Anda di halaman 1dari 101

A.2.2.1.

HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.1 (K3) Pembuatan 1 m2 pagar sementara dari Kayutinggi 2 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.400 120,000.00 48,000.00
Tukang kayu L.02 OH 0.200 150,000.00 30,000.00
Kepala tukang L.03 OH 0.020 160,000.00 3,200.00
Mandor L.04 OH 0.020 130,000.00 2,600.00
TOTAL UPAH TENAGA 83,800.00
B BAHAN
Dolken kayu Ø 8-10 panjang 400 cm Batang 1.250 15,000.00 18,750.00
Semen portland Kg 5.000 1,900.00 9,500.00
Pasir beton m3 0.005 180,000.00 900.00
Kayu balok 5/7 m3 0.009 2,380,000.00 21,420.00
Paku biasa 2"-5" Kg 0.072 25,000.00 1,800.00
Residu Liter 0.400 0.00 0.00
TOTAL BIAYA BAHAN 52,370.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 136,170.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 136,170.00

A. 2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang kayu L.02 OH 0.400 150,000.00 60,000.00
Kepala tukang L.03 OH 0.020 160,000.00 3,200.00
Mandor L.04 OH 0.020 130,000.00 2,600.00
TOTAL UPAH TENAGA 89,800.00
B BAHAN
Dolken kayu Ø 8-10 panjang 400 cm Batang 1.250 15,000.00 18,750.00
Semen portland Kg 2.500 1,900.00 4,750.00
Seng Gelombang BJLS 0,20 mm 6 kaki Lbr 1.200 67,000.00 80,400.00
Pasir beton m3 0.005 180,000.00 900.00
Kerikil (Maks 30 mm) m3 0.009 430,000.00 3,870.00
Kayu balok 5/7 m3 0.072 2,380,000.00 171,360.00
Paku biasa 2"-5" Kg 0.060 25,000.00 1,500.00
Meni besi Liter 0.450 35,000.00 15,750.00
TOTAL BIAYA BAHAN 297,280.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 387,080.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 387,080.00

A. 2.2.1.3 (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1.8 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang kayu L.02 OH 0.300 150,000.00 45,000.00
Kepala tukang L.03 OH 0.020 160,000.00 3,200.00
Mandor L.04 OH 0.020 130,000.00 2,600.00
TOTAL UPAH TENAGA 74,800.00
B BAHAN
Dolken kayu Ø 8-10 panjang 400 cm Batang 1.000 15,000.00 15,000.00
Semen portland Kg 2.000 1,900.00 3,800.00
Kawat duri m' 25.000 95,000.00 2,375,000.00
Pasir beton m3 0.005 180,000.00 900.00
Kerikil (Maks 30 mm) m3 0.009 430,000.00 3,870.00
Paku biasa 2"-5" Kg 0.060 25,000.00 1,500.00
TOTAL BIAYA BAHAN 2,400,070.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 2,474,870.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 2,474,870.00

A. 2.2.1.3 (K3) Pembuatan 1 m2 pagar Pengaman dari kawat duri Jarak 20 Cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang kayu L.02 OH 0.300 150,000.00 45,000.00
Kepala tukang L.03 OH 0.020 160,000.00 3,200.00
Mandor L.04 OH 0.020 130,000.00 2,600.00
TOTAL UPAH TENAGA 74,800.00
B BAHAN
Kawat duri m' 5.000 95,000.00 475,000.00
TOTAL BIAYA BAHAN 475,000.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 549,800.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 549,800.00

A. 2.2.1.4 Pengukuran dan pemasangan 1m' Bouwplank


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang kayu L.02 OH 0.100 150,000.00 15,000.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.005 130,000.00 650.00
TOTAL UPAH TENAGA 29,250.00
B BAHAN
Kayu balok 5/7 m3 0.012 2,380,000.00 28,560.00
Paku biasa 2"-5" Kg 0.020 25,000.00 500.00
Kayu papan 3/20 m3 0.007 2,580,000.00 18,060.00
TOTAL BIAYA BAHAN 47,120.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 76,370.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 76,370.00

A. 2.2.1.5 (K3) Pembuatan 1 m2 kantor sementara lantai plesteran


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 2.000 120,000.00 240,000.00
Tukang kayu L.02 OH 2.000 150,000.00 300,000.00
Tukang batu L.02 OH 1.000 150,000.00 150,000.00
Kepala tukang L.03 OH 0.300 160,000.00 48,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 744,500.00
B BAHAN
Dolken Kayu Ø 8 -10 / 400 cm Batang 1.250 #N/A #N/A
Kayu m3 0.180 #N/A #N/A
Paku biasa 2"-5" Kg 0.080 25,000.00 2,000.00
Besi strip Kg 1.100 #N/A #N/A
Semen portland Kg 35.000 1,900.00 66,500.00
Pasir pasang m3 0.150 180,000.00 27,000.00
Pasir beton m3 0.100 180,000.00 18,000.00
Kerikil beton 2-3 Cm m3 0.150 #N/A #N/A
Bata merah Bh 30.000 900.00 27,000.00
Seng plat Lbr 0.250 #N/A #N/A
Jendela naco Bh 0.200 #N/A #N/A
Kaca polos m2 0.080 #N/A #N/A
Kunci tanam Bh 0.150 #N/A #N/A
Plywood 4mm Lbr 0.060 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.6 (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang kayu L.02 OH 1.500 150,000.00 225,000.00
Kepala tukang L.03 OH 0.150 160,000.00 24,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 375,500.00
B BAHAN
Dolken Kayu Ø 8 -10 / 400 cm Batang 3.000 #N/A #N/A
Kayu m3 0.276 #N/A #N/A
Paku biasa 2"-5" Kg 0.700 25,000.00 17,500.00
Seng gelombang Lbr 1.500 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.7 (K3) Pembuatan 1 m2 gudang semen dan peralatan


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang kayu L.02 OH 2.000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.200 160,000.00 32,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 458,500.00
B BAHAN
Dolken Kayu Ø 8 -10 / 400 cm Batang 1.700 #N/A #N/A
Kayu m3 0.210 #N/A #N/A
Paku biasa 2"-5" Kg 0.300 25,000.00 7,500.00
Semen portland Kg 10.500 1,900.00 19,950.00
Pasir beton m3 0.030 180,000.00 5,400.00
Kerikil beton 2-3 Cm m3 0.050 #N/A #N/A
Seng gelombang Lbr 1.500 #N/A #N/A
Seng plat Lbr 0.250 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.8 (K3) Pembuatan 1 m2 bedeng pekerja


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang kayu L.02 OH 2.000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.200 160,000.00 32,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 458,500.00
B BAHAN
Dolken Kayu Ø 8 -10 / 400 cm Batang 1.250 #N/A #N/A
Kayu m3 0.186 #N/A #N/A
Paku biasa 2"-5" Kg 0.300 25,000.00 7,500.00
Semen portland Kg 18.000 1,900.00 34,200.00
Pasir beton m3 0.030 180,000.00 5,400.00
Kerikil beton 2-3 Cm m3 0.050 #N/A #N/A
Seng gelombang Lbr 1.500 #N/A #N/A
Plywood 4mm Lbr 1.350 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.9 (K3) Pembersihan 1 m2 lapangan dan perataan


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 18,500.00
B BAHAN
0.00
TOTAL BIAYA BAHAN 0.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 18,500.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 18,500.00

A. 2.2.1.10 (K3) Pembuatan 1 m2 steger/perancah dari bambu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang kayu L.02 OH 2.000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.200 160,000.00 32,000.00
Mandor L.04 OH 0.050 130,000.00 6,500.00
TOTAL UPAH TENAGA 458,500.00
B BAHAN
Bambu Ø 6-8 / 600 cm Batang 1.250 #N/A #N/A
Tali ijuk m3 0.186 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Tukang kayu L.02 OH 0.300 150,000.00 45,000.00
Kepala tukang L.03 OH 0.030 160,000.00 4,800.00
TOTAL UPAH TENAGA 49,800.00
B BAHAN
Kayu papan kelas III m3 0.036 #N/A #N/A
Kayu balok 5/7 kelas III m3 0.014 #N/A #N/A
Paku biasa 2"-5" Kg 0.080 25,000.00 2,000.00
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.12 Pembuatan 1 m2 jalan sementara


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.000 #N/A #N/A
Mandor L.04 OH 0.005 130,000.00 650.00
TOTAL UPAH TENAGA #N/A
B BAHAN
Batu belah m3 0.150 #N/A #N/A
Batu pecah m3 0.090 #N/A #N/A
Pasir pasang m3 0.010 180,000.00 1,800.00
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 0% x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 2.2.1.13 Pembongkaran 1 m3 beton bertulang


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 13.334 120,000.00 1,600,080.00
Mandor L.04 OH 0.666 130,000.00 86,580.00
TOTAL UPAH TENAGA 1,686,660.00
B BAHAN
0.00
TOTAL BIAYA BAHAN 0.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 1,686,660.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 1,686,660.00

A. 2.2.1.14 Pembongkaran 1 m3 dinding tembok bata


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 6.667 120,000.00 800,040.00
Mandor L.04 OH 0.333 130,000.00 43,290.00
TOTAL UPAH TENAGA 843,330.00
B BAHAN
0.00
TOTAL BIAYA BAHAN 0.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 843,330.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 843,330.00

A. 2.2.1.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.042 120,000.00 5,040.00
Tukang kayu L.02 OH 0.004 150,000.00 600.00
Kepala tukang L.03 OH 0.002 160,000.00 320.00
Mandor L.04 OH 0.042 130,000.00 5,460.00
TOTAL UPAH TENAGA 11,420.00
B BAHAN
Kawat Harmonika 4Cm Tinggi 1,2 Mtr M2 1.000 5,080,000.00 5,080,000.00
TOTAL BIAYA BAHAN 5,080,000.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 5,091,420.00
E Overhead + profit 0% x D 0.00
F Harga satuan pekerjaan (D + E) 5,091,420.00
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECETAN
A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 18,390.00
B BAHAN
Soda api Kg 0.050 20,000.00 1,000.00
TOTAL BIAYA BAHAN 1,000.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 19,390.00
E Overhead + profit 15 % x D 2,908.50
F Harga satuan pekerjaan (D + E) 22,298.50

A.4.7.1.2. 1 m2 Pencucian bidang permukaan tembok yang pernah dicat


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 18,390.00
B BAHAN
Sabun Kg 0.050 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 15 % x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A.4.7.1.3. 1 m2 Pengerokan karat pada permukaan baja cara manual


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 19,040.00
B BAHAN
Sabun Kg 0.050 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 15 % x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A.4.7.1.4. 1 m2 Pengecetan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.070 120,000.00 8,400.00
Tukang cat L.02 OH 0.009 150,000.00 1,350.00
Kepala tukang L.03 OH 0.006 160,000.00 960.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 11,100.00
B BAHAN
Meni Kayu Kg 0.200 35,000.00 7,000.00
Plamur Kg 0.150 20,000.00 3,000.00
Dempul Impra Kg 0.170 50,000.00 8,500.00
Cat Gloteks Kg 0.260 65,000.00 16,900.00
Kuas Biasa 2,5" buah 0.010 15,000.00 150.00
Tiner A Kg 0.030 50,000.00 1,500.00
Amplas Halus Lbr 0.200 10,000.00 2,000.00
TOTAL BIAYA BAHAN 39,050.00
C PERALATAN
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 50,150.00
E Overhead + profit 15 % x D 7,522.50
F Harga satuan pekerjaan (D + E) 57,672.50

A.4.7.1.11. Pengecetan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.028 120,000.00 3,360.00
Tukang cat L.02 OH 0.042 150,000.00 6,300.00
Kepala tukang L.03 OH 0.0042 160,000.00 672.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 10,722.00
B BAHAN
Alkali Kg 0.120 25,000.00 3,000.00
Cat Tembok Kg 0.180 30,000.00 5,400.00
TOTAL BIAYA BAHAN 8,400.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 19,122.00
E Overhead + profit 15 % x D 2,868.30
F Harga satuan pekerjaan (D + E) 21,990.30
Perhitungan Hydrolis Desa Pongkowulu
Kriteria Desain :
Formula Hazen William :
Kebut. Air = 70 lt / org / hari S (slope) = ( ^H/L)*100
Pertumbuhan Pddk = 1.4 % / thn D (diam) teoritis = ((3.59*Q*10^6)/(S^0.54*C))^0.38
Periode Desain = 15 thn Hloss / 100 m = ((3.59*Q*10^6)/(D^2.63*C))^1.85
Faktor Jam Puncak, jp = 1.5 V = 4*Q/1000(3.14*(D/1000)^2)
Minor Loss = 10 %

DATA BEBAN NODE BEBAN PIPA PERHITUNGAN HEAD LOSS


No Node Elevasi Beda Tinggi Pjg Pipa Slope Jmlh. Pddk Kebuth. Air Jmlh. Pddk Kebut. Air Kebut air Jmlh. Pddk Jmlh. Pddk Flow Flow Koeff HW Diam. Pipa Diam. Pipa Hloss Total Hloss HGL Sisa Kcptan
Jalur h ^h L S yg dilayani Proy 15 thn Proy 15 thn jam puncak yg disuplai Proy 15 thn Jam Puncak C D teoritis D desain per 100 m (+10% minor) Tekan V
(+ m) (m) (m) (%) (jiwa) (lt/d) (jiwa) (lt/dt) (l/dt) (jiwa) (jiwa) (lt/dt) (lt/dt) (mm) (mm) (m) (m) (m) (m) (m/dtk)

PMA 259.00 259.00


PMA - P1 P1 257.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 90.00 0.10 0.05 258.95 1.95 0.25
1 P1 - P2 P2 256.50 0.50 50 1.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 55.39 90.00 0.10 0.05 258.90 2.40 0.25
2 P2 - P3 P3 256.00 0.50 50 1.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 55.39 90.00 0.10 0.05 258.84 2.84 0.25
P3 - P3.1 P3.1 254.00 2.00 16 12.50 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 32.99 90.00 0.10 0.02 258.83 4.83 0.25
3 P3.1 - P4 P4 243.00 13.00 34 38.24 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 26.23 90.00 0.10 0.04 258.81 15.81 0.25
4 P4 - P5 P5 239.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 90.00 0.10 0.05 258.75 19.75 0.25
5 P5 - P6 P6 230.00 9.00 50 18.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 30.61 90.00 0.10 0.05 258.70 28.70 0.25
6 P6 - P7 P7 229.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 258.40 29.40 0.52
7 P7 - P8 P8 228.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 258.11 30.11 0.52
8 P8 - P9 P9 230.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 257.81 27.81 0.52
9 P9 - P10 P10 229.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 120 52.30 63.00 0.82 0.45 257.36 28.36 0.52
10 P10 - P11 P11 228.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 257.06 29.06 0.52
11 P11 - P12 P12 229.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 256.76 27.76 0.52
12 P12 - P13 P13 227.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 256.47 29.47 0.52
13 P13 - P14 P14 228.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 256.17 28.17 0.52
14 P14 - P15 P15 219.00 9.00 50 18.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 30.61 63.00 0.54 0.30 255.87 36.87 0.52
15 P15 - P16 P16 215.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 63.00 0.54 0.30 255.57 40.57 0.52
16 P16 - P17 P17 220.00 -5.00 50 (10.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 34.54 63.00 0.54 0.30 255.28 35.28 0.52
17 P17 - P18 P18 218.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 254.98 36.98 0.52
18 P18 - P19 P19 217.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 254.68 37.68 0.52
19 P19 - P20 P20 220.00 -3.00 50 (6.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 254.38 34.38 0.52
20 P20 - P21 P21 227.00 -7.00 50 (14.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 32.23 63.00 0.54 0.30 254.09 27.09 0.52
21 P21 - P22 P22 223.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 63.00 0.54 0.30 253.79 30.79 0.52
22 P22 - P23 P23 222.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 253.49 31.49 0.52
23 P23 - P24 P24 221.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 253.19 32.19 0.52
24 P24 - P25 P25 218.00 3.00 50 6.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 252.90 34.90 0.52
25 P25 - P26 P26 211.00 7.00 50 14.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 32.23 63.00 0.54 0.30 252.60 41.60 0.52
26 P26 - P27 P27 206.00 5.00 50 10.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 34.54 63.00 0.54 0.30 252.30 46.30 0.52
27 P27 - P28 P28 207.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 252.00 45.00 0.52
28 P28 - P29 P29 205.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 251.71 46.71 0.52
29 P29 - P30 P30 204.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 251.41 47.41 0.52
30 P30 - P31 P31 206.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 251.11 45.11 0.52
31 P31 - P32 P32 205.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 250.81 45.81 0.52
32 P32 - P33 P33 207.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 250.52 43.52 0.52
33 P33 - P34 P34 209.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 250.22 41.22 0.52
34 P34 - P35 P35 203.00 6.00 50 12.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 33.27 63.00 0.54 0.30 249.92 46.92 0.52
35 P35 - P36 P36 192.00 11.00 50 22.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 29.38 63.00 0.54 0.30 249.62 57.62 0.52
36 P36 - P37 P37 186.00 6.00 50 12.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 33.27 63.00 0.54 0.30 249.32 63.32 0.52
37 P37 - P38 P38 187.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 249.03 62.03 0.52
38 P38 - P39 P39 190.00 -3.00 50 (6.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 248.73 58.73 0.52
39 P39 - P40 P40 192.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 248.43 56.43 0.52
40 P40 - P41 P41 191.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 248.13 57.13 0.52
41 P41 - P42 P42 187.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 63.00 0.54 0.30 247.84 60.84 0.52
42 P42 - P43 P43 186.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 247.54 61.54 0.52
43 P43 - P44 P44 184.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 247.24 63.24 0.52
44 P44 - P45 P45 185.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 246.94 61.94 0.52
45 P45 - P46 P46 181.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 63.00 0.54 0.30 246.65 65.65 0.52
46 P46 - P47 P47 180.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 246.35 66.35 0.52
47 P47 - P48 P48 181.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 246.05 65.05 0.52
48 P48 - P49 P49 178.00 3.00 50 6.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 245.75 67.75 0.52
49 P49 - P50 P50 186.00 -8.00 50 (16.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 31.36 63.00 0.54 0.30 245.46 59.46 0.52
50 P50 - P51 P51 187.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 245.16 58.16 0.52
51 P51 - P52 P52 189.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 244.86 55.86 0.52
52 P52 - P53 P53 188.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 244.56 56.56 0.52
53 P53 - P54 P54 189.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 244.27 55.27 0.52
54 P54 - P55 P55 188.00 1.00 50 2.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 243.97 55.97 0.52
55 P55 - P56 P56 197.00 -9.00 50 (18.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 30.61 63.00 0.54 0.30 243.67 46.67 0.52
56 P56 - P57 P57 190.00 7.00 50 14.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 32.23 63.00 0.54 0.30 243.37 53.37 0.52
57 P57 - P58 P58 187.00 3.00 50 6.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 243.08 56.08 0.52
58 P58 - P59 P59 183.00 4.00 50 8.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 36.15 63.00 0.54 0.30 242.78 59.78 0.52
59 P59 - P60 P60 181.00 2.00 50 4.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 41.68 63.00 0.54 0.30 242.48 61.48 0.52
60 P60 - P61 P61 182.00 -1.00 50 (2.00) 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 48.05 63.00 0.54 0.30 242.18 60.18 0.52
61 P61 - P62 P62 179.00 3.00 50 6.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.35 63.00 0.54 0.30 241.89 62.89 0.52
62 P62 - P63 P63 173.00 6.00 50 12.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 33.27 63.00 0.54 0.30 241.59 68.59 0.52
63 P63 - P64 P64 164.00 9.00 50 18.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 30.61 63.00 0.54 0.30 241.29 77.29 0.52
64 P64 - P65 P65 159.00 5.00 50 10.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 34.54 63.00 0.54 0.30 240.99 81.99 0.52
65 P65 - BPT BPT 154.00 5.00 50 10.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 34.54 63.00 0.54 0.30 240.69 86.69 0.52

