JUMLAH HARGA
No. URAIAN PEKERJAAN
Rp.
Total 70,283,697,815.89
PPN 10% 7,028,369,781.59
Jumlah 77,312,067,597.48
Dibulatkan 77,312,000,000.00
Terbilang = "Tujuh puluh tujuh milyar tiga ratus dua belas juta rupiah"
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH HARGA
No. URAIAN PEKERJAAN
Rp.
Total 12,199,899,165.45
PPN 10% 1,219,989,916.54
Jumlah 13,419,889,081.99
Dibulatkan 13,419,000,000.00
Terbilang = "Tiga belas milyar empat ratus sembilan belas juta rupiah"
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH I 47,000,000.00
JUMLAH II 142,063,651.47
B LANTAI 1
1 Balok B1 30/60 tulangan 225 kg 93.99 M3 5,304,039.00 498,520,260.76
2 Balok B2 40/70 tulangan 175 kg 26.54 M3 4,779,039.00 126,854,811.22
3 Balok B3 25/40 tulangan 195 kg 20.73 M3 4,989,039.00 103,442,734.63
4 Balok B4 20/40 tulangan 180 kg 4.33 M3
4,831,539.00 20,914,766.02
5 Balok B5 20/30 tulangan 100 kg 0.48 M3 3,991,539.00 1,915,938.72
6 Balok BA1 20/40 tulangan 180 kg 25.54 M3
4,831,539.00 123,416,832.22
7 Balok BA2 20/30 tulangan 100 kg 2.64 M3 3,991,539.00 10,537,662.96
8 Balok Lift BL 15/40 tulangan 250 kg 0.72 M3 5,566,539.00 4,007,908.08
9 Kolom K1 Ø50 tulangan 205 kg 45.73 M3
5,581,475.00 255,219,921.22
10 Kolom K1a Ø50 tulangan 250 kg 7.85 M3 6,053,975.00 47,523,703.75
11 Kolom K3 40/40 tulangan 140 kg 8.48 M3
4,898,975.00 41,543,308.00
12 Kolom Lift KL tulangan 330 kg 1.08 M3 6,893,975.00 7,445,493.00
13 Pelat Lantai 12 cm tulangan 125 kg 201.12 M3
3,854,491.00 775,224,480.70
14 Pelat Tangga 15 cm tulangan 150 kg 7.20 M3 4,116,991.00 29,642,335.20
15 Pelat Dinding Lift tulangan 150 kg 4.50 M3 3,173,991.00 14,282,959.50
16 Kolom Praktis 296.00 M' 56,034.00 16,586,064.00
17 Balok latai 10/15 78.60 M' 63,391.00 4,982,532.60
C LANTAI 2
1 Balok B0 40/80 tulangan 160 kg 6.40 M3 4,621,539.00 29,577,849.60
2 Balok B1 30/60 tulangan 225 kg 51.97 M3 5,304,039.00 275,648,785.21
3 Balok B2 40/70 tulangan 175 kg 21.34 M3 4,779,039.00 101,965,576.10
4 Balok B3 25/40 tulangan 195 kg 12.57 M3
4,989,039.00 62,712,220.23
5 Balok BK1 30/60 tulangan 225 kg 2.16 M3 5,304,039.00 11,456,724.24
6 Balok BK2 20/40 tulangan 180 kg 1.44 M3
4,831,539.00 6,957,416.16
7 Balok BA1 20/40 tulangan 180 kg 8.92 M3 4,831,539.00 43,093,462.65
8 Balok BA2 20/30 tulangan 100 kg 4.07 M3 3,991,539.00 16,261,529.89
9 Balok Lift BL 15/40 tulangan 250 kg 0.72 M3 5,566,539.00 4,007,908.08
10 Kolom K1 Ø50 tulangan 205 kg 36.40 M3 5,581,475.00 203,190,108.95
11 Kolom K1a Ø50 tulangan 250 kg 6.87 M3 6,053,975.00 41,583,240.78
12 Kolom K3 40/40 tulangan 140 kg 2.80 M3 4,898,975.00 13,717,130.00
13 Kolom Lift KL tulangan 330 kg 0.72 M3
6,893,975.00 4,963,662.00
14 Pelat Lantai 12 cm tulangan 125 kg 98.58 M3 3,854,491.00 379,989,598.95
15 Pelat Dinding Lift tulangan 150 kg 6.00 M3 3,173,991.00 19,043,946.00
16 Kolom Praktis 192.50 M' 56,034.00 10,786,545.00
17 Balok latai 11/15 36.00 M' 63,391.00 2,282,076.00
D ATAP
1 Balok B1 30/60 tulangan 225 kg 45.09 M3 5,304,039.00 239,159,118.51
2 Balok B2 40/70 tulangan 175 kg 15.34 M3 4,779,039.00 73,329,574.42
3 Balok B3 25/40 tulangan 195 kg 15.29 M3
4,989,039.00 76,287,395.35
4 Balok BK1 30/60 tulangan 225 kg 6.17 M3 5,304,039.00 32,747,136.79
5 Balok BK2 20/40 tulangan 180 kg 2.74 M3 4,831,539.00 13,257,743.02
6 Balok BA1 20/40 tulangan 180 kg 4.69 M3
4,831,539.00 22,650,254.83
7 Balok BA2 20/30 tulangan 100 kg 5.52 M3 3,991,539.00 22,033,295.28
8 Balok Lift BL 15/40 tulangan 250 kg 0.96 M3
5,566,539.00 5,343,877.44
9 Balok Ring BR 20/30 tulangan 100 kg 7.92 M3 3,991,539.00 31,612,988.88
13 Kolom Lift KL tulangan 330 kg 0.07 M3 6,893,975.00 465,343.31
14 Kolom Atap KA1 20/20 tulangan 285 kg 6.60 M3
6,421,475.00 42,381,735.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
15 Pelat Atap 10 cm tulangan 125 kg 76.33 M3 3,854,491.00 294,197,880.07
16 Kolom Praktis 24.00 M' 56,034.00 1,344,816.00
17 Balok latai 11/15 184.20 M' 63,391.00 11,676,622.20
JUMLAH IV 6,306,542,135.55
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
B LANTAI 1
1 Pasangan bata 1:3:10 1,346.37 M2 61,160.00 82,343,989.20
2 Pasangan bata transram 1:4 117.00 M2 66,407.50 7,769,677.50
3 Plesteran 1:3:10 2,692.74 M2 19,519.00 52,559,592.06
4 Plesteran transram 1:4 234.00 M2 23,320.00 5,456,880.00
5 Plesteran beton 1:2 452.16 M2 32,301.50 14,605,446.24
6 Sponengan sudut 1:2 567.26 M' 6,546.50 3,713,567.59
7 Pasang keramik polos 60 x 60 1,422.34 M2 349,273.50 496,785,669.99
8 Pasang keramik motif 40 x 40 89.56 M2 344,273.50 30,833,134.66
9 Pasang keramik jeruk 30 x 30 29.54 M2
269,273.50 7,954,339.19
10 Pasang keramik jeruk 20 x 20 10.57 M2 264,273.50 2,793,370.90
11 Pasang keramik arstistik Ø 1.20 m 2.00 bh 873,183.75 1,746,367.50
12 Pasang lantai parquet 100.53 M2 239,788.50 24,105,937.91
13 List keramik motif 20 x 20 85.58 M2
299,273.50 25,613,023.22
14 List keramik jeruk 20 x 20 25.52 M2 264,273.50 6,743,731.17
15 Plint dinding keramik motif 10 x 20 427.92 M' 149,636.75 64,032,558.06
16 Pasang keramik dinding KM/WC 20 x 25 163.83 M2 287,337.50 47,074,502.63
17 Plint keramik dinding toilet 10 x 20 109.22 M' 143,668.75 15,691,500.88
18 Meja granit dark green untuk wastafel 4.14 M2 894,376.25 3,702,717.68
19 Pasang keramik motif 20 x 20 tangga 192.72 M2 299,273.50 57,675,988.92
20 Step nozing tangga 10 x 20 153.80 M' 68,552.50 10,543,374.50
21 Pasang penutup dinding luar alucopan rangka besi 951.00 M2 750,000.00 713,250,000.00
22 Pasang dinding akuistik rangka kayu kamfer 536.96 M2 215,000.00 115,446,400.00
23 Pasang batu alam 31.56 M2 204,602.50 6,457,254.90
24 Pasang asesoris tiang kanopi 4.00 bh 2,000,000.00 8,000,000.00
C LANTAI 2
1 Pasangan bata 1:3:10 1,241.68 M2 61,160.00 75,941,148.80
2 Pasangan bata transram 1:4 88.50 M2 66,407.50 5,877,063.75
3 Plesteran 1:3:10 2,483.36 M2
19,519.00 48,472,703.84
4 Plesteran transram 1:4 177.00 M2 23,320.00 4,127,640.00
