UTS ESTIMASI BIAYA KONSTRUKSI

Disusun Oleh:
Dian Condrowati (17050534001)

JURUSAN TEKNIK SIPIL


FAKULTAS TEKNIK
UNIVERSITAS NEGERI SURABAYA
2019
DAFTAR ISI

UTS ESTIMASI BIAYA KONSTRUKSI ..................................................................................................... i

DAFTAR ISI ................................................................................................................................................. ii

UTS ESTIMASI BIAYA KONSTRUKSI ....................................................................................................3

A. Soal................................................................................................................................................3
B. Diketahui .......................................................................................................................................3
C. Ditanya ..........................................................................................................................................3
D. Jawab .............................................................................................................................................3

UTS EBK ii
UTS ESTIMASI BIAYA KONSTRUKSI

A. Soal

sdsdvrfge

B. Diketahui

1. Jumlah kolom pedestal ukuran 0,55m x 0,55m (n) = 1(X) = 11buah


2. Mutu beton f’c = 19,3 MPa
3. Selimut beton = 0,02m
4. Sengkang = ∅8 − 150𝑚𝑚
5. Tulangan Pokok = 16 D22
6. 𝜌 𝑝𝑎𝑠𝑖𝑟 = 1400 kg/m2
7. 𝜌 𝑘𝑒𝑠𝑟𝑖𝑘𝑖𝑙 = 1350 kg/m2
8. Panjang kolom (p) = 0,55m
9. Lebar kolom (l) = 0,55m
10. Tinggi kolom (t) = 1,00m
11. Tebal pelat lantai (t1) = 0,15m
12. Tebal pasir urug (t2) = 0,10m
13. Tebal tanah urug (t3) = 0,35m
14. Jumlah pemakaian bekisting (n) = 2 kali
15. Jumlah tulangan pokok 16 D22 = 22 buah
16. Diameter tulangan (d) = 0,022mm
17. 𝛾 𝑏𝑒𝑠𝑖 = 7850kg/m3

C. Ditanya

1. Hitung volume pekerjaan kolom pedestal 0,55mx0,55m


2. Hitung analisa modifikasi
3. Hitung RAB

D. Jawab

1. Uraian Pekerjaan Volume


a. Kolom pedestal Uk. 0,55x0,55m
1) Panjang kolom (p) = 0,55m
2) Lebar kolom (l) = 0,55m
3) Tinggi kolom (t) = 1,60m
4) Jumlah kolom pedestal ukuran 0,55m x 0,55m (n) = 1(X) = 11buah
5) Total volume kolom =pxlxtxn
= 0,55m x 0,55m x 1,60m x 11 buah
= 5,324 m3
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒
6) Volume perkolom =
𝑛
5,324 𝑚3
=
11
= 0,484m3
b. Bekisting
1) Panjang kolom (p) = 0,55m
2) Tinggi kolom (t) = 1,00m
3) Jumlah kolom pedestal ukuran 0,55m x 0,55m (n) = 1(X) = 11buah
4) Sisi bekisting = 4 sisi
5) Total volume bekisting= ((p x t) x sisi bekisting x n ) /2
= ((0,55m x 1,00m) x 4sisi x 11 buah) /2
= 12,10m2
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑢𝑚𝑒
6) Volume perbekisting =
𝑛
12,10𝑚2
=
11
= 1,10m2
7) Koefisien 𝐵𝑒𝑘𝑖𝑠𝑡𝑖𝑛𝑔
𝑣𝑜𝑙𝑢𝑚𝑒 𝑏𝑒𝑘𝑖𝑠𝑡𝑖𝑛𝑔
=
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑘𝑜𝑙𝑜𝑚
12,10𝑚2
=
5,324 𝑚3