BPT 154.00 154.00


66 BPT - B1 B1 141.00 13.00 119 10.92 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 33.91 112.00 0.03 0.04 153.96 12.96 0.16
67 B1 - B2 B2 135.00 6.00 120 5.00 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 39.81 113.00 0.03 0.04 153.92 18.92 0.16
68 B2 - B3 B3 128.00 7.00 121 5.79 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 38.64 114.00 0.03 0.04 153.88 25.88 0.16
69 B3 - B4 B4 125.00 3.00 122 2.46 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 46.06 115.00 0.03 0.04 153.84 28.84 0.16
70 B4 - B5 B5 122.00 3.00 123 2.44 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 46.13 116.00 0.03 0.04 153.80 31.80 0.15
71 B5 - B6 B6 120.00 2.00 124 1.61 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 50.22 117.00 0.03 0.04 153.76 33.76 0.15
72 B6 - B7 B7 119.00 1.00 125 0.80 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 57.99 118.00 0.03 0.04 153.73 34.73 0.15
73 B7 - B8 B8 116.00 3.00 126 2.38 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 46.36 119.00 0.02 0.03 153.69 37.69 0.15
74 B8 - BAK BAK 114.00 2.00 127 1.57 0 0.00 0 0.00 0.00 1081 1332 1.08 1.62 150 50.47 120.00 0.02 0.03 153.66 39.66 0.14

BAK 114.00
75 BAK - BA1 BA1 98.00 16.00 128 12.50 58 0.05 71 0.06 0.09 1081 1332 1.08 1.62 150 32.99 121.00 0.02 0.03 153.63 55.63 0.14
76 BA1 - BA2 BA2 95.00 3.00 129 2.33 59 0.05 73 0.06 0.09 1081 1332 1.08 1.62 150 46.59 122.00 0.02 0.03 153.60 58.60 0.14
77 BA2 - BA3 BA3 93.00 2.00 130 1.54 60 0.05 74 0.06 0.09 1081 1332 1.08 1.62 150 50.71 123.00 0.02 0.03 153.57 60.57 0.14
78 BA3 - BA4 BA4 90.00 3.00 131 2.29 61 0.05 75 0.06 0.09 1081 1332 1.08 1.62 150 46.73 124.00 0.02 0.03 153.54 63.54 0.13
79 BA4 - BA5 BA5 88.00 2.00 132 1.52 62 0.05 76 0.06 0.09 1081 1332 1.08 1.62 150 50.87 125.00 0.02 0.03 153.51 65.51 0.13
80 BA5 - BA6 BA6 82.00 6.00 133 4.51 63 0.05 78 0.06 0.09 1081 1332 1.08 1.62 150 40.66 126.00 0.02 0.03 153.48 71.48 0.13
81 BA6 - BA7 BA7 72.00 10.00 134 7.46 64 0.05 79 0.06 0.10 1081 1332 1.08 1.62 150 36.67 127.00 0.02 0.03 153.46 81.46 0.13
82 BA7 - BA8 BA8 65.00 7.00 135 5.19 65 0.05 80 0.06 0.10 1081 1332 1.08 1.62 150 39.52 128.00 0.02 0.03 153.43 88.43 0.13
83 BA8 - BA9 BA9 60.00 5.00 136 3.68 66 0.05 81 0.07 0.10 1081 1332 1.08 1.62 150 42.41 129.00 0.02 0.02 153.41 93.41 0.12
84 BA9 - BA10 BA10 59.00 1.00 137 0.73 67 0.05 83 0.07 0.10 1081 1332 1.08 1.62 150 59.09 130.00 0.02 0.02 153.38 94.38 0.12
85 BA10 - BA11 BA11 58.00 1.00 138 0.72 68 0.06 84 0.07 0.10 1081 1332 1.08 1.62 150 59.18 131.00 0.02 0.02 153.36 95.36 0.12
86 BA11 - BA12 BA12 56.00 2.00 139 1.44 69 0.06 85 0.07 0.10 1081 1332 1.08 1.62 150 51.41 132.00 0.01 0.02 153.34 97.34 0.12
87 BA12 - BA13 BA13 48.00 8.00 140 5.71 70 0.06 86 0.07 0.10 1081 1332 1.08 1.62 150 38.74 133.00 0.01 0.02 153.32 105.32 0.12
88 BA13 - BA14 BA14 46.00 2.00 141 1.42 71 0.06 87 0.07 0.11 1081 1332 1.08 1.62 150 51.56 134.00 0.01 0.02 153.29 107.29 0.11
89 BA14 - BA15 BA15 47.00 -1.00 142 (0.70) 72 0.06 89 0.07 0.11 1081 1332 1.08 1.62 150 59.53 135.00 0.01 0.02 153.27 106.27 0.11
90 BA15 - BA16 BA16 48.00 -1.00 143 (0.70) 73 0.06 90 0.07 0.11 1081 1332 1.08 1.62 150 59.61 136.00 0.01 0.02 153.25 105.25 0.11
91 BA16 - BA17 BA17 47.00 1.00 144 0.69 74 0.06 91 0.07 0.11 1081 1332 1.08 1.62 150 59.70 137.00 0.01 0.02 153.23 106.23 0.11
92 BA17 - BA18 BA18 49.00 -2.00 145 (1.38) 75 0.06 92 0.07 0.11 1081 1332 1.08 1.62 150 51.86 138.00 0.01 0.02 153.21 104.21 0.11
93 BA18 - BA19 BA19 39.00 10.00 146 6.85 76 0.06 94 0.08 0.11 1081 1332 1.08 1.62 150 37.32 139.00 0.01 0.02 153.20 114.20 0.11
94 BA19 - BA20 BA20 236.00 -197.00 147 (134.01) 77 0.06 95 0.08 0.12 1081 1332 1.08 1.62 150 20.28 140.00 0.01 0.02 153.18 -82.82 0.11
95 BA20 - BA21 BA21 29.00 207.00 148 139.86 78 0.06 96 0.08 0.12 1081 1332 1.08 1.62 150 20.10 141.00 0.01 0.02 153.16 124.16 0.10
BPT1 #REF!
11 BPT-P17 P17 137.00 -81.00 110 (73.64) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 120 26.34 50.00 3.27 3.96 #REF! #REF! 0.95
12 P17-P18 P18 135.00 -2.00 50 (4.00) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 150 43.99 50.00 2.17 1.19 #REF! #REF! 0.95
13 P18-P19 P19 130.00 -5.00 100 (5.00) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 150 42.02 50.00 2.17 2.38 #REF! #REF! 0.95
14 P19-P20 P20 123.00 -7.00 100 (7.00) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 120 42.69 50.00 3.27 3.60 #REF! #REF! 0.95
15 P20-P21 P21 115.00 -8.00 100 (8.00) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 150 38.16 50.00 2.17 2.38 #REF! #REF! 0.95
16 P21-P22 P22 110.00 -5.00 53 (9.43) 0 0.00 0 0.00 0.00 1246 1535 1.24 1.87 150 36.89 50.00 2.17 1.26 #REF! #REF! 0.95
P22-R R 89.00 -21.00 50 (42.00) 1 0.00 1 0.00 0.00 1246 1535 1.24 1.87 150 27.15 50.00 2.17 1.19 #REF! #REF! 0.95
R 89.00
17 P22-P23 P23 74.00 -36.00 60 (60.00) 5 0.00 6 0.00 0.01 1246 1535 1.24 1.87 150 25.24 110.00 0.05 0.03 88.97 14.97 0.20
18 P23-P24 P24 71.00 -3.00 102 (2.94) 13 0.01 16 0.01 0.02 1246 1535 1.24 1.87 150 46.86 63.00 0.70 0.79 88.18 17.18 0.60
19 P24-SPG31SPG31 50.00 -21.00 129 (16.28) 34 0.03 42 0.03 0.05 1102 1358 1.10 1.65 150 31.48 63.00 0.56 0.80 87.38 37.38 0.53
20 SPG31-P25 P25 31.00 -19.00 156 (12.18) 77 0.06 95 0.08 0.12 1068 1316 1.07 1.60 150 33.01 63.00 0.53 0.91 86.48 55.48 0.51
21 P25-P26 P26 30.50 -0.50 141 (0.35) 69 0.06 85 0.07 0.10 991 1221 0.99 1.48 150 66.30 63.00 0.46 0.71 85.76 55.26 0.48
22 P26-SPG32SPG32 30.00 -0.50 185 (0.27) 83 0.07 102 0.08 0.12 922 1136 0.92 1.38 150 68.20 63.00 0.40 0.82 84.94 54.94 0.44
23 SPG32-P27 P27 30.50 0.50 147 0.34 123 0.10 152 0.12 0.18 839 1034 0.84 1.26 150 62.77 63.00 0.34 0.55 84.39 53.89 0.40
24 P27-SPG33SPG33 31.00 0.50 136 0.37 106 0.09 131 0.11 0.16 716 882 0.71 1.07 150 58.16 63.00 0.25 0.38 84.02 53.02 0.34
25 SPG33-SPG34SPG34 31.50 0.50 155 0.32 134 0.11 165 0.13 0.20 610 751 0.61 0.91 150 56.22 50.00 0.58 0.99 83.03 51.53 0.47
26 SPG34-P28 P28 31.00 -0.50 163 (0.31) 83 0.07 102 0.08 0.12 476 586 0.48 0.71 150 51.69 50.00 0.37 0.65 82.38 51.38 0.36
27 P28-P29 P29 30.00 -1.00 140 (0.71) 69 0.06 85 0.07 0.10 393 484 0.39 0.59 150 40.41 50.00 0.26 0.39 81.98 51.98 0.30
28 P29-JBTN JBTN 30.50 0.50 143 0.35 61 0.05 75 0.06 0.09 324 399 0.32 0.49 150 43.48 50.00 0.18 0.28 81.70 51.20 0.25
29 JBTN-JBTN1JBTN1 31.00 0.50 12 4.17 42 0.03 52 0.04 0.06 263 324 0.26 0.39 150 24.16 50.00 0.12 0.02 81.68 50.68 0.20
30 JBTN1-LR SDLR SD 33.00 2.00 243 0.82 33 0.03 41 0.03 0.05 221 272 0.22 0.33 150 31.54 50.00 0.09 0.24 81.45 48.45 0.17
30 LR SD-P30 P30 34.00 1.00 223 0.45 27 0.02 33 0.03 0.04 221 272 0.22 0.33 150 35.72 50.00 0.09 0.22 81.47 47.47 0.17
31 P30-P31 P31 36.00 2.00 224 0.89 13 0.01 16 0.01 0.02 194 239 0.19 0.29 150 29.52 50.00 0.07 0.17 81.30 45.30 0.15
32 P31-P32 P32 38.00 2.00 225 0.89 19 0.02 23 0.02 0.03 181 223 0.18 0.27 150 28.78 50.00 0.06 0.15 81.14 43.14 0.14
33 P32-P33 P33 49.00 11.00 250 4.40 14 0.01 17 0.01 0.02 162 200 0.16 0.24 150 19.87 50.00 0.05 0.14 81.01 32.01 0.12
34 P33-P34 P34 50.00 1.00 260 0.38 17 0.01 21 0.02 0.03 148 182 0.15 0.22 150 31.66 50.00 0.04 0.12 80.89 30.89 0.11
35 P34-P35 P35 55.00 5.00 250 2.00 18 0.01 22 0.02 0.03 131 161 0.13 0.20 150 21.55 50.00 0.03 0.09 80.79 25.79 0.10
36 P35-P36 P36 60.00 5.00 200 2.50 16 0.01 20 0.02 0.02 113 139 0.11 0.17 150 19.46 50.00 0.03 0.06 80.74 20.74 0.09
37 P36-P37 P37 62.00 2.00 200 1.00 10 0.01 12 0.01 0.01 97 119 0.10 0.15 150 22.16 50.00 0.02 0.04 80.70 18.70 0.07
38 P37-P38 P38 63.00 1.00 255 0.39 11 0.01 14 0.01 0.02 87 107 0.09 0.13 150 25.77 50.00 0.02 0.04 80.65 17.65 0.07
39 P38-P39 P39 67.00 4.00 260 1.54 12 0.01 15 0.01 0.02 76 94 0.08 0.11 150 18.49 50.00 0.01 0.04 80.62 13.62 0.06
40 P39-P40 P40 73.00 6.00 260 2.31 23 0.02 28 0.02 0.03 64 79 0.06 0.10 150 15.94 50.00 0.01 0.03 80.59 7.59 0.05
41 P40-BTS DSBTS DS 73.00 43.00 200 21.50 8 0.01 10 0.01 0.01 41 51 0.04 0.06 150 8.51 50.00 0.00 0.01 80.58 7.58 0.03

1102 2.07 3140.07 2.54 3.82


SPG31 50.00
1 SPG31-DOP DOP 21.00 29.00 65 44.62 21 0.02 26 0.02 0.03 21 26 0.02 0.03 150 5.68 50.00 0.00 0.00 50.00 29.00 0.0160

21 0 26 0 0
SPG32 30.00
1 SPG32-P41 P41 20.00 10.00 50 20.00 13 0.01 16 0.01 0.02 18 22 0.02 0.03 120 6.88 50.00 0.00 0.00 30.00 10.00 0.01
2 P41-DOP1 DOP1 18.00 2.00 60 3.33 5 0.00 6 0.00 0.01 5 6 0.00 0.01 120 6.11 50.00 0.00 0.00 30.00 12.00 0.00

18 0.01 22.17 0.02 0.03

SPG33 31.00
1 SPG33-P42 P19 21.00 10.00 72 13.89 9 0.01 11 0.01 0.01 57 70 0.06 0.09 120 11.49 50.00 0.01 0.01 30.99 9.99 0.04
2 P42-P43 P20 18.00 3.00 73 4.11 27 0.02 33 0.03 0.04 48 59 0.05 0.07 120 13.82 50.00 0.01 0.01 30.99 12.99 0.04
2 P43-DOP2 DOP2 17.00 4.00 59 6.78 21 0.02 26 0.02 0.03 21 26 0.02 0.03 120 9.11 50.00 0.00 0.00 30.98 13.98 0.02
57 0.05 70.22 0.06 0.09

SPG34 31.50
1 SPG34-P44 P44 23.00 8.50 119 7.14 18 0.01 22 0.02 0.03 31 38 0.03 0.05 120 10.45 50.00 0.00 0.00 31.50 8.50 0.02
2 P44-DOP3 DOP3 22.00 1.00 11 9.09 13 0.01 16 0.01 0.02 13 16 0.01 0.02 120 7.15 50.00 0.00 0.00 31.50 9.50 0.01

31 0.025 38.188 0.031 0.046


LR SD 33.00
1 LR SD-DOP4DOP4 21.00 12.00 9 133.33 17 0.01 21 0.02 0.03 17 21 0.02 0.03 120 4.56 50.00 0.00 0.00 33.00 12.00 0.01

17 0.01 20.94 0.02 0.03


13,105 1246 2.18 3317 2.69 4.03
DATA SURVEI SPAM DAK 2023
DESA PONKOWULU KEC. KAMBOWA
KEBUTUHAN PIPA LAYANAN
KETERANGAN
RENCANA
NO URUT NAMA KEPALA KELUARGA JUMLAH JUMLAH ALAMAT
RUMAH JIWA RUMAH PANJANG PIPA PANJANG PIPA KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

1 YUNUS 7 DESA PONGKOWULU P1


2 12 m KIRI
2 WALI MUNA 1 DESA PONGKOWULU P2

3 ADLAN, SP 2 DESA PONGKOWULU P3

4 LA LIY 3 3 23 m DESA PONGKOWULU KIRI

5 SARLAN 3 DESA PONGKOWULU P4

6 ALI TABA 7 1 6m DESA PONGKOWULU KIRI P5

7 ANTON LANDI, Sos 2 DESA PONGKOWULU P6

8 ANAS 5 3 36 m DESA PONGKOWULU KIRI

9 BAHARUDIN 2 DESA PONGKOWULU P7

10 LA RUKE 4 DESA PONGKOWULU P8


2
11 M. GANDRI 5 12 m DESA PONGKOWULU KANAN P9
12 LA ODE WELMADI 4 1 DESA PONGKOWULU P10

13 FELMAN 3 DESA PONGKOWULU P11

14 FIRDAUS 3 DESA PONGKOWULU


4 26 m KANAN
15 RIDWAN 4 DESA PONGKOWULU

16 WA DINA 4 DESA PONGKOWULU P12

17 ASRULLAH 4 DESA PONGKOWULU P13

18 JA HARIYAH 2 3 23 m DESA PONGKOWULU KANAN

19 SUSIANI 3 DESA PONGKOWULU P14

20 LA SITENI 7 DESA PONGKOWULU P15

21 JU YA 2 3 28 m DESA PONGKOWULU KANAN

22 GUSLAN 6 DESA PONGKOWULU P16

23 RUSNA 3 DESA PONGKOWULU P17


2 23 m KANAN

PONGKOWULU 16
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)
2 23 m KANAN
24 JAHADIN 5 DESA PONGKOWULU P18

25 JUSRIN 4 DESA PONGKOWULU P19

26 NURMIA 6 3 18 m DESA PONGKOWULU KANAN

27 LA ODE ALUSDIN 6 DESA PONGKOWULU P20

28 MALWI 3 1 6m DESA PONGKOWULU KANAN P21

29 LA ODE ARIF RAHMAN 3 1 6m DESA PONGKOWULU KANAN P22

30 BADARUDIN 4 DESA PONGKOWULU P23

31 LA ODE FIRMAN 6 3 18 m DESA PONGKOWULU KANAN

32 SYARIF 4 DESA PONGKOWULU P24

33 SUWARDIN 2 DESA PONGKOWULU P25

34 Drs. LA BIA, MM 7 DESA PONGKOWULU


4 38 m KANAN
35 SINURDIN 1 DESA PONGKOWULU

36 KAMALUDIN 5 DESA PONGKOWULU P26

37 WA MIYA 1 DESA PONGKOWULU P27

38 ABDUL HAMID 3 3 18 m DESA PONGKOWULU KANAN

39 NASARUDIN 9 DESA PONGKOWULU P28

40 WA MATU 3 1 6m DESA PONGKOWULU KANAN P29

41 LA FULI 8 DESA PONGKOWULU P30


2 14 m KANAN
42 WA FIA 5 DESA PONGKOWULU P31

43 WA IMPI 2 DESA PONGKOWULU P32


2 12 m KANAN
44 ASLIMIN 10 DESA PONGKOWULU P33

45 WA HAMIMA 4 DESA PONGKOWULU P34


2 34 m KANAN
46 DARTI 2 DESA PONGKOWULU P35

47 AMBOENA 1 DESA PONGKOWULU P36

48 SALUNA 10 3 24 m DESA PONGKOWULU KANAN

PONGKOWULU 17
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
3 1''24(M)
m 1/2'' (M) KANAN