5 Plesteran beton 1:2 395.64 M2 32,301.50 12,779,765.46
6 Sponengan sudut 1:2 527.26 M' 6,546.50 3,451,707.59
7 Pasang keramik polos 60 x 60 312.52 M2 349,273.50 109,154,954.22
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
8 Pasang keramik motif 40 x 40 196.50 M2 344,273.50 67,649,742.75
9 Pasang keramik jeruk 30 x 30 20.48 M2 269,273.50 5,514,721.28
10 Pasang keramik jeruk 20 x 20 5.59 M 2
264,273.50 1,477,288.87
11 List keramik motif 20 x 20 104.56 M2 299,273.50 31,291,678.03
12 List keramik jeruk 20 x 20 20.41 M2 264,273.50 5,394,984.94
13 Plint dinding keramik motif 10 x 20 522.79 M' 149,636.75 78,229,195.08
14 Pasang keramik dinding KM/WC 20 x 25 131.06 M2 287,337.50 37,659,602.10
15 Plint keramik dinding toilet 10 x 20 87.38 M' 143,668.75 12,553,200.70
16 Meja granit dark green untuk wastafel 3.36 M2 894,376.25 3,005,104.20
17 Dinding partisi kaca bening 8 mm rangka allumunium 32.40 M 2
327,512.15 10,611,393.66
18 Pasang dinding akuistik rangka kayu kamfer 408.24 M2 215,000.00 87,771,600.00
D ATAP
1 Pasangan bata 1:3:10 189.14 M2 61,160.00 11,567,557.76
2 Plesteran 1:3:10 378.27 M 2
19,519.00 7,383,491.17
3 Plesteran beton 1:2 866.46 M2 32,301.50 27,987,957.69
4 Sponengan sudut 1:2 1,039.68 M' 6,546.50 6,806,265.12
JUMLAH V 2,695,530,223.95
JUMLAH VI 1,037,202,564.37
JUMLAH IX 93,815,300.00
X. PEKERJAAN AKSESORIS
1 Satu set Air Mancur 2.00 bh 5,000,000.00 10,000,000.00
2 Huruf steinless steel t=50cm (atas canopy depan) 25.00 bh 250,000.00 6,250,000.00
3 Huruf steinless steel t=100cm (sisi samping convention) 25.00 bh 600,000.00 15,000,000.00
JUMLAH IX 31,250,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
B. PEMBANGUNAN HOTEL
JUMLAH HARGA
No. URAIAN PEKERJAAN
Rp.
Total 30,985,007,517.82
PPN 10% 3,098,500,751.78
Jumlah 34,083,508,269.60
Dibulatkan 34,083,000,000.00
Terbilang = "Tiga puluh empat milyar delapan puluh tiga juta rupiah"
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
B. PEMBANGUNAN HOTEL
JUMLAH I 12,500,000.00
JUMLAH II 623,533,777.06
C LANTAI 2
1 Balok B0 40/70 tulangan 175 kg 76.30 M3 4,779,039.00 364,640,675.70
2 Balok B1 30/60 tulangan 225 kg 156.50 M3 5,304,039.00 830,082,103.50
3 Balok B2 25/40 tulangan 195 kg 79.75 M3 4,989,039.00 397,875,860.25
4 Balok B3 15/40 tulangan 250 kg 2.64 M3 5,566,539.00 14,695,662.96
5 Balok BK1 30/60 tulangan 225 kg 1.80 M3 5,304,039.00 9,547,270.20
6 Balok BK2 20/40 tulangan 180 kg 4.20 M3 4,831,539.00 20,292,463.80
7 Balok BA1 20/40 tulangan 180 kg 97.55 M3 4,831,539.00 471,316,629.45
8 Balok BA2 20/30 tulangan 100 kg 22.17 M3 3,991,539.00 88,492,419.63
9 Kolom K1 50 x 50 tulangan 140 kg 75.00 M3 4,898,975.00 367,423,125.00
10 Kolom K2 Ø50 tulangan 205 kg 10.21 M3 5,581,475.00 56,986,859.75
11 Kolom K3 45 x 45 tulangan 150 kg 111.78 M3 5,003,975.00 559,344,325.50
12 Kolom K4 30 x 30 tulangan 180 kg 2.16 M3 5,318,975.00 11,488,986.00
13 Kolom K5 (L) 30 x 30 x 15 tulangan 330 kg 2.43 M3 6,893,975.00 16,752,359.25
14 Kolom K6 (T) 50 x 50 x 15 tulangan 250 kg 2.55 M3 6,053,975.00 15,437,636.25
15 Pelat Lantai 12 cm tulangan 125 kg 504.01 M3 3,854,491.00 1,942,702,008.91
16 Pelat Dinding Lift tulangan 150 kg 33.90 M3 3,173,991.00 107,598,294.90
17 Kolom Praktis 2,472.00 M' 56,034.00 138,516,048.00
18 Balok latai 11/15 536.90 M' 63,391.00 34,034,627.90
D ATAP
1 Balok B0 40/70 tulangan 175 kg 74.20 M3 4,779,039.00 354,604,693.80
2 Balok B1 30/60 tulangan 225 kg 146.59 M3 5,304,039.00 777,519,077.01
3 Balok B2 25/40 tulangan 195 kg 74.05 M3 4,989,039.00 369,438,337.95
4 Balok B3 15/40 tulangan 250 kg 2.88 M3 5,566,539.00 16,031,632.32
5 Balok BK1 30/60 tulangan 225 kg 3.42 M3 5,304,039.00 18,139,813.38
6 Balok BK2 20/40 tulangan 180 kg 4.04 M3 4,831,539.00 19,519,417.56
7 Balok BA1 20/40 tulangan 180 kg 56.14 M3 4,831,539.00 271,242,599.46
8 Balok BA2 20/30 tulangan 100 kg 12.59 M3 3,991,539.00 50,253,476.01
9 Kolom K1 50 x 50 tulangan 140 kg 81.00 M3 4,898,975.00 396,816,975.00
10 Kolom K2 Ø50 tulangan 205 kg 8.64 M3 5,581,475.00 48,223,944.00
11 Kolom K3 45 x 45 tulangan 150 kg 131.87 M3 5,003,975.00 659,874,183.25
12 Kolom K4 30 x 30 tulangan 180 kg 2.70 M3 5,318,975.00 14,361,232.50
13 Kolom K5 (L) 30 x 30 x 15 tulangan 330 kg 2.70 M3 6,893,975.00 18,613,732.50
14 Kolom K6 (T) 50 x 50 x 15 tulangan 250 kg 3.83 M3 6,053,975.00 23,156,454.38
15 Pelat Atap 12 cm tulangan 125 kg 522.43 M3 3,854,491.00 2,013,701,733.13
16 Kolom Praktis 43.20 M' 56,034.00 2,420,668.80
17 Balok latai 11/15 184.20 M' 63,391.00 11,676,622.20
18 Balok ring atap B1 30/60 tulangan 225 kg 25.20 M3 5,304,039.00 133,661,782.80
19 Balok ring atap B2 25/40 tulangan 195 kg 22.40 M3 4,989,039.00 111,754,473.60
20 Balok ring atap B3 15/40 tulangan 250 kg 3.36 M3 5,566,539.00 18,703,571.04
JUMLAH IV 16,932,251,148.65
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
B LANTAI 1
1 Pasangan bata 1:3:10 6,791.88 M2 61,160.00 415,391,380.80
2 Pasangan bata transram 1:4 839.40 M2 66,407.50 55,742,455.50
3 Plesteran 1:3:10 13,583.76 M2 19,519.00 265,141,411.44
4 Plesteran transram 1:4 1,678.80 M2 23,320.00 39,149,616.00
5 Plesteran beton 1:2 2,584.00 M2 32,301.50 83,467,076.00
6 Sponengan sudut 1:2 5,168.00 M' 6,546.50 33,832,312.00
7 Pasang keramik polos 60 x 60 857.84 M2 349,273.50 299,620,779.24
8 Pasang keramik polos 40 x 40 664.59 M2 329,273.50 218,831,875.37
9 Pasang keramik polos 30 x 30 256.24 M2 294,273.50 75,404,641.64
10 Pasang keramik jeruk 30 x 30 64.50 M2 269,273.50 17,368,140.75
11 Pasang keramik motif 30 x 30 1,183.50 M2 319,273.50 377,860,187.25
12 Pasang keramik jeruk 20 x 20 112.60 M2 264,273.50 29,757,196.10
13 Pasang keramik arstistik Ø 1.20 m 1.00 bh 873,183.75 873,183.75
14 List keramik motif 40 x 40 109.22 M2 344,273.50 37,601,551.67
15 List keramik motif 30 x 30 181.79 M2 319,273.50 58,040,729.57
