kg 828 418.33 346,380.00
Kerikil (Maks 30 mm) kg 1,012 418.33 423,353.33
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,241,527.33
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,456,742.33
E Overhead & Profit (10%) 10% x D 145,674.23
F Harga Satuan Pekerjaan (D+E) 1,602,416.57

A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12.2 Mpa (K 150),slump (12 ± 2) cm, w/c = 0.72
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 299 1,631.50 487,818.50
Pasir Beton kg 799 418.33 334,248.33
Kerikil (Maks 30 mm) kg 1,017 418.33 425,445.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,269,011.83
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,484,226.83
E Overhead & Profit (10%) 10% x D 148,422.68
F Harga Satuan Pekerjaan (D+E) 1,632,649.52

A. 4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa (K 100),slump (3 - 6) cm, w/c = 0.87
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.200 100,000.00 120,000.00
Tukang batu OH 0.200 131,000.00 26,200.00
Kepala Tukang OH 0.020 157,000.00 3,140.00
Mandor OH 0.060 118,000.00 7,080.00
Jumlah Tenaga Kerja 156,420.00
B BAHAN
Semen Portland kg 230 1,631.50 375,245.00
Pasir Beton kg 893 418.33 373,571.67
Kerikil (Maks 30 mm) kg 1,027 418.33 429,628.33
Air Liter 200 100.00 20,000.00
Jumlah Harga Bahan 1,198,445.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,354,865.00
E Overhead & Profit (10%) 10% x D 135,486.50
F Harga Satuan Pekerjaan (D+E) 1,490,351.50
A. 4.1.1.5 Membuat 1 m3 beton mutu f'c = 14.5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0.66
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 326 1,631.50 531,869.00
Pasir Beton kg 760 418.33 317,933.33
Kerikil (Maks 30 mm) kg 1,029 418.33 430,465.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,301,767.33
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,516,982.33
E Overhead & Profit (10%) 10% x D 151,698.23
F Harga Satuan Pekerjaan (D+E) 1,668,680.57

A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 352 1,631.50 574,288.00
Pasir Beton kg 731 418.33 305,801.67
Kerikil (Maks 30 mm) kg 1,031 418.33 431,301.67
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,332,891.33
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,548,106.33
E Overhead & Profit (10%) 10% x D 154,810.63
F Harga Satuan Pekerjaan (D+E) 1,702,916.97

A. 4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0.58
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 371 1,631.50 605,286.50
Pasir Beton kg 698 418.33 291,996.67
Kerikil (Maks 30 mm) kg 1,047 418.33 437,995.00
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,356,778.17
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,571,993.17
E Overhead & Profit (10%) 10% x D 157,199.32
F Harga Satuan Pekerjaan (D+E) 1,729,192.48
A. 4.1.1.8 Membuat 1 m3 beton mutu f'c = 21.7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0.56
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang batu OH 0.275 131,000.00 36,025.00
Kepala Tukang OH 0.028 157,000.00 4,396.00
Mandor OH 0.083 118,000.00 9,794.00
Jumlah Tenaga Kerja 215,215.00
B BAHAN
Semen Portland kg 384 1,631.50 626,496.00
Pasir Beton kg 692 418.33 289,486.67
Kerikil (Maks 30 mm) kg 1,039 418.33 434,648.33
Air Liter 215 100.00 21,500.00
Jumlah Harga Bahan 1,372,131.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,587,346.00
E Overhead & Profit (10%) 10% x D 158,734.60
F Harga Satuan Pekerjaan (D+E) 1,746,080.60

A. 4.1.1.17 Pembesian 10 kg dengan besi polos


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.070 100,000.00 7,000.00
Tukang besi OH 0.070 131,000.00 9,170.00
Kepala Tukang OH 0.007 157,000.00 1,099.00
Mandor OH 0.004 118,000.00 472.00
Jumlah Tenaga Kerja 17,741.00
B BAHAN
Besi Beton Polos kg 10.500 17,068.00 179,214.00
Kawat Beton kg 0.150 25,100.00 3,765.00
Jumlah Harga Bahan 182,979.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 200,720.00
E Overhead & Profit (10%) 10% x D 20,072.00
F Harga Satuan Pekerjaan (D+E) 220,792.00
G Harga Satuan per kg besi F : 10 kg 22,079.20