49 FIRLAN 7 DESA PONGKOWULU P37

50 ASRIFAH 3 DESA PONGKOWULU P38

51 LADUNIMA 10 3 25 m DESA PONGKOWULU KANAN

52 SARIMUDIN, Sos 5 DESA PONGKOWULU P39

53 LA ABU DINA 4 DESA PONGKOWULU P40

54 LA IGE 3 DESA PONGKOWULU


4 54 m KANAN
55 JEMI 3 DESA PONGKOWULU

56 AKSA AJAS 4 DESA PONGKOWULU P41

57 WASIUN 3 DESA PONGKOWULU P42

58 LA ODE ARIIFIN 4 3 54 - DESA PONGKOWULU KANAN

59 ROSITA 4 DESA PONGKOWULU P43

60 KADIRMAN 4 DESA PONGKOWULU P44

61 SAHAMIY 4 3 22 - DESA PONGKOWULU KANAN

62 ALIMIN, W 6 DESA PONGKOWULU P45

63 LA ODE IMBRAN 5 DESA PONGKOWULU P46


2 10 - KANAN
64 LA ODE SARIFUDIN 3 DESA PONGKOWULU P47

65 DIAN PRAMANA, Spd 4 DESA PONGKOWULU P48

66 BAMBANG 5 DESA PONGKOWULU


4 33 - KANAN
67 DARMIN 4 DESA PONGKOWULU

68 LA LEBA 2 DESA PONGKOWULU P49

69 ASRULL 5 DESA PONGKOWULU P50

70 AGUS SALIM 4 DESA PONGKOWULU


4 16 - KANAN
71 RUHIMA 4 DESA PONGKOWULU

72 HAEBUDI 3 DESA PONGKOWULU P51

73 SARIANTO 4 DESA PONGKOWULU P52

4 41 - KANAN

PONGKOWULU 18
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

74 DASRAT 4 DESA PONGKOWULU


4 41 - KANAN
75 LD. AYUDIN 5 DESA PONGKOWULU

76 WA NIRI 4 DESA PONGKOWULU P53

77 ARNA 5 DESA PONGKOWULU P54

78 LA ONI 4 3 30 - DESA PONGKOWULU KANAN

79 SUKARMIN 9 DESA PONGKOWULU P55

80 WA HAW 2 DESA PONGKOWULU P56

81 LA BIMBO 6 3 27 - DESA PONGKOWULU KANAN

82 LA ODE 3 DESA PONGKOWULU P57

83 NASWATI 2 DESA PONGKOWULU P58

84 JUMAWATI 5 DESA PONGKOWULU


4 46 - KANAN
85 KARSEN 4 DESA PONGKOWULU

86 ASBEN 3 DESA PONGKOWULU P59

87 ANIS 3 DESA PONGKOWULU P60

88 LAMBOI 6 DESA PONGKOWULU


4 28 - KANAN
89 SUKRI SAMPULAWA 4 DESA PONGKOWULU

90 LA ODE RUSLIN 2 DESA PONGKOWULU P61

91 RUSDIANTO 6 DESA PONGKOWULU P62

92 PA YUDIN 5 DESA PONGKOWULU


4 26 - KANAN
93 WA UMBE 1 DESA PONGKOWULU

94 LA BARUGA 6 DESA PONGKOWULU P63

95 LA MELO 8 DESA PONGKOWULU P64

96 LD. ABA 3 DESA PONGKOWULU


4 22 - KANAN
97 WD. JARUWI 5 DESA PONGKOWULU

98 LA ABANI 8 DESA PONGKOWULU P65

PONGKOWULU 19
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

99 SAMLI 2 DESA PONGKOWULU P66

100 ARIFIN 6 DESA PONGKOWULU

101 RUSMIN 5 5 20 - DESA PONGKOWULU KANAN

102 SALUFIN 4 DESA PONGKOWULU

103 LD. GAZARUDIN 3 DESA PONGKOWULU P67

104 WA JAMLY 2 DESA PONGKOWULU P68

105 SUPARMAN ADO 6 DESA PONGKOWULU

106 SAUDIN SERA 5 5 60 - DESA PONGKOWULU KANAN

107 LA DUNE 10 DESA PONGKOWULU

108 LISWAN 3 DESA PONGKOWULU P69

109 NURLIFA LANDI 4 DESA PONGKOWULU P70


2 10 - KIRI
110 LA BAILI 6 DESA PONGKOWULU P71

111 SAFARUDDIN 5 - DESA PONGKOWULU P72

112 JAHARUDDIN 2 6 DESA PONGKOWULU

113 HAMIDIN 5 5 34 DESA PONGKOWULU KIRI

114 WA ODE 4 6 DESA PONGKOWULU

115 TASMAN 4 DESA PONGKOWULU P73

116 LA ULIA 3 DESA PONGKOWULU P74

117 KASDIN 4 DESA PONGKOWULU


4 18 -
118 UBIMA 4 DESA PONGKOWULU

119 JAYA 2 DESA PONGKOWULU P75

120 HIDAYA 4 DESA PONGKOWULU P76


2 18 - KIRI
121 WA SENA/IZAR 4 DESA PONGKOWULU P77

122 LA DINGI 8 DESA PONGKOWULU P78

123 FIRMAN 5 3 18 - DESA PONGKOWULU KIRI

PONGKOWULU 20
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
3 1'' (M) 18 1/2'' (M) - KIRI

124 RUSMAN 5 DESA PONGKOWULU P79

125 DAHLAN 6 DESA PONGKOWULU P80

126 HASWIA 3 3 18 - DESA PONGKOWULU KIRI

127 DEDI 2 DESA PONGKOWULU P81

128 SUHYADIN 10 1 - 6 DESA PONGKOWULU KIRI P82

129 LA RIM 4 DESA PONGKOWULU P83

130 LA GUU 3 DESA PONGKOWULU


4 44 - KIRI
131 LD. FIRMAN. S 2 DESA PONGKOWULU

132 LILI 1 DESA PONGKOWULU P84

133 LA LABE 8 DESA PONGKOWULU P85

134 DIANTO 5 3 18 - DESA PONGKOWULU KIRI

135 MUKRAMIN 4 DESA PONGKOWULU P86

136 BURHAN 4 DESA PONGKOWULU P87

137 AYUNA 2 DESA PONGKOWULU


4 34 - KIRI
138 JUFRIN 5 DESA PONGKOWULU

139 ALMIMI 3 DESA PONGKOWULU P88

140 WISNU 3 DESA PONGKOWULU P89

141 WANGKIDI 3 DESA PONGKOWULU


4 32 - KIRI
142 BASTIA 1 DESA PONGKOWULU

143 BASRI 5 DESA PONGKOWULU P90

144 SUNUSIA 1 1 - - DESA PONGKOWULU KIRI P91

145 M. ALI BARANTA 3 1 - - DESA PONGKOWULU KIRI P91 A

146 MURSYD 7 1 - - DESA PONGKOWULU KIRI P92

147 JAHAWIYAH 7 1 - - DESA PONGKOWULU KIRI P93

148 WA UNE 2 DESA PONGKOWULU P94


2 24 - KIRI

PONGKOWULU 21
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)
2 24 - KIRI
149 TAMRIN 5 DESA PONGKOWULU P95

150 TEGUH YULIANTO 8 DESA PONGKOWULU P94 A


2 24 0 KIRI
151 LA TONI 5 DESA PONGKOWULU P94 B

152 SARMIN 7 1 - - DESA PONGKOWULU KIRI P95 A

153 MAULIMA 2 1 - 6 DESA PONGKOWULU KIRI P96

154 PELIS TONO 4 1 - 12 DESA PONGKOWULU KIRI P97

155 SAMIHA 2 DESA PONGKOWULU P98

156 WAFUD 4 DESA PONGKOWULU


4 24 - KIRI
157 ANDI M. ARIF 4 DESA PONGKOWULU

158 WA TAIMA 2 DESA PONGKOWULU P99

159 BASILA 3 2 - 6 DESA PONGKOWULU KIRI P100

160 LANGKAWILO 4 DESA PONGKOWULU P101

161 ARBI LAGONI 5 3 27 - DESA PONGKOWULU KIRI

162 LD. SYARIFUDIN. M 8 DESA PONGKOWULU P102

163 WD. HARNI 8 DESA PONGKOWULU P103

164 ARDIN 4 DESA PONGKOWULU

165 RANDI 3 DESA PONGKOWULU


6 32 - KIRI
166 HASAN. K 4 DESA PONGKOWULU

167 ISMANI 4 DESA PONGKOWULU

168 LD. HANIF 2 DESA PONGKOWULU P104

169 KAZMAN 4 DESA PONGKOWULU P105

170 SARMAN BANUS 3 DESA PONGKOWULU

171 ALIDIN 3 5 60 DESA PONGKOWULU KIRI

172 LA SUDI 4 DESA PONGKOWULU

173 ALWIN 4 6 DESA PONGKOWULU P106

PONGKOWULU 22
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

174 WA AYANI 2 DESA PONGKOWULU P107

175 RASNI 6 DESA PONGKOWULU


4 20 - KIRI
176 SUMARLIN 5 DESA PONGKOWULU

177 KASRIN 2 DESA PONGKOWULU P108

178 LANDILI 4 DESA PONGKOWULU P109

179 HENDRA 5 DESA PONGKOWULU


4 28 - KIRI
180 WA ALMI 3 DESA PONGKOWULU

181 NARDIN 4 DESA PONGKOWULU P110

182 WAROKAH 1 DESA PONGKOWULU P111

183 ROKLAH 4 DESA PONGKOWULU


4 19 - KIRI
184 LD. RAHMAN 5 DESA PONGKOWULU

185 SAFLUDIN 5 DESA PONGKOWULU P112

186 HARMINA 3 DESA PONGKOWULU P114

187 IRMAN 6 3 22 - DESA PONGKOWULU KIRI

188 NOERKASAN 4 DESA PONGKOWULU P115

189 JAFAR SALIM 4 DESA PONGKOWULU P116


2 12 - KIRI
190 PAPE 1 DESA PONGKOWULU P117

191 HASRIA 5 2 6 - DESA PONGKOWULU KIRI P118

192 ASHAR 5 1 12 - DESA PONGKOWULU KIRI P119

193 LA EMIO 2 2 22 - DESA PONGKOWULU KIRI P120

194 YUDI 5 DESA PONGKOWULU P211

195 AMINAH 1 3 - 6 DESA PONGKOWULU KIRI

196 MARDI 2 DESA PONGKOWULU P212

197 TAARI 8 1 - - DESA PONGKOWULU KIRI P213

198 JAMI 4 DESA PONGKOWULU P123

3 24 - KIRI

PONGKOWULU 23
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

199 LA SARISUM 3 3 24 - DESA PONGKOWULU KIRI

200 SARTIA 2 DESA PONGKOWULU P124

201 ELI ISKANDAR 4 DESA PONGKOWULU P125

202 ALUSE 6 DESA PONGKOWULU


4 40 - KIRI
203 AMIRUDIN 3 DESA PONGKOWULU

204 LA SUMI 4 DESA PONGKOWULU P126

205 CHAERUDIN 3 DESA PONGKOWULU P127

206 LA OMBA 5 3 40 - DESA PONGKOWULU KIRI

207 LD. RISMAN DESA PONGKOWULU P113

208 DARMAN 3 DESA PONGKOWULU P128


2 12 - KIRI
209 HAERUDIN 5 DESA PONGKOWULU P129

210 JAMALUDIN (BAKSO) 1 DESA PONGKOWULU P130


2 24 - KIRI
211 MUSTAJA 1 DESA PONGKOWULU P131

212 LA TAKE 4 DESA PONGKOWULU P132

213 MUSTAJA 4 DESA PONGKOWULU


4 30 - KIRI
214 ARIANTO 4 DESA PONGKOWULU

215 BASNI 1 DESA PONGKOWULU P133

216 KAHARUDIN 4 1 - 6 DESA PONGKOWULU KIRI P134

217 LA MUDIN 6 DESA PONGKOWULU P135

218 M. ARIS 6 3 30 - DESA PONGKOWULU KIRI

219 M. ASRI DARMIN 4 DESA PONGKOWULU P136

220 JAMLI 1 1 - 6 DESA PONGKOWULU KIRI P137

221 KIRODIOS 4 DESA PONGKOWULU P138


2 120 - KIRI
222 LA BAETU 2 DESA PONGKOWULU P139

223 LA ADE 7 DESA PONGKOWULU O140

3 24 - KIRI

PONGKOWULU 24
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

224 RUSMAN 4 3 24 - DESA PONGKOWULU KIRI

225 ALIMIN 7 DESA PONGKOWULU P140

226 ATIMA (TPQ) 1 1 - - DESA PONGKOWULU KIRI P142

227 WA URI 1 DESA PONGKOWULU P143

228 ANSAR 7 3 30 - DESA PONGKOWULU KIRI

229 LD. IMRAN 5 DESA PONGKOWULU P144

230 LD. ANULDIN 8 1 - 12 DESA PONGKOWULU KIRI P145

231 NENI ARNIA 4 DESA PONGKOWULU P146


2 12 KIRI
232 LA PANDU 3 DESA PONGKOWULU P147

233 LD. RIANTO 6 DESA PONGKOWULU P148


2 18 - KIRI
234 WD. SAIDA 1 DESA PONGKOWULU P149

235 ARDIANTO 3 DESA PONGKOWULU P150


2 24 - KIRI
236 SAERUDIN 3 DESA PONGKOWULU P151

237 LD. RUSLIN 5 DESA PONGKOWULU P152


2 30 - KIRI
238 AKRI 4 DESA PONGKOWULU P153

239 SAMSUDIN 5 1 - 50 DESA PONGKOWULU KIRI P154

240 ABU. N 2 DESA PONGKOWULU P155


2 18 - KIRI
241 WA HIRA 3 DESA PONGKOWULU P156

242 IRWAN 9 DESA PONGKOWULU P157


2 30 - KIRI
243 LANDAU 7 DESA PONGKOWULU P158

244 SALIM 3 1 - - DESA PONGKOWULU KIRI P159

245 RASIDIN 3 DESA PONGKOWULU P160

246 LA URAWA 6 3 36 - DESA PONGKOWULU KIRI

247 LANCAWE 10 DESA PONGKOWULU P161

248 JABAR 5 1 - 12 DESA PONGKOWULU KIRI P162

PONGKOWULU 25
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

249 NASDIN 6 DESA PONGKOWULU P163


2 24 - KIRI
250 MITA 5 DESA PONGKOWULU P164

251 LA SIRUDI 5 1 - 18 DESA PONGKOWULU KIRI P165

252 JUMADI 7 1 - 18 DESA PONGKOWULU KIRI P166

253 LA ASI 3 DESA PONGKOWULU P167

254 SULIMIN 4 DESA PONGKOWULU


4 84 - KIRI
255 YUSUF 5 DESA PONGKOWULU

256 LA SINAENI 2 DESA PONGKOWULU P168

257 WA AWI 2 1 - 12 DESA PONGKOWULU KIRI P169

258 PATRIA 4 1 - 12 DESA PONGKOWULU KIRI P170

259 LA RASIMA 2 DESA PONGKOWULU P171


2 60 - KIRI
260 ARIANI 3 DESA PONGKOWULU P172

JUMLAH 1081 263 1721 200 DESA PONGKOWULU


#VALUE! DESA PONGKOWULU

#VALUE! 220 DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

PONGKOWULU 26
KEBUTUHAN PIPA LAYANAN KETERANGAN
RENCANA
NO URUT JUMLAH JUMLAH
NAMA KEPALA KELUARGA PANJANG PIPA PANJANG PIPA ALAMAT
RUMAH JIWA RUMAH KIRI/KANAN KODE GPS
1'' (M) 1/2'' (M)

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU

#VALUE! DESA PONGKOWULU W

PONGKOWULU 27
BACK UP DATA
Instansi :
Pekerjaan :
Lokasi :
Tahun Anggaran :
Item Pekerjaan : Bak Reservoir Uk. 3,5 X 3,5 X 2,5 Mtr

No. Jenis Pekerjaan

A Pekerjaan Persiapan Panjang (M) Lebar ( M )


1 Pekerjaan Pemasangan Bouwplang 3 3
B Pekerjaan Galian Tanah Dan Urugan Panjang (M) Lebar ( M ) Tinggi (M)
1 Galian Tanah Pasangan Pondasi 8 0.63 0.500
2 Urugan Pasir Alas Pondasi 8 0.63 0.005
3 Urugan Kembali Galian Pondasi = (1/3 x Galian Tanah Pondasi)
4 Urugan Tanah Timbunan Pondasi 2.87 2.87 0.400
C Pekerjaan Pasangan
1 Pasangan Pondasi Batu kosong 8 0.63 0.15

2 Pasangan Pondasi Batu Gunung Panjang (M)


Lebar Atas Lebar
( M ) Bawah ( M )
8 0.25 0.50
D Pekerjaan Beton
1 Pek. Rabat lantai kerja beton Panjang (M) Lebar ( M ) Tebal (M)
1.75 1.75 0.05

2 Pek. Plat Lantai Beton Dan Dinding Jumlah sisi Panjang (M) Lebar (M)
- Plat Lantai 2.00 2.00
- Dinding 4 2.00 2.00
Total Beton Lantai dan Dinding
3 Pek. Plat Lantai Penutup Panjang (M) Lebar (M)
a. Vol. Plat Keseluruhan 2.35 2.35
b. Vol. Plat Manhole 0.90 0.90
Vol. Plat netto = (Vol.a - Vol.b)

E Pekerjaan Pembesian Plat Lantai, dinding Dan Plat Penutup


Jumlah
Tulangan/ Panjang/ Berat
1 Pek. Pembesian 1 kg Plat Lantai Bawah Dan Dinding (Pem Potongan potongan Besi/ Mtr
(Bh) (M) (Kg)

- Tulangan Pokok (Besi Ø 12 mm) 56.0 6.5 0.888


- Tulangan Pembagi (Besi Ø 10 mm) 24.0 8.5 0.617
Total Pembesian Lantai Dan Dinding
2 Pek. Pembesian Plat Lantai Atas (Besi Ø 10 mm) 60 2.3 0.617
F Pekerjaan Bekisting, Plat Lantai, Dinding, Dan Plat Penutup

1 Pek. Bekisting Dinding Dan Plat Lantai Panjang (M) Tinggi (M) Jumlah
Sisi Luar
a. Bekisting Luar 2.15 1.88 4.00
b. Bekisting Dalam 1.85 1.76 4.00
Total Pek. Bekisting Dinding Dan Lantai
2 Pek. Bekisting Plat Lantai Atas Panjang (M) Lebar (M)
a. Luas Bekisting Keseluruhan 2.3 2.30
b. Luas Manhole 0.9 0.90
Total Luas Bekisting Plat = (Luas a - Luas b)

G Pekerjaan Plesteran Dan Acian Panjang (M) Lebar (M)


1 Plesteran Dinding Luar 8.6 1.88
2 Plesteran Dinding Dalam 7.4 1.76
Total Plesteran Dinding
3 Plesteran Pondasi L.a (M) L.b (M) L. rata-rata (M)
2.25 3.55 2.90
Total Pekerjaan Plesteran
Volume Total KET.