UTS EBK 3
= 2,277
c. Beton f’c 19,3 MPa
1) Panjang kolom (p) = 0,55m
2) Lebar kolom (l) = 0,55m
3) Tinggi kolom (t) = 1,60m
4) Jumlah kolom pedestal ukuran 0,55m x 0,55m (n) = 1(X) = 11buah
5) Total volume beton =pxlxtxn
= 0,55m x 0,55m x 1,60m x 11 buah
= 5,324 m3
8) Koefisien Beton f’c 19,3 MPa
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑏𝑒𝑡𝑜𝑛
=
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑘𝑜𝑙𝑜𝑚
5,324 𝑚3
=
5,324 𝑚3
= 1,000

2. Bestat
a. Tulangan Pokok 16 D22

1.00m

0.10m
0.35m

25.d 25.d

15.d 15.d

1) Jumlah tulangan pokok 16 D22 (n1) = 16 buah


2) Diameter tulangan (d) = 0,022mm
3) Jumlah kolom pedestal ukuran 0,55m x 0,55m (n 2) = 1(X) = 11buah
4) Tinggi kolom (t) = 1,00m
5) Tebal pelat lantai (t1) = 0,15m
6) Tebal pasir urug (t2) = 0,10m
7) Tebal tanah urug (t3) = 0,35m
8) Perpanjangan kolom ke pile cap (t4) = 25 x d
= 25 x 0,022m
= 0,55m
9) Pengait tulangan pokok (t5) = (15 x d)
= 15 x 0,022m
= 0,33m
10) Panjang potongan = (t + t1 + t2 + t3 + t4 + t5)
= (1,00m + 0,15m + 0,10m + 0,35m + 0,55m + 0,33m
= 2,48m
11) Jumlah potongan tulangan pokok disemua kolom
= n1 x n2
= 16buah x 11buah
= 176buah
12) Jumlah panjang potongan = panjang potongan x jumlah potongan tulangan pokok disemua
kolom
= 2,480m x 176buah
= 436,48m
1
13) Berat tulangan permeter (w1) = 𝑥𝜋𝑥𝑑2 𝑥𝛾𝑏𝑒𝑠𝑖
4
1
= 𝑥 3,14 𝑥 (0,022𝑚)2 𝑥 7850𝑘𝑔/𝑚3
4
= 2,982529kg/m
14) Total berat tulangan (wt) = jumlah panjang potongan x w1
= 436,48m x 2,982529kg/m
= 1301,814258kg
𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑏𝑒𝑠𝑖 1 𝑙𝑜𝑛𝑗𝑜𝑟
15) Jumlah potongan perlonjor =
𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛

UTS EBK 4
12,000𝑚
=
2,480𝑚
= 4,838 buah
= (dibulatkan jadi 4 buah)
16) Sisa panjang potongan
= 𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑏𝑒𝑠𝑖 1 𝑙𝑜𝑛𝑗𝑜𝑟 − (𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛 𝑝𝑒𝑟𝑙𝑜𝑛𝑗𝑜𝑟 𝑥 𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛)
= 12,000m – (4buah x 2,480m)
= 2,08m
17) Kebutuhan tulangan
𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛
=
𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛 𝑝𝑒𝑟𝑙𝑜𝑛𝑗𝑜𝑟
176 𝑏𝑢𝑎ℎ
=
4 𝑏𝑢𝑎ℎ
= 44 lonjor (tulangan D22)
18) Koefisien tulangan 16 𝐷22
𝑡𝑜𝑡𝑎𝑙 𝑏𝑒𝑟𝑎𝑡 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛
=
𝑣𝑜𝑙𝑢𝑚𝑒 𝑘𝑜𝑙𝑜𝑚
1301,814258 𝑘𝑔
=
5,324 𝑚3
= 244,518074

