DAFTAR HARGA BAHAN KONSTRUKSI DAN UPAH

DALAM WILAYAH KOTA PALOPO TAHUN 2015

No. URAIAN Satuan Harga Satuan (Rp)


A TENAGA
1 Pekerja OH 80,000.00
2 Tukang Kayu OH 110,000.00
3 Tukang Batu OH 110,000.00
4 Tukang khusus Aluminium OH 110,000.00
5 Tukang Kaca OH 110,000.00
6 Kepala Tukang OH 120,000.00
7 Mandor OH 110,000.00

B BAHAN
1 Semen Portland Kg 1,337.50
2 Pasir Beton M3 224,700.00
3 Kerikil Kg 535,000.00
4 Air Ltr 30.00
5 Batu Bata Bh 700.00
6 Kayu kelas II (Jenis bitti),Balok M3 3,766,400.00
7 Kayu kelas II (Jenis bitti),Papan M3 3,766,400.00
8 Profil Aluminium M 145,000.00
9 Sekrup Fixer Bh 5,200.00
10 Sealant Tube 16,445.00
11 Profil Kaca M 165,000.00
12 Ubin Keramik 30x30 cm (puitih) Bh 4,863.64
13 Ubin Keramik 30x30 cm(warna) Bh 6,027.27
14 kuku Keramik Polos, 10 cm Bh 700.00
15 Pasir Pasang M3 203,300.00
16 Semen Warna Kg 11,800.00
17 Asbes Semen M2 21,835.53
18
19 Paku Tripleks Kg 26,800.00
20 Kayu Klas III (Balok) M3 3,766,400.00
21 Paku 7 - 10 cm Kg 18,200.00
22 Kunci tanam biasa Bh 74,900.00
23 Kunci silinder Bh 82,400.00
24 Gerendel Bh 10,700.00
25 Engsel Pintu Bh 26,800.00
26 Kaca tebal 5 mm M2 88,148.35
27 Pipa PVC (class AW ), Ø3/4" Btg 28,900.00
28 Kran air AMICO, Uk. Ø3/4" Bh 25,000.00
29 Seal tape Bh 6,500.00
30 Kabel NYM eterna, Uk.2x1.5 mm m 5,885.00
31 Kabel NYM eterna, Uk.3x2.5 mm m 11,770.00
32 Pipa union untuk Kabel Ø5/8" Btg 8,600.00
33 Saklar Tunggal Bh 15,000.00
34 Saklar Ganda Bh 17,100.00
35 Stop Kontak Bh 16,100.00
36 Fitting Bh 16,100.00
37 Lampu 18 wat Bh 34,100.00
38 Isolasi Bh 8,200.00
39 Soda Api Kg 10,000.00
40 Sabun Kg 2,500.00
41 Cat menie Kg 20,900.00
42 Plamur Kg 9,640.00
43 Cat Dasar Kg 20,120.00
44 Cat Penutup Kg 20,120.00
45 Cat Kayu Kg 59,900.00
46 Kuas Bh 6,400.00
47 Pengencer Ltr 10,700.00
48 Ampelas Lbr 4,300.00
49 Teak Oil Ltr 7,500.00
50 Politur Ltr 58,900.00
51 Politur Jadi Ltr 58,900.00
52 Exhaust Fan Type Axial Bh 374,000.00
53 Turbin Ventilator Bh 975,000.00
ANALISA BIAYA KONSTRUKSI

A.2.2.1.4 Pengukuran dan pemasangan 1 m' Bowplank

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 0.100 113,000.00
Tukang batu L.02 OH 0.100 141,000.00
Kepala Tukang L.03 OH 0.010 153,000.00
Mandor L.04 OH 0.005 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Kayu Balok 5/7 cm m3 0.012 2,000,000.00
Paku 2" - 3" Kg 0.020 20,000.00
Kayu Papan 3/20 cm m3 0.007 2,000,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )

A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 0.750 113,000.00
Mandor L.04 OH 0.025 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )
A.2.3.1.9 Pengurugan Kembali 1 m3 galian tanah
Galian di hitung dari 1/3 dari koefisien pekerjaan galian
Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 0.50 113,000.00
Mandor L.04 OH 0.05 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 0.300 113,000.00
Mandor L.04 OH 0.010 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan
1 Pasir urug m3 1.200 160,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )
A.3.2.1.9 Pamasangan 1 m3 batu kosong (anstamping)

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 0.780 113,000.00
Tukang batu L.02 OH 0.390 141,000.00
Kepala Tukang L.03 OH 0.039 153,000.00
Mandor L.04 OH 0.039 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Batu kali m3 1.200 320,000.00
Pasir urug m 3
0.432 160,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )

A.3.2.1.2 Pamasangan 1 m3 pondasi batu kali camp. 1 SP : 4 PP

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
Pekerja L.01 OH 1.500 113,000.00
Tukang batu L.02 OH 0.750 141,000.00
Kepala Tukang L.03 OH 0.075 153,000.00
Mandor L.04 OH 0.075 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan
Batu kali m3 1.200 320,000.00
Pasir pasang m 3
0.520 225,000.00
Portland semen Kg 163.000 1,175.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m3 ( D+E )
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk Sloof