K = (P + L) X 2
12 M'
V= PXLXT
2.520 M3
0.025 M3
0.840 M3
3.295 M3

0.756 M3

Tinggi (M) V = ((L1 + L2)/2) x T X P


0.90 2.70 M3

V=PXLXT
0.15 M3

Tinggi (M) V = P X L X M3
0.15 0.6000 M3
0.15 2.4000 M3
3.00 M3 14.66667
Tebal (M) V = P X L X M3 14
0.12 0.66 M3 56
0.12 0.10 M3 12
0.57 M3

Jumlah (Kg)

TABEL BERAT BESI


323.05 Kg DIMENSI KG/MTR
125.80 Kg Ø 16 1.578333
448.85 Kg Ø 14 1.208333
85.10 Kg Ø 12 0.8875
Ø 10 0.616667
Ø8 0.394167
L=PXL
Ø6 0.221667
16.17 M2
13.02 M2
29.19 M2
L=PXL
5.29 M2
0.81 M2
6.10 M2

L=PXL
16.17 M2
13.02 M2
29.19 M2
Tinggi (M)
0.44 1.26 M2
30.45 M2

0
0
0

-
0
KG/BTG
18.94
14.5
10.65
7.4
4.73

2.66
REKAPITULASI BIAYA

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

NO URAIAN KEGIATAN JUMLAH HARGA (Rp)

NO/DIV 2 3

A PEKERJAAN PERSIAPAN 7,350,000.00


B RENCANA KESELAMATAN DAN KESEHATAN KERJA (RK3K) 6,430,000.00
C PEKERJAAN BAK 57,758,690.38
D PEKERJAAN BOX VALVE 39,753,227.67
F PEKERJAAN SAMBUNGAN RUMAH (SR) 282,985,667.02
G PEKERJAAN PIPA DAN AKSESORIES 861,378,744.79
I JUMLAH 1,255,656,329.86
II Pajak Pertambahan Nilai ( PPN ) = 11% x (I) 138,122,196.28
III TOTAL COST( I + II + ) 1,393,778,526.15
IV DI BULATKAN 1,393,778,000.00
Terbilang : #NAME?

Buranga, November 2022


Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
SR HARGA SATUAN PAGU SELISIH
REAL 263 7,500,000.00 1,972,500,000.00 -
PAGU 190 7,500,000.00 1,425,000,000.00 1,425,000,000.00
DAFTAR KUANTITAS DAN HARGA

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA
DIV. URAIAN KEGIATAN SAT. VOL JUMLAH HARGA
SATUAN

1 2 3 4 5 6 = (4 x 5)
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Jalur Pipa Ls 1 2,500,000.00 2,500,000.00
2 Pengukuran dan Pemasangan Patok Jalur Pipa Ls 1 2,000,000.00 2,000,000.00
3 Papan Nama Proyek Ls 1 350,000.00 350,000.00
4 Administrasi Foto dan Dokumentasi Ls 1 2,500,000.00 2,500,000.00
JUMLAH TOTALPEKERJAAN PERSIAPAN 7,350,000.00

Buranga, November 2022


Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
DAFTAR KUANTITAS DAN HARGA

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA JUMLAH
No/DIV. URAIAN KEGIATAN SAT. VOL
SATUAN (Rp) HARGA (Rp)

1 2 3 4 5 6 = (4 x 5)
B RENCANA KESELAMATAN DAN KESEHATAN KERJA (RK3K)
1 Penyiapan Dokumen Penerapan SMKK :
- Pembuatan Prosedur Dan Instruksi Kerja Ls 1 500,000.00 500,000.00
2 Alat PelindUng Kerja dan Alat pelindung diri
a.
- Alat
Topi Pelindung Diri (APD)
Pelindung (Safety Helmet)
Bh 3 75,000.00 225,000.00
- Masker
Sarung Tangan (Safety Gloves) Dos 1 350,000.00 350,000.00
- Sepatu Keselamatan (Safety Shoes) Bh 3 10,000.00 30,000.00
Bh 3 200,000.00 600,000.00
- Rompi Keselamatan (Safety Vest) Bh 3 50,000.00 150,000.00
3 Sosialisasi, Promosi dan Pelatihan
- Pelatihan K3 Org 0 100,000.00 0.00
- Spanduk K3 (banner) Bh 1 0.00
- Spanduk K3 (Banner) Bh 1 70,000.00 70,000.00
- Papan Informasi K3 Bh 1 50,000.00 50,000.00
4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi
- Asuransi (Construktion All Risk/CAR) Ls 1 1,000,000.00 1,000,000.00
5 Personel Keselamatan Konstruksi K3
- Petugas K3 Ls 3 800,000.00 2,400,000.00
6 Fasilitas Sarana,prasarana dan alat Kesehatan
- Peralatan P3K (Kotak P3k, Obat Luka dan Perban) Set 1 350,000.00 350,000.00
7 Ranbu-rambu K3
- Rambu Larangan Bh 1 35,000.00 35,000.00
- Rambu Peringatan Bh 1 35,000.00 35,000.00
8 Konsultasi dengan tenaga ahli terkait keselamatan konstruksi
- Ahli Lingkungan Ls 1 600,000.00 600,000.00
9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konstruksi
- Bendera K3 Bh 1 35,000.00 35,000.00
JUMLAH SUB. 6,430,000.00
JUMLAH SUB. (Dipindahkan Ke Rekapitulasi) 6,430,000.00

Buranga, November 2022

Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang
Ahmat Haafi, ST
Nip.19900325 21903 1 015
DAFTAR KUANTITAS DAN HARGA
KABUPATEN : BUTON UTARA
INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA
JUMLAH
NO/ DIV URAIAN KEGIATAN SAT. VOL SATUAN
HARGA (Rp)
(Rp)
1 2 3 4 5 6 = (4 x 5)
D PEKERJAAN BAK 2
1.1.1 Pekerjaan Persiapan
1.1.1.4 Pek. Pemasangan Bouwplang M2 12 76,370 916,440.00
Jumlah Sub Pek. Pemasangan Bouwplang 916,440.00
2.3.1 Pekerjaan Tanah
Penggalian 1 m3 tanah biasa sedalam 1 m Pondasi Batu
2.3.1.1 M3 2.52 107,237.50 270,238.50
Gunung
2.3.1.9 Pek. Urugan Kembali Alur Pondasi Batu Gunung M3 0.84 76,475.00 64,239.00
2.3.1.11 Pek. Urugan Pasir Alas Pondasi dan Alas Lantai M 3
0.03 291,295.00 7,340.63
2.3.1.9 Pek. Urugan Kembali Tanah Alas Lantai Bekas Galian M3 3.29 76,475.00 251,966.77
Jumlah Sub Pekerjaan Tanah 593,784.91
3.2.1 Pekerjaan Pondasi
3.2.1.9 Pek. Pas. Pondasi Batu Kosong M3 0.76 656,845.50 496,575.20
3.2.1.2 Pek. Pas. Pondasi BT. Gunung 1 : 4 M 3
2.70 1,204,682.50 3,252,642.75
Jumlah Sub Pekerjaan Pondasi 3,749,217.95
4.1.1 Pekerjaan Beton
4.1.1.4 Pek. Membuat 1 m3 lantai kerja M3 0.15 1,337,112.94 204,745.42
4.1.1.6 Pek. Dinding dan Lantai Beton tebal 15 Cm Camp. 1:2:3 M3 3.00 1,504,600.40 4,513,801.20
4.1.1.17 Pek. Pembesian 1 kg Besi Polos Lantai dan Dinding Kg 449 24,614.60 11,048,263.21
4.1.1.25 Pek. Bekisting Dinding M2 29.19 485,840.50 14,182,655.88
4.1.1.6 Pek. Plat Penutup Beton Tebal 12 CM Camp. 1:2:3 M3 0.57 1,504,600.40 850,851.53
4.1.1.17 Pek. Pembesian 1 kg Besi Polos Plat Penutup Kg 85.10 24,614.60 2,094,702.46
4.1.1.25 Pek. Bekisting Plat Penutup M2 6.10 469,165.50 2,861,909.55
Jumlah Sub Pekerjaan Beton 35,756,929.24
4.4.2 Pekerjaan Plesteran
4.4.2.3 Pek. 1 m2 plesteran 1SP : 3PP tebal 15mm. (Dinding
M2 30.45 90,879.90 2,767,611.03
Luar Dalam Dan Pondasi)
4.4.2.27
Pek. Pemasangan 1 m2 acian Dinding Luar Dan Dalam M2 55,286.25 1,683,659.81
30.45
Jumlah Sub Pekerjaan Plesteran 4,451,270.85
4.7.1 Pekerjaan Pengecatan
Pek. Pengecatan 1 m2 tembok + Lantai Dalam (Cat
4.7.1.10 M2 30.45 21,990.30 669,681.60
Anti Bocor)
Jumlah Sub Pekerjaan Pengecatan 669,681.60
Dihitung Pekerjaan Lainnya
Pek. Pengadaan dan Pemasangan Papan Nama Granit
1 Bh 1 2,500,000.00 2,500,000.00
Ukir Uk 60 X 120 Cm
Jumlah Sub Pekerjaan Lainnya 2,500,000.00
10.4.1 Pekerjaan Pipa Dan Aksesories
10.4.1.33 Pek. Pipa Gi Ø 2" Medium A ( Pipa Outlate ) M' 2 154,985.50 309,971.00
Dihitung Pek. Pipa Gi Ø 1,5" Medium A ( Pipa Inlate ) M' 4 198,738.21 794,952.83
10.4.1.33 Pek. Pipa Gi Ø 2" Medium A ( Penguras dan peluap ) M' 4 154,985.50 619,942.00
Pek. Pengadaan Gate Valve Flange Ø 2" Bh 1 3,125,000.00 3,125,000.00
Pek. Pengadaan Flange Drat GI 2" Bh 2 113,500.00 227,000.00
Pek. Paking Ø 2" Bh 2 20,250.00 40,500.00
Knee Gip Ø 2" Bh 2 102,000.00 204,000.00
Pek. Tangga Monyet Ls 1 2,500,000.00 2,500,000.00
Pek. Pengadaan Manhole 90x90 CM LS 1 1,300,000.00 1,300,000.00
Jumlah Sub Pekerjaan Pipa Dan Aksesories 9,121,365.83

Jumlah Total Pekerjaan Bak 2 57,758,690

Buranga, November 2022

Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
DAFTAR KUANTITAS DAN HARGA

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA
NO/DIV URAIAN KEGIATAN SAT. VOL JUMLAH HARGA
SATUAN

1 2 3 4 5 6 = (4 x 5)
E PEKERJAAN BOX VALVE
2.3.1 Pekerjaan Tanah
2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m M3 1.18 107,237.50 126,861.96
Jumlah Sub.Pekerjaan Tanah 126,861.96
4.4.1 Pekerjaan Pasangan Dinding
Pek. Pemasangan 1m2 dinding bata merah (5x11x22)
4.4.1.8 M2 4.14 347,627.75 1,439,178.89
cm tebal 1 batu campuran 1SP : 3PP
Jumlah Sub.Pekerjaan Pasangan Dinding 1,439,178.89
4.4.2 Pekerjaan Plesteran
4.4.2.3 Pek. Plesteran Tembok Luar dan Dalam 1 : 4 M2 4.88 90,879.90 443,493.91
4.4.2.27 Pek. Acian Dinding Luar Tembok M2
2.08 55,286.25 114,995.40
Jumlah Sub.Pekerjaan Plesteran 558,489.31
4.7.1 Pekerjaan Pengecattan DLL
1 Pek. Pemb. Plat Penutup Manhole 100 x 100 cm Ls 1.00 1,300,000.00 1,300,000.00
Pek. Pengecatan 1 m2 tembok baru ( 1lapis
4.7.1.10 M2 2.08 20,939.20 43,553.54
plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Jumlah Sub.Pekerjaan Pengecattan Dll 1,343,553.54
Jumlah Sub.Pekerjaan Box Valve 3,468,083.70
Jumlah Total Pekerjaan Box Valve 7.00 BH 24,276,585.87

Buranga, November 2022


Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
RENCANA ANGGARAN BIAYA SAMBUNGAN RUMAH (SR)

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA
DIV. URAIAN KEGIATAN SAT. VOL JUMLAH HARGA
SATUAN

1 2 3 4 5 6 = (4 x 5)
F PEKERJAAN SAMBUNGAN RUMAH (SR)
2.3.1 Pekerjaan Tanah
Penggalian 1 m3 tanah biasa sedalam 1 m
2.3.1.1 Jalur Pipa, Dudukan Box Materan, Dan M3 0.08 107,237.50 8,364.53
Dudukan Ember
2.3.1.9 Pek. Urugan Kembali Jalur Pipa M3 0.06 76,475.00 4,492.40
JUMLAH I 12,856.92
4.1.1 Pekerjaan beton
Pek. Membuat 1 m3 beton Tumbuk Camp,
4.1.1.4 1:3:5 Dudukan Box Materan, Dudukan M3 0.04 1,337,112.94 59,688.72
Ember, Dan Sandaran Pipa SR
Pek. Pemasangan 1 m2 bekisting untuk
Dihitung M2 0.628 260,210.50 163,412.19
kolom, Sandaran Pipa SR
JUMLAH II 223,100.92
4.4.2 PEKERJAAN PLESTERAN
Pek. Acian Dudukan Box Materan, Dudukan
4.4.2.27 M2 0.288 55,286.25 15,922.44
Ember, Dan Sandaran Pipa SR
JUMLAH II 15,922.44
Dihitung PEKERJAAN PENGADAAN PIPA DAN ASESORIES (SAMBUNGAN RUMAH)
1 Soket Drat Luar PVC SNI Ø1/2" Bh 1 4,995.00 4,995.00
2 Knee PVC SNI Ø1/2" Bh 4 5,940.00 23,760.00
3 Faucet Elbow PVC SNI Ø1/2" Bh 2 4,995.00 9,990.00
4 Double Nipple GI Ø 1/2" Bh 1 4,781.25 4,781.25
5 Stop Kran Gi Ø 1/2" Kuningan Bh 1 103,000.00 103,000.00
6 Water Meter 1/2" (Standar PDAM) Bh 1 378,000.00 378,000.00
7 Boks Meteran Bh 1 98,550.00 98,550.00
8 Tee PVC SNI Ø 1/2" Bh 1 9,990.00 9,990.00
9 Socket Drat Dalam PVC SNI Ø 1/2" Bh 1 4,995.00 4,995.00
10 Kran Air GI Ø1/2" Bh 1 33,750.00 33,750.00
11 Dop PVC SNI Ø1/2" Bh 1 3,510.00 3,510.00
12 Paku Beton 5 CM Bh 4 1,000.00 4,000.00
JUMLAH III 679,321.25
8.4.1 PEKERJAAN PEMASANGAN PIPA PIPA SR
Dihitung Pek. Pemasangan 1 m’ pipa PVC Dia 1/2” M1 6 24,131.60 144,789.60
JUMLAH IV 144,789.60
JUMLAH TOTAL 1,075,991.13
JUMLAH TOTALPEKERJAAN SAMBUNGAN RUMAH (SR) 263 bh 282,985,667.02

Buranga, November 2022

Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
DAFTAR KUANTITAS DAN HARGA

KABUPATEN : BUTON UTARA


INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

HARGA
DIV. URAIAN KEGIATAN SAT. VOLUME JUMLAH HARGA
SATUAN

1 2 3 4 5 6 = (4 x 5)
G PEKERJAAN PIPA DAN AKSESORIES
2.3.1 Pekerjaan Tanah
2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m M3 401.88 107,237.50 43,096,606.50
2.3.1.4 Penggalian 1 m3 tanah Keras sedalam 1 m M 3 142,784.00 0.00
2.3.1.9 Pek. Urugan kembali galian M 3
656.57 76,475.00 50,210,818.84
Jumlah Sub Pekerjaan Tanah 93,307,425.34
10.4.1 PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA TRANSMISI, DISTRIBUSI DAN LAYANAN
a Pekerjaan Pengadaan Dan Pemasangan Pipa Transmisi
Dihitung Pek. Pipa HDPE PN-10 Ø 3" M' 168 164,283.25 27,599,586.00
10.4.2.17 Pek. Pipa HDPE PN-10 Ø 2" Relokasi M' 100 13,961.00 1,396,100.00
10.4.2.1.1 Pek. Pipa HDPE PN-10 Ø 2" M' 3,463 60,561.30 209,723,781.90
Dihitung Pek. Pipa PVC SNI S-12,5 Ø 1,5" Relokasi M' 3,258 10,327.00 33,645,366.00
Jumlah Sub Pekerjaan Pengadaan Dan Pemasangan Pipa Transmisi 272,364,833.90
b Pekerjaan Pengadaan Dan Pemasangan Pipa Distribusi
Dihitung Pek. Pipa HDPE PN-10 Ø 3" M' 1,021 164,283.25 167,733,198.25
10.4.2.1.2 Pek. Pipa PVC SNI S-12,5 Ø 3" M' 1,560 107,801.00 168,169,560.00
10.4.2.1.1 Pek. Pipa PVC SNI S-12,5 Ø 2" M' 1,428 83,320.38 118,981,495.50
Dihitung Pek. Pipa PVC SNI S-12,5 Ø 1,5" M' 696 51,913.30 36,131,656.80
Jumlah Sub Pekerjaan Pengadaan Dan Pemasangan Pipa Distribusi 491,015,910.55
c Pekerjaan Pengadaan Dan Pemasangan Pipa Layanan
Dihitung Pek. Pipa PVC SNI S-10 Ø 1" ( Pipa Layanan ) M' 33,350.00 0.00
Dihitung Pek. Pipa PVC SNI S-6,3 Ø 1/2" Pipa SR M' 27,029.60 0.00
Jumlah Sub Pekerjaan Pengadaan Dan Pemasangan Pipa Layanan 0.00
Dihitung Pek. Pengadaan Aksesoris Pipa
d Pengadaan Aksesoris Pipa HDPE
1 Flange HDPE Ø 3" Bh 0 157,545.00 0.00
2 Flange HDPE Ø 2" Bh 0 104,355.00 0.00
3 Stube End HDPE Ø 3" Bh 306,720.00 0.00
4 Stube End HDPE Ø 2" Bh 281,340.00 0.00
5 Tee All Flange HDPE Ø 3" Bh 0.00
6 Tee All Flange HDPE Ø 2" Bh 0.00
7 Tee Reducer HDPE Ø 3"X2" Bh 302,130.00 0.00
8 Tee Reducer HDPE Ø 3"X1,5" Bh 294,975.00 0.00
9 Elbow HDPE 90° Ø 3" Bh 417,150.00 0.00
10 Elbow HDPE 90° Ø 2" Bh 291,330.00 0.00
11 End Cup HDPE Ø 2" Bh 281,340.00 0.00
Pengadaan Aksesoris Pipa Galvanis (Gi)
1 Gate Valve Flange GiØ 3" Bh 3,125,000.00 0.00
2 Gate Valve Flange GiØ 2" Bh 2,062,500.00 0.00
3 Water Meter Flange Ø 3" Bh 3,591,250.00 0.00
4 Water Meter Flange Ø 2" Bh 2,534,125.00 0.00
5 Clamp sadle Gi Ø 3"X1" Bh 108,250.00 0.00
6 Clamp sadle Gi Ø 3"X1/2" Bh 104,000.00 0.00
7 Clamp sadle Gi Ø 2"X1" Bh 71,000.00 0.00
8 Clamp sadle Gi Ø 2"X1/2" Bh 67,875.00 0.00
9 Clamp sadle Gi Ø 1"X1/2" Bh 63,897.50 0.00
10 Air Valve Drat Ø 1" Bh 318,750.00 0.00
Pengadaan Aksesoris PipaPVC
1 Tee PVC Ø 1" Bh 0 17,685.00 0.00
2 Sok drat luar PVC Ø 1" Bh 0 8,370.00 0.00
3 Knee PVC Ø 1" Bh 20 11,475.00 229,500.00
4 dop PVC Ø 1" Bh 0 7,560.00 0.00
Pengadaan Aksesoris dan Bahan Lainnya
1 Pressure Guage 16 Bar Bh 3 114,750.00 344,250.00
2 Paking Karet Ø 3" Bh 0 20,250.00 0.00
3 Paking Karet Ø 2" Bh 0 13,500.00 0.00
4 Baut Flange Shock Bh 0 10,937.50 0.00
5 Lem Pipa 400 Gram Klg 24 78,300.00 1,879,200.00
6 Saltipe Bh 255 8,775.00 2,237,625.00
Jumlah Sub Pek. Pengadaan Aksesoris Pipa 4,690,575.00
Jumlah Total Pekerjaan Pipa Dan Aksesoris 861,378,744.79