b. Sengkang ∅12 − 150𝑚𝑚


1) Diameter tulangan (d) = 0,012m
2) Jarak sengkang (r) = 0,150m
3) Jumlah kolom pedestal ukuran 0,55m x 0,55m (n 2) = 1(X) = 11buah
4) Tinggi kolom (t) = 1,00m
5) Panjang kait =8xd
= 8 x 0,012m
= 0,096m
6) Panjang potongan
= (4 x0,55m – (4 x 0,02m)) + (2 x (0,096m))
= 2,312m
𝑡
7) Jumlah potongan perkolom = +1
𝑟
1,000𝑚
= +1
0,150𝑚
= 7,66
= (dibulatkan menjadi 7 buah)
8) Jumlah potongan sengkang di semua kolom
= jumlah potongan perkolom x n2
= 7 buah x 11buah
= 77 buah
9) Jumlah panjang potongan = panjang potongan x jumlah potongan sengkang disemua kolom
= 2,312m x 77buah
= 178,024 m
1
10) Berat tulangan permeter (w1) = 𝑥𝜋𝑥𝑑2 𝑥𝛾𝑏𝑒𝑠𝑖
4
1
= 𝑥 3,14 𝑥 (0,012𝑚)2 𝑥 7850𝑘𝑔/𝑚3
4
= 0,887364 kg/m
11) Total berat tulangan (wt) = jumlah panjang potongan x w1
= 178,024 m x 0,887364 kg/m
= 157,9720887 kg
𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑏𝑒𝑠𝑖 1 𝑙𝑜𝑛𝑗𝑜𝑟
12) Jumlah potongan perlonjor =
𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛
12,000𝑚
=
2,312𝑚
= 5,190311419 buah
= (dibulatkan jadi 5 buah)
13) Sisa panjang potongan
= 𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑏𝑒𝑠𝑖 1 𝑙𝑜𝑛𝑗𝑜𝑟 − (𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛 𝑝𝑒𝑟𝑙𝑜𝑛𝑗𝑜𝑟 𝑥 𝑝𝑎𝑛𝑗𝑎𝑛𝑔 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛)
= 12,000m – (5buah x 2,312m)
= 0,44m
14) Kebutuhan tulangan
𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛
=
𝑗𝑢𝑚𝑙𝑎ℎ 𝑝𝑜𝑡𝑜𝑛𝑔𝑎𝑛 𝑝𝑒𝑟𝑙𝑜𝑛𝑗𝑜𝑟
77𝑏𝑢𝑎ℎ
=
5 𝑏𝑢𝑎ℎ
= 16 lonjor (tulangan ∅12 )

UTS EBK 5
15) Koefisien tulangan ∅8
𝑡𝑜𝑡𝑎𝑙 𝑏𝑒𝑟𝑎𝑡 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛
=
𝑣𝑜𝑙𝑢𝑚𝑒 𝑘𝑜𝑙𝑜𝑚
157,9720887 𝑘𝑔
=
5,324 𝑚3
= 29,67169209

3. Analisa harga satuan pekerja


a. A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 MPa = Rp 1,051,600.00

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


.
(Rp) (Rp)

A. TENAGA

Pekerja L.01 OH 1,650 Rp 100,000.00 Rp 165,000.00

Tukang Batu L.02 OH 0,275 Rp 120,000.00 Rp 33,000.00

Kepala Tukang L.03 OH 0,028 Rp 130,000.00 Rp 3,640.00

Mandor L.04 OH 0,083 Rp 150,000.00 Rp 12,450.00

JUMLAH TENAGA KERJA Rp 214,090.00

B. BAHAN

Semen Portland Kg 371 Rp 1,150.00 Rp 426,650.00

Pasir Beton Kg 698 Rp 193.00 Rp 134,714.00

Kerikil (maks Kg 1047 Rp 156.00 Rp 163,332.00


30mm)