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A Tenaga Kerja
1 Pekerja L.01 OH 0.520 113,000.00
2 Tukang kayu L.02 OH 0.260 141,000.00
3 Kepala Tukang L.03 OH 0.026 153,000.00
4 Mandor L.04 OH 0.026 176,000.00
Jumlah Harga Tenaga Kerja
B Bahan
1 Kayu kelas III m3 0.045 2,000,000.00
2 Paku 5 - 10 cm Kg 0.300 20,000.00
3 Minyak bekisting Ltr 0.100 24,000.00
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per-m2 ( D+E )

A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.660 113,000.00
Tukang kayu L.02 OH 0.330 141,000.00
Kepala Tukang L.03 OH 0.033 153,000.00
Mandor L.04 OH 0.033 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Kayu kelas III m3 0.040 2,000,000.00
Paku 5 cm - 12 cm Kg 0.400 20,000.00
Minyak bekisting Ltr 0.200 24,000.00
Balok kayu kelas III m3 0.015 2,000,000.00
Plywood tebal 3 mm Lbr 0.350 50,000.00
Dolken kayu Btg 2.000 30,000.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )
A.A.4.1.1.5 Membuat 1 m3 beton mutu, f'c = 14,5 Mpa ( K175 ), slump (12 ± 2) cm, w/c = 0,66

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 1.650 113,000.00
Tukang batu L.02 OH 0.275 141,000.00
Kepala Tukang L.03 OH 0.028 153,000.00
Mandor L.04 OH 0.083 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Portland semen Kg 326.000 1,175.00
Pasir m3 0.543 225,000.000
Batu Pecah 2-3 cm m3 0.762 300,000.00
Air Ltr 215.000 2.50
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m3 ( D+E )

A.4.1.1.17 Pembesian 1 kg dengan besi polos atau ulir

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.007 113,000.00
Tukang besi L.02 OH 0.007 141,000.00
Kepala Tukang L.03 OH 0.0007 153,000.00
Mandor L.04 OH 0.0004 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Besi Beton Polos Kg 1.050 5,664.58
Kawat Ikat Kg 0.015 20,750.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 kg ( D+E )
A.4.4.1.8 Pamasangan 1 m2 dinding bata merah tebal 1/2 batu camp. 1 SP : 3 PP

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.300 113,000.00
Tukang batu L.02 OH 0.100 141,000.00
Kepala Tukang L.03 OH 0.010 153,000.00
Mandor L.04 OH 0.015 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Bata merah Bh 70.000 1,000.00
Pasir pasang m3 0.040 225,000.000
Portland semen Kg 14.370 1,175.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )

A.4.4.2.3 Pemasangan 1 m2 Plesteran campuran 1 SP : 3 PP Tebal 15 Mm

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.300 113,000.00
Tukang batu L.02 OH 0.150 141,000.00
Kepala Tukang L.03 OH 0.015 153,000.00
Mandor L.04 OH 0.015 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Pasir pasang m3 0.023 225,000.000
Portland semen Kg 7.776 1,175.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )
A.4.4.2.20 Pemasangan 1 m' Plesteran Skoning campuran 1 SP : 3 PP lebar 10 cm

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.080 113,000.00
Tukang batu L.02 OH 0.400 141,000.00
Kepala Tukang L.03 OH 0.040 153,000.00
Mandor L.04 OH 0.004 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Pasir pasang m3 0.013 225,000.000
Portland semen Kg 0.500 1,175.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m' ( D+E )

A.4.4.2.27 Pemasangan 1 m2 acian dinding

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.200 113,000.00
Tukang batu L.02 OH 0.100 141,000.00
Kepala Tukang L.03 OH 0.010 153,000.00
Mandor L.04 OH 0.010 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Portland semen Kg 3.25 1,175.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )
A.4.4.3.57 Pamasangan 1 m2 dinding batu paras / batu alam

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.700 113,000.00
Tukang batu L.02 OH 0.350 141,000.00
Kepala Tukang L.03 OH 0.035 153,000.00
Mandor L.04 OH 0.035 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Batu Paras / Batu Alam Bh 1.100 105,000.00
Semen Portlan Kg 11.750 1,175.00
Pasir Pasang m3 0.035 225,000.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )

A.4.7.1.10 Pengecatan 1 m2 bidang tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Satuan
No Uraian Kode Satuan Koefisien
( Rp. )
A TENAGA
Pekerja L.01 OH 0.020 113,000.00
Tukang Cat L.02 OH 0.063 141,000.00
Kepala Tukang L.03 OH 0.0063 153,000.00
Mandor L.04 OH 0.003 176,000.00
Jumlah Harga Tenaga Kerja
B BAHAN
Plamur Kg 0.100 9,000.00
Cat dasar Kg 0.100 13,000.00
Cat penutup Kg 0.260 104,000.00
Jumlah Harga Bahan
C PERALATAN

Jumlah Harga Peralatan


D Jumlah Harga Tenaga, Bahan dan Peralatan ( A+B+C )
E Overhead + Profit ( 10% )
F Harga Satuan Pekerjaan Per - 1 m2 ( D+E )
LISA BIAYA KONSTRUKSI

Jumlah
( Rp. )

11,300.00
14,100.00
1,530.00
880.00
27,810.00

24,000.00
400.00
14,000.00
38,400.00

66,210.00
6,621.00
72,831.00

Jumlah
( Rp. )