Buranga, November 2022


Di Buat Oleh :
Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang

Ahmat Haafi, ST
Nip.19900325 21903 1 015
A.8.4.1. HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 20 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 20 mm m 1.000 6,594.00 6,594.00
TOTAL BIAYA BAHAN 6,594.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 23,504.00
E Overhead + profit 15 % x D 3,525.60
F Harga satuan pekerjaan (D + E) 27,029.60

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 25 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 25 mm m 1.000 10,828.00 10,828.00
TOTAL BIAYA BAHAN 10,828.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 27,738.00
E Overhead + profit 15 % x D 4,160.70
F Harga satuan pekerjaan (D + E) 31,898.70

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 32 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 32 mm m 1.000 12,090.00 12,090.00
TOTAL BIAYA BAHAN 12,090.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 29,000.00
E Overhead + profit 15 % x D 4,350.00
F Harga satuan pekerjaan (D + E) 33,350.00

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 40 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 40 mm m 1.000 17,872.00 17,872.00
TOTAL BIAYA BAHAN 17,872.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 34,782.00
E Overhead + profit 15 % x D 5,217.30
F Harga satuan pekerjaan (D + E) 39,999.30

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 50 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 50 mm m 1.000 28,232.00 28,232.00
TOTAL BIAYA BAHAN 28,232.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 45,142.00
E Overhead + profit 15 % x D 6,771.30
F Harga satuan pekerjaan (D + E) 51,913.30

Dihitung Pemasangan 1 m pipa PVC Ø 50 mm Relokasi


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.016 120,000.00 1,944.00
Tukang pipa L.02 OH 0.016 150,000.00 2,430.00
Mandor L.04 OH 0.016 130,000.00 2,106.00
TOTAL UPAH TENAGA 6,480.00
B BAHAN
Pipa PVC Ø 50 mm m 1.000 0.00 0.00
TOTAL BIAYA BAHAN 0.00
C PERALATAN
Biaya Angkut Pipa m 1.000 2,500.00 2,500.00
0.00
TOTAL BIAYA PERALATAN 2,500.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 8,980.00
E Overhead + profit 15 % x D 1,347.00
F Harga satuan pekerjaan (D + E) 10,327.00

A. 8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 63 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang pipa L.02 OH 0.041 150,000.00 6,150.00
Mandor L.04 OH 0.008 130,000.00 1,040.00
TOTAL UPAH TENAGA 16,910.00
B BAHAN
Pipa PVC Ø 63 mm m 1.000 35,752.00 35,752.00
TOTAL BIAYA BAHAN 35,752.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 52,662.00
E Overhead + profit 15 % x D 7,899.30
F Harga satuan pekerjaan (D + E) 60,561.30

Catatan :

Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang tercantum pada tabel. Apabila ada
tambahan peralatan yang digunakan, maka harus disesuaikan dengan spesifikasi dan gambar kerja.
A. 8.4.1.2 (K3) Pemasangan 1 m pipa PVC Ø 90 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.094 120,000.00 11,280.00
Tukang pipa L.02 OH 0.047 150,000.00 7,050.00
Mandor L.04 OH 0.009 130,000.00 1,170.00
TOTAL UPAH TENAGA 19,500.00
B BAHAN
Pipa PVC Ø 90 mm m 1.000 74,240.00 74,240.00
TOTAL BIAYA BAHAN 74,240.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.008 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 93,740.00
E Overhead + profit 15 % x D 14,061.00
F Harga satuan pekerjaan (D + E) 107,801.00

A. 8.4.1.3 (K3) Pemasangan 1 m pipa PVC Ø 110 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.105 120,000.00 12,600.00
Tukang pipa L.02 OH 0.053 150,000.00 7,950.00
Mandor L.04 OH 0.011 130,000.00 1,430.00
TOTAL UPAH TENAGA 21,980.00
B BAHAN
Pipa PVC Ø 100 mm m 1.000 109,678.00 109,678.00
TOTAL BIAYA BAHAN 109,678.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 131,658.00
E Overhead + profit 15 % x D 19,748.70
F Harga satuan pekerjaan (D + E) 151,406.70

A. 8.4.1.4 (K3) Pemasangan 1 m pipa PVC Ø 150 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.118 120,000.00 14,160.00
Tukang pipa L.02 OH 0.059 150,000.00 8,850.00
Mandor L.04 OH 0.012 130,000.00 1,560.00
TOTAL UPAH TENAGA 24,570.00
B BAHAN
Pipa PVC Ø 150 mm m 1.000 #N/A #N/A
TOTAL BIAYA BAHAN #N/A
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.012 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) #N/A
E Overhead + profit 15 % x D #N/A
F Harga satuan pekerjaan (D + E) #N/A

A. 8.4.1.17 (K3) Pemasangan 1 m pipa HDPE Ø 63 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.035 120,000.00 4,200.00
Tukang pipa L.02 OH 0.017 150,000.00 2,550.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 7,140.00
B BAHAN
HDPE Ø 2" m 1.000 60,312.50 60,312.50
TOTAL BIAYA BAHAN 60,312.50
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
0.00
TOTAL BIAYA PERALATAN 5,000.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 72,452.50
E Overhead + profit 15 % x D 10,867.88
F Harga satuan pekerjaan (D + E) 83,320.38

Dihitung Pemasangan 1 m pipa HDPE Ø 63 mm Relokasi Pipa


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.035 120,000.00 4,200.00
Tukang pipa L.02 OH 0.017 150,000.00 2,550.00
Mandor L.04 OH 0.003 130,000.00 390.00
TOTAL UPAH TENAGA 7,140.00
B BAHAN
HDPE Ø 2" m 1.000 0.00 0.00
TOTAL BIAYA BAHAN 0.00
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
0.00
TOTAL BIAYA PERALATAN 5,000.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 12,140.00
E Overhead + profit 15 % x D 1,821.00
F Harga satuan pekerjaan (D + E) 13,961.00
A. 8.4.1.18 (K3) Pemasangan 1 m pipa HDPE Ø 90 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.040 100,000.00 4,000.00
Tukang pipa L.02 OH 0.020 130,000.00 2,600.00
Mandor L.04 OH 0.004 120,000.00 480.00
TOTAL UPAH TENAGA 7,080.00
B BAHAN
HDPE Ø 3" m 1.000 119,375.00 119,375.00
TOTAL BIAYA BAHAN 119,375.00
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
Sewa Tripot/Tackel & handle crane 2 T Hari 0.019 600,000.00 11,400.00
TOTAL BIAYA PERALATAN 16,400.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 142,855.00
E Overhead + profit 15 % x D 21,428.25
F Harga satuan pekerjaan (D + E) 164,283.25

A. 8.4.1.18 (K3) Pemasangan 1 m pipa HDPE Ø 110 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.040 100,000.00 4,000.00
Tukang pipa L.02 OH 0.020 130,000.00 2,600.00
Mandor L.04 OH 0.004 120,000.00 480.00
TOTAL UPAH TENAGA 7,080.00
B BAHAN
HDPE Ø 4" m 1.000 178,275.00 178,275.00
TOTAL BIAYA BAHAN 178,275.00
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
Sewa Tripot/Tackel & handle crane 2 T Hari 0.019 600,000.00 11,400.00
TOTAL BIAYA PERALATAN 16,400.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 201,755.00
E Overhead + profit 15 % x D 30,263.25
F Harga satuan pekerjaan (D + E) 232,018.25

A. 8.4.1.19 (K3) Pemasangan 1 m pipa HDPE Ø 125 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.045 100,000.00 4,500.00
Tukang pipa L.02 OH 0.023 130,000.00 2,990.00
Mandor L.04 OH 0.005 120,000.00 600.00
TOTAL UPAH TENAGA 8,090.00
B BAHAN
HDPE Ø 5" m 1.000 227,237.50 227,237.50
TOTAL BIAYA BAHAN 227,237.50
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
Sewa Tripot/Tackel & handle crane 2 T Hari 0.019 600,000.00 11,400.00
TOTAL BIAYA PERALATAN 16,400.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 251,727.50
E Overhead + profit 15 % x D 37,759.13
F Harga satuan pekerjaan (D + E) 289,486.63

A. 8.4.1.20 (K3) Pemasangan 1 m pipa HDPE Ø 150 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.062 100,000.00 6,200.00
Tukang pipa L.02 OH 0.031 130,000.00 4,030.00
Mandor L.04 OH 0.006 120,000.00 720.00
TOTAL UPAH TENAGA 10,950.00
B BAHAN
HDPE Ø 6" m 1.000 373,437.50 373,437.50
TOTAL BIAYA BAHAN 373,437.50
C PERALATAN
Sewa Butt Fusion Welding/ Mesin Las HDPE Jam 0.025 200,000.00 5,000.00
Sewa Tripot/Tackel & handle crane 2 T Hari 0.019 600,000.00 11,400.00
TOTAL BIAYA PERALATAN 16,400.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 400,787.50
E Overhead + profit 15 % x D 60,118.13
F Harga satuan pekerjaan (D + E) 460,905.63

Dihitung Pemasangan 1 m pipa GIP Ø 32 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.345 100,000.00 34,500.00
Tukang pipa L.02 OH 0.172 130,000.00 22,360.00
Mandor L.04 OH 0.034 120,000.00 4,080.00
TOTAL UPAH TENAGA 60,940.00
B BAHAN
Pipa Gi Ø 1" m 1.000 73,830.00 73,830.00
TOTAL BIAYA BAHAN 73,830.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 134,770.00
E Overhead + profit 15 % x D 20,215.50
F Harga satuan pekerjaan (D + E) 154,985.50

Dihitung Pemasangan 1 m pipa GIP Ø 40 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.345 100,000.00 34,500.00
Tukang pipa L.02 OH 0.172 130,000.00 22,360.00
Mandor L.04 OH 0.034 120,000.00 4,080.00
TOTAL UPAH TENAGA 60,940.00
B BAHAN
Pipa Gi Ø 1,25" m 1.000 97,366.67 97,366.67
TOTAL BIAYA BAHAN 97,366.67
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 158,306.67
E Overhead + profit 15 % x D 23,746.00
F Harga satuan pekerjaan (D + E) 182,052.67

Dihitung Pemasangan 1 m pipa GIP Ø 50 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.345 100,000.00 34,500.00
Tukang pipa L.02 OH 0.172 130,000.00 22,360.00
Mandor L.04 OH 0.034 120,000.00 4,080.00
TOTAL UPAH TENAGA 60,940.00
B BAHAN
Pipa Gi Ø 1,5" m 1.000 111,875.83 111,875.83
TOTAL BIAYA BAHAN 111,875.83
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 172,815.83
E Overhead + profit 15 % x D 25,922.38
F Harga satuan pekerjaan (D + E) 198,738.21

A. 8.4.1.33 (K3) Pemasangan 1 m pipa GIP Ø 63 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.345 100,000.00 34,500.00
Tukang pipa L.02 OH 0.172 130,000.00 22,360.00
Mandor L.04 OH 0.034 120,000.00 4,080.00
TOTAL UPAH TENAGA 60,940.00
B BAHAN
Pipa Gi Ø 2" m 1.000 152,643.33 152,643.33
TOTAL BIAYA BAHAN 152,643.33
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 213,583.33
E Overhead + profit 15 % x D 32,037.50
F Harga satuan pekerjaan (D + E) 245,620.83

A. 8.4.1.34 (K3) Pemasangan 1 m pipa GIP Ø 90 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.400 100,000.00 40,000.00
Tukang pipa L.02 OH 0.200 130,000.00 26,000.00
Mandor L.04 OH 0.040 120,000.00 4,800.00
TOTAL UPAH TENAGA 70,800.00
B BAHAN
Pipa Gi Ø 3" m 1.000 251,543.33 251,543.33
TOTAL BIAYA BAHAN 251,543.33
C PERALATAN
Sewa Butt Fusion Welding Jam 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 322,343.33
E Overhead + profit 15 % x D 48,351.50
F Harga satuan pekerjaan (D + E) 370,694.83

A. 8.4.1.34 (K3) Pemasangan 1 m pipa GIP Ø 100 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.400 100,000.00 40,000.00
Tukang pipa L.02 OH 0.200 130,000.00 26,000.00
Mandor L.04 OH 0.040 120,000.00 4,800.00
TOTAL UPAH TENAGA 70,800.00
B BAHAN
Pipa Gi Ø 4" m 1.000 364,051.67 364,051.67
TOTAL BIAYA BAHAN 364,051.67
C PERALATAN
Sewa Butt Fusion Welding Jam 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 434,851.67
E Overhead + profit 15 % x D 65,227.75
F Harga satuan pekerjaan (D + E) 500,079.42

A. 8.4.1.35 (K3) Pemasangan 1 m pipa GIP Ø 125 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.448 100,000.00 44,800.00
Tukang pipa L.02 OH 0.224 130,000.00 29,120.00
Mandor L.04 OH 0.045 120,000.00 5,400.00
TOTAL UPAH TENAGA 79,320.00
B BAHAN
Pipa Gi Ø 5" m 1.000 489,976.67 489,976.67
TOTAL BIAYA BAHAN 489,976.67
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 569,296.67
E Overhead + profit 15 % x D 85,394.50
F Harga satuan pekerjaan (D + E) 654,691.17

A. 8.4.1.36 (K3) Pemasangan 1 m pipa GIP Ø 150 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 0.506 100,000.00 50,600.00
Tukang pipa L.02 OH 0.253 130,000.00 32,890.00
Mandor L.04 OH 0.051 120,000.00 6,120.00
TOTAL UPAH TENAGA 89,610.00
B BAHAN
Pipa Gi Ø 6" m 1.000 583,299.17 583,299.17
TOTAL BIAYA BAHAN 583,299.17
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T Hari 0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 672,909.17
E Overhead + profit 15 % x D 100,936.38
F Harga satuan pekerjaan (D + E) 773,845.54
Pengakatan Pipa/30 meter

30 6 5
BACK UP DATA
Instansi : :
Pekerjaan : :
Lokasi : :
Tahun Anggaran : :
Item Pekerjaan : Pek. Pemasangan Pipa

Panjang TInggi
No. Jenis Pekerjaan (M) Lebar ( M ) (M)

I PERHITUNGAN GALIAN TANAH PEK. PIPA


A Pekerjaan Galian Tanah TRANSMISI
1 Pek. Pipa HDPE PN-10 Ø 3" 168 0.3 0.50
2 Pek. Pipa HDPE PN-10 Ø 2" (PIPA RELOKASI) 100 0.2 0.30
3 Pek. Pipa HDPE PN-10 Ø 2" 3463 0.2 0.30
4 Pek. Pipa PVC SNI S-12,5 Ø 1,5" (PIPA RELOKASI) 3258 0.2 0.25
Jumlah Pekerjaan Galian Tanah TRANSMISI
B Pekerjaan Galian Tanah Biasa Pemasangan Pipa Distribusi
1 Pek. Pipa HDPE PN-10 Ø 3" 1021 0.3 0.3
2 Pek. Pipa PVC SNI S-12,5 Ø 3" 1560 0.25 0.29
3 Pek. Pipa PVC SNI S-12,5 Ø 2" 1428 0.2 0.25
4 Pek. Pipa PVC SNI S-12,5 Ø 1,5" 696 0.2 0.2
Jumlah Pekerjaan Galian Tanah Biasa Pemasangan Pipa Distribusi
C Pekerjaan Galian Tanah Pemasangan Pipa Layanan dan Sambungan Rumah
1 Pek. Pipa PVC SNI S-6,3 Ø 1" 0.15 0.15
2 Pek. Pipa PVC SNI S-10 Ø 1/2" 0.15 0.15
Jumlah Pekerjaan Galian Tanah Pemasangan Pipa Layanan dan Sambungan Rumah
II PERHITUNGAN URUGAN KEMBALI GALIAN TANAH PEK. PIPA
A Perhitungan Volume Pi Pjg Pipa Luas Penampang (M2)
Ø Pipa (M) (M) = (μr2)
1 HDPE Ø 3" 0.09 168 0.006
2 HDPE Ø 2" 0.063 3,563 0.003
PVC Ø 3" 0.09 3,954 0.006
PVC Ø 2" 0.063 1,428 0.003
PVC Ø 1.5" 0.05 3,954 0.002
3 PVC Ø 1" 0.032 0 0.001
4 PVC Ø 1/2" 0.02 0 0.000

* Vol. Urugan = Vol. Galian - Vol. Pipa


* Vol. Galian Pipa
* Vol. Pipa
TOTAL PEKERJAAN GALIAN PIPA
B Pergantian Kerusakan Pipa Eksisting 300

0.00
0
0

0
0
Volume Total
V=PXLXT KET.
M3

78
25.20 M3 240
6.00 M3 96
207.78 M3 54
162.90 M3 162
401.88 M3 66
696
91.89 M3
113.10 M3
71.40 M3
27.84 M3
304.23 M3
-
- M3
- M3
- M3

V. Pipa = P X Luas p (M3)

1.07 M3
11.11 M3
25.15
4.45
7.76
- M3
- M3
49.54 M3
pa
706.11 M3
49.54 M3
656.57 M3

0
0
-

-
0
DAFTAR HARGA BAHAN

KABUPATEN :
INSTANSI :
NAMA PEKERJAAN :
LOKASI :
TAHUN ANGGARAN :