16 List keramik polos 30 x 30 68.08 M2 294,273.50 20,034,139.88
17 List keramik jeruk 20 x 20 140.08 M2 264,273.50 37,019,431.88
18 Pasang keramik dinding KM/WC 20 x 25 744.78 M2 287,337.50 214,003,223.25
19 Plint keramik dinding toilet 10 x 20 496.52 M' 143,668.75 71,334,407.75
20 Meja granit dark green untuk wastafel 37.25 M2 894,376.25 33,315,515.31
21 Pasang keramik motif 20 x 20 tangga 96.00 M2 299,273.50 28,730,256.00
22 Step nozing tangga 10 x 20 48.00 M' 68,552.50 3,290,520.00
23 Pasang penutup dinding luar alucopan rangka besi 405.00 M2 750,000.00 303,750,000.00
24 Pasang dinding partisi kaca bening 8 mm 210.40 M2 327,512.15 68,908,556.36
25 Pasang dinding akuistik rangka kayu kamfer 129.08 M2 215,000.00 27,752,200.00
C LANTAI 2
1 Pasangan bata 1:3:10 6,232.90 M2 61,160.00 381,204,164.00
2 Pasangan bata transram 1:4 779.10 M2 66,407.50 51,738,083.25
3 Plesteran 1:3:10 12,465.80 M2 19,519.00 243,319,950.20
4 Plesteran transram 1:4 1,558.20 M2 23,320.00 36,337,224.00
5 Plesteran beton 1:2 2,454.80 M2 32,301.50 79,293,722.20
6 Sponengan sudut 1:2 4,909.60 M' 6,546.50 32,140,696.40
7 Pasang keramik polos 60 x 60 1,412.46 M2 349,273.50 493,334,847.81
8 Pasang keramik polos 40 x 40 442.73 M2 329,273.50 145,779,256.66
9 Pasang keramik polos 30 x 30 242.57 M2 294,273.50 71,381,922.90
10 Pasang keramik jeruk 30 x 30 51.46 M2 269,273.50 13,856,814.31
11 Pasang keramik motif 30 x 30 1,183.50 M2 319,273.50 377,860,187.25
12 Pasang keramik jeruk 20 x 20 108.76 M2 264,273.50 28,742,385.86
13 List keramik motif 40 x 40 60.26 M2 344,273.50 20,745,921.11
14 List keramik motif 30 x 30 205.78 M2 319,273.50 65,700,100.83
15 List keramik polos 30 x 30 421.07 M2 294,273.50 123,909,742.65
16 List keramik jeruk 30 x 30 6.49 M2 269,273.50 1,747,585.02
17 List keramik jeruk 20 x 20 133.59 M2 264,273.50 35,304,296.87
18 Pasang keramik dinding KM/WC 20 x 25 744.78 M2 287,337.50 214,003,223.25
19 Plint keramik dinding toilet 10 x 20 496.52 M' 143,668.75 71,334,407.75
20 Meja granit dark green untuk wastafel 37.25 M2 894,376.25 33,315,515.31
21 Pasang dinding akuistik rangka kayu kamfer 469.81 M2 215,000.00 101,008,075.00
D ATAP
1 Pasangan bata 1:3:10 691.56 M2 61,160.00 42,295,809.60
2 Plesteran 1:3:10 1,383.12 M2 19,519.00 26,997,119.28
3 Plesteran beton 1:2 4,353.55 M2 32,301.50 140,626,195.33
4 Sponengan sudut 1:2 1,759.00 M' 6,546.50 11,515,293.50
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
JUMLAH V 5,759,851,922.80
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
VI. PEKERJAAN ATAP DAN PLAFOND
1 Pasang struktur atap baja ringan 2,465.66 M2 185,000.00 456,147,100.00
2 Pasang penutup atap multiroof 2,465.66 M2 153,570.00 378,651,406.20
3 Pasang bubungan multiroof 294.40 M' 104,262.00 30,694,732.80
4 Paang listplank kayu jati 2x3/30 412.30 M' 212,700.00 87,696,210.00
5 Pasang rangka plafond hollow 7,264.48 M2 70,225.00 510,148,108.00
6 Pasang plafond kalsiboard 6,887.54 M2 36,175.00 249,156,759.50
7 Pasang plafond akustik 376.94 M2 74,395.00 28,042,451.30
8 List plafond gypsum 10,896.72 M' 18,009.00 196,239,030.48
JUMLAH VI 1,936,775,798.28
JUMLAH IX 970,228,890.00
X. PEKERJAAN AKSESORIS
1 Tumpuan Huruf depan Hotel bahan alucubon & kaca 52.00 m2 750,000.00 39,000,000.00
2 Huruf steinless steel t=75cm 14.00 bh 450,000.00 6,300,000.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
JUMLAH IX 45,300,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH HARGA
No. URAIAN PEKERJAAN
Rp.
Total 2,703,435,879.16
PPN 10% 270,343,587.92
Jumlah 2,973,779,467.07
Dibulatkan 2,973,000,000.00
Terbilang = "Dua milyar sembilan ratus tujuh puluh tiga juta rupiah"
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH I 3,500,000.00
JUMLAH II 22,580,424.72
B LANTAI 2
1 Balok B1 25/50 tulangan 160 kg 17.50 M3 4,621,539.00 80,876,932.50
2 Balok BK1 20/35 tulangan 270 kg 0.07 M3 5,776,539.00 404,357.73
3 Balok BA1 20/35 tulangan 270 kg 7.63 M3 5,776,539.00 44,074,992.57
4 Balok BA1 20/30 tulangan 100 kg 1.50 M3 3,991,539.00 5,987,308.50
4 Balok 25/40 tulangan 195 kg 3.10 M3 4,989,039.00 15,466,020.90
5 Kolom K Ø 40 tulangan 235 kg 8.54 M3 5,896,475.00 50,360,613.68
6 Pelat Lantai 12 cm tulangan 125 kg 31.20 M3 3,854,491.00 120,260,119.20
7 Kolom Praktis 128.00 M' 56,034.00 7,172,352.00
8 Balok latai 10/15 72.00 M' 63,391.00 4,564,152.00
C ATAP
1 Balok B1 25/40 tulangan 195 kg 14.90 M3 4,989,039.00 74,336,681.10
2 Balok BA1 20/35 tulangan 240 kg 7.63 M3 5,461,539.00 41,671,542.57
3 Pelat Atap 10 cm tulangan 125 kg 27.00 M3 3,854,491.00 104,071,257.00
JUMLAH IV 689,065,811.89
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
B LANTAI 2
1 Pasangan bata 1:3:10 299.88 M2 61,160.00 18,340,660.80
2 Pasangan bata transram 1:4 53.40 M2 66,407.50 3,546,160.50
3 Plesteran 1:3:10 599.76 M2 19,519.00 11,706,715.44
4 Plesteran transram 1:4 106.80 M2 23,320.00 2,490,576.00
5 Plesteran beton 1:2 92.94 M2 32,301.50 3,002,230.62
6 Sponengan sudut 1:2 200.00 M' 6,546.50 1,309,300.00
7 Pasang keramik polos 30 x 30 32.31 M2 294,273.50 9,507,976.79
8 Pasang keramik serit motif 30 x 30 43.20 M2 319,273.50 13,792,615.20
9 Pasang keramik serit 20 x 20 20.00 M2 264,273.50 5,285,470.00
10 Pasang lantai parquet 179.76 M2 239,788.50 43,104,380.76
11 Pasang keramik dinding KM/WC 20 x 25 67.20 M2 287,337.50 19,309,080.00
12 Plint keramik dinding toilet 10 x 20 44.80 M' 143,668.75 6,436,360.00
13 Pasang dinding batu alam 335.92 M2 204,602.50 68,730,071.80
14 Meja granit dark green untuk wastafel 1.80 M2 894,376.25 1,609,877.25
15 Pasang alucopan rangka besi 751.96 M2 750,000.00 563,970,000.00
C ATAP
1 Plesteran beton 1:2 270.00 M2 32,301.50 8,721,405.00
2 Sponengan sudut 1:2 341.80 M' 6,546.50 2,237,593.70
JUMLAH V 1,662,180,995.46
JUMLAH VI 25,648,833.24
JUMLAH IX 61,676,080.00
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH HARGA
No. URAIAN PEKERJAAN
Rp.