84,750.00
4,400.00
89,150.00

89,150.00
8,915.00
98,065.00
Jumlah
( Rp. )

56,500.00
8,800.00
65,300.00

65,300.00
6,530.00
71,830.00

Jumlah
( Rp. )

33,900.00
1,760.00
35,660.00

192,000.00
192,000.00

-
227,660.00
22,766.00
250,426.00
Jumlah
( Rp. )

88,140.00
54,990.00
5,967.00
6,864.00
155,961.00

384,000.00
69,120.00
453,120.00

-
609,081.00
60,908.10
669,989.10

Jumlah
( Rp. )

169,500.00
105,750.00
11,475.00
13,200.00
299,925.00

384,000.00
117,000.00
191,525.00
692,525.00

-
992,450.00
99,245.00
1,091,695.00
Jumlah
( Rp. )

58,760.00
36,660.00
3,978.00
4,576.00
103,974.00

90,000.00
6,000.00
2,400.00
98,400.00

202,374.00
20,237.40
222,611.40

Jumlah
( Rp. )

74,580.00
46,530.00
5,049.00
5,808.00
131,967.00

80,000.00
8,000.00
4,800.00
30,000.00
17,500.00
60,000.00
200,300.00
332,267.00
33,226.70
365,493.70
Jumlah
( Rp. )

186,450.00
38,775.00
4,284.00
14,608.00
244,117.00

383,050.00
122,175.00
228,600.00
537.50
734,362.50

-
978,479.50
97,847.95
1,076,327.45

Jumlah
( Rp. )

791.00
987.00
107.10
70.40
1,955.50

5,947.81
311.25
6,259.06

8,214.56
821.46
9,036.02
Jumlah
( Rp. )

33,900.00
14,100.00
1,530.00
2,640.00
52,170.00

70,000.00
9,000.00
16,884.75
95,884.75

-
148,054.75
14,805.48
162,860.23

Jumlah
( Rp. )

33,900.00
21,150.00
2,295.00
2,640.00
59,985.00

5,175.00
9,136.80
14,311.80

74,296.80
7,429.68
81,726.48
Jumlah
( Rp. )

9,040.00
56,400.00
6,120.00
704.00
72,264.00

2,925.00
587.50
3,512.50

75,776.50
7,577.65
83,354.15

Jumlah
( Rp. )

22,600.00
14,100.00
1,530.00
1,760.00
39,990.00

3,818.75
3,818.75

43,808.75
4,380.88
48,189.63
Jumlah
( Rp. )

79,100.00
49,350.00
5,355.00
6,160.00
139,965.00

115,500.00
13,806.25
7,875.00
137,181.25

-
277,146.25
27,714.63
304,860.88

Jumlah
( Rp. )

2,260.00
8,883.00
963.90
528.00
12,634.90

900.00
1,300.00
27,040.00
29,240.00

-
41,874.90
4,187.49
46,062.39
I. PEKERJAAN PAGAR
A. PEKERJAAN TANAH DAN PONDASI
1. TANAH
a. Galian Tanah b. Urugan Pasir di Bawah Pondasi c. Timbunan Tanah
P = 57.64 m P = 57.64 m P = 57.64 m
l = 0.55 m l = 0.55 m la = 0.10 m
t = 0.60 m t = 0.05 m lb = 0.70 m
t = 0.20 m
V = P x l x t V = P x l x t
= 19.021 m3 = 1.585 m3 V = P x la x t
= 4.611 m3

d. Urugan Tanah Kembali = 0.8646 m3

2. PONDASI
a. Pasangan Batu Kosong b. Pasangan Pondasi
P = 57.64 m P = 57.64 m
l = 0.55 m la = 0.30 m
t = 0.20 m lb = 0.50 m
t = 0.60 m
V = P x l x t
= 6.340 m3 V = ( la + lb ) / 2 x P x t
= 13.834 m3

B. PEKERJAAN BETON BERTULANG


1. SLOOF
a. Beton b. Bekisting
P = 57.64 m P = 57.64 m
l = 0.20 m l = 0.50 m
t = 0.25 m

V = P x l x t L = P x l
= 2.882 m3 = 28.820 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Jt = 4 bh
P = 57.64 m

Pt = ( P x Jt )
= ( 57.64 x 4 )
= 230.56 m

Jbt = Pt /12 = 230.56 / 12 = 19.21 btg

Vb = G x Jb = 10.65 x 19.21 = 204.59 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 385 bh
P = 0.74 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt


= { 0.74 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 385
= 335.72 m

Jbt = Pt /12 = 335.72 / 12 = 27.98 btg

Vb = G x Jb = 2.66 x 27.98 = 74.427 kg

2. KOLOM
KOLOM (20/20) cm
a. Beton b. Bekisting
T = 1.68 m P = 1.68 m
l = 0.20 m l = 0.80 m
t = 0.20 m J = 12 bh
J = 12 bh

V = T x l x t x J L = P x l x J
= 0.806 m3 = 16.13 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Pb7 = 0.095 m
Jb = 8 bh
Jt = 4 bh
P = 1.68 m

Pt = ( P x Jt ) x Jumlah Kolom
= ( 1.68 x 4 ) x 12
= 80.64 m

Jbt = Pt /12 = 80.64 / 12 = 6.72 btg

Vb = G x Jb = 10.65 x 6.72 = 71.568 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 12 bh
P = 0.64 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt x Jumlah Kolom