HARGA
NO UPAH TENAGA/MATERIAL SAT SPESIFIKASI KETERANGAN
SATUAN\
1 2 3
A. UPAH TENAGA
1 Pekerja OH 120,000.00
2 Tukang kayu OH 150,000.00
3 Tukang batu OH 150,000.00
4 Tukang besi OH 150,000.00
5 Tukang pipa OH 150,000.00
6 Tukang cat OH 150,000.00
7 Kepala tukang OH 160,000.00
8 Mandor OH 130,000.00
B BAHAN DASAR
1 Tanah urug M3 110,000.00
2 Pasir urug M3 180,000.00
3 Pasir pasang M3 180,000.00
4 Pasir beton M3 180,000.00
5 Pasir beton M3 380,000.00 PEK. PMA
6 Batu belah M3 275,000.00
7 Bata merah Bh 900.00
8 Batako Uk. 10 x 20 x 40 Bh 6,083.33
9 Split 2-3 Cm M3 430,000.00
10 Kerikil (Maks 30 mm) M3 430,000.00
Kerikil (Maks 30 mm) M3 630,000.00 PEK. PMA
11 Sirtu M3 165,000.00
12 Semen Portland Kg 1,900.00
13 Semen Portland Kg 3,800.00
14 Air Liter 41.67
C. BAHAN KAYU
1 Papan Kayu Jati M3 5,080,000.00
2 Balok Kayu Jati M3 5,080,000.00
3 Papan Kayu Bayam M3 5,080,000.00
4 Balok Kayu Bayam M3 5,080,000.00
5 Papan Kayu Kalapi M3 4,625,000.00
6 Balok Kayu Kalapi M3 4,550,000.00
7 Papan Kayu Biti M3 4,880,000.00
8 Balok Kayu Biti M3 4,580,000.00
9 Papan Kayu Meranti M3 2,580,000.00
10 Balok Kayu Meranti M3 2,430,000.00
11 Kayu Balok 5/7 M3 2,380,000.00
12 Kayu Papan 3/20 M3 2,580,000.00
13 Balok kayu kelas II M3 2,380,000.00
14 Papan Kayu Kelas III M3 1,880,000.00
15 Penjaga jarak bekisting / spacer Bh 16,600.00
16 Dolken kayu Ø 8-10 panjang 400 cm Btg 15,000.00
D. BAHAN BESI
1 Besi beton (polos/ulir) Kg 18,000.00
2 Besi beton (polos/ulir) 21,000.00 PEK. PMA
3 Kawat Beton Kg 30,000.00
4 Kawat Nyamuk M2 130,000.00
5 Kawat Ayak M2 115,000.00
6 Kawat Duri M' 95,000.00
7 Kawat Harmonika Tinggi 4 Cm 1,2 Mtr (50 Rol 5,080,000.00
8 Kawat Harmonika 4Cm Tinggi 1,2 Mtr M2 5,080,000.00
9 Paku Biasa 2"-5" Kg 25,000.00
10 Paku Tripleks Kg 40,000.00
11 Paku Beton Kg 75,000.00
12 Paku Seng Kg 50,000.00
13 Paku Skrup Kg 50,000.00
14 Paku Tembok 5 CM Bh 1,000.00
15 Hollow Metal 40x60x2 mm M' 41,000.00
16 Hollow Metal 50x100x2 mm M' 51,000.00
17 Anchor Bolt M12 x 400 mm Buah 5,000.00
18 Besi Siku 30x30x3 mm btg 125,000.00
19 Besi Siku 40x40x4 mm btg 140,000.00
20 Besi Siku 50x50x5 mm btg 240,000.00
E. BAHAN ATAP
1 Soka Abadi (4x4) P(140) L(80) Ef(1,12mm) Lbr 80,000.00
2 Sakura (2x4) P(77) L(80) T(0,22mm)
3 Multi Color (2x4) P(77) L(100) T(0,4mm)
4 Seng Gelombang BJLS 0,20 mm 6 kaki Lbr 67,000.00
5 Seng Plat BJLS 0,20 mm M' 15,000.00
6 Nok 180 Cm
7 Nok 105 Cm
8 Nok 95 Cm
F. BAHAN LANGIT-LANGIT
1 Playwood 4 mm Lbr 80,000.00
2 Playwood 6 mm Lbr 120,000.00
3 Playwood 9 mm Lbr 160,000.00
4 Multipleks 4 mm
5 Multipleks 6 mm
6 Multipleks 9 mm
7 Kalsiboard 3,5 mm
8 Kalsiboard Ling 4 mm
9 Kalsiboard Ling 6 mm
10 Kalsiboard Ling 9 mm
11 Gipsum Board 4mm
12 Gipsum Board 9 mm
13 Lem Kayu Kg 15,011.00
14 List Profil 2 x 3 Cm
15 List Profil 3 x 3 Cm
16 List Profil 4 x 4 Cm
17 List Profil 2 x 5 Cm
18 Tegel Kramik
19 Putih 10 x 20 Cm
20 Warna 10 x 20 Cm
21 Putih 20 x 20 Cm
22 Warna 20 x 20 Cm
23 Putih 20 x 25 Cm
24 Warna 20 x 25 Cm
25 Putih 30 x 30 Cm
26 Warna 30 x 30 Cm
27 Putih 40 x 40 Cm
28 Warna 40 x 40 Cm
29 Putih 50 x 50 Cm
30 Warna 50 x 50 Cm
31 Putih 60 x 60 Cm
32 Warna 60 x 60 Cm
33 Granit Tile
34 Ukuran 40 x 40 Cm
35 Ukuran 50 x 50 Cm
36 Ukuran 60 x 60 Cm
37 Batu Alam Uk. Kecil
38 Batu Alam Uk. Besar
39 Pavin Block
G. BAHAN CAT
1 Cat Tembok Kg 30,000.00
2 Alkali Kg 25,000.00
3 Cat Gloteks Kg 65,000.00
4 Cat Avian Kg 60,000.00
5 Meni Kayu Kg 35,000.00
6 Dempul Impra Kg 50,000.00
7 Meni Besi Kg 35,000.00
8 Plamur Kg 20,000.00
9 Tiner A ltr 50,000.00
10 Minyak Cat ltr 10,000.00
11 Kuas Biasa 2,5" Bh 15,000.00
12 Amplas Kasar Lbr 10,000.00
13 Amplas Halus Lbr 10,000.00
14 Soda api Kg 20,000.00
15 Minyak Bekisting Kg 14,000.00
H. Pipa Galvanis Medium A Pjg 6 Meter
1 Pipa Gi Ø 6" M' 583,299.17
2 Pipa Gi Ø 5" M' 489,976.67
3 Pipa Gi Ø 4" M' 364,051.67
4 Pipa Gi Ø 3" M' 251,543.33
5 Pipa Gi Ø 2,5" M' 194,618.33
6 Pipa Gi Ø 2" M' 152,643.33 GALVANIS SNI
MEDIUM A
7 Pipa Gi Ø 1,5" M' 111,875.83
8 Pipa Gi Ø 1,25" M' 97,366.67
GALVANIS SNI
MEDIUM A

9 Pipa Gi Ø 1" M' 73,830.00


10 Pipa Gi Ø 3/4" M' 48,970.83
11 Pipa Gi Ø 1/2" M' 38,065.00
I Assesories Pipa GI
a Knee Gip 90°
- Ukuran dia. 6" Bh 733,125.00
- Ukuran dia. 4" Bh 184,875.00
- Ukuran dia. 3" Bh 102,000.00
- Ukuran dia. 2,5" Bh 66,937.50
- Ukuran dia. 2 Bh 35,062.50
- Ukuran dia. 1,5" Bh 22,312.50
- Ukuran dia. 1,25" Bh 17,850.00
- Ukuran dia. 1" Bh 11,156.25
- Ukuran dia. 3/4" Bh 7,650.00
- Ukuran dia. 1/2" Bh 5,418.75
b Knee Gip 45°
- Ukuran dia. 4" Bh 207,187.50
- Ukuran dia. 3" Bh 121,125.00
- Ukuran dia. 2,5" Bh 79,687.50
- Ukuran dia. 2" Bh 38,250.00
- Ukuran dia. 1,5" Bh 25,500.00
- Ukuran dia. 1,25" Bh 20,718.75
- Ukuran dia. 1" Bh 12,750.00
- Ukuran dia. 3/4" Bh 8,606.25
- Ukuran dia. 1/2" Bh 6,125.00
c Tee
- Ukuran dia. 4" Bh 242,250.00
- Ukuran dia. 3" Bh 133,875.00
- Ukuran dia. 2,5" Bh 102,000.00
- Ukuran dia. 2" Bh 44,625.00
- Ukuran dia. 1,5" Bh 29,962.50
- Ukuran dia. 1,25" Bh 23,587.50
- Ukuran dia. 1" Bh 15,618.75
- Ukuran dia. 3/4" Bh 9,881.25
- Ukuran dia. 1/2" Bh 6,693.75
d SOK
- Ukuran dia. 4" Bh 114,750.00
- Ukuran dia. 3" Bh 70,125.00
- Ukuran dia. 2,5" Bh 47,812.50
- Ukuran dia. 2" Bh 25,500.00
- Ukuran dia. 1,5" Bh 16,575.00
- Ukuran dia. 1,25" Bh 13,387.50
- Ukuran dia. 1" Bh 9,562.50
- Ukuran dia. 3/4" Bh 5,737.50
- Ukuran dia. 1/2" Bh 4,687.50
e Baut Flange
- Ukuran dia. 3/4" pjng 7 cm Bh 12,913.75
- Ukuran dia. 5/8" pjng 7 cm Bh 10,937.50
- Ukuran dia. 1/2" pjng 5 cm Bh 6,625.00
f Gate Valve Flange
- Ukuran dia. 6" Bh 5,625,000
- Ukuran dia. 4" Bh 3,750,000
- Ukuran dia. 3" Bh 3,125,000
- Ukuran dia. 2,5" Bh 2,750,000
- Ukuran dia. 2" Bh 2,062,500
- Ukuran dia. 1,5" Bh 1,225,000
g Flange Drat
- Ukuran dia. 6" Bh 318,750
- Ukuran dia. 4" Bh 175,250
- Ukuran dia. 3" Bh 113,500
- Ukuran dia. 2,5" Bh 89,250
- Ukuran dia. 2" Bh 54,188
h Gate Valve kuningan
- Ukuran dia. 3" Bh 1,375,000
- Ukuran dia. 2 Bh 561,000
- Ukuran dia. 1,5 Bh 385,000
- Ukuran dia. 1 Bh 131,500
- Ukuran dia. 1/2" Bh 103,000
i Clamp Saddle GI
- Clamp Saddle GI ø 4 " x 1" Bh 116,250
- Clamp Saddle GI ø 4 " x 1/2" Bh 113,750
- Clamp Saddle GI ø 3 " x 1" Bh 108,250
- Clamp Saddle GI ø 3 " x 1/2" Bh 104,000
- Clamp Saddle GI ø 2 " x 1" Bh 71,000
- Clamp Saddle GI ø 2 " x 1/2" Bh 67,875
- Clamp Saddle GI ø 1,5" x 1" Bh 62,125
- Clamp Saddle GI ø 1,5" x 1/2" Bh 58,125
- Clamp Saddle GI ø 1" x 1/2" Bh 63,898
j Water Moer
- Ukuran dia. 4" Bh 382,500
- Ukuran dia. 3" Bh 238,313
- Ukuran dia. 2,5" Bh 127,500
- Ukuran dia. 2" Bh 73,313
- Ukuran dia. 1,5" Bh 51,000
- Ukuran dia. 1,25" Bh 38,250
- Ukuran dia. 1" Bh 27,094
- Ukuran dia. 3/4" Bh 22,313
- Ukuran dia. 1/2" Bh 18,169
k double Nepel
- Ukuran dia. 4" Bh 111,563
- Ukuran dia. 3" Bh 70,125
- Ukuran dia. 2,5" Bh 41,438
- Ukuran dia. 2" Bh 24,863
- Ukuran dia. 1,5" Bh 18,169
- Ukuran dia. 1,25" Bh 13,069
- Ukuran dia. 1" Bh 8,925
- Ukuran dia. 3/4" Bh 6,375
- Ukuran dia. 1/2" Bh 4,781
l Reducer Drat Gi
- Reducer Drat 4X3 Bh 268,750
- Reducer Drat 4X2 Bh 231,250
- Reducer Drat 3X2 Bh 150,000
l Air Valve/Pentil Udara Drat
- Air Valve/Pentil Udara Uk. 4" Bh 2,437,500
- Air Valve/Pentil Udara Uk. 3" Bh 1,593,750
- Air Valve/Pentil Udara Uk. 2" Bh 1,232,500
- Air Valve/Pentil Udara Uk. 1" Bh 318,750
m Water Meter
- Water Meter Flange 6" Bh 4,738,750
- Water Meter Flange 4" Bh 4,175,000
- Water Meter Flange 3" Bh 3,591,250
- Water Meter Flange 2" Bh 2,534,125
- Water Meter 1/2"+Boks Penutup (Standar PDAM) 400,000
m lainnya
- Kran Air GI Dia. 1/2" Bh 32,300.00

J Pipa PVC SNI S12,5 -SC


- Pipa PVC Ø 100 mm M' 109,678
- Pipa PVC Ø 90 mm M' 74,240 PVC SNI S-12,5
- Pipa PVC Ø 75 mm M' 51,252 PJG 6 METER
- Pipa PVC Ø 63 mm M' 35,752
- Pipa PVC Ø 50 mm M' 28,232
PVC SNI S-10 PJG
- Pipa PVC Ø 40 mm M' 17,872
6 METER
- Pipa PVC Ø 32 mm M' 12,090
- Pipa PVC Ø 25 mm M' 10,828
PVC SNI S-6,3 PJG 6 METER
- Pipa PVC Ø 20 mm M' 6,594
K Assesories Pipa PVC
a Bend/Elbow 90°-SC
- Bend 90° Ø 4" Bh 221,130.00
- Bend 90° Ø 3" Bh 151,335.00
- Bend 90° Ø 2" Bh 70,335.00
- Bend 90° Ø 1,5 Bh 47,790.00
- Bend 90° Ø 1,25" Bh 43,470.00
- Knee 90° Ø 1" Bh 11,475.00
- Knee 90° Ø 1/2" Bh 5,940.00
b Bend/Elbow 45°-SC
- Bend 45° Ø 4" Bh 198,045.00
- Bend 45° Ø 3" Bh 130,680.00
- Bend 45° Ø 2" Bh 60,750.00
- Bend 45° Ø 1,5" Bh 39,555.00
- Bend 45° Ø 1,25" Bh 35,235.00
- knee 45° Ø 1" Bh 7,560.00
- Knee 45° Ø 1/2" Bh 9,990.00
c Socket Drat Luar/ valve socket-SC
- valve socket Ø 4" Bh 292,545.00
- valve socket Ø 3" Bh 121,500.00
- valve socket Ø 2" Bh 46,845.00
- valve socket Ø 1" Bh 8,370.00
- valve socket Ø 1/2" Bh 4,995.00
d Socket Drat Dalam/ Foucet socket-SC
- Foucet socket Ø 4" Bh 127,035.00
- Foucet socket Ø 3" Bh 63,450.00
- Foucet socket Ø 2" Bh 31,725.00
- Foucet socket Ø 1,5" Bh 16,200.00
- Foucet socket Ø 1" Bh 8,370.00
- Foucet socket Ø 1/2" Bh 4,995.00
e Tee-SC
- Tee Ø 4" 284,323.50
- Tee Ø 3" Bh 172,354.50
- Tee Ø 2" Bh 85,171.50
- Tee Ø 1,5" Bh -
- Tee Ø 1 " Bh 17,685.00
- Tee Ø 1/2 " Bh 9,990.00
f Reducer-SC
- Reducer Ø 4" x 3" Bh 106,920.00
- Reducer Ø 4" x 2" Bh 101,520.00
- Reducer Ø 3" x 2" Bh 87,750.00
- Reducer Ø 3" x 1-1/2" Bh 78,840.00
- Reducer Ø 2" x 1-1/2" Bh 61,155.00
- Reducer Ø 2"x 1" Bh 52,245.00
g End Cap / Dop-SC
- End Cap Ø 6" Bh 249,480.00
- End Cap Ø 4" Bh 106,515.00
- End Cap Ø 3" Bh 53,325.00
- End Cap Ø 2" Bh 30,240.00
- End Cap Ø 1,5" Bh 15,525.00
- End Cap Ø 1" Bh 7,560.00
- End Cap Ø 1/2" Bh 3,510.00
h Faucet Elbow 90°-SC
- Faucet Elbow Ø 1" Bh 15,255.00
- Faucet Elbow Ø 3/4" Bh 8,640.00
- Faucet Elbow Ø 1/2" Bh 4,995.00
i Shock-SC
- Shock PVC Ø 4" Bh 156,465.00
- Shock PVC Ø 3" Bh 49,545.00
- Shock PVC Ø 2" Bh 26,730.00
- Shock PVC Ø 1,5" Bh 11,475.00
- Shock PVC Ø 1" Bh 7,425.00
- Shock PVC Ø 1/2" Bh 4,860.00
j Flange Shock-SC
- Flange Shock Ø 4"-SC Bh 547,897.50
- Flange Shock Ø 3"-SC Bh 427,882.50
- Flange Shock Ø 2"-SC Bh 314,145.00
PIPA HDPE
L
- HDPE Ø 6" M' 373,437.50
- HDPE Ø 5" M' 227,237.50
- HDPE Ø 4" M' 178,275.00
PN-10
- HDPE Ø 3" M' 119,375.00
- HDPE Ø 2" M' 60,312.50
- HDPE Ø 1,5" M' 37,712.50
L Aksesories HDPE
1 Aksesoris HDPE Compression Joint (Sambungan Drat)
a Coupler
- Coupler Ø 3" 616,950.00
- Coupler Ø 2" 264,600.00
- Coupler Ø 1,5" 191,700.00
- Coupler Ø 1" 87,750.00
- Coupler Ø 1/2" 56,700.00
b Tee
- Tee Ø 3" 953,100.00
- Tee Ø 2" 396,900.00
- Tee Ø 1,5" 279,450.00
- Tee Ø 1" 125,550.00
- Tee Ø 1/2" 74,250.00
c Elbow 90°
- Elbow Ø 3" 602,100.00
- Elbow Ø 2" 251,100.00
- Elbow Ø 1,5" 206,550.00
- Elbow Ø 1" 68,850.00
- Elbow Ø 1/2" 27,000.00
d End Cap
- End Cap Ø 3" 469,800.00
- End Cap Ø 2" 172,800.00
- End Cap Ø 1,5" 128,250.00
- End Cap Ø 1" 43,200.00
- End Cap Ø 1/2" 29,700.00
e Famale Thread Adaptor ( Shock Drat Dalam)
- Famale Thread Adaptor Ø 3" 391,500.00
- Famale Thread Adaptor Ø 2" 166,050.00
- Famale Thread Adaptor Ø 1,5" 118,800.00
- Famale Thread Adaptor Ø 1" 52,650.00
- Famale Thread Adaptor Ø 1/2" 39,150.00
f Male Thread Adaptor ( Shock Drat Luar)
- Male Thread Adaptor Ø 3" 382,050.00
- Male Thread Adaptor Ø 2" 163,350.00
- Male Thread Adaptor Ø 1,5" 114,750.00
- Male Thread Adaptor Ø 1" 48,600.00
- Male Thread Adaptor Ø 1/2" 32,400.00
g Reducing Coupler
- Reducing Coupler Ø 3" X 2" 602,100.00
- Reducing Coupler Ø 3" X 1,5" 475,200.00
- Reducing Coupler Ø 2" X 1,5" 251,100.00
- Reducing Coupler Ø 2" X 1" 243,318.60
- Reducing Coupler Ø 1,5" X 1" 176,850.00
- Reducing Coupler Ø 1" X 1/2" 146,963.70
2 Aksesoris HDPE Segmented Joint (Sambungan menggunakan mesin)
a Tee Segmented Hdpe
- Tee Ø 6" 891,270.00
- Tee Ø 4" 579,285.00
- Tee Ø 3" 494,910.00
- Tee Ø 2" 359,235.00
b Tee Reduser Segmented Hdpe -
- Tee Ø 4"X4"X3" 407,295.00
- Tee Ø 4"X4"X2" 402,030.00
- Tee Ø 3"X3"X2" 302,130.00
- Tee Ø 3"X3"X1,5" 294,975.00
c Elbow 90° Segmented Hdpe -
- Elbow Ø 6" 1,041,795.00
- Elbow Ø 4" 512,595.00
- Elbow Ø 3" 417,150.00
- Elbow Ø 2" 249,480.00
d Elbow 45° Segmented Hdpe -
- Elbow Ø 6" 797,985.00
- Elbow Ø 4" 416,745.00
- Elbow Ø 3" 320,220.00
- Elbow Ø 2" 291,330.00
e Stube End (Sambungan Flange) Hdpe -
- Stube End Ø 6" 649,215.00
- Stube End Ø 4" 378,810.00
- Stube End Ø 3" 306,720.00
- Stube End Ø 2" 281,340.00
f Flange Hdpe -
- Flange Ø 6" 363,015.00
- Flange Ø 4" 210,060.00
- Flange Ø 3" 157,545.00
- Flange Ø 2" 104,355.00
g End Cap (Dop) Hdpe -
- End Cap Ø 6" -
- End Cap Ø 5" -
- End Cap Ø 4" 1,011,150.00
- End Cap Ø 3" 469,800.00
- End Cap Ø 2" 172,800.00
- End Cap Ø 1,5" -
- End Cap Ø 1" -
- End Cap Ø 1/2" -
h Reduser Hdpe -
- Reducer Ø 6" X 4" -
- Reducer Ø 4" X 3" -
- Reducer Ø 4" X 2" 1,011,150.00
- Reducer Ø 3" X 2" 469,800.00
- Reducer Ø 2" X 1,5" 172,800.00
M Assesories Dan Bahan Lainnya
- Water Meter 1/2" (Standar PDAM) Bh 378,000.00
- Box Meteran Air (30 cm x 15 cm x 20 cm) Bh 98,550.00
- Kran Air GI Dia. 1/2" Bh 33,750.00
- Double Nipple GI dia. 1/2" Bh 28,350.00
- Paking Karet Ø 6" Bh 60,750.00
- Paking Karet Ø 4" Bh 40,500.00
- Paking Karet Ø 3" Bh 20,250.00
- Paking Karet Ø 2" Bh 13,500.00
- Pressure Guage 16 bar Bh 114,750.00
- Sealtape Bh 8,775.00
- Lem Pipa 400 Gram Kaleng 78,300.00
- Kunci Pipa Ukuran 18" Bh 438,750.00