Total 5,795,847,819.63
PPN 10% 579,584,781.96
Jumlah 6,375,432,601.59
Dibulatkan 6,375,000,000.00
Terbilang = "Enam milyar tiga ratus tujuh puluh lima juta rupiah"
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN SUTAN RAJA HOTEL & CONVENTION CENTER
JUMLAH I 209,554,758.78
JUMLAH II 54,409,010.77
JUMLAH IV 995,440,254.58
JUMLAH V 1,027,020,887.24
c. Swimming Pool
1 Galian tanah 2,019.95 M3 16,320.00 32,965,584.00
2 Urugan pasir 80.80 M 3
131,080.00 10,591,001.84
3 Rabat beton 1:3:5 tebal 5 cm 40.40 M2 64,228.00 2,594,746.97
4 Balok rusuk 25/50 41.68 M3 3,387,140.00 141,180,229.13
5 Pelat lantai tebal 20 cm 161.60 M3 2,809,640.00 454,026,585.44
7 Pelat dinding tebal 15 cm 34.04 M3 3,906,991.00 132,974,438.69
8 Pasang bata lantai 1:3:10 350.00 M 2
61,160.00 21,406,000.00
9 Pasang keramik lantai 888.78 M2 344,273.50 305,982,712.78
10 Pasang keramik dinding 226.90 M2 344,273.50 78,115,657.15
1,179,836,956.00
JUMLAH VI 1,818,913,275.07
IX PEMBANGUNAN MAINGATE
1 Galian Tanah 24.38 M3 16,320.00 397,816.32
2 Urugan pasir 1.90 M 3
131,080.00 248,789.84
3 Rabat beton 1:3:5 tebal 5 cm 8.48 M2 64,228.00 544,653.44
4 Sloof 15/20 tulangan 170 kg 0.62 M3 4,726,539.00 2,906,821.49
5 Kolom Praktis 11.50 M' 56,034.00 644,391.00
6 Kolom Struktur 15/25 2.51 M3 5,318,975.00 13,363,924.69
7 Ring Balk 15/20 tulangan 170 kg 0.90 M3 4,726,539.00 4,253,885.10
8 Pelat beton 15 cm 0.45 M 3
3,854,491.00 1,734,520.95
9 Pondasi foot plate 1.32 M3 3,906,991.00 5,172,856.08
10 Pasangan bata 1:3:10 48.00 M2 61,160.00 2,935,680.00
11 Plesteran 1:3:10 96.00 M 2
19,519.00 1,873,824.00
12 Plesteran beton 1:2 18.20 M2 32,301.50 587,887.30
13 Sponengan sudut 1:2 290.00 M' 6,546.50 1,898,485.00
14 Pasangan Batu Candi 40.00 M2 204,602.50 8,184,100.00
15 Besi Tempa Ukir 10.44 M2 500,000.00 5,220,000.00
16 Cat tembok 3.00 M 2
31,758.00 95,274.00
17 Cat kayu pintu dan kusen 4.70 M2 45,459.00 213,839.14
JUMLAH IX 50,276,748.34
X PEMBANGUNAN LANDSCAPE
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
Rp. Rp.
1 Perkerasan jalan aspal 6,000.00 M2 110,000.00 660,000,000.00
2 Perkerasan paving block 2,500.00 M2 95,000.00 237,500,000.00
3 Pasang kanstin 2,042.00 M' 45,000.00 91,890,000.00
4 Cat Kantin 816.80 M2 31,758.00 25,939,934.40
5 Plester Pagar Keliling (existing) 4,950.00 M 2
19,519.00 96,619,050.00
6 Sponengan sudut 1:2 pagar existing 3,960.00 M' 6,546.50 25,924,140.00
7 Cat tembok 2,475.00 M2 31,758.00 78,601,050.00
8 Beton Plat Penutup saluran Depan t=20cm 12.80 M 3
3,906,991.00 50,009,484.80
9 Grill Besi Manhole utk saluran depan 4.00 bh 1,500,000.00 6,000,000.00
10 Saluran air hujan U40 995.00 M' 210,000.00 208,950,000.00
11 Bak kontrol 60.00 unit 275,000.00 16,500,000.00
JUMLAH X 1,497,933,659.20
HARGA SATUAN POKOK KEGIATAN (HSPK)
B. PEKERJAAN PONDASI
1 Pasangan pondasi batu belah 1pc : 3kp : 10ps m3 368,519.50
2 Pasangan pondasi batu kosong m3 232,452.00
3 Pilecap (besi 170 kg + begisting) m3 3,282,140.00
4 Pondasi Bored Pile (besi 110 kg ) m' 520,482.48
5 Pondasi Bored Pile (besi 125 kg ) m' 794,004.26
6 Pondasi beton bertulang (besi 150 kg + begisting) m3 3,072,140.00
7 Pondasi beton bertulang (besi 160 kg + begisting) m3 3,177,140.00
C. PEKERJAAN DINDING
1 Pasang bata merah tebal 1/2 bata, 1pc:3kp:10ps m2 61,160.00
2 Pasang bata merah tebal 1/2 bata, 1pc:4ps m2 66,407.50
3 Pasang batu alam bh 204,602.50
D. PEKERJAAN PLESTERAN
1 Plesteran 1pc:4ps, tebal 1,5 cm m2 23,320.00
2 Plesteran 1pc:3kp:10ps, tebal 1,5 cm m2 19,519.00
3 Plesteran beton 1pc:2ps, tebal 1,5 cm m2 32,301.50
4 Plesteran skoning 1pc:2ps m' 6,546.50
E. PEKERJAAN KAYU
1 Pasang kusen pintu dan jendela kayu kamper m3 9,777,400.00
2 Pasang pintu panel kayu kamper m2 516,150.00
3 Pasang lisplank ukuran 2 x(3 x 30) cm, kayu kamper m' 212,700.00
F. PEKERJAAN BETON
1 Membuat lantai kerja beton tumbuk, 1pc:3ps:5kr, tebal 5 cm m2 64,228.00
2 Sloof beton bertulang (besi 100 kg + begisting) m3 2,547,140.00
3 Sloof beton bertulang (besi 135 kg + begisting) m3 2,914,640.00
4 Sloof beton bertulang (besi 180 kg + begisting) m3 3,387,140.00
5 Sloof beton bertulang (besi 195 kg + begisting) m3 3,544,640.00
6 Pondasi beton bertulang (besi 130 kg + begisting) m3 2,862,140.00
7 Balok beton bertulang (besi 100 kg + begisting) m3 3,991,539.00
8 Balok beton bertulang (besi 160 kg + begisting) m3 4,621,539.00
9 Balok beton bertulang (besi 170 kg + begisting) m3 4,726,539.00
10 Balok beton bertulang (besi 175 kg + begisting) m3 4,779,039.00
11 Balok beton bertulang (besi 180 kg + begisting) m3 4,831,539.00
28
NO URAIAN SATUAN HARGA
12 Balok beton bertulang (besi 195 kg + begisting) m3 4,989,039.00
13 Balok beton bertulang (besi 225 kg + begisting) m3 5,304,039.00
14 Balok beton bertulang (besi 240 kg + begisting) m3 5,461,539.00
15 Balok beton bertulang (besi 250 kg + begisting) m3 5,566,539.00
16 Balok beton bertulang (besi 270 kg + begisting) m3 5,776,539.00
17 Tangga beton bertulang (besi 150 kg + begisting) m3 4,116,991.00
18 Pelat beton bertulang (besi 125 kg + begisting) m3 3,854,491.00
19 Pelat basement beton bertulang (besi 140 kg + begisting) m3 2,967,140.00