= { 0.64 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 12 x 12
= 111.17 m

Jbt = Pt /12 = 111.17 / 12 = 9.26 btg

Vb = G x Jb = 2.66 x 9.26 = 24.632 kg

KOLOM (20/20) cm
a. Beton b. Bekisting
T = 1.88 m P = 1.88 m
l = 0.20 m l = 0.80 m
t = 0.20 m J = 3 bh
J = 3 bh

V = T x l x t x J L = P x l x J
= 0.226 m3 = 4.51 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Pb7 = 0.095 m
Jb = 8 bh
Jt = 4 bh
P = 1.88 m

Pt = ( P x Jt ) x Jumlah Kolom
= ( 1.88 x 4 ) x 3
= 22.56 m

Jbt = Pt /12 = 22.56 / 12 = 1.88 btg

Vb = G x Jb = 10.65 x 1.88 = 20.022 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 13 bh
P = 0.64 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt x Jumlah Kolom


= { 0.64 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 13 x 3
= 30.11 m

Jbt = Pt /12 = 30.11 / 12 = 2.51 btg

Vb = G x Jb = 2.66 x 2.51 = 6.6766 kg

3. RINGBALK
a. Beton b. Bekisting
P = 57.64 m P = 57.64 m
l = 0.12 m l = 0.24 m
t = 0.12 m

V = P x l x t L = P x l
= 0.830 m3 = 13.834 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Jt = 4 bh
P = 57.64 m

Pt = ( P x Jt )
= ( 57.64 x 4 )
= 230.56 m
Jbt = Pt /12 = 230.56 / 12 = 19.21 btg

Vb = G x Jb = 10.65 x 19.21 = 204.6 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 385 bh
P = 0.32 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt


= { 0.32 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 385
= 174.02 m

Jbt = Pt /12 = 174.02 / 12 = 14.50 btg

Vb = G x Jb = 2.66 x 14.50 = 38.57 kg

C. PEKERJAAN PASANGAN BATU BATA, PLESTERAN DAN ACIAN


1. PASANGAN BATU BATA
a. Pasangan Batu Bata 1/2 Bata
Tinggi = 1.68 m Tinggi = 2.05 m Lubang
P = 52.84 m l = 0.80 m t = 0.60 m
JK = 12 bh l = 0.16 m
JL = 50 bh
La1 = P x t La2 = l x t x JK
= 88.77 m2 = 19.68 m2 Lbg = l x t x JL
= 4.80 m2

b. Pasangan Batu Bata 1/2 Bata Dinding Kolam Bagian Depan


Tinggi = 1.80 m
P = 11.50 m

Lb1 = P x t
= 20.70 m2

c. Pasangan Batu Bata 1/2 Bata Dinding Samping Pos jaga


Tinggi = 1.88 m
P = 7.30 m
Lc1 = P x t
= 13.72 m2

Total Luas Pekerjaan Pasangan Batu Bata 1/2 Batu


La = ( La1 + La2 + Lb1 + Lc1 ) - Lbg
= 138.07 m2

2. PLESTERAN
a. Plesteran Biasa
Tinggi = 2.05 m Tinggi = 2.05 m Pleteran Pada Roster/Lubang Pagar
L = 0.90 m P = 57.64 m l = 0.16 m t = 0.15
JK = 12 bh T = 0.60 m JL = 50

L1 = L x t x JK L2 = P x t x 2 sisi L5 = l x t x T x JL
= 22.14 m2 = 236.32 m2 = 11.40 m2

P = 0.40 m l = 0.15 m P = 15.10 m


l = 0.30 m P = 52.84 m t = 0.15 m
JK = 12 bh

L3 = P x l x JK L4 = P x l L6 = P x t
= 1.44 m2 = 7.93 m2 = 2.27 m2

P = 26.60 m P = 7.30 m
t = 0.20 m t = 2.00 m

L7 = P x t L8 = P x t x 2 sisi
= 5.32 m2 = 29.20 m2

Total Luas Pekerjaan Plesteran Biasa


Lt = L1 + L2 + L3 + L4 + L5 + L6 + L7 + L8
= 316.02 m2

b. Plesteran Skoning / Profil


P = 275.53 m'

3. ACIAN DINDING
Luas Acian Dinding = Luas Plestean = 316.02 m2

D. PEKERJAAN BESI
1. PINTU PAGAR BESI HOLLOW
P = 9.30 m
l = 1.80 m
L = P x l
= 16.74 m2

E. PEKERJAAN PEMASANGAN BATU ALAM


a. Pemasangan Batu Alam Pada Kolom Pagar c. Pemasangan Batu Alam Pada Dinding Pagar
T = 1.70 m P = 3.50 m
l = 0.20 m l = 1.40 m
JK = 12 bh

L1 = T x l x JK x 1 sisi L3 = P x l
= 4.08 m2 = 4.90 m2

b. Pemasangan Batu Alam Pada Dinding Pagar


P = 52.84 m
l = 0.30 m
Total Luas Pekerjaan Pasangan Batu Alam
L2 = P x l x 1 sisi La = { ( L1 + L2 + L3 ) - Lbg }
= 15.85 m2 = 20.03 m2