Air liter 215 Rp 80.00 Rp 17,200.00

JUMLAH HARGA BAHAN Rp 741,896.00

C. PERALATAN

JUMLAH HARGA ALAT Rp 000,000.00

D. Jumlah (A + B + C) Rp 955,986.00

E. Overhead & Profit (10%) Rp 95,598.60

F. Harga Satuan Pekerjaan (D + E) Rp 1,051,600.00

1) Jumlah harga pekerja


= koefisien x harga satuan
= 1,650 x Rp 100,000.00
= Rp 165,000.00
2) Jumlah harga tukang batu
= koefisien x harga satuan
= 0,275 x Rp 120,000.00
= Rp 33,000.00
3) Jumlah harga Kepala Tukang
= koefisien x harga satuan
= 0,028 x Rp 130,000.00
= Rp 3,640.00
4) Jumlah harga Mandor
= koefisien x harga satuan
= 0,083 x Rp 150,000.00
= Rp 12,450.00

UTS EBK 6
5) Jumlah tenaga kerja
= Jumlah harga pekerja + Jumlah harga tukang batu + Jumlah harga Kepala Tukang + Jumlah harga
Mandor
= Rp 165,000.00 + Rp 33,000.00 + Rp 3,640.00 + Rp 12,450.00
= Rp 214,090.00
6) Harga satuan semen
ℎ𝑎𝑟𝑔𝑎 𝑠𝑒𝑚𝑒𝑛 1 𝑧𝑎𝑘
=
𝑏𝑒𝑟𝑎𝑡 𝑠𝑒𝑚𝑒𝑛 1 𝑧𝑎𝑘
𝑅𝑝 46,000.00
=
40 𝑘𝑔
= Rp 1,150.00
7) Jumlah harga semen
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑠𝑒𝑚𝑒𝑛 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 𝑠𝑒𝑚𝑒𝑛
= 371 x Rp 1,150.00
= Rp 426,650.00
8) Harga satuan pasir beton
𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛 1𝑚3
𝑥ℎ𝑎𝑟𝑔𝑎 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛 1𝑚3
𝜌 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛
=
𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛 1𝑚3
698
𝑥 𝑅𝑝 270,000.00
1400 𝑘𝑔/𝑚3
=
698
= Rp 192.85
= (dibulatkan menjadi Rp 193.00)
9) Jumlah harga pasir beton
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛
= 698 x Rp 193.00
= Rp 134,714.00
10) Harga satuan kerikil
𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 kerikil 1𝑚3
𝑥ℎ𝑎𝑟𝑔𝑎 kerikil 1𝑚3
𝜌 𝑝𝑎𝑠𝑖𝑟 𝑏𝑒𝑡𝑜𝑛
=
𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 kerikil 1𝑚3
1047
𝑥 𝑅𝑝 210,000.00
1350𝑘𝑔/𝑚3
=
1047
= Rp 156.00
11) Jumlah harga kerikil
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 kerikil 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 kerikil
= 1047 x Rp 156.00
= Rp 163,332.00
12) Jumlah harga air
= koefisien air x harga satuan air
= 215 x Rp 80.00
= Rp 17,200.00
13) Jumlah harga bahan
= Jumlah harga semen + Jumlah harga pasir beton + Jumlah harga kerikil + Jumlah harga air
= Rp 426,650.00 + Rp 134,714.00 + Rp 163,332.00 + Rp 17,200.00
= Rp 741,896.00
14) Jumlah (A + B + C)
= (Rp 214,090.00 + Rp 741,896.00 + Rp 000,000.00)
= Rp 955,986.00
15) Overhead & Profit (10%)
= Jumlah x 10%
= Rp 955,986.00 x 10%
= Rp 95,598.60
16) Harga satuan pekerjaan (D + E)
= (Rp 955,986.00 + Rp 95,598.60)
= Rp 1,051,600.00

b. A.4.1.1.17. Pembesian 10kg dengan besi polos atau besi ulir = Rp 11,182.60

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


.
(Rp) (Rp)