A. 4.1.1.17a Pembesian 10 kg dengan besi ulir


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.070 100,000.00 7,000.00
Tukang besi OH 0.070 131,000.00 9,170.00
Kepala Tukang OH 0.007 157,000.00 1,099.00
Mandor OH 0.004 118,000.00 472.00
Jumlah Tenaga Kerja 17,741.00
B BAHAN
Besi Beton Ulir kg 10.500 23,343.00 245,101.50
Kawat Beton kg 0.150 25,100.00 3,765.00
Jumlah Harga Bahan 248,866.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 266,607.50
E Overhead & Profit (10%) 10% x D 26,660.75
F Harga Satuan Pekerjaan (D+E) 293,268.25
G Harga Satuan per kg besi F : 10 kg 29,326.83
A. 4.1.1.20 Pemasangan 1m2 bekesting untuk pondasi
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.520 100,000.00 52,000.00
Tukang kayu OH 0.260 131,000.00 34,060.00
Kepala Tukang OH 0.026 157,000.00 4,082.00
Mandor OH 0.026 118,000.00 3,068.00
Jumlah Tenaga Kerja 93,210.00
B BAHAN
Kayu Klas III m3 0.040 5,647,500.00 225,900.00
Paku 5 - 10 cm kg 0.300 18,825.00 5,647.50
Minyak Bekesting liter 0.100 9,450.00 945.00
Jumlah Harga Bahan 232,492.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 325,702.50
E Diambil Untuk 2 x pakai 162,851.25
F Overhead & Profit (10%) 10% x D 16,285.13
G Harga Satuan Pekerjaan (E+F) 179,136.38

A. 4.1.1.21 Pemasangan 1m2 bekesting untuk sloof


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.520 100,000.00 52,000.00
Tukang kayu OH 0.260 131,000.00 34,060.00
Kepala Tukang OH 0.026 157,000.00 4,082.00
Mandor OH 0.026 118,000.00 3,068.00
Jumlah Tenaga Kerja 93,210.00
B BAHAN
Kayu Klas III m3 0.045 5,647,500.00 254,137.50
Paku 5 - 10 cm kg 0.300 18,825.00 5,647.50
Minyak Bekesting liter 0.100 9,450.00 945.00
Jumlah Harga Bahan 260,730.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 353,940.00
E Diambil Untuk 2 x pakai 176,970.00
F Overhead & Profit (10%) 10% x D 17,697.00
G Harga Satuan Pekerjaan (E+F) 194,667.00

A. 4.1.1.22 Pemasangan 1m2 bekesting untuk kolom


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang kayu OH 0.330 131,000.00 43,230.00
Kepala Tukang OH 0.033 157,000.00 5,181.00
Mandor OH 0.033 118,000.00 3,894.00
Jumlah Tenaga Kerja 118,305.00
B BAHAN
Kayu Klas III m3 0.040 5,647,500.00 225,900.00
Paku 5 - 10 cm kg 0.400 18,825.00 7,530.00
Minyak Bekesting liter 0.200 9,450.00 1,890.00
Balok Kayu Klas II m3 0.015 6,902,500.00 103,537.50
Plywood tebal 9 mm Lbr 0.350 169,425.00 59,298.75
Dolken kayu ᴓ 8 - 10 cm - panjang 4 m Batang 2.000 30,000.00 60,000.00
Jumlah Harga Bahan 458,156.25
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 576,461.25
E Diambil Untuk 2 x pakai 288,230.63
F Overhead & Profit (10%) 10% x D 28,823.06
G Harga Satuan Pekerjaan (E+F) 317,053.69
A. 4.1.1.22.a Pemasangan 1m2 bekesting untuk kolom Praktis dan Balok Praktis
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang kayu OH 0.330 131,000.00 43,230.00
Kepala Tukang OH 0.033 157,000.00 5,181.00
Mandor OH 0.033 118,000.00 3,894.00
Jumlah Tenaga Kerja 118,305.00
B BAHAN
Kayu Klas III m3 0.020 5,647,500.00 112,950.00
Paku 5 - 10 cm kg 0.200 18,825.00 3,765.00
Minyak Bekesting liter 0.200 9,450.00 1,890.00
Balok Kayu Klas II m3 0.007 6,902,500.00 48,317.50
Jumlah Harga Bahan 166,922.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 285,227.50
E Diambil Untuk 2 x pakai 142,613.75
F Overhead & Profit (10%) 10% x D 14,261.38
G Harga Satuan Pekerjaan (E+F) 156,875.13