20 Retaining Wall (besi 150 kg + begisting) m3 3,173,991.00
21 Pelat lantai beton bertulang untuk groundtank / IPAL (besi 125 kg + begisting) m3 2,809,640.00
22 Pelat dinding beton bertulang untuk groundtank / IPAL (besi 130 kg + begisting) m3 3,906,991.00
23 Kolom beton bertulang (besi 330 kg + begisting) m3 6,893,975.00
24 Kolom beton bertulang (besi 285 kg + begisting) m3 6,421,475.00
25 Kolom beton bertulang (besi 250 kg + begisting) m3 6,053,975.00
26 Kolom beton bertulang (besi 235 kg + begisting) m3 5,896,475.00
27 Kolom beton bertulang (besi 205 kg + begisting) m3 5,581,475.00
28 Kolom beton bertulang (besi 195 kg + begisting) m3 5,461,975.00
29 Kolom beton bertulang (besi 180 kg + begisting) m3 5,318,975.00
30 Kolom beton bertulang (besi 150 kg + begisting) m3 5,003,975.00
31 Kolom beton bertulang (besi 140 kg + begisting) m3 4,898,975.00
32 Kolom penguat beton bertulang (11 x 11) cm m' 56,034.00
33 Ring balok beton bertulang (10 x 15) cm m' 63,391.00
H. PEKERJAAN LANGIT-LANGIT
1 Plafon kalsiboard m2 36,175.00
Plafon akustik m2 74,395.00
2 List gypsum m' 18,009.00
I. PEKERJAAN SANITASI
1 Memasang 1 buah kloset duduk sekelas TOTO bh 2,401,430.00
2 Memasang 1 buah urinoir TOTO bh 2,309,500.00
3 Memasang 1 bh wastafel TOTO bh 1,194,300.00
4 Memasang 1 buah bathtub bh 5,475,430.00
29
NO URAIAN SATUAN HARGA
30
NO URAIAN SATUAN HARGA
L. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pasang lantai keramik polos 60 x 60 cm m2 349,273.50
2 Pasang lantai keramik motif 40 x 40 cm m2 344,273.50
3 Pasang lantai keramik polos 40 x 40 cm m2 329,273.50
4 Pasang lantai keramik motif 30 x 30 cm m2 319,273.50
5 Pasang lantai keramik polos 30 x 30 cm m2 294,273.50
6 Pasang lantai keramik jeruk 30 x 30 cm m2 269,273.50
7 Pasang lantai keramik motif 20 x 20 cm m2 299,273.50
8 Pasang lantai keramik jeruk 20 x 20 cm m2 264,273.50
9 Pasang keramik dinding motif 20 x 25 m2 287,337.50
10 Pasang granit dark green m2 894,376.25
11 Pasang step nozing tangga m' 68,552.50
12 Pasang alucopan rangka besi m2 750,000.00
13 Pasang lantai parquet jati m2 239,788.50
14 Pasang dinding akustik m2 215,000.00
15 Pasang lantai artistik Ø 1.20 m bh 873,183.75
M. PEKERJAAN PENGECATAN
1 Pengecatan kayu bidang kayu baru m2 45,459.00
2 Pengecatan tembok baru m2 31,758.00
3 Politur m2 34,835.00
31
NO URAIAN SATUAN HARGA
12 Jendela (J1) unit 830,974.96
13 Jendela (J2) unit 747,877.46
14 Jendela (J3) unit 1,661,949.92
15 Jendela (J4) unit 2,492,924.88
16 Jendela (J5) unit 2,077,437.40
17 Jendela (J6) unit 706,328.72
18 Jendela (J7) unit 4,154,874.80
19 Jendela (J8) unit 3,323,899.84
c Café & Fitness Center
1 Pintu PVC (P1, P2, P3, P4) unit 959,000.00
2 Pintu allumunium (P5, P6) unit 2,209,644.19
3 Pintu allumunium (P7) unit 3,595,684.98
4 Pintu allumunium (P8) unit 2,549,687.99
5 Jendela (J1) unit 2,934,478.88
6 Jendela (J2) unit 4,327,855.79
7 Bouven unit 447,569.01
32
HARGA SATUAN DASAR (HSD)
UPAH
NO URAIAN SATUAN HARGA
1 2 3 4
33
HARGA SATUAN DASAR (HSD)
BAHAN
NO URAIAN SATUAN HARGA
1 2 3 4
A. PEKERJAAN TANAH
1 : 1m3 Galian tanah biasa
Pekerja 0.4000 Oh x Rp 35,000.00 = Rp 14,000.00
Mandor 0.0400 Oh x Rp 58,000.00 = Rp 2,320.00
= Rp 16,320.00
2 : 1m3 Urugan kembali
Pekerja 0.1920 Oh x Rp 35,000.00 = Rp 6,720.00
Mandor 0.0190 Oh x Rp 58,000.00 = Rp 1,102.00
= Rp 7,822.00
3 : 1m3 Pemadatan tanah
Pekerja 0.5000 Oh x Rp 35,000.00 = Rp 17,500.00
Mandor 0.0500 Oh x Rp 58,000.00 = Rp 2,900.00
= Rp 20,400.00
4 : 1m3 Urugan pasir
Bahan :
Pasir urug 1.2000 m3 x Rp 100,000.00 = Rp 120,000.00
= Rp 120,000.00
Tenaga :
Pekerja 0.3000 Oh x Rp 35,000.00 = Rp 10,500.00
Mandor 0.0100 Oh x Rp 58,000.00 = Rp 580.00
= Rp 11,080.00
= Rp 131,080.00
B. PEKERJAAN PONDASI
1 : 1m3 Pasangan pondasi batu belah 1pc : 3kp : 10ps
Bahan :
Batu belah 15/20 cm 1.1000 m3 x Rp 127,500.00 = Rp 140,250.00
Semen portland 61.0000 Kg x Rp 1,075.00 = Rp 65,575.00
Kapur padam 0.1470 m3 x Rp 93,500.00 = Rp 13,744.50
Pasir pasang 0.4920 m3 x Rp 125,000.00 = Rp 61,500.00
= Rp 281,069.50
Tenaga
Pekerja 1.5000 Oh x Rp 35,000.00 = Rp 52,500.00
Tukang batu 0.6000 Oh x Rp 46,000.00 = Rp 27,600.00
Kepala tukang 0.0600 Oh x Rp 50,000.00 = Rp 3,000.00
Mandor 0.0750 Oh x Rp 58,000.00 = Rp 4,350.00
= Rp 87,450.00
= Rp 368,519.50
2 : 1m3 Pasangan pondasi batu kosong
Bahan :
Batu belah 15/20 cm 1.2000 m3 x Rp 127,500.00 = Rp 153,000.00
Pasir urug 0.3000 m3 x Rp 100,000.00 = Rp 30,000.00
= Rp 183,000.00
Tenaga
Pekerja 0.7800 Oh x Rp 35,000.00 = Rp 27,300.00
Tukang batu 0.3900 Oh x Rp 46,000.00 = Rp 17,940.00
Kepala tukang 0.0390 Oh x Rp 50,000.00 = Rp 1,950.00
Mandor 0.0390 Oh x Rp 58,000.00 = Rp 2,262.00
= Rp 49,452.00
= Rp 232,452.00
37
4 : 1m3 Pondasi Bored Pile (besi 110 kg )
Bahan :
Kayu sengon 0.2700 m3 x Rp 1,782,500.00 = Rp 481,275.00
Paku biasa 2"-5" 2.0000 Kg x Rp 17,000.00 = Rp 34,000.00
Minyak begisting 0.6000 ltr x Rp 6,000.00 = Rp 3,600.00
Besi beton (polos/ulir) 110.0000 Kg x Rp 10,500.00 = Rp 1,155,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
= Rp 2,297,800.00
Tenaga :
Pekerja 4.8500 Oh x Rp 35,000.00 = Rp 169,750.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 1.5600 Oh x Rp 48,000.00 = Rp 74,880.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.3310 Oh x Rp 50,000.00 = Rp 16,550.00