F. PENGECATAN DINDING PAGAR


1. Luas Pengecatan Pagar = Luas Acian Dinding = 300.17 m2
m
bh
I. PEKERJAAN PAGAR
A. PEKERJAAN TANAH DAN PONDASI
1. TANAH
a. Galian Tanah b. Urugan Pasir di Bawah Pondasi c. Timbunan Tanah
P = 7.50 m P = 7.50 m P = 7.50 m
l = 0.55 m l = 0.55 m la = 0.10 m
t = 0.60 m t = 0.05 m lb = 0.70 m
t = 0.20 m
V = P x l x t V = P x l x t
= 2.475 m3 = 0.206 m3 V = P x la x t
= 0.600 m3

d. Urugan Tanah Kembali = 0.1125 m3

2. PONDASI
a. Pasangan Batu Kosong b. Pasangan Pondasi
P = 7.50 m P = 7.50 m
l = 0.55 m la = 0.30 m
t = 0.20 m lb = 0.50 m
t = 0.60 m
V = P x l x t
= 0.825 m3 V = ( la + lb ) / 2 x P x t
= 1.800 m3

B. PEKERJAAN BETON BERTULANG


1. SLOOF
a. Beton b. Bekisting
P = 7.50 m P = 7.50 m
l = 0.20 m l = 0.50 m
t = 0.25 m

V = P x l x t L = P x l
= 0.375 m3 = 3.750 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Jt = 4 bh
P = 7.50 m

Pt = ( P x Jt )
= ( 7.50 x 4 )
= 30.00 m

Jbt = Pt /12 = 30.00 / 12 = 2.50 btg

Vb = G x Jb = 10.65 x 2.50 = 26.625 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 50 bh
P = 0.74 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt


= { 0.74 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 50
= 43.60 m

Jbt = Pt /12 = 43.60 / 12 = 3.63 btg

Vb = G x Jb = 2.66 x 3.63 = 9.6558 kg

2. KOLOM
KOLOM (20/20) cm
a. Beton b. Bekisting
T = 1.68 m P = 1.68 m
l = 0.12 m l = 0.48 m
t = 0.12 m J = 2 bh
J = 2 bh

V = T x l x t x J L = P x l x J
= 0.048 m3 = 1.61 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Pb7 = 0.095 m
Jb = 8 bh
Jt = 4 bh
P = 1.68 m

Pt = ( P x Jt ) x Jumlah Kolom
= ( 1.68 x 4 ) x 2
= 13.44 m

Jbt = Pt /12 = 13.44 / 12 = 1.12 btg

Vb = G x Jb = 10.65 x 1.12 = 11.928 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 12 bh
P = 0.32 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt x Jumlah Kolom


= { 0.32 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 12 x 2
= 10.85 m

Jbt = Pt /12 = 10.85 / 12 = 0.90 btg

Vb = G x Jb = 2.66 x 0.90 = 2.394 kg

3. RINGBALK
a. Beton b. Bekisting
P = 7.50 m P = 7.50 m
l = 0.12 m l = 0.24 m
t = 0.12 m

V = P x l x t L = P x l
= 0.108 m3 = 1.800 m2

c. Besi
Tulangan Utama
Ø = 12 mm = 10.65 kg
Jt = 4 bh
P = 7.50 m

Pt = ( P x Jt )
= ( 7.50 x 4 )
= 30.00 m
Jbt = Pt /12 = 30.00 / 12 = 2.50 btg

Vb = G x Jb = 10.65 x 2.50 = 26.6 kg

Tulangan Sengkang
Ø = 6 mm = 2.66 kg
Pb9 = 0.014 m
Pb10 = 0.045 m
Jb9 = 3 bh
Jb10 = 2 bh
Jt = 50 bh
P = 0.32 m

Pt = { P + ( Pb9 x Jb9 ) + ( Pb10 x Jb10 ) } x Jt


= { 0.32 + ( 0.014 x 3 ) + ( 0.045 x 2 ) x 50
= 22.60 m

Jbt = Pt /12 = 22.60 / 12 = 1.88 btg

Vb = G x Jb = 2.66 x 1.88 = 5.0008 kg

C. PEKERJAAN PASANGAN BATU BATA, PLESTERAN DAN ACIAN


1. PASANGAN BATU BATA
a. Pasangan Batu Bata 1/2 Bata
Tinggi = 1.68 m
P = 7.50 m

La1 = P x t
= 12.60 m2

Total Luas Pekerjaan Pasangan Batu Bata 1/2 Batu


La = La1
= 12.60 m2

2. PLESTERAN
a. Plesteran Biasa
Tinggi = 1.80 m
P = 7.50 m

L2 = P x t x 2 sisi
= 27.00 m2

Total Luas Pekerjaan Plesteran Biasa


Lt = L2
= 27.00 m2

3. ACIAN DINDING
Luas Acian Dinding = Luas Plestean = 27.00 m2

F. PENGECATAN DINDING PAGAR


1. Luas Pengecatan Pagar = Luas Acian Dinding = 27.00 m2
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PERENCANAAN REHABILITASI PAGAR RUMAH DINAS KAPOLRESTABES