A. 4.1.1.23 Pemasangan 1m2 bekesting untuk balok


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang kayu OH 0.330 131,000.00 43,230.00
Kepala Tukang OH 0.033 157,000.00 5,181.00
Mandor OH 0.033 118,000.00 3,894.00
Jumlah Tenaga Kerja 118,305.00
B BAHAN
Kayu Klas III m3 0.040 5,647,500.00 225,900.00
Paku 5 - 10 cm kg 0.400 18,825.00 7,530.00
Minyak Bekesting liter 0.200 9,450.00 1,890.00
Balok Kayu Klas II m3 0.018 6,902,500.00 124,245.00
Plywood tebal 9 mm Lbr 0.350 169,425.00 59,298.75
Dolken kayu ᴓ 8 - 10 cm - panjang 4 m Batang 2.000 30,000.00 60,000.00
Jumlah Harga Bahan 478,863.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 597,168.75
E Diambil Untuk 2 x pakai 298,584.38
F Overhead & Profit (10%) 10% x D 29,858.44
G Harga Satuan Pekerjaan (E+F) 328,442.81

A. 4.1.1.24 Pemasangan 1m2 bekesting untuk lantai


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang kayu OH 0.330 131,000.00 43,230.00
Kepala Tukang OH 0.033 157,000.00 5,181.00
Mandor OH 0.033 118,000.00 3,894.00
Jumlah Tenaga Kerja 118,305.00
B BAHAN
Kayu Klas III m3 0.040 5,647,500.00 225,900.00
Paku 5 - 10 cm kg 0.400 18,825.00 7,530.00
Minyak Bekesting liter 0.200 9,450.00 1,890.00
Balok Kayu Klas II m3 0.015 6,902,500.00 103,537.50
Plywood tebal 9 mm Lbr 0.350 169,425.00 59,298.75
Dolken kayu ᴓ 8 - 10 cm - panjang 4 m Batang 6.000 30,000.00 180,000.00
Jumlah Harga Bahan 578,156.25
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 696,461.25
E Diambil Untuk 2 x pakai 348,230.63
F Overhead & Profit (10%) 10% x D 34,823.06
G Harga Satuan Pekerjaan (E+F) 383,053.69
A. 4.1.1.26 Pemasangan 1m2 bekesting untuk tangga
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang kayu OH 0.330 131,000.00 43,230.00
Kepala Tukang OH 0.033 157,000.00 5,181.00
Mandor OH 0.033 118,000.00 3,894.00
Jumlah Tenaga Kerja 118,305.00
B BAHAN
Kayu Klas III m3 0.030 5,647,500.00 169,425.00
Paku 5 - 10 cm kg 0.400 18,825.00 7,530.00
Minyak Bekesting liter 0.150 9,450.00 1,417.50
Balok Kayu Klas II m3 0.010 6,902,500.00 69,025.00
Plywood tebal 9 mm Lbr 0.350 169,425.00 59,298.75
Dolken kayu ᴓ 8 - 10 cm - panjang 4 m Batang 2.000 30,000.00 60,000.00
Jumlah Harga Bahan 366,696.25
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 485,001.25
E Overhead & Profit (10%) 10% x D 48,500.13
F Harga Satuan Pekerjaan (D+E) 533,501.38

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM

A. 4.2.1.2 Memasang 1 kg besi profil


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.060 100,000.00 6,000.00
Tukang besi OH 0.060 131,000.00 7,860.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 15,156.00
B BAHAN
Besi Baja Profil kg 1.150 29,925.00 34,413.75
Jumlah Harga Bahan 34,413.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 49,569.75
E Overhead & Profit (10%) 10% x D 4,956.98
F Harga Satuan Pekerjaan (D+E) 54,526.73