0 0
0 0
HARGA TOKO PPN 11% BIAYA TRANSPORT 15% HARGA SATUAN
30,000 - 80,000 - 110,000
100,000 - 80,000 - 180,000
100,000 - 80,000 - 180,000
100,000 - 80,000 - 180,000
100,000 - 280,000 - 380,000
150,000 - 125,000 - 275,000
650,000 - 250,000 - 900,000
650,000 - 80,000 - 730,000
350,000 - 80,000 - 430,000
350,000 - 80,000 - 430,000
350,000 - 280,000 - 630,000
65,000 - 100,000 - 165,000
1,800 - 100 - 1,900
1,800 - 2,000 - 3,800
42 - - 42

5,000,000 - 80,000 - 5,080,000


5,000,000 - 80,000 - 5,080,000
5,000,000 - 80,000 - 5,080,000
5,000,000 - 80,000 - 5,080,000
4,500,000 - 125,000 - 4,625,000
4,300,000 - 250,000 - 4,550,000
4,800,000 - 80,000 - 4,880,000
4,500,000 - 80,000 - 4,580,000
2,500,000 - 80,000 - 2,580,000
2,350,000 - 80,000 - 2,430,000
2,300,000 - 80,000 - 2,380,000
2,500,000 - 80,000 - 2,580,000
2,300,000 - 80,000 - 2,380,000
1,800,000 - 80,000 - 1,880,000
15,000 - 1,600 - 16,600
10,000 - 5,000 - 15,000 DIAMETER
Ø 16
- - Ø 14

30,000 - - - 30,000 Ø 12
50,000 - 80,000 - 130,000 Ø 27
35,000 - 80,000 - 115,000 Ø 28
15,000 - 80,000 - 95,000 Ø 29
5,000,000 - 80,000 - 5,080,000 Ø 30
5,000,000 - 80,000 - 5,080,000 Ø 31
25,000 - - - 25,000 Ø 10
40,000 - - - 40,000
75,000 - - 75,000
50,000 - - 50,000
50,000 - - - 50,000
1,000 - - - 1,000
40,000 - 1,000 - 41,000
50,000 - 1,000 - 51,000
5,000 - - - 5,000
120,000 - 5,000 - 125,000
135,000 - 5,000 - 140,000
235,000 - 5,000 - 240,000

- -
- -
- -
66,000 - 1,000 - 67,000
15,000 - - - 15,000
235,002 - 5,002 - 240,004
235,003 - 5,003 - 240,006
235,004 - 5,004 - 240,008

80,000 - - 80,000
120,000 - - 120,000
160,000 - - 160,000
15,002 - - 15,002
15,003 - - 15,003
15,004 - - 15,004
15,005 - - 15,005
15,006 - - 15,006
15,007 - - 15,007
15,008 - - 15,008
15,009 - - 15,009
15,010 - - 15,010
15,011 - - 15,011
15,012 1,651 12 2,501 19,177
15,013 1,651 13 2,502 19,179
15,014 1,652 14 2,502 19,181
15,015 1,652 15 2,502 19,184
15,017 1,652 17 2,503 19,189
15,018 1,652 18 2,503 19,191
15,019 1,652 19 2,504 19,194
15,020 1,652 20 2,504 19,196
15,021 1,652 21 2,504 19,198
15,022 1,652 22 2,504 19,201
15,023 1,653 23 2,505 19,203
15,024 1,653 24 2,505 19,206
15,025 1,653 25 2,505 19,208
15,026 1,653 26 2,506 19,211
15,027 1,653 27 2,506 19,213
15,028 1,653 28 2,506 19,215
15,029 1,653 29 2,507 19,218
15,030 1,653 30 2,507 19,220
15,031 1,653 31 2,507 19,223
15,032 1,654 32 2,508 19,225
15,033 1,654 33 2,508 19,228
15,034 1,654 34 2,508 19,230
15,035 1,654 35 2,509 19,232
15,036 1,654 36 2,509 19,235
15,037 1,654 37 2,509 19,237
15,038 1,654 38 2,510 19,240

507,217 - 76,083 583,299.17 3,043,300 ###


426,067 - 63,910 489,976.67 2,556,400 ###
316,567 - 47,485 364,051.67 1,899,400 ###
218,733 - 32,810 251,543.33 1,312,400 ###
169,233 - 25,385 194,618.33 1,015,400 ###
132,733 - 19,910 152,643.33 796,400 ###
97,283 - 14,593 111,875.83 583,700 ###
84,667 - 12,700 97,366.67 508,000 ###
64,200 - 9,630 73,830.00 385,200 ###
42,583 - 6,388 48,970.83 255,500 ###
33,100 - 4,965 38,065.00 198,600 ###
HARGA TOKO PPN 11% BIAYA TRANSPORT 15% HARGA SATUAN
10%
586,500 58,650 87,975 733,125.00
147,900 14,790 22,185 184,875.00
81,600 8,160 12,240 102,000.00
53,550 5,355 8,033 66,937.50
28,050 2,805 4,208 35,062.50
17,850 1,785 2,678 22,312.50
14,280 1,428 2,142 17,850.00
8,925 893 1,339 11,156.25
6,120 612 918 7,650.00
4,335 434 650 5,418.75

165,750 16,575 24,863 207,187.50


96,900 9,690 14,535 121,125.00
63,750 6,375 9,563 79,687.50
30,600 3,060 4,590 38,250.00
20,400 2,040 3,060 25,500.00
16,575 1,658 2,486 20,718.75
10,200 1,020 1,530 12,750.00
6,885 689 1,033 8,606.25
4,900 490 735 6,125.00

193,800 19,380 29,070 242,250.00


107,100 10,710 16,065 133,875.00
81,600 8,160 12,240 102,000.00
35,700 3,570 5,355 44,625.00
23,970 2,397 3,596 29,962.50
18,870 1,887 2,831 23,587.50
12,495 1,250 1,874 15,618.75
7,905 791 1,186 9,881.25
5,355 536 803 6,693.75

91,800 9,180 13,770 114,750.00


56,100 5,610 8,415 70,125.00
38,250 3,825 5,738 47,812.50
20,400 2,040 3,060 25,500.00
13,260 1,326 1,989 16,575.00
10,710 1,071 1,607 13,387.50
7,650 765 1,148 9,562.50
4,590 459 689 5,737.50
3,750 375 563 4,687.50

10,331 1,033 1,550 12,913.75


8,750 875 1,313 10,937.50
5,300 530 795 6,625.00

4,500,000 450,000 675,000 5,625,000.00


3,000,000 300,000 450,000 3,750,000.00
2,500,000 250,000 375,000 3,125,000.00
2,200,000 220,000 330,000 2,750,000.00
1,650,000 165,000 247,500 2,062,500.00
980,000 98,000 147,000 1,225,000.00

255,000 25,500 38,250 318,750.00


140,200 14,020 21,030 175,250.00
90,800 9,080 13,620 113,500.00
71,400 7,140 10,710 89,250.00
43,350 4,335 6,503 54,187.50

1,375,000 137,500 206,250 1,718,750.00


561,000 56,100 84,150 701,250.00
385,000 38,500 57,750 481,250.00
131,500 13,150 19,725 164,375.00
103,000 10,300 15,450 128,750.00

93,000 9,300 13,950 116,250.00


91,000 9,100 13,650 113,750.00
86,600 8,660 12,990 108,250.00
83,200 8,320 12,480 104,000.00
56,800 5,680 8,520 71,000.00
54,300 5,430 8,145 67,875.00
49,700 4,970 7,455 62,125.00
46,500 4,650 6,975 58,125.00
51,118 5,112 7,668 63,897.50

306,000 30,600 45,900 382,500.00


190,650 19,065 28,598 238,312.50
102,000 10,200 15,300 127,500.00
58,650 5,865 8,798 73,312.50
40,800 4,080 6,120 51,000.00
30,600 3,060 4,590 38,250.00
21,675 2,168 3,251 27,093.75
17,850 1,785 2,678 22,312.50
14,535 1,454 2,180 18,168.75

89,250 8,925 13,388 111,562.50


56,100 5,610 8,415 70,125.00
33,150 3,315 4,973 41,437.50
19,890 1,989 2,984 24,862.50
14,535 1,454 2,180 18,168.75
10,455 1,046 1,568 13,068.75
7,140 714 1,071 8,925.00
5,100 510 765 6,375.00
3,825 383 574 4,781.25

215,000 21,500 32,250 268,750.00


185,000 18,500 27,750 231,250.00
120,000 12,000 18,000 150,000.00

1,950,000 195,000 292,500 2,437,500.00


1,275,000 127,500 191,250 1,593,750.00
986,000 98,600 147,900 1,232,500.00
255,000 25,500 38,250 318,750.00

3,791,000 379,100 568,650 4,738,750.00


3,340,000 334,000 501,000 4,175,000.00
2,873,000 287,300 430,950 3,591,250.00
2,027,300 202,730 304,095 2,534,125.00

TRILLIUN PRO / BATANG


HARGA PPN 11% LANGSIRAN PIHAK KE-3 TOTAL HARGA
PRICELIST 0% 20% 0% SATUAN
548,390 - 109,678 - 658,068.00
371,200 - 74,240 - 445,440.00
256,260 - 51,252 - 307,512.00
178,760 - 35,752 - 214,512.00
141,160 - 28,232 - 169,392.00
89,360 - 17,872 - 107,232.00
60,450 - 12,090 - 72,540.00
54,140 - 10,828 - 64,968.00
32,970 - 6,594 - 39,564.00
HARGA TOKO PPN 11% BIAYA TRANSPORT PIHAK KE-3 HARGA SATUAN
0% 20% 15%
163,800 - 32,760 24,570 221,130.00
112,100 - 22,420 16,815 151,335.00
52,100 - 10,420 7,815 70,335.00
35,400 - 7,080 5,310 47,790.00
32,200 - 6,440 4,830 43,470.00
8,500 - 1,700 1,275 11,475.00
4,400 - 880 660 5,940.00

146,700 - 29,340 22,005 198,045.00


96,800 - 19,360 14,520 130,680.00
45,000 - 9,000 6,750 60,750.00
29,300 - 5,860 4,395 39,555.00
26,100 - 5,220 3,915 35,235.00
5,600 - 1,120 840 7,560.00
7,400 - 1,480 1,110 9,990.00

216,700 - 43,340 32,505 292,545.00


90,000 - 18,000 13,500 121,500.00
34,700 - 6,940 5,205 46,845.00
6,200 - 1,240 930 8,370.00
3,700 - 740 555 4,995.00

94,100 - 18,820 14,115 127,035.00


47,000 - 9,400 7,050 63,450.00
23,500 - 4,700 3,525 31,725.00
12,000 - 2,400 1,800 16,200.00
6,200 - 1,240 930 8,370.00
3,700 - 740 555 4,995.00

210,610 - 42,122 31,592 284,323.50


127,670 - 25,534 19,151 172,354.50
63,090 - 12,618 9,464 85,171.50
- - - -
13,100 - 2,620 1,965 17,685.00
7,400 - 1,480 1,110 9,990.00

79,200 - 15,840 11,880 106,920.00


75,200 - 15,040 11,280 101,520.00
65,000 - 13,000 9,750 87,750.00
58,400 - 11,680 8,760 78,840.00
45,300 - 9,060 6,795 61,155.00
38,700 - 7,740 5,805 52,245.00

184,800 - 36,960 27,720 249,480.00


78,900 - 15,780 11,835 106,515.00
39,500 - 7,900 5,925 53,325.00
22,400 - 4,480 3,360 30,240.00
11,500 - 2,300 1,725 15,525.00
5,600 - 1,120 840 7,560.00
2,600 - 520 390 3,510.00

11,300 - 2,260 1,695 15,255.00


6,400 - 1,280 960 8,640.00
3,700 - 740 555 4,995.00

115,900 - 23,180 17,385 156,465.00


36,700 - 7,340 5,505 49,545.00
19,800 - 3,960 2,970 26,730.00
8,500 - 1,700 1,275 11,475.00
5,500 - 1,100 825 7,425.00
3,600 - 720 540 4,860.00

405,850 - 81,170 60,878 547,897.50


316,950 - 63,390 47,543 427,882.50
232,700 - 46,540 34,905 314,145.00
HARGA TOTAL HARGA
PRICELIST PPN 11% LANGSIRAN PIHAK KE-3 SATUAN
11% 10% 15%
298,750 29,875 44,813 373,437.50
181,790 18,179 27,269 227,237.50
142,620 14,262 21,393 178,275.00
95,500 9,550 14,325 119,375.00
48,250 4,825 7,238 60,312.50
30,170 3,017 4,526 37,712.50
457,000 - 91,400 68,550 616,950.00
196,000 - 39,200 29,400 264,600.00
142,000 - 28,400 21,300 191,700.00
65,000 - 13,000 9,750 87,750.00
42,000 - 8,400 6,300 56,700.00

706,000 - 141,200 105,900 953,100.00


294,000 - 58,800 44,100 396,900.00
207,000 - 41,400 31,050 279,450.00
93,000 - 18,600 13,950 125,550.00
55,000 - 11,000 8,250 74,250.00

446,000 - 89,200 66,900 602,100.00


186,000 - 37,200 27,900 251,100.00
153,000 - 30,600 22,950 206,550.00
51,000 - 10,200 7,650 68,850.00
20,000 - 4,000 3,000 27,000.00

348,000 - 69,600 52,200 469,800.00


128,000 - 25,600 19,200 172,800.00
95,000 - 19,000 14,250 128,250.00
32,000 - 6,400 4,800 43,200.00
22,000 - 4,400 3,300 29,700.00

290,000 - 58,000 43,500 391,500.00


123,000 - 24,600 18,450 166,050.00
88,000 - 17,600 13,200 118,800.00
39,000 - 7,800 5,850 52,650.00
29,000 - 5,800 4,350 39,150.00

283,000 - 56,600 42,450 382,050.00


121,000 - 24,200 18,150 163,350.00
85,000 - 17,000 12,750 114,750.00
36,000 - 7,200 5,400 48,600.00
24,000 - 4,800 3,600 32,400.00

446,000 - 89,200 66,900 602,100.00


352,000 - 70,400 52,800 475,200.00
186,000 - 37,200 27,900 251,100.00
180,236 - 36,047 27,035 243,318.60
131,000 - 26,200 19,650 176,850.00
108,862 - 21,772 16,329 146,963.70
- - - -

660,200 - 132,040 99,030 891,270.00


429,100 - 85,820 64,365 579,285.00
366,600 - 73,320 54,990 494,910.00
266,100 - 53,220 39,915 359,235.00

301,700 - 60,340 45,255 407,295.00


297,800 - 59,560 44,670 402,030.00
223,800 - 44,760 33,570 302,130.00
218,500 - 43,700 32,775 294,975.00

771,700 - 154,340 115,755 1,041,795.00


379,700 - 75,940 56,955 512,595.00
309,000 - 61,800 46,350 417,150.00
184,800 - 36,960 27,720 249,480.00

591,100 - 118,220 88,665 797,985.00


308,700 - 61,740 46,305 416,745.00
237,200 - 47,440 35,580 320,220.00
215,800 - 43,160 32,370 291,330.00

480,900 - 96,180 72,135 649,215.00


280,600 - 56,120 42,090 378,810.00
227,200 - 45,440 34,080 306,720.00
208,400 - 41,680 31,260 281,340.00

268,900 - 53,780 40,335 363,015.00


155,600 - 31,120 23,340 210,060.00
116,700 - 23,340 17,505 157,545.00
77,300 - 15,460 11,595 104,355.00

- - - -
- - - -
749,000 - 149,800 112,350 1,011,150.00
348,000 - 69,600 52,200 469,800.00
128,000 - 25,600 19,200 172,800.00
- - - -
- - - -
- - - -

- - - -
- - - -
749,000 - 149,800 112,350 1,011,150.00
348,000 - 69,600 52,200 469,800.00
128,000 - 25,600 19,200 172,800.00
- - - -
280,000 - 56,000 42,000 378,000.00
73,000 - 14,600 10,950 98,550.00
25,000 - 5,000 3,750 33,750.00
21,000 - 4,200 3,150 28,350.00
45,000 - 9,000 6,750 60,750.00
30,000 - 6,000 4,500 40,500.00
15,000 - 3,000 2,250 20,250.00
10,000 - 2,000 1,500 13,500.00
85,000 - 17,000 12,750 114,750.00
6,500 - 1,300 975 8,775.00
58,000 - 11,600 8,700 78,300.00
325,000 - 65,000 48,750 438,750.00
BERAT/MTBERAT/BTG TABEL BERAT BESI
DIMENSI KG/MTR KG/BTG
Ø 16 1.5783333 18.94 18000 340,920.00
Ø 14 1.2083333 14.5 18000 261,000.00
0.887 10.644 #REF! Ø 12 0.8875 10.65 18000 191,700.00
0 #REF! Ø 10 0.6166667 7.4 18000 133,200.00
0 #REF! Ø8 0.3941667 4.73 18000 85,140.00
0 #REF! Ø6 0.2216667 2.66 18000 47,880.00
0 #REF!
0 #REF!
0.62 7.44 #REF!
INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
PEKERJAAN : Perencanaan Perluasan Jaringan SPAM Perkotaan/Desa Dengan SR
LOKASI : Desa Pongkowulu Kec. Kambowa
T.A : 2023
0 : 0