Mandor 0.1700 Oh x Rp 58,000.00 = Rp 9,860.00
= Rp 354,340.00
= Rp 2,652,140.00
38
7 : 1m3 Pondasi beton bertulang (besi 160 kg + begisting)
Bahan :
Kayu sengon 0.2700 m3 x Rp 1,782,500.00 = Rp 481,275.00
Paku biasa 2"-5" 2.0000 Kg x Rp 17,000.00 = Rp 34,000.00
Minyak begisting 0.6000 ltr x Rp 6,000.00 = Rp 3,600.00
Besi beton (polos/ulir) 160.0000 Kg x Rp 10,500.00 = Rp 1,680,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
= Rp 2,822,800.00
Tenaga :
Pekerja 4.8500 Oh x Rp 35,000.00 = Rp 169,750.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 1.5600 Oh x Rp 48,000.00 = Rp 74,880.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.3310 Oh x Rp 50,000.00 = Rp 16,550.00
Mandor 0.1700 Oh x Rp 58,000.00 = Rp 9,860.00
= Rp 354,340.00
= Rp 3,177,140.00
C. PEKERJAAN DINDING
1 : 1m2 Pasang bata merah tebal 1/2 bata, 1pc:3kp:10ps
Bahan :
Bata merah 70.0000 bh x Rp 450.00 = Rp 31,500.00
Semen portland 4.5000 kg x Rp 1,075.00 = Rp 4,837.50
Kapur padam 0.0150 m3 x Rp 93,500.00 = Rp 1,402.50
Pasir pasang 0.0500 m3 x Rp 125,000.00 = Rp 6,250.00
= Rp 43,990.00
Tenaga :
Pekerja 0.3200 Oh x Rp 35,000.00 = Rp 11,200.00
Tukang batu 0.1000 Oh x Rp 46,000.00 = Rp 4,600.00
Kepala tukang 0.0100 Oh x Rp 50,000.00 = Rp 500.00
Mandor 0.0150 Oh x Rp 58,000.00 = Rp 870.00
= Rp 17,170.00
= Rp 61,160.00
39
D. PEKERJAAN PLESTERAN
1 : 1m2 Plesteran 1pc:4ps, tebal 1,5 cm
Bahan :
Semen portland 5.2000 Kg x Rp 1,075.00 = Rp 5,590.00
Pasir pasang 0.0200 m3 x Rp 125,000.00 = Rp 2,500.00
= Rp 8,090.00
Tenaga :
Pekerja 0.2000 Oh x Rp 35,000.00 = Rp 7,000.00
Tukang batu 0.1500 Oh x Rp 46,000.00 = Rp 6,900.00
Kepala tukang 0.0150 Oh x Rp 50,000.00 = Rp 750.00
Mandor 0.0100 Oh x Rp 58,000.00 = Rp 580.00
= Rp 15,230.00
= Rp 23,320.00
2 : 1m2 Plesteran 1pc:3kp:10ps, tebal 1,5 cm
Bahan :
Semen portland 1.8400 Kg x Rp 1,075.00 = Rp 1,978.00
Kapur padam 0.0060 m3 x Rp 93,500.00 = Rp 561.00
Pasir pasang 0.0140 m3 x Rp 125,000.00 = Rp 1,750.00
= Rp 4,289.00
Tenaga :
Pekerja 0.2000 Oh x Rp 35,000.00 = Rp 7,000.00
Tukang batu 0.1500 Oh x Rp 46,000.00 = Rp 6,900.00
Kepala tukang 0.0150 Oh x Rp 50,000.00 = Rp 750.00
Mandor 0.0100 Oh x Rp 58,000.00 = Rp 580.00
= Rp 15,230.00
= Rp 19,519.00
3 : 1m2 Plesteran beton 1pc:2ps, tebal 1,5 cm
Bahan :
Semen portland 9.3000 Kg x Rp 1,075.00 = Rp 9,997.50
Pasir pasang 0.0180 m3 x Rp 125,000.00 = Rp 2,250.00
= Rp 12,247.50
Tenaga :
Pekerja 0.2600 Oh x Rp 35,000.00 = Rp 9,100.00
Tukang batu 0.2000 Oh x Rp 46,000.00 = Rp 9,200.00
Kepala tukang 0.0200 Oh x Rp 50,000.00 = Rp 1,000.00
Mandor 0.0130 Oh x Rp 58,000.00 = Rp 754.00
= Rp 20,054.00
= Rp 32,301.50
4 : 1m' Plesteran skoning 1pc:2ps
Bahan :
Semen portland 0.5000 Kg x Rp 1,075.00 = Rp 537.50
Pasir pasang 0.0020 m3 x Rp 125,000.00 = Rp 250.00
= Rp 787.50
Tenaga :
Pekerja 0.0570 Oh x Rp 35,000.00 = Rp 1,995.00
Tukang batu 0.0380 Oh x Rp 46,000.00 = Rp 1,748.00
Kepala tukang 0.0380 Oh x Rp 50,000.00 = Rp 1,900.00
Mandor 0.0020 Oh x Rp 58,000.00 = Rp 116.00
= Rp 5,759.00
= Rp 6,546.50
40
E. PEKERJAAN KAYU
1 : 1m3 Pasang kusen pintu dan jendela kayu kamper
Bahan :
Kayu kamper balok 1.2000 m3 x Rp 7,150,000.00 = Rp 8,580,000.00
= Rp 8,580,000.00
Tenaga :
Pekerja 6.0000 Oh x Rp 35,000.00 = Rp 210,000.00
Tukang kayu 18.0000 Oh x Rp 48,000.00 = Rp 864,000.00
Kepala tukang 2.0000 Oh x Rp 53,000.00 = Rp 106,000.00
Mandor 0.3000 Oh x Rp 58,000.00 = Rp 17,400.00
= Rp 1,197,400.00
= Rp 9,777,400.00
2 : 1m2 Pasang pintu panel kayu kamper
Bahan :
Kayu kamper, papan 0.0400 m3 x Rp 8,625,000.00 = Rp 345,000.00
= Rp 345,000.00
Tenaga :
Pekerja 1.0000 Oh x Rp 35,000.00 = Rp 35,000.00
Tukang kayu 2.5000 Oh x Rp 48,000.00 = Rp 120,000.00
Kepala tukang 0.2500 Oh x Rp 53,000.00 = Rp 13,250.00
Mandor 0.0500 Oh x Rp 58,000.00 = Rp 2,900.00
= Rp 171,150.00
= Rp 516,150.00
3 : 1m2 Pasang pintu plywood rangkap, rangka kayu kamper
Bahan :
Kayu kamper, papan 0.0196 m3 x Rp 8,625,000.00 = Rp 169,050.00
Paku biasa 1/2"-1" 0.3000 kg x Rp 17,000.00 = Rp 5,100.00
Lem kayu 0.3000 lt x Rp 12,650.00 = Rp 3,795.00
Plywood 4 x 8 x 4 mm 1.0000 lbr x Rp 75,000.00 = Rp 75,000.00
= Rp 169,050.00
Tenaga :
Pekerja 0.6000 Oh x Rp 35,000.00 = Rp 21,000.00
Tukang kayu 2.0000 Oh x Rp 48,000.00 = Rp 96,000.00
Kepala tukang 0.2000 Oh x Rp 53,000.00 = Rp 10,600.00
Mandor 0.0400 Oh x Rp 58,000.00 = Rp 2,320.00
= Rp 129,920.00
= Rp 298,970.00
4 : 1m' Pasang lisplank ukuran 2 x(3 x 30) cm, kayu kamper
Bahan :
Kayu kamper, papan 0.0220 m3 x Rp 8,625,000.00 = Rp 189,750.00
Paku biasa 2"-5" 0.0750 Kg x Rp 17,000.00 = Rp 1,275.00
= Rp 191,025.00
Tenaga :
Pekerja 0.1500 Oh x Rp 35,000.00 = Rp 5,250.00
Tukang kayu 0.3000 Oh x Rp 48,000.00 = Rp 14,400.00
Kepala tukang 0.0300 Oh x Rp 53,000.00 = Rp 1,590.00
Mandor 0.0075 Oh x Rp 58,000.00 = Rp 435.00
= Rp 21,675.00
= Rp 212,700.00
F. PEKERJAAN BETON
1 : 1m2 Membuat lantai kerja beton tumbuk, 1pc:3ps:5kr, tebal 5 cm
Bahan :
Semen portland 10.0000 Kg x Rp 1,075.00 = Rp 10,750.00
Pasir beton 0.0260 m3 x Rp 160,000.00 = Rp 4,160.00
Koral beton 0.0440 m3 x Rp 175,000.00 = Rp 7,700.00