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A. 4.4.1.7 Pemasangan 1 m2 dinding bata merah (5 x11x 22) cm tebal 1/2 batu campuran 1SP : 2PP
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 46,440.00
B BAHAN
Bata Merah bh 70.000 1,192.00 83,440.00
Semen Portland kg 18.950 1,631.50 30,916.93
Pasir Pasang m3 0.038 156,875.00 5,961.25
Jumlah Harga Bahan 120,318.18
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 166,758.18
E Overhead & Profit (10%) 10% x D 16,675.82
F Harga Satuan Pekerjaan (D+E) 183,433.99
A. 4.4.1.9 Pemasangan 1 m2 dinding bata merah (5 x11x 22) cm tebal 1/2 batu campuran 1SP : 4PP
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 46,440.00
B BAHAN
Bata Merah bh 70.000 1,192.00 83,440.00
Semen Portland kg 11.500 1,631.50 18,762.25
Pasir Pasang m3 0.043 156,875.00 6,745.63
Jumlah Harga Bahan 108,947.88
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 155,387.88
E Overhead & Profit (10%) 10% x D 15,538.79
F Harga Satuan Pekerjaan (D+E) 170,926.66

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A. 4.4.2.2 Pemasangan 1 m2 Plesteran 1SP : 2PP tebal 15 mm


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.150 131,000.00 19,650.00
Kepala Tukang OH 0.015 157,000.00 2,355.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 53,775.00
B BAHAN
Semen Portland kg 10.224 1,631.50 16,680.46
Pasir Pasang m3 0.020 156,875.00 3,137.50
Jumlah Harga Bahan 19,817.96
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 73,592.96
E Overhead & Profit (10%) 10% x D 7,359.30
F Harga Satuan Pekerjaan (D+E) 80,952.25

A. 4.4.2.4 Pemasangan 1 m2 Plesteran 1SP : 4PP tebal 15 mm


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang batu OH 0.150 131,000.00 19,650.00
Kepala Tukang OH 0.015 157,000.00 2,355.00
Mandor OH 0.015 118,000.00 1,770.00
Jumlah Tenaga Kerja 53,775.00
B BAHAN
Semen Portland kg 6.240 1,631.50 10,180.56
Pasir Pasang m3 0.024 156,875.00 3,765.00
Jumlah Harga Bahan 13,945.56
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 67,720.56
E Overhead & Profit (10%) 10% x D 6,772.06
F Harga Satuan Pekerjaan (D+E) 74,492.62
A. 4.4.2.27 Pemasangan 1 m2 Acian
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.200 100,000.00 20,000.00
Tukang batu OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.010 118,000.00 1,180.00
Jumlah Tenaga Kerja 35,850.00
B BAHAN
Semen Portland kg 3.250 1,631.50 5,302.38
Jumlah Harga Bahan 5,302.38
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 41,152.38
E Overhead & Profit (10%) 10% x D 4,115.24
F Harga Satuan Pekerjaan (D+E) 45,267.61

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A. 4.4.3.9 Pemasangan 1 m2 Lantai Granit ukuran 60 x 60 cm


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.250 100,000.00 25,000.00
Tukang batu OH 0.125 131,000.00 16,375.00
Kepala Tukang OH 0.013 157,000.00 2,041.00
Mandor OH 0.013 118,000.00 1,534.00
Jumlah Tenaga Kerja 44,950.00
B BAHAN
Granit 60 x 60 cm m2 1.060 326,300.00 345,878.00
Semen Portland kg 9.800 1,631.50 15,988.70
Pasir Pasang m3 0.045 156,875.00 7,059.38
Semen Warna kg 1.300 4,643.50 6,036.55
Jumlah Harga Bahan 374,962.63
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 419,912.63
E Overhead & Profit (10%) 10% x D 41,991.26
F Harga Satuan Pekerjaan (D+E) 461,903.89