LOKASI : JL. HAJI BAU, KOTA MAKASSAR
TAHUN ANGGARAN : 2019

KODE VOLUME BIAYA


No. URAIAN PEKERJAAN
ANALISA SATUAN KONSTRUKSI

I PEKERJAAN PERSIAPAN
1 Papan Proyek - 1.000 Ls Rp 250,000.00
2 Pengukuran dan Pemasangan Bowplank - 1.000 Ls Rp 1,355,000.00
3 Pembongkaran Pagar Eksisting (Dinding, Kolom dan
- 1.000 Ls Rp 1,500,000.00
Pondasi)
Jumlah
II PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah A.2.3.1.1 21.496 m3 Rp 98,065.00
2 Urugan Tanah Kembali A.2.3.1.9 6.188 m3 Rp 71,830.00
3 Urugan Pasir di Bawah Pondasi A.2.3.1.11 1.791 m3 Rp 250,426.00
4 Pasangan Batu Kosong A.3.2.1.9 7.165 m3 Rp 669,989.10
5 Pasangan Batu Kali 1PC : 4PP A.3.2.1.2 15.634 m3 Rp 1,091,695.00
Jumlah
III PEKERJAAN BETON, DINDING PAGAR DAN PINTU PAGAR BESI
1 Sloof 20/25 cm
a. Bekisting A.4.1.1.21 32.57 m2 Rp 222,611.40
b. Besi A.4.1.1.17 315.29 Kg Rp 9,036.02
c. Beton A.A.4.1.1.5 3.26 m3 Rp 1,076,327.45
2 Kolom 20/20 cm
a. Bekisting A.4.1.1.22 22.250 m2 Rp 365,493.70
b. Besi A.4.1.1.17 137.220 Kg Rp 9,036.02
c. Beton A.A.4.1.1.5 1.032 m3 Rp 1,076,327.45
3 Ringbalk 12/12 cm
a. Bekisting A.4.1.1.21 15.634 m2 Rp 222,611.40
b. Besi A.4.1.1.17 274.771 Kg Rp 9,036.02
c. Beton A.A.4.1.1.5 0.938 m3 Rp 1,076,327.45
Jumlah
4 Pek. Pasangan Batu Bata 1/2 Bata, Camp. 1PC : 3PP A.4.4.1.8 150.670 m2 Rp 162,860.23
5 Pekerjaan Plesteran Tebal 15 mm, Camp. 1PC : 3PP A.4.4.2.3 343.020 m2 Rp 81,726.48
6 Pekerjaan Plesteran Skoning / Profil, Camp. 1PC : 3PP A.4.4.2.20 275.530 m' Rp 83,354.15
7 Pekerjaan Acian Dinding A.4.4.2.27 343.020 m2 Rp 48,189.63
8 Pekerjaan Pasangan Batu Alam A.4.4.3.57 20.030 m2 Rp 304,860.88
Jumlah
Harga +
Pintu Pagar Besi Hollow (2x4) cm dan (4x4) cm +
9 Overhead + 16.740 m2 Rp 495,000.00
Pengecatan
Profit 10%
10 Pengecatan Dinding Pagar A.4.7.1.10 327.170 m2 Rp 46,062.39
Jumlah
IV PEKERJAAN PEMBERSIHAN
1 Pembersihan Sisa Pekerjaan - 1.000 Ls Rp 1,250,000.00
Jumlah
JUMLAH
HARGA

Rp 250,000.00
Rp 1,355,000.00

Rp 1,500,000.00

Rp 3,105,000.00

Rp 2,108,005.24
Rp 444,484.04
Rp 448,512.97
Rp 4,800,471.90
Rp 17,067,559.63
Rp 24,869,033.78

Rp 7,250,453.30
Rp 2,848,966.75
Rp 3,508,827.49

Rp 8,132,234.83
Rp 1,239,922.66
Rp 1,110,769.93

Rp 3,480,306.63
Rp 2,482,836.25
Rp 1,009,595.15
Rp 31,063,912.99
Rp 24,538,150.85
Rp 28,033,817.17
Rp 22,966,568.95
Rp 16,530,006.88
Rp 6,106,363.43
Rp 98,174,907.28

Rp 8,286,300.00

Rp 15,070,232.14
Rp 152,595,352.41

Rp 1,250,000.00
Rp 1,250,000.00
REKAPITULASI RAB

PEKERJAAN : PERENCANAAN REHABILITASI PAGAR RUMAH DINAS KAPOLRESTABES


LOKASI : JL. HAJI BAU, KOTA MAKASSAR
TAHUN ANGGARAN : 2019

No. URAIAN PEKERJAAN

I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH DAN PONDASI
III PEKERJAAN BETON, DINDING PAGAR DAN PINTU PAGAR BESI
IV PEKERJAAN PEMBERSIHAN
REAL COST (RC)
PPN 10%
JUMLAH
DIBULATKAN
TERBILANG :
DUA RATUS JUTA RUPIAH

Makassar, 2019

Diperiksa, Palopo, Konsultan


2016 Perencana
KEPALA SEKSI CV. NDIVA CONSULTANT
PEMELIHARAAN GEDUNG PEMERINTAH
KONSULTAN PERENCANA :
CV. M A T R I X

SUHAIR, ST. ANDI ARYA ARMANANSYAH,


Nip. 19690531 200212 1 002 Direktur

MUNZIR F. UMAR, ST
Team Leader
Mengetahui, Menyetujui,
KEPALA BINA TEKNIK KEPALA BIDANG
PRASARANA DAN BANGUNAN PEM
SELAKU KUASA PENGGUNA ANGG

ANSUARD, ST., MT. ZUHAELSI ZUBIR, ST., MT.