= Rp 22,610.00
Tenaga :
Pekerja 1.1500 Oh x Rp 35,000.00 = Rp 40,250.00
Tukang batu 0.0200 Oh x Rp 46,000.00 = Rp 920.00
Kepala tukang 0.0020 Oh x Rp 50,000.00 = Rp 100.00
Mandor 0.0060 Oh x Rp 58,000.00 = Rp 348.00
= Rp 41,618.00
= Rp 64,228.00
41
2 : 1m3 Sloof beton bertulang (besi 100 kg + begisting)
Bahan :
Kayu sengon 0.2700 m3 x Rp 1,782,500.00 = Rp 481,275.00
Paku biasa 2"-5" 2.0000 Kg x Rp 17,000.00 = Rp 34,000.00
Minyak begisting 0.6000 ltr x Rp 6,000.00 = Rp 3,600.00
Besi beton (polos/ulir) 100.0000 Kg x Rp 10,500.00 = Rp 1,050,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
= Rp 2,192,800.00
Tenaga :
Pekerja 4.8500 Oh x Rp 35,000.00 = Rp 169,750.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 1.5600 Oh x Rp 48,000.00 = Rp 74,880.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.3310 Oh x Rp 50,000.00 = Rp 16,550.00
Mandor 0.1700 Oh x Rp 58,000.00 = Rp 9,860.00
= Rp 354,340.00
= Rp 2,547,140.00
42
5 : 1m3 Sloof beton bertulang (besi 195 kg + begisting)
Bahan :
Kayu sengon 0.2700 m3 x Rp 1,782,500.00 = Rp 481,275.00
Paku biasa 2"-5" 2.0000 Kg x Rp 17,000.00 = Rp 34,000.00
Minyak begisting 0.6000 ltr x Rp 6,000.00 = Rp 3,600.00
Besi beton (polos/ulir) 195.0000 Kg x Rp 10,500.00 = Rp 2,047,500.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
= Rp 3,190,300.00
Tenaga :
Pekerja 4.8500 Oh x Rp 35,000.00 = Rp 169,750.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 1.5600 Oh x Rp 48,000.00 = Rp 74,880.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.3310 Oh x Rp 50,000.00 = Rp 16,550.00
Mandor 0.1700 Oh x Rp 58,000.00 = Rp 9,860.00
= Rp 354,340.00
= Rp 3,544,640.00
43
8 : 1m3 Balok beton bertulang (besi 160 kg + begisting)
Bahan :
Kayu sengon 0.3200 m3 x Rp 1,782,500.00 = Rp 570,400.00
Paku biasa 2"-5" 3.2000 Kg x Rp 17,000.00 = Rp 54,400.00
Minyak begisting 1.6000 ltr x Rp 6,000.00 = Rp 9,600.00
Besi beton (polos/ulir) 160.0000 Kg x Rp 10,500.00 = Rp 1,680,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1400 m3 x Rp 4,715,000.00 = Rp 660,100.00
Triplek 2.8000 Lbr x Rp 115,000.00 = Rp 322,000.00
Bambu ori 16.0000 Btg x Rp 15,000.00 = Rp 240,000.00
= Rp 4,160,425.00
Tenaga :
Pekerja 5.9600 Oh x Rp 35,000.00 = Rp 208,600.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.8000 Oh x Rp 48,000.00 = Rp 134,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4550 Oh x Rp 50,000.00 = Rp 22,750.00
Mandor 0.2080 Oh x Rp 58,000.00 = Rp 12,064.00
= Rp 461,114.00
= Rp 4,621,539.00
44
11 : 1m3 Balok beton bertulang (besi 180 kg + begisting)
Bahan :
Kayu sengon 0.3200 m3 x Rp 1,782,500.00 = Rp 570,400.00
Paku biasa 2"-5" 3.2000 Kg x Rp 17,000.00 = Rp 54,400.00
Minyak begisting 1.6000 ltr x Rp 6,000.00 = Rp 9,600.00
Besi beton (polos/ulir) 180.0000 Kg x Rp 10,500.00 = Rp 1,890,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1400 m3 x Rp 4,715,000.00 = Rp 660,100.00
Triplek 2.8000 Lbr x Rp 115,000.00 = Rp 322,000.00
Bambu ori 16.0000 Btg x Rp 15,000.00 = Rp 240,000.00
= Rp 4,370,425.00
Tenaga :
Pekerja 5.9600 Oh x Rp 35,000.00 = Rp 208,600.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.8000 Oh x Rp 48,000.00 = Rp 134,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4550 Oh x Rp 50,000.00 = Rp 22,750.00
Mandor 0.2080 Oh x Rp 58,000.00 = Rp 12,064.00
= Rp 461,114.00
= Rp 4,831,539.00
45
14 : 1m3 Balok beton bertulang (besi 240 kg + begisting)
Bahan :
Kayu sengon 0.3200 m3 x Rp 1,782,500.00 = Rp 570,400.00
Paku biasa 2"-5" 3.2000 Kg x Rp 17,000.00 = Rp 54,400.00
Minyak begisting 1.6000 ltr x Rp 6,000.00 = Rp 9,600.00
Besi beton (polos/ulir) 240.0000 Kg x Rp 10,500.00 = Rp 2,520,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1400 m3 x Rp 4,715,000.00 = Rp 660,100.00
Triplek 2.8000 Lbr x Rp 115,000.00 = Rp 322,000.00
Bambu ori 16.0000 Btg x Rp 15,000.00 = Rp 240,000.00
= Rp 5,000,425.00
Tenaga :
Pekerja 5.9600 Oh x Rp 35,000.00 = Rp 208,600.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.8000 Oh x Rp 48,000.00 = Rp 134,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4550 Oh x Rp 50,000.00 = Rp 22,750.00
Mandor 0.2080 Oh x Rp 58,000.00 = Rp 12,064.00
= Rp 461,114.00
= Rp 5,461,539.00
46
17 : 1m3 Tangga beton bertulang (besi 150 kg + begisting)
Bahan :
Kayu sengon 0.2500 m3 x Rp 1,782,500.00 = Rp 445,625.00
Paku biasa 2"-5" 3.0000 Kg x Rp 17,000.00 = Rp 51,000.00
Minyak begisting 1.2000 ltr x Rp 6,000.00 = Rp 7,200.00
Besi beton (polos/ulir) 150.0000 Kg x Rp 10,500.00 = Rp 1,575,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1050 m3 x Rp 4,715,000.00 = Rp 495,075.00
Triplek 2.5000 Lbr x Rp 115,000.00 = Rp 287,500.00
Bambu ori 14.0000 Btg x Rp 15,000.00 = Rp 210,000.00
= Rp 3,695,325.00
Tenaga :
Pekerja 5.6000 Oh x Rp 35,000.00 = Rp 196,000.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.3000 Oh x Rp 48,000.00 = Rp 110,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4050 Oh x Rp 50,000.00 = Rp 20,250.00
Mandor 0.2020 Oh x Rp 58,000.00 = Rp 11,716.00
= Rp 421,666.00
= Rp 4,116,991.00
47
20 : 1m3 Retaining Wall (besi 150 kg + begisting)
Bahan :
Kayu sengon 0.2500 m3 x Rp 1,782,500.00 = Rp 445,625.00