A. 4.4.3.24 Pemasangan 1 m' Step Nosing Granit ukuran 10 x 60 cm


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.090 100,000.00 9,000.00
Tukang batu OH 0.090 131,000.00 11,790.00
Kepala Tukang OH 0.009 157,000.00 1,413.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 22,793.00
B BAHAN
Plint Granit 10 x 60 cm Bh 1.767 45,000.00 79,500.00
Semen Portland kg 1.140 1,631.50 1,859.91
Semen Warna kg 0.100 4,643.50 464.35
Pasir Pasang m3 0.003 156,875.00 470.63
Jumlah Harga Bahan 82,294.89
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 105,087.89
E Overhead & Profit (10%) 10% x D 10,508.79
F Harga Satuan Pekerjaan (D+E) 115,596.67
A. 4.4.3.54b Pemasangan 1 m2 Dinding Keramik ukuran 30 x 60 cm
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.900 100,000.00 90,000.00
Tukang batu OH 0.450 131,000.00 58,950.00
Kepala Tukang OH 0.045 157,000.00 7,065.00
Mandor OH 0.045 118,000.00 5,310.00
Jumlah Tenaga Kerja 161,325.00
B BAHAN
Keramik 30 x 60 cm m2 1.060 155,000.00 164,300.00
Semen Portland kg 9.300 1,631.50 15,172.95
Pasir Pasang m3 0.018 156,875.00 2,823.75
Semen Warna kg 1.940 4,643.50 9,008.39
Jumlah Harga Bahan 191,305.09
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 352,630.09
E Overhead & Profit (10%) 10% x D 35,263.01
F Harga Satuan Pekerjaan (D+E) 387,893.10

A.4.5.1. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A. 4.5.1.7 Pemasangan 1 m2 Langit-langit Gypsum Board ukuran (120 x 240) cm, tebal 9 mm
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang Kayu OH 0.050 131,000.00 6,550.00
Kepala Tukang OH 0.005 157,000.00 785.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 17,925.00
B BAHAN
Gypsum Board Lembar 0.364 200,800.00 73,091.20
Paku Skrup kg 0.110 31,500.00 3,465.00
Jumlah Harga Bahan 76,556.20
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 94,481.20
E Overhead & Profit (10%) 10% x D 9,448.12
F Harga Satuan Pekerjaan (D+E) 103,929.32

A. 4.5.1.9 Pemasangan 1 m' List Langit-langit Gypsum


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.050 100,000.00 5,000.00
Tukang Kayu OH 0.050 131,000.00 6,550.00
Kepala Tukang OH 0.005 157,000.00 785.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 12,689.00
B BAHAN
List Profil Gypsum m' 1.050 16,315.00 17,130.75
Paku Skrup kg 0.010 31,500.00 315.00
Jumlah Harga Bahan 17,445.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 30,134.75
E Overhead & Profit (10%) 10% x D 3,013.48
F Harga Satuan Pekerjaan (D+E) 33,148.23
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

A. 4.5.2.38 Pemasangan 1 m2 Atap Seng Spandek


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.120 100,000.00 12,000.00
Tukang Kayu OH 0.060 131,000.00 7,860.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.006 118,000.00 708.00
Jumlah Tenaga Kerja 21,510.00
B BAHAN
Seng Spandek m2 1.100 78,000.00 85,800.00
Paku Seng kg 0.200 25,100.00 5,020.00
Jumlah Harga Bahan 90,820.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 112,330.00
E Overhead & Profit (10%) 10% x D 11,233.00
F Harga Satuan Pekerjaan (D+E) 123,563.00

A. 4.5.2.39 Pemasangan 1 m' Nok Atap Seng Spandek


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.150 100,000.00 15,000.00
Tukang Kayu OH 0.070 131,000.00 9,170.00
Kepala Tukang OH 0.007 157,000.00 1,099.00
Mandor OH 0.006 118,000.00 708.00
Jumlah Tenaga Kerja 25,977.00
B BAHAN
Nok seng Spandek m 1.100 42,500.00 46,750.00
Paku Seng kg 0.100 25,100.00 2,510.00
Jumlah Harga Bahan 49,260.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 75,237.00
E Overhead & Profit (10%) 10% x D 7,523.70
F Harga Satuan Pekerjaan (D+E) 82,760.70

A. 4.5.2.40 1 m' Pasang talang datar/ jurai seng


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.200 100,000.00 20,000.00
Tukang Kayu OH 0.400 131,000.00 52,400.00
Kepala Tukang OH 0.250 157,000.00 39,250.00
Mandor OH 0.010 118,000.00 1,180.00
Jumlah Tenaga Kerja 112,830.00
B BAHAN
Seng Plat Lbr 0.375 42,500.00 15,937.50
Papan Kayu m3 0.002 8,157,500.00 15,499.25
Paku Seng Kg 0.285 25,100.00 7,153.50
Jumlah Harga Bahan 38,590.25
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 151,420.25
E Overhead & Profit (10%) 45 10% x D 15,142.03
F Harga Satuan Pekerjaan (D+E) 166,562.28
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU

A. 4.6.1.21 Pemasangan 1 m' Listplank ukuran (3 x 20) cm, Kayu Klas II


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang Kayu OH 0.200 131,000.00 26,200.00
Kepala Tukang OH 0.020 157,000.00 3,140.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 39,930.00
B BAHAN
Papan Kayu m3 0.011 8,157,500.00 88,101.00
Paku 5 dan 7 cm kg 0.100 18,825.00 1,882.50
Jumlah Harga Bahan 89,983.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 129,913.50
E Overhead & Profit (10%) 10% x D 12,991.35
F Harga Satuan Pekerjaan (D+E) 142,904.85

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN

A. 4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.070 100,000.00 7,000.00
Tukang Cat OH 0.009 131,000.00 1,179.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,475.00
B BAHAN
Cat Menie kg 0.200 81,575.00 16,315.00
Plamur kg 0.150 27,610.00 4,141.50
Cat Dasar kg 0.170 52,710.00 8,960.70
Cat Penutup kg 0.260 175,700.00 45,682.00
Kuas Bh 0.010 31,375.00 313.75
Pengencer/Thinner kg 0.030 31,375.00 941.25
Amplas Lbr 0.200 12,550.00 2,510.00
Jumlah Harga Bahan 78,864.20
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 88,339.20
E Overhead & Profit (10%) 10% x D 8,833.92
F Harga Satuan Pekerjaan (D+E) 97,173.12

A. 4.7.1.8 Pelaburan 1 m2 bidang kayu dengan cat residu dan Ter


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Mandor OH 0.006 118,000.00 708.00
Jumlah Tenaga Kerja 10,708.00
B BAHAN
Residu atau ter Liter 0.350 9,450.00 3,307.50
Jumlah Harga Bahan 3,307.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 14,015.50
E Overhead & Profit (10%) 10% x D 1,401.55
F Harga Satuan Pekerjaan (D+E) 15,417.05
A. 4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.020 100,000.00 2,000.00
Tukang Cat OH 0.063 131,000.00 8,253.00
Kepala Tukang OH 0.0063 157,000.00 989.10
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 11,596.10
B BAHAN
Plamur kg 0.100 27,610.00 2,761.00
Cat Dasar kg 0.100 52,710.00 5,271.00
Cat Penutup kg 0.260 175,700.00 45,682.00
Jumlah Harga Bahan 53,714.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 65,310.10
E Overhead & Profit (10%) 10% x D 6,531.01
F Harga Satuan Pekerjaan (D+E) 71,841.11

A. 4.7.1.12 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.028 100,000.00 2,800.00
Tukang Cat OH 0.042 131,000.00 5,502.00
Kepala Tukang OH 0.0042 157,000.00 659.40
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 9,315.40
B BAHAN
Cat Dasar kg 0.120 52,710.00 6,325.20
Cat Penutup kg 0.180 175,700.00 31,626.00
Jumlah Harga Bahan 37,951.20
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 47,266.60
E Overhead & Profit (10%) 10% x D 4,726.66
F Harga Satuan Pekerjaan (D+E) 51,993.26

A. 4.7.1.18 Pengecatan 1 m2 Permukaan baja 4 lapis


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.250 100,000.00 25,000.00
Tukang Cat OH 0.250 131,000.00 32,750.00
Kepala Tukang OH 0.025 157,000.00 3,925.00
Mandor OH 0.0013 118,000.00 153.40
Jumlah Tenaga Kerja 61,828.40
B BAHAN
Cat Menie kg 0.200 81,575.00 16,315.00
Cat Penutup kg 0.160 81,575.00 13,052.00
Kuas Bh 0.010 31,375.00 313.75
Pengencer Ltr 0.010 31,375.00 313.75
Jumlah Harga Bahan 29,994.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 91,822.90
E Overhead & Profit (10%) 10% x D 9,182.29
F Harga Satuan Pekerjaan (D+E) 101,005.19
A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A. 5.1.1.1 Pemasangan 1 buah Kloset Duduk