Nip. 19611031 200312 1 001 Nip. 19770707 200212 2 011
Mengetahui, Menyetujui,
KEPALA BINA TEKNIK KEPALA BIDANG
PRASARANA DAN BANGUNAN PEM
SELAKU KUASA PENGGUNA ANGG

ANSUARD, ST., MT. ZUHAELSI ZUBIR, ST., MT.


Nip. 19611031 200312 1 001 Nip. 19770707 200212 2 011
EKAPITULASI RAB

LITASI PAGAR RUMAH DINAS KAPOLRESTABES

JUMLAH HARGA

Rp 3,105,000.00
Rp 24,869,033.78
Rp 152,595,352.41
Rp 1,250,000.00
Rp 181,819,386.19
Rp 18,181,938.62
Rp 200,001,324.81
Rp 200,000,000.00

Makassar, 2019

Konsultan Perencana
CV. NDIVA CONSULTANT

KONSULTAN PERENCANA :
CV. M A T R I X

ANDI ARYA ARMANANSYAH, SH


Direktur

MUNZIR F. UMAR, ST
Team Leader
Menyetujui,
KEPALA BIDANG
PRASARANA DAN BANGUNAN PEMERINTAH
SELAKU KUASA PENGGUNA ANGGARAN

ZUHAELSI ZUBIR, ST., MT.


Nip. 19770707 200212 2 011
Menyetujui,
KEPALA BIDANG
PRASARANA DAN BANGUNAN PEMERINTAH
SELAKU KUASA PENGGUNA ANGGARAN

ZUHAELSI ZUBIR, ST., MT.


Nip. 19770707 200212 2 011
UPAH DAN HARGA BAHAN

NO UPAH / BAHAN / MATERIAL SATUAN

A. UPAH
1 Pekerja Oh
2 Tukang Oh
3 Kepala Tukang Oh
4 Mandor Oh
B. BAHAN / MATERIAL
5 Batu Kali m3
6 Batu Pecah 2 - 3 cm m3
7 Batu Bata Standar bh
8 Batu Alam Motif Strip/dipahat 20x40 cm bh
9 Pasir Kasar/Pasir Beton/Pasir Pasang m3
10 Pasir Timbunan m3
11 Tanah Timbunan m3
12 Semen (Bosowa 40 kg) kg
13 Semen (Tonasa 50 kg) kg
14 Semen (Tonasa 40 kg) kg
15 Semen (Tiga Roda 40 kg) kg
16 Semen (Holcim 40 kg) kg
17 Besi Hollow 40.60.1,2 mm (P = 6 m) Btg
18 Besi Hollow 40.40.2 mm (P = 6 m) Btg
19 Besi Hollow 40.20.2 mm (P = 6 m) Btg
24 Besi Beton Polos kg/m'
25 Kawat Ikat Beton 1 Roll 20 kg kg
26 Triplex Tebal 3 mm, Uk. 120 cm x 240 cm lmbr
27 Paku Campuran ( 5-10 cm ) kg
28 Bambu Sedang btg
29 Kayu kelas III, Balok m3
30 Kayu kelas III, Papan m3
31 Amplas / kertas gosok lmbr
32 Cat Penutup Besi/kayu (2,5) kg
33 Cat Dasar Besi/Kayu (1 kg) kg
34 Cat Dasar Tembok (3,5 kg) klg
35 Cat Penutup Tembok Luar (2,5 kg) klg
36 Cat Tembok Aries (5 kg) kg
37 Cat Penutup Tembok Dalam (2,5 kg) Klg
38 Cat Meni (3,5 kg) Kg
39 Minyak Cat ltr
40 Kuas 2" bh
41 Plamur kg
42 Minyak bekisting ltr
43 Kawat Las Listrik RD260, Ø2.0 mm (Nikko Steel), berat isi 5 kg Dos
AN

HARGA ( Rp )

Rp 113,000
Rp 141,000
Rp 153,000
Rp 176,000

Rp 320,000.00
Rp 300,000.00
Rp 1,000.00
Rp 105,000.00
Rp 225,000.00
Rp 160,000.00
Rp 200,000.00
Rp 1,175.00
Rp 1,300.00
Rp 1,200.00
Rp 1,175.00
Rp 1,125.00
Rp 183,000.00
Rp 190,000.00
Rp 135,000.00
Rp 5,664.58
Rp 20,750.00
Rp 50,000.00
Rp 20,000.00
Rp 30,000.00
Rp 2,000,000.00
Rp 2,000,000.00
Rp 5,000.00
Rp 80,000.00
Rp 30,000.00
Rp 95,000.00
Rp 260,000.00
Rp 65,000.00
Rp 165,000.00
Rp 27,428.57
Rp 8,000.00
Rp 8,000.00
Rp 9,000.00
Rp 24,000.00
Rp 150,000
Besi
Rumus bengkokan besi (sumber : SK SNI 03 TATACARA PERHITUNGAN STRUKTUR BETON
UNTUK BANGUNAN GEDUNG
Kait standar untuk tulangan utama
kait db D lt
180o 10 - 25 mm 6.db 4.db atau 60 mm
135 o
10 - 25 mm 6.db 6.db atau 75 mm
90o 10 - 25 mm 6.db 12.db
Ketentuan panjang sambungan untuk besi polos 45db
TULANGAN UTAMA
Ø = 14 mm
Ps1 = 45. db = 45 x 14 = 0.630 m
Kait 90o
D = 3. db = 3 x 14 = 0.042 m
lt = 8. db = 8 x 14 = 0.112 m