A. TENAGA

UTS EBK 7
Pekerja L.01 OH 0,070 Rp 100,000.00 Rp 7,000.00

Tukang Batu L.02 OH 0,070 Rp 120,000.00 Rp 8,400.00

Kepala Tukang L.03 OH 0,007 Rp 130,000.00 Rp 910.00

Mandor L.04 OH 0,004 Rp 150,000.00 Rp 600.00

JUMLAH TENAGA KERJA Rp 16,910.00

B. BAHAN

Besi beton polos / Kg 10,500 Rp 7,800.00 Rp 81,900.00


ulir

Kawat Beton Kg 0,150 Rp 19,000.00 Rp 2,850.00

JUMLAH HARGA BAHAN Rp 84,750.00

C. PERALATAN

JUMLAH HARGA ALAT Rp 000,000.00

D. Jumlah (A + B + C) Rp 101,660.00

E. Overhead & Profit (10%) Rp 10,166.60

F. Harga Satuan Pekerjaan (D + E) Rp 111,826.00

1) Jumlah harga pekerja


= koefisien x harga satuan
= 0,070 x Rp 100,000.00
= Rp 7,000.00
2) Jumlah harga tukang batu
= koefisien x harga satuan
= 0,070 x Rp 120,000.00
= Rp 8,400.00
3) Jumlah harga Kepala Tukang
= koefisien x harga satuan
= 0,007 x Rp 130,000.00
= Rp 910.00
4) Jumlah harga Mandor
= koefisien x harga satuan
= 0,004 x Rp 150,000.00
= Rp 600.00
5) Jumlah tenaga kerja
= Jumlah harga pekerja + Jumlah harga tukang batu + Jumlah harga Kepala Tukang + Jumlah harga
Mandor
= Rp 7,000.00 + Rp 8,400.00 + Rp 910.00 + Rp 600.00
= Rp 16,910.00
6) Jumlah harga besi beton polos / ulir
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑏𝑒𝑠𝑖 𝑏𝑒𝑡𝑜𝑛 𝑝𝑜𝑙𝑜𝑠/𝑢𝑙𝑖𝑟 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 besi beton polos / ulir
= 10,5 x Rp 7,800.00
= Rp 81,900.00
7) Jumlah harga Kawat Beton
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝐾𝑎𝑤𝑎𝑡 𝐵𝑒𝑡𝑜𝑛 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Kawat Beton
= 0,150 x Rp 19,000.00
= Rp 2,850.00
8) Jumlah harga bahan
= Jumlah harga besi beton polos / ulir + Jumlah harga Kawat Beton
= Rp 81,900.00 + Rp 2,850.00
= Rp 84,750.00
9) Jumlah (A + B + C)
UTS EBK 8
= (Rp 16,910.00 + Rp 84,750.00+ Rp 000,000.00)
= Rp 101,660.00
10) Overhead & Profit (10%)
= Jumlah x 10%
= Rp 101,660.00 x 10%
= Rp 10,166.60
11) Harga satuan pekerjaan (D + E) / 10kg
= (Rp 101,660.00 + Rp 10,166.60) / 10kg
= Rp 111,826.00 / 10kg
= Rp 11,182.60

c. A.4.1.1.22. Pemasangan 1m2 bekisting untuk kolom = Rp 469,359.00

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


.
(Rp) (Rp)