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 3.300 100,000.00 330,000.00
Tukang OH 1.100 131,000.00 144,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.160 118,000.00 18,880.00
Jumlah Tenaga Kerja 494,550.00
B BAHAN
Kloset Duduk Bh 1.000 4,000,000.00 4,000,000.00
Perlengkapan 6% x Kloset Ls 1.000 240,000.00 240,000.00
Jumlah Harga Bahan 4,240,000.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 4,734,550.00
E Overhead & Profit (10%) 10% x D 473,455.00
F Harga Satuan Pekerjaan (D+E) 5,208,005.00

A. 5.1.1.5 Pemasangan 1 buah Wastafel


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.200 100,000.00 120,000.00
Tukang OH 1.450 131,000.00 189,950.00
Kepala Tukang OH 0.150 157,000.00 23,550.00
Mandor OH 0.060 118,000.00 7,080.00
Jumlah Tenaga Kerja 340,580.00
B BAHAN
Wastafel Unit 1.000 1,250,000.00 1,250,000.00
Semen Portland Kg 6.000 1,631.50 9,789.00
Pasir Pasang M3 0.010 156,875.00 1,568.75
Perlengkapan 12% x Wastafel Ls 1.000 150,000.00 150,000.00
Jumlah Harga Bahan 1,411,357.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,751,937.75
E Overhead & Profit (10%) 10% x D 175,193.78
F Harga Satuan Pekerjaan (D+E) 1,927,131.53

A. 5.1.1.6 Pemasangan 1 buah Shower Mandi


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 1.200 100,000.00 120,000.00
Tukang OH 1.450 131,000.00 189,950.00
Kepala Tukang OH 0.150 157,000.00 23,550.00
Mandor OH 0.060 118,000.00 7,080.00
Jumlah Tenaga Kerja 340,580.00
B BAHAN
Shower Mandi Unit 1.000 475,000.00 475,000.00
Semen Portland Kg 6.000 1,631.50 9,789.00
Pasir Pasang M3 0.010 156,875.00 1,568.75
Perlengkapan 12% x Shower Mandi Ls 1.000 57,000.00 57,000.00
Jumlah Harga Bahan 543,357.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 883,937.75
E Overhead & Profit (10%) 10% x D 88,393.78
F Harga Satuan Pekerjaan (D+E) 972,331.53
A. 5.1.1.19 Pemasangan Kran Air 1/2" atau 3/4"
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.010 100,000.00 1,000.00
Tukang OH 0.400 131,000.00 52,400.00
Kepala Tukang OH 0.040 157,000.00 6,280.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 60,270.00
B BAHAN
Kran Air Bh 1.000 45,000.00 45,000.00
Sealtape Bh 0.025 4,000.00 100.00
Jumlah Harga Bahan 45,100.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 105,370.00
E Overhead & Profit (10%) 10% x D 10,537.00
F Harga Satuan Pekerjaan (D+E) 115,907.00

A. 5.1.1.14 1 Bh Pemasangan Floordrain


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.010 100,000.00 1,000.00
Tukang OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 16,260.00
B BAHAN
Floor Drain Bh 1.000 55,000.00 55,000.00
0.00
Jumlah Harga Bahan 55,000.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 71,260.00
E Overhead & Profit (10%) 10% x D 7,126.00
F Harga Satuan Pekerjaan (D+E) 78,386.00

A. 5.1.1.15 1 Bh Pemasangan Roof drain


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.010 100,000.00 1,000.00
Tukang OH 0.100 131,000.00 13,100.00
Kepala Tukang OH 0.010 157,000.00 1,570.00
Mandor OH 0.005 118,000.00 590.00
Jumlah Tenaga Kerja 16,260.00
B BAHAN
Roof Drain Bh 1.000 60,000.00 60,000.00
0.00
Jumlah Harga Bahan 60,000.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 76,260.00
E Overhead & Profit (10%) 10% x D 7,626.00
F Harga Satuan Pekerjaan (D+E) 83,886.00
A. 5.1.1.25 Pemasangan Pipa PVC Tipe AW Diameter 1/2"
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.036 100,000.00 3,600.00
Tukang Pipa OH 0.060 131,000.00 7,860.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.002 118,000.00 236.00
Jumlah Tenaga Kerja 12,638.00
B BAHAN
Pipa PVC 1/2" M 1.200 7,600.00 9,120.00
Perlengkapan 35% x Pipa Ls 1.000 2,660.00 2,660.00
Jumlah Harga Bahan 11,780.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 24,418.00
E Overhead & Profit (10%) 10% x D 2,441.80
F Harga Satuan Pekerjaan (D+E) 26,859.80