Pb0 = [( 1/2 ) . π . ( D/2 )]


= 0.5 x 3.14 x 0.021
= 0.03297 m

Pb1 = [( 1/2 ) . π . ( D/2 )] + lt


= 0.5 x 3.14 x 0.021 + 0.112
= 0.14497 m

Kait 135o
D = 3. db = 3 x 14 = 0.042 m
lt = 6. db = 6 x 14 = 0.084 m

Pb2 = [( 3/4 ) . π . ( D/2 )] + lt


= 0.75 x 3.14 x 0.021 + 0.084
= 0.13346 m

Kait 180o
D = 3. db = 3 x 14 = 0.042 m
lt = 4. db = 4 x 14 = 0.056 m

Pb11 = [( 1/2 ) . π . D ] + lt
= 0.5 x 3.14 x 0.042 + 0.056
= 0.12194 m

Ø = 12 mm
Ps2 = 45. db = 45 x 12 = 0.54 m
Kait 90o
D = 3. db = 3 x 12 = 0.036 m
lt = 8. db = 8 x 12 = 0.096 m

Pb3 = [( 1/2 ) . π . ( D/2 )] + lt


= 0.5 x 3.14 x 0.018 + 0.096
= 0.12426 m

Pb01 = [( 1/2 ) . π . ( D/2 )]


= 0.5 x 3.14 x 0.018
= 0.02826 m

Kait 135o
D = 3. db = 3 x 12 = 0.036 m
lt = 6. db = 6 x 12 = 0.072 m

Pb4 = [( 3/4 ) . π . ( D/2 )] + lt


= 0.75 x 3.14 x 0.018 + 0.072
= 0.11439 m

Kait 180o
D = 3. db = 3 x 12 = 0.036 m
lt = 4. db = 4 x 12 = 0.048 m

Pb5 = [( 1/2 ) . π . D ] + lt
= 0.5 x 3.14 x 0.036 + 0.048
= 0.10452 m

Ø = 10 mm
Ps3 = 45. db = 45 x 10 = 0.450 m
Kait 90o
D = 3. db = 3 x 10 = 0.03 m
lt = 8. db = 8 x 10 = 0.08 m

Pb6 = [( 1/2 ) . π . ( D/2 )] + lt


= 0.5 x 3.14 x 0.015 + 0.08
= 0.10355 m

Pb02 = [( 1/2 ) . π . ( D/2 )]


= 0.5 x 3.14 x 0.015
= 0.02355 m
Kait 135o
D = 3. db = 3 x 10 = 0.030 m
lt = 6. db = 6 x 10 = 0.06 m

Pb7 = [( 3/4 ) . π . ( D/2 )] + lt


= 0.75 x 3.14 x 0.015 + 0.06
= 0.09533 m

Kait 180o
D = 3. db = 3 x 10 = 0.03 m
lt = 4. db = 4 x 10 = 0.04 m

Pb8 = [( 1/2 ) . π . D ] + lt
= 0.5 x 3.14 x 0.03 + 0.04
= 0.0871 m

TULANGAN SENGKANG
Ø = 6 mm
Kait 90o
D = 3. ds = 3 x 6 = 0.018 m
lt = 4. ds = 4 x 6 = 0.024 m

Pb9 = ( 1/2 ) . π . ( D/2 )


= 0.5 x 3.14 x 0.009
= 0.01413 m

Kait 135o
D = 3. ds = 3 x 6 = 0.018 m
lt = 4. ds = 4 x 6 = 0.024 m

Pb10 = [( 3/4 ) . π . ( D/2 )] + lt


= 0.75 x 3.14 x 0.009 + 0.024
= 0.0452 m

Ø = 8 mm
Kait 90o
D = 3. ds = 3 x 8 = 0.024 m
lt = 4. ds = 4 x 8 = 0.032 m

Pb11 = ( 1/2 ) . π . ( D/2 )


= 0.5 x 3.14 x 0.012
= 0.01884 m
Kait 135o
D = 3. ds = 3 x 8 = 0.024 m
lt = 4. ds = 4 x 8 = 0.032 m

Pb12 = [( 3/4 ) . π . ( D/2 )] + lt


= 0.75 x 3.14 x 0.012 + 0.032
= 0.06026 m

Note : db merupakan diameter terkecil tulangan longitudinal


ds merupakan diameter tulangan shape (sengkang)
Jp = Jumlah podasi poor plat
Jt = Jumlah tulangan
Jbt = Jumlah batang
Pt = Panjang total
G = Berat besi perbatang
Ps = Panjang sambungan besi
Pb = Panjang bengkokan besi
D = Diameter bengkokan besi
lt = Perpanjangan bengkokan besi
Jb = Jumlah bengkokan