A. TENAGA

Pekerja L.01 OH 0,660 Rp 100,000.00 Rp 66,000.00

Tukang Batu L.02 OH 0,330 Rp 120,000.00 Rp 39,600.00

Kepala Tukang L.03 OH 0,033 Rp 130,000.00 Rp 4,290.00

Mandor L.04 OH 0,033 Rp 150,000.00 Rp 4,950.00

JUMLAH TENAGA KERJA Rp 114,840.00

B. BAHAN

Kayu Kelas II m3 0,040 Rp 4,000,000.00 Rp 160,000.00

Paku 5cm – 12cm Kg 0,400 Rp 25,000.00 Rp 10,000.00

Minyak bekisting liter 0,200 Rp 28,000.00 Rp 5,600.00

Balok kayu kelas m3 0,015 Rp 4,500,000.00 Rp 67,500.00


II

Plywood tebal lembar 0,350 Rp 145,000.00 Rp 50,750.00


9mm

Dolken kayu ∅8 – barang 2,000 Rp 9,000.00 Rp 18,000.00


10cm panjang 4m

JUMLAH HARGA BAHAN Rp 311,850.00

C. PERALATAN

JUMLAH HARGA ALAT Rp 000,000.00

D. Jumlah (A + B + C) Rp 426,690.00

E. Overhead & Profit (10%) Rp 42,669.00

F. Harga Satuan Pekerjaan (D + E) Rp 469,359.00

1) Jumlah harga pekerja


= koefisien x harga satuan
= 0,660 x Rp 100,000.00
= Rp 66,000.00

UTS EBK 9
2) Jumlah harga tukang batu
= koefisien x harga satuan
= 0,330 x Rp 120,000.00
= Rp 39,600.00
3) Jumlah harga Kepala Tukang
= koefisien x harga satuan
= 0,033 x Rp 130,000.00
= Rp 4,290.00
4) Jumlah harga Mandor
= koefisien x harga satuan
= 0,033 x Rp 150,000.00
= Rp 4,950.00
5) Jumlah tenaga kerja
= Jumlah harga pekerja + Jumlah harga tukang batu + Jumlah harga Kepala Tukang + Jumlah harga
Mandor
= Rp 66,000.00 + Rp 39,600.00 + Rp 4,290.00 + Rp 4,950.00
= Rp 114,840.00
6) Jumlah harga Kayu Kelas II
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 Kayu Kelas II 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Kayu Kelas II
= 0,040 x Rp 4,000,000.00
= Rp 160,000.00
7) Jumlah harga Paku 5cm – 12cm
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑃𝑎𝑘𝑢 5𝑐𝑚 – 12𝑐𝑚 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Paku 5cm – 12cm
= 0,400 x Rp 25,000.00
= Rp 10,000.00
8) Jumlah harga Minyak bekisting
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑀𝑖𝑛𝑦𝑎𝑘 𝑏𝑒𝑘𝑖𝑠𝑡𝑖𝑛𝑔 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Minyak bekisting
= 0,200 x Rp 28,000.00
= Rp 5,600.00
9) Jumlah harga Balok kayu kelas II
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝐵𝑎𝑙𝑜𝑘 𝑘𝑎𝑦𝑢 𝑘𝑒𝑙𝑎𝑠 𝐼𝐼 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Balok kayu kelas II
= 0,015 x Rp 4,500,000.00
= Rp 67,500.00
10) Jumlah harga Plywood tebal 9mm
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑃𝑙𝑦𝑤𝑜𝑜𝑑 𝑡𝑒𝑏𝑎𝑙 9𝑚𝑚 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Plywood tebal 9mm
= 0,350 x Rp 145,000.00
= Rp 50,750.00
11) Jumlah harga Dolken kayu ∅8 – 10cm panjang 4m
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝐷𝑜𝑙𝑘𝑒𝑛 𝑘𝑎𝑦𝑢 ∅8 – 10𝑐𝑚 𝑝𝑎𝑛𝑗𝑎𝑛𝑔 4𝑚 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Dolken kayu ∅8 – 10cm
= 2,000 x Rp 9,000.00
= Rp 18,000.00
12) Jumlah harga bahan
= Jumlah harga Kayu Kelas II + Jumlah harga Paku 5cm – 12cm + Jumlah harga Paku 5cm – 12cm
+ Jumlah harga Minyak bekisting + Jumlah harga Balok kayu kelas II + Jumlah harga Plywood tebal
9mm + Jumlah harga Dolken kayu ∅8 – 10cm panjang 4m
= Rp 160,000.00 + Rp 10,000.00 + Rp 5,600.00 + Rp 67,500.00 + Rp 50,750.00 + Rp 18,000.00
= Rp 311,850.00
12) Jumlah (A + B + C)
= (Rp 114,840.00 + Rp 311,850.00+ Rp 000,000.00)
= Rp 426,690.00
13) Overhead & Profit (10%)
= Jumlah x 10%
= Rp 426,690.00 x 10%
= Rp 42,669.00
14) Harga satuan pekerjaan (D + E)
= (Rp 426,690.00 + Rp 42,669.00)
= Rp 469,359.00