K
LEVEL JENIS PEKERJAAN
PEKERJAA
Divisi 1 1.1.1 Pekerjaan persiapan
1.1.1.1 Pembuatan 1 m' pagar sementara dari kayu tinggi 2 meter
1.1.1.2 Pembuatan 1 m' pagar sementara dari seng gelombang tinggi 2 meter
1.1.1.3 Pembuatan 1 m' pagar sementara dari kawat tinggi 1,8 meterat duri
Dihitung Pembuatan 1 m' pagar Pengaman dari kawat Duri Jarak 20 Cm
1.1.1.4 Pengukuran dan pemasangan 1 m' Bouwplank
1.1.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran
1.1.1.6 Pembuatan 1 m2 gudang semen dan peralatan
1.1.1.7 Pembuatan 1 m2 rumah jaga
1.1.1.8 Pembersihan 1 m2dan perataan lapangan
1.1.1.9 Pembuatan 1 m2 bedeng pekerja
1.1.1.10 Pembuatan 1 m2 bak adukan ukuran 40 cm x 50 cm x 25 cm
1.1.1.11 Pembuatan 1 m2 perancah dari bambu s.d. Tinggi 6 meter
1.1.1.12 Pembuatan 1 m2 jalan sementara
1.1.1.13 Pembuatan 1 m2 gudang
1.1.1.14 Pembongkaran 1 m3 beton bertulang
1.1.1.15 Pembongkaran 1 m2 dinding tembok
1.1.1.16 Pemasangan 1 m2 kawat jaring galvanis
1.1.1.17 Pemasangan 1 m2 pagar beton pracetak 50x50x240 untuk pagar
Divisi 2 2.3.1 Pekerjaan Tanah
2.3.1.1 Penggalian tanah biasa sedalam 1 m
2.3.1.2 Penggalian tanah biasa sedalam 2 m
2.3.1.3 Penggalian tanah biasa sedalam 3 m
2.3.1.4 Penggalian tanah keras sedalam 1 m
2.3.1.5 Penggalian tanah cadas sedalam 1 m
2.3.1.6 Penggalian tanah lumpur sedalam 1 m
2.3.1.7 Pengerjaan stripping setinggi 1 m
2.3.1.8 Pembuangan tanah sejauh 30 m
2.3.1.9 Pengurugan kembali 1 m3 galian tanah
2.3.1.10 Pemadatan tanah per 20 cm
2.3.1.11 Pengurugan dengan pasir urug
3.2.1
Divisi 3
Pekerjaan pondasi
3.2.1.1 Pemasangan pondasi batu belah 1PC:3PP
3.2.1.2 Pemasangan pondasi batu belah 1PC:4PP
3.2.1.9 Pemasangan batu kosong (aanstamping)
Divisi 4 4.1.1 Pekerjaan beton
4.1.1.1 Pembuatan 1 m3 beton mutu fc 7,4 MPa
4.1.1.2 Pembuatan 1 m3 beton mutu fc 9,8 MPa
4.1.1.3 Pembuatan 1 m3 beton mutu fc 12,2 MPa
4.1.1.5 Membuat 1 m3 beton mutu f'c = 14.5 MPa ( Camp. 1 : 2 : 3 )
4.1.1.5 Membuat 1 m3 beton mutu f'c = 14.5 MPa ( Camp. 1 : 2 : 3 )
4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 MPa
4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 MPa
4.1.1.8 Membuat 1 m3 beton mutu f'c = 21.7 MPa
4.1.1.9 Membuat 1 m3 beton mutu f'c = 24 MPa
4.1.1.10 Membuat 1 m3 beton mutu f'c = 26.4 MPa
4.1.1.12 Membuat 1 m3 beton mutu f'c = 28.8 MPa
4.1.1.15 Pembesian 10 kg dengan besi polos atau ulir
4.1.1.15 Pembesian 1 kg dengan besi polos atau ulir
4.1.1.15 Pembesian 1 kg dengan besi polos atau ulir PMA
4.1.1.18 Pemasangan 1 m2 bekisting untuk pondasi
4.1.1.19 Pemasangan 1 m2 bekisting untuk sloof
4.1.1.20 Pemasangan 1 m2 bekisting untuk kolom
4.1.1.21 Pemasangan 1 m2 bekisting untuk balok
Hitung Pemasangan 1 m2 bekisting untuk Kolom Sandaran SR
4.1.1.22 Pemasangan 1 m2 bekisting untuk lantai
4.1.1.23 Pemasangan 1 m2 bekisting untuk dinding
4.1.1.24 Pemasangan 1 m2 bekisting untuk tangga
4.1.1.26 Pembuatan 1 m' kolom praktis beton bertulang (11x11)
4.1.1.27
4.4.1 Pembuatan 1 m' ring balok beton bertulang (10x15)
Divisi 4 Pekerjaan Pasangan dinding
4.4.1.8 Pemasangan dinding bata merah 1/2 batu campuran 1PC:3PP
4.4.1.9 Pemasangan dinding bata merah 1/2 batu campuran 1PC:4PP
Divisi 4 4.4.2 Pekerjaan plesteran
4.4.2.3. Pemasangan plesteran 1PC:3PP tebal 15 mm
Pemasangan plesteran 1PC:3PP tebal 15 mm PEK. PMA
4.4.2.4. Pemasangan plesteran 1PC:4PP tebal 15 mm
4.4.2.27 Pemasangan acian
Divisi 4 4.5.2 Pekerjaan penutup atap
4.5.2.39 40. Pemasangan 1 m2 atap seng gelombang
4.5.2.40 41. Pemasangan 1 m2 nok atap seng
4.5.2.41 42. Pemasangan 1 m2 atap alumunium gelombang
4.5.2.42 43. Pemasangan 1 m2 nok atap alumunium gelombang
44. Pemasangan 1 m2 lapisan aluminium foil
Divisi 4 4.6.1 Pekerjaan kayu
4.6.1.1 1. Pembuatan & pemasangan kusen kayu kelas I
2. Pembuatan & pemasangan kusen kayu kelas II
dan III
3. Pembuatan & pemasangan kayu klam kayu
kelas
4. II
Pembuatan & pemasangan pintu klam kayu
kelas III
4.6.1.5 5. Pembuatan & pemasangan pintu panel kayu kelas I atau II
6. Pembuatan & pemasangan pintu/jendela kaca
kayu
7. kelas I atau
Pembuatan II
& pemasangan pintu/jendela
jalusi kayu kelas I atau II
8. Pembuatan & pemasangan pintu plywood rangkap
9. Pembuatan & pemasangan pintu plywood rangka ekspose kayu kelas I atau II
4.6.1.10 10.Pembuatan & pemasangan jalusi kusen kayu kelas I atau II
11.Pembuatan & pemasangan pintu teakwood
rangka ekspose kayu kelas I
12.Pembuatan & pemasangan pintu lapis formika rangka ekspose kayu kelas II
4.6.1.13 13.Pemasangan kuda-kuda konvensional kayu kelas I,II,III
14.Pemasangan kuda-kuda ekpose kayu kelas I
4.6.1.15 15.Pemasangan konstruksi gordeng kayu kelas II
16.Pemasangan rangka atap genteng keramik kayu kelas II
17.Pemasangan rangka atap genteng beton kayu
kelas II
18.Pemasangan rangka atap sirap kayu kelas II
19.Pemasangan rangka langit-langit 50x100 kayu
kelas II & III
20.Pemasangan rangka langit-langit 60x60 kayu kelas II atau III
4.6.1.21 21.Pemasangan lisplank 3x20 kayu kelas I dan II
22.Pemasangan lisplank 3/30 kayu kelas I dan II
23.Pemasangan rangka dinding pemisah kayu kelas II atau III
24.Pemasangan dinding pemisah teakwood double
kayu kelas II dinding pemisah plywood
25.Pemasangan
rangkap kayu kelas II
26.Pemasangan dinding lambrisering kayu kelas I
27.Pemasangan dinding lambrisering dari
plywood
28.Pemasangan dinding bilik rangka kayu kelas
III
4.6.1.29
4.6.2 29.Pemasangan 1 m3, Kolom Kayu Kelas II
Divisi 4 Pekerjaan kunci &
kaca 1. Pemasangan 1 buah kunci tanam antik
2. Pemasangan 1 buah kunci tanam biasa
3. Pemasangan 1 buah kunci tanam kamar
mandi
4. Pemasangan 1 buah kunci tanam silinder
5. Pemasangan 1 buah engsel pintu
6. Pemasangan 1 buah engsel jendela kupu-kupu
7. Pemasangan 1 buah engsel angin
8. Pemasangan 1 buah spring knip
9. Pemasangan 1 buah kait angin
10.Pemasangan 1 buah doorcloser
11.Pemasangan 1 buah slot
12.Pemasangan 1 buah doorholder
13.Pemasangan 1 buah doorstop
14.Pemasangan 1 buah rel pintu dorong
15.Pemasangan 1 buah kunci lemari
16.Pemasangan 1 m2 kaca polos tebal 3 mm
17.Pemasangan 1 m2 kaca polos tebal 5 mm
18.Pemasangan 1 m2 kaca polos tebal 8 mm
19.Pemasangan 1 m2 kaca polos tebal 12 mm
20.Pemasangan 1 m2 kaca cermin tebal 5 mm
21.Pemasangan 1 m2 kaca cermin tebal 6 mm
22.Pemasangan 1 m2 kaca cermin tebal 8 mm
23.Pemasangan 1 m2 kaca wiremesh glass tebal 5
mm
24.Pemasangan 1 m2 kaca patri tebal 5 mm
Divisi 4 4.7.1 Pekerjaan pengecatan
4.7.1.1 Pengikisan/pengerokan 1 m2 permukaan cat tembok lama
4.7.1.2 Pencucian 1 m2 permukaan dinding lama
4.7.1.3 Pengerokan 1 m2 karat atau cat lama permukaan baja
4.7.1.4 Pengecatan bidang kayu baru 1 lapis cat dasar 2 lapis penutup
4.7.1.10 Pengecetan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup)
4.7.1.11 Pengecatan tembok lama
4.7.1.12 Pelaburan 1 m2 tembok dengan kalkarium
4.7.1.13 Pelaburan 1 m2 tembok baru dengan kapur
4.7.1.14 Pelaburan 1 m2 tembok lama dengan kapur
4.7.1.15 Pemasangan wall paper
4.7.1.16 Pengecatan 1 m2 permukaan baja dengan menie dangan perancah
4.7.1.17 Pengecatan 1 m2 permukaan baja galvani cara manual 4 lapis
4.7.1.18 Pengecatan 1 m2 permukaan baja galvani cara manual 1 lapis
4.7.1.19 Pengecatan 1 m2 permukaan baja galvanis cara manual 3 lapis
4.7.1.20 Pengecatan 1 m2 permukaan baja galvanis semprot 1 lapis
4.7.1.21 Plituran 10 m2 dengan melamic
Divisi 10 10.4.1 Pekerjaan pemasangan pipa di luar gedung
Dihitung Pemasangan 1 m pipa PVC Ø 20 mm
Dihitung Pemasangan 1 m pipa PVC Ø 25 mm
Dihitung Pemasangan 1 m pipa PVC Ø 32 mm
Dihitung Pemasangan 1 m pipa PVC Ø 40 mm
Dihitung Pemasangan 1 m pipa PVC Ø 50 mm
Dihitung Pemasangan 1 m pipa PVC Ø 50 mm Relokasi
10.4.1.1 Pemasangan 1 m pipa PVC Ø 63 mm
Dihitung Pemasangan 1 m pipa PVC Ø 63 mm Relokasi
10.4.1.2 Pemasangan 1 m pipa PVC Ø 90 mm
10.4.1.3 Pemasangan 1 m pipa PVC Ø 110 mm
10.4.1.17 Pemasangan 1 m pipa HDPE Ø 63 mm
Dihitung Pemasangan 1 m pipa HDPE Ø 90 mm
10.4.1.18 Pemasangan 1 m pipa HDPE Ø 110 mm
10.4.1.19 Pemasangan 1 m pipa HDPE Ø 125 mm
10.4.1.20 Pemasangan 1 m pipa HDPE Ø 150 mm
Dihitung Pemasangan 1 m pipa GIP Ø 32 mm
Dihitung Pemasangan 1 m pipa GIP Ø 40 mm
Dihitung Pemasangan 1 m pipa GIP Ø 50 mm
10.4.1.33 Pemasangan 1 m pipa GIP Ø 63 mm
Dihitung Pemasangan 1 m pipa GIP Ø 90 mm
10.4.1.34 Pemasangan 1 m pipa GIP Ø 100 mm
10.4.1.35 Pemasangan 1 m pipa GIP Ø 125 mm
10.4.1.36 Pemasangan 1 m pipa GIP Ø 150 mm
CV. KARYA REKAYAS
HARGA SATUAN KETERANGAN

136,170.00
387,080.00
2,474,870.00
549,800.00
76,370.00
#N/A
#N/A
#N/A
18,500.00
#N/A
#N/A
#N/A
#N/A

1,686,660.00
843,330.00
5,091,420.00
0.00

107,237.50
130,927.50
154,916.50
142,784.00
215,970.00
172,327.50
7,647.50
47,035.00
76,475.00
76,475.00
291,295.00

1,282,652.50
1,204,682.50
656,845.50

1,337,112.94
1,399,177.65
1,003,720.24
1,504,600.40
2,517,078.65
1,557,855.14
1,600,351.59
1,624,939.08
1,667,064.37
1,343,494.65
1,809,387.94
246,146.00
24,614.60
28,237.10
221,996.00
232,806.00
400,165.50
408,376.50
260,210.50
469,165.50
485,840.50
377,740.50
143,968.50
176,410.00

361,197.75
347,627.75

94,029.06
116,309.62
90,879.90
55,286.25

0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00
22,298.50

57,672.50
21,990.30

27,029.60
31,898.70
33,350.00
39,999.30
51,913.30
10,327.00
60,561.30
13,961.00
107,801.00
151,406.70
83,320.38
164,283.25
232,018.25
289,486.63
460,905.63
154,985.50
182,052.67
198,738.21
245,620.83
370,694.83
500,079.42
654,691.17
773,845.54
0

Konsultan Perencana
CV. KARYA REKAYASA KONSULTAN
0

Estimator
0
BACK UP DATA
Instansi : :
Pekerjaan : :
Lokasi : :
Tahun Anggaran : :
Item Pekerjaan : Pek. Boks Valve

Panjang Jumlah
No. Jenis Pekerjaan (M) Lebar (M) TInggi (M) (bh/
Bidang)
A Pekerjaan Tanah
1 Galian Tanah Biasa 1.30 1.30 0.70
B Pekerjaan Pasangan
1 Pek. Pemasangan 1m2 dinding bata merah 1.15 0.90 4.00
2 Pek. Plesteran Tembok
- Plesteran Tembok Bagian Dalam 1 0.70 4.00
- Plesteran Tembok Bagian Luar 1.3 0.40 4.00
Total Plesteran
3 Pek. Acian 1.3 0.40 4.00
4 Pek. Pengecattan 1.3 0.40 4.00
Volume Total
V = ((L1 + L2)/2) x P KET.
M3

1.18 M3

4.14 M2

2.80 M2
2.08 M2
4.88 M2
2.08 M2
2.08 M2

0
0
0

-
0
BACK UP DATA

Instansi : :
Pekerjaan : :
Lokasi : :
Tahun Anggaran : :
Item Pekerjaan : Pekerjaan Sambungan Rumah (SR)

Panjang TInggi
No. Jenis Pekerjaan (M) Lebar ( M ) Tebal ( M ) (M)

A Pek. Galian Tanah


1 Pek. Galian Tanah Pasangan Pipa 4 0.1 0.15
2 Pek. Galian Tanah Dudukan Ember 0.6 0.4 0.05
3 Pek. Galian Tanah Dudukan Meteran 0.3 0.4 0.05
Total Pek. Galian Tanah
B Pek. Urugan Kembali Galian Tanah
Pek. Urugan Galian Tanah Pasangan Pipa Luas
1 ( Volume Galian - Volume Pipa) Pjg Pipa Ø Pipa (M) Penampan
(M) g (M2)
4 0.02 0.00031
Total Pek. Urugan Kembali Galian Tanah
C Pek. Bekisting
1 Pek. Bekisting Dudukan Boks Meteran 1.4 0.1
2 Pek. Bekisting Dududkan Ember 2 0.1
3 Pek. Bekisting Sandaran Pipa SR 0.48 0.6
Total Pek. Bekisting
D Pek. Beton Tumbuk
1 Plat Beton Dudukan Box Meteran 0.30 0.40 0.10
2 Plat Beton Dudukan Ember 0.60 0.40 0.10
3 Kolom Beton Sandaran Pipa SR 0.12 0.12 0.60
Total Pek. Beton Tumbuk
E Pek. Acian
1 Plat Beton Sandaran Pipa SR 0.48 0.60
Total Pek. Acian
F Pek. Pengadaan Aksesories Sambungan Rumah
Soket Drat Luar PVC SNI Ø 1" X 1/2"
Knee PVC SNI Ø1/2"
Faucet Elbow PVC SNI Ø1/2"
Double Nipple GI Ø 1/2"
Stop Kran Gi Ø 1/2" Kuningan
Water Meter 1/2" (Standar PDAM) + Box Meteran
Tee PVC SNI Ø 1/2"
Socket Drat Dalam PVC SNI Ø 1/2"
Kran Air GI Ø1/2"
Dop PVC SNI Ø1/2"
Paku Beton 5 CM

0.00
0
0

0
0
Volume Total
V = ((L1 + L2)/2) x P KET.
M3

0.060 M3
0.012 M3
0.006 M3
0.078 M3

Volume Pipa

0.0013 M3
0.059 M3

0.14 M2
0.2 M2
0.288 M2
0.628 M2

0.012 M3
0.024 M3
0.009 M3
0.045 M3

0.288 M2
0.288 M3

1 Bh
4 Bh
2 Bh
1 Bh
1 Bh
1 Bh
1 Bh
1 Bh
1 Bh
1 Bh
4 Bh

0
0
0

-
0
KABUPATEN : BUTON UTARA
INSTANSI : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
NAMA PEKERJAAN : Pengembangan Jaringan Distribusi Dan Sambungan Rumah SPAM
LOKASI : Desa Pongkowulu Kec. Kambowa
TAHUN ANGGARAN : 2023

Mengetahui/Menyetujui Oleh : Diperiksa Oleh :


Pejabat Pembuat Komitmen (PPK) Staf Teknik Bidang Cipta Karya
Dinas Pekerjaan Umum Dan Penataan Ruang Dinas Pekerjaan Umum Dan Penataan Ruang
Kabupaten Buton Utara

NURHIDAH, ST Ahmat Haafi, ST


NIP. 19810305 201101 2 008 Nip.19900325 21903 1 015
Buranga, November 2022

Di Buat Oleh : Dibuat Oleh: Dibuat Oleh:


Staf Teknik Bidang Cipta Karya Konsultan Perencana Konsultan Perencana
Dinas Pekerjaan Umum Dan Penataan Ruang CV. KARYA REKAYASA KONSULTAN CV. KARYA REKAYASA KONSUL

Ahmat Haafi, ST TRISNA EFENDI ENGKI SAPUTRA Syamsuddin Nur, S.Ars


Nip.19900325 21903 1 015 Direktur
Dibuat Oleh:
Konsultan Perencana
CV. KARYA REKAYASA KONSULTAN

Syamsuddin Nur, S.Ars Mengetahui:


Estimator

Anda mungkin juga menyukai