A. 5.1.1.26 Pemasangan Pipa PVC Tipe AW Diameter 3/4"


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.036 100,000.00 3,600.00
Tukang Pipa OH 0.060 131,000.00 7,860.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.002 118,000.00 236.00
Jumlah Tenaga Kerja 12,638.00
B BAHAN
Pipa PVC 3/4" M 1.200 9,100.00 10,920.00
Perlengkapan 35% x Pipa Ls 1.000 3,185.00 3,185.00
Jumlah Harga Bahan 14,105.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 26,743.00
E Overhead & Profit (10%) 10% x D 2,674.30
F Harga Satuan Pekerjaan (D+E) 29,417.30

A. 5.1.1.27 Pemasangan Pipa PVC Tipe AW Diameter 1"


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.036 100,000.00 3,600.00
Tukang Pipa OH 0.060 131,000.00 7,860.00
Kepala Tukang OH 0.006 157,000.00 942.00
Mandor OH 0.002 118,000.00 236.00
Jumlah Tenaga Kerja 12,638.00
B BAHAN
Pipa PVC 1" M 1.200 12,600.00 15,120.00
Perlengkapan 35% x Pipa Ls 1.000 4,410.00 4,410.00
Jumlah Harga Bahan 19,530.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 32,168.00
E Overhead & Profit (10%) 10% x D 3,216.80
F Harga Satuan Pekerjaan (D+E) 35,384.80
A. 5.1.1.29 Pemasangan Pipa PVC Tipe AW Diameter 2"
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.054 100,000.00 5,400.00
Tukang Pipa OH 0.090 131,000.00 11,790.00
Kepala Tukang OH 0.009 157,000.00 1,413.00
Mandor OH 0.003 118,000.00 354.00
Jumlah Tenaga Kerja 18,957.00
B BAHAN
Pipa PVC 2" M 1.200 19,000.00 22,800.00
Perlengkapan 35% x Pipa Ls 1.000 6,650.00 6,650.00
Jumlah Harga Bahan 29,450.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 48,407.00
E Overhead & Profit (10%) 10% x D 4,840.70
F Harga Satuan Pekerjaan (D+E) 53,247.70

A. 5.1.1.31 Pemasangan Pipa PVC Tipe AW Diameter 3"


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.081 100,000.00 8,100.00
Tukang Pipa OH 0.135 131,000.00 17,685.00
Kepala Tukang OH 0.0135 157,000.00 2,119.50
Mandor OH 0.004 118,000.00 472.00
Jumlah Tenaga Kerja 28,376.50
B BAHAN
Pipa PVC 3" M 1.200 42,000.00 50,400.00
Perlengkapan 35% x Pipa Ls 1.000 14,700.00 14,700.00
Jumlah Harga Bahan 65,100.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 93,476.50
E Overhead & Profit (10%) 10% x D 9,347.65
F Harga Satuan Pekerjaan (D+E) 102,824.15

A. 5.1.1.32 Pemasangan Pipa PVC Tipe AW Diameter 4"


No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.081 100,000.00 8,100.00
Tukang Pipa OH 0.135 131,000.00 17,685.00
Kepala Tukang OH 0.0135 157,000.00 2,119.50
Mandor OH 0.004 118,000.00 472.00
Jumlah Tenaga Kerja 28,376.50
B BAHAN
Pipa PVC 4" M 1.200 51,000.00 61,200.00
Perlengkapan 35% x Pipa Ls 1.000 17,850.00 17,850.00
Jumlah Harga Bahan 79,050.00
C PERALATAN

Jumlah Harga Alat 0.00


D Jumlah (A + B + C) 107,426.50
E Overhead & Profit (10%) 10% x D 10,742.65
F Harga Satuan Pekerjaan (D+E) 118,169.15