d. Membuat 1 m3 kolom pedestal Uk. 0,55x0,55m = Rp 5,186,500.00

UTS EBK 10
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

(Rp) (Rp)

A. Beton f’c 19,3 m3 1,000 Rp 1,051,600.00 Rp 1,051,600.00


MPa

B. Pembesian besi Kg 244,51807 Rp 11,182.60 Rp 2,734,347.814


D22 4

C. Pembesian besi Kg 29,671692 Rp 11,182.60 Rp 331,806.664


∅12 09

D. Bekisting kolom m2 2,277 Rp 469,359.00 Rp 1,068,730.443

E. Jumlah (A + B + C+D) Rp 5,186,484.921

F. Dibulatkan Rp 5,186,500.00

1) Jumlah harga Beton f’c 19,3 MPa


= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝐵𝑒𝑡𝑜𝑛 𝑓’𝑐 19,3 𝑀𝑃𝑎 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Beton f’c 19,3 MPa
= 1,000 x Rp 1,051,600.00
= Rp 1,051,600.00
2) Jumlah harga Pembesian besi D22
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑃𝑒𝑚𝑏𝑒𝑠𝑖𝑎𝑛 𝑏𝑒𝑠𝑖 𝐷22 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Pembesian besi D22
= 244,518074 x Rp 11,182.60
= Rp 2,734,347.814
3) Jumlah harga Pembesian besi ∅8
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝑃𝑒𝑚𝑏𝑒𝑠𝑖𝑎𝑛 𝑏𝑒𝑠𝑖 ∅8 1𝑚3 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Pembesian besi ∅8
= 29,67169209 x Rp 11,182.60
= Rp 331,806.664
4) Jumlah harga Bekisting kolom
= 𝑘𝑜𝑒𝑓𝑖𝑠𝑖𝑒𝑛 𝐵𝑒𝑘𝑖𝑠𝑡𝑖𝑛𝑔 𝑘𝑜𝑙𝑜𝑚 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 Bekisting kolom
= 2,277 x Rp 469,359.00
= Rp 1,068,730.443
5) Jumlah harga bahan
= Jumlah harga Beton f’c 19,3 MPa + Jumlah harga Pembesian besi D22 + Jumlah harga Pembesian
besi ∅8 + Jumlah harga Bekisting kolom
= Rp 1,051,600.00 + Rp 2,734,347.814 + 331,806.664 + Rp 1,068,730.443
= Rp 5,186,484.921
= Rp 5,186,500.00

4. Analisa harga satuan pekerja


a. Rencana anggaran biaya

No. Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga

(Rp) (Rp)

1. kolom pedestal 5,324 m3 5,186,500.00 Rp 27,612,926.00


Uk. 0,55x0,55m

Jumlah Rp 27,612,926.00

Harga pembulatan Rp 27,613,000.00

1) Jumlah harga Bekisting pekerjaan kolom pedestal Uk. 0,55x0,55m


= 𝑣𝑜𝑙𝑢𝑚𝑒 𝑘𝑜𝑙𝑜𝑚 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑎𝑡𝑢𝑎𝑛 pekerjaan kolom pedestal Uk. 0,55x0,55m
= 5,3243 m3 x Rp 5,065,900.00
= Rp 27,612,926.00
2) Harga pembulatan

UTS EBK 11
= dibulatkan menjadi Rp 27,613,000.00

UTS EBK 12