Paku biasa 2"-5" 3.0000 Kg x Rp 17,000.00 = Rp 51,000.00
Minyak begisting 1.2000 ltr x Rp 6,000.00 = Rp 7,200.00
Besi beton (polos/ulir) 150.0000 Kg x Rp 10,500.00 = Rp 1,575,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1050 m3 x Rp 115,000.00 = Rp 12,075.00
Triplek 2.5000 Lbr x Rp 15,000.00 = Rp 37,500.00
Bambu ori 14.0000 Btg x Rp 0.00 = Rp -
= Rp 2,752,325.00
Tenaga :
Pekerja 5.6000 Oh x Rp 35,000.00 = Rp 196,000.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.3000 Oh x Rp 48,000.00 = Rp 110,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4050 Oh x Rp 50,000.00 = Rp 20,250.00
Mandor 0.2020 Oh x Rp 58,000.00 = Rp 11,716.00
= Rp 421,666.00
= Rp 3,173,991.00
21 : 1m3 Pelat lantai beton bertulang untuk groundtank / IPAL (besi 125 kg + begisting)
Bahan :
Kayu sengon 0.2700 m3 x Rp 1,782,500.00 = Rp 481,275.00
Paku biasa 2"-5" 2.0000 Kg x Rp 17,000.00 = Rp 34,000.00
Minyak begisting 0.6000 ltr x Rp 6,000.00 = Rp 3,600.00
Besi beton (polos/ulir) 125.0000 Kg x Rp 10,500.00 = Rp 1,312,500.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
= Rp 2,455,300.00
Tenaga :
Pekerja 4.8500 Oh x Rp 35,000.00 = Rp 169,750.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 1.5600 Oh x Rp 48,000.00 = Rp 74,880.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.3310 Oh x Rp 50,000.00 = Rp 16,550.00
Mandor 0.1700 Oh x Rp 58,000.00 = Rp 9,860.00
= Rp 354,340.00
= Rp 2,809,640.00
22 : 1m3 Pelat dinding beton bertulang untuk groundtank / IPAL (besi 130 kg + begisting)
Bahan :
Kayu sengon 0.2500 m3 x Rp 1,782,500.00 = Rp 445,625.00
Paku biasa 2"-5" 3.0000 Kg x Rp 17,000.00 = Rp 51,000.00
Minyak begisting 1.2000 ltr x Rp 6,000.00 = Rp 7,200.00
Besi beton (polos/ulir) 130.0000 Kg x Rp 10,500.00 = Rp 1,365,000.00
Kawat beton 3.0000 Kg x Rp 19,000.00 = Rp 57,000.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1050 m3 x Rp 4,715,000.00 = Rp 495,075.00
Triplek 2.5000 Lbr x Rp 115,000.00 = Rp 287,500.00
Bambu ori 14.0000 Btg x Rp 15,000.00 = Rp 210,000.00
= Rp 3,485,325.00
Tenaga :
Pekerja 5.6000 Oh x Rp 35,000.00 = Rp 196,000.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 2.3000 Oh x Rp 48,000.00 = Rp 110,400.00
Tukang besi 1.4000 Oh x Rp 48,000.00 = Rp 67,200.00
Kepala tukang 0.4050 Oh x Rp 50,000.00 = Rp 20,250.00
Mandor 0.2020 Oh x Rp 58,000.00 = Rp 11,716.00
= Rp 421,666.00
= Rp 3,906,991.00
48
23 : 1m3 Kolom beton bertulang (besi 330 kg + begisting)
Bahan :
Kayu sengon 0.4000 m3 x Rp 1,782,500.00 = Rp 713,000.00
Paku biasa 2"-5" 4.0000 Kg x Rp 17,000.00 = Rp 68,000.00
Minyak begisting 2.0000 ltr x Rp 6,000.00 = Rp 12,000.00
Besi beton (polos/ulir) 330.0000 Kg x Rp 10,500.00 = Rp 3,465,000.00
Kawat beton 4.5000 Kg x Rp 19,000.00 = Rp 85,500.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1500 m3 x Rp 4,715,000.00 = Rp 707,250.00
Triplek 3.5000 Lbr x Rp 115,000.00 = Rp 402,500.00
Bambu ori 20.0000 Btg x Rp 15,000.00 = Rp 300,000.00
= Rp 6,320,175.00
Tenaga :
Pekerja 7.3000 Oh x Rp 35,000.00 = Rp 255,500.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 3.3000 Oh x Rp 48,000.00 = Rp 158,400.00
Tukang besi 2.1000 Oh x Rp 48,000.00 = Rp 100,800.00
Kepala tukang 0.5700 Oh x Rp 50,000.00 = Rp 28,500.00
Mandor 0.2500 Oh x Rp 58,000.00 = Rp 14,500.00
= Rp 573,800.00
= Rp 6,893,975.00
49
26 : 1m3 Kolom beton bertulang (besi 235 kg + begisting)
Bahan :
Kayu sengon 0.4000 m3 x Rp 1,782,500.00 = Rp 713,000.00
Paku biasa 2"-5" 4.0000 Kg x Rp 17,000.00 = Rp 68,000.00
Minyak begisting 2.0000 ltr x Rp 6,000.00 = Rp 12,000.00
Besi beton (polos/ulir) 235.0000 Kg x Rp 10,500.00 = Rp 2,467,500.00
Kawat beton 4.5000 Kg x Rp 19,000.00 = Rp 85,500.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1500 m3 x Rp 4,715,000.00 = Rp 707,250.00
Triplek 3.5000 Lbr x Rp 115,000.00 = Rp 402,500.00
Bambu ori 20.0000 Btg x Rp 15,000.00 = Rp 300,000.00
= Rp 5,322,675.00
Tenaga :
Pekerja 7.3000 Oh x Rp 35,000.00 = Rp 255,500.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 3.3000 Oh x Rp 48,000.00 = Rp 158,400.00
Tukang besi 2.1000 Oh x Rp 48,000.00 = Rp 100,800.00
Kepala tukang 0.5700 Oh x Rp 50,000.00 = Rp 28,500.00
Mandor 0.2500 Oh x Rp 58,000.00 = Rp 14,500.00
= Rp 573,800.00
= Rp 5,896,475.00
50
29 : 1m3 Kolom beton bertulang (besi 180 kg + begisting)
Bahan :
Kayu sengon 0.4000 m3 x Rp 1,782,500.00 = Rp 713,000.00
Paku biasa 2"-5" 4.0000 Kg x Rp 17,000.00 = Rp 68,000.00
Minyak begisting 2.0000 ltr x Rp 6,000.00 = Rp 12,000.00
Besi beton (polos/ulir) 180.0000 Kg x Rp 10,500.00 = Rp 1,890,000.00
Kawat beton 4.5000 Kg x Rp 19,000.00 = Rp 85,500.00
Semen portland 323.0000 Kg x Rp 1,075.00 = Rp 347,225.00
Pasir beton 0.5200 m3 x Rp 160,000.00 = Rp 83,200.00
Koral beton 0.7800 m3 x Rp 175,000.00 = Rp 136,500.00
Kayu meranti 0.1500 m3 x Rp 4,715,000.00 = Rp 707,250.00
Triplek 3.5000 Lbr x Rp 115,000.00 = Rp 402,500.00
Bambu ori 20.0000 Btg x Rp 15,000.00 = Rp 300,000.00
= Rp 4,745,175.00
Tenaga :
Pekerja 7.3000 Oh x Rp 35,000.00 = Rp 255,500.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Tukang kayu 3.3000 Oh x Rp 48,000.00 = Rp 158,400.00
Tukang besi 2.1000 Oh x Rp 48,000.00 = Rp 100,800.00
Kepala tukang 0.5700 Oh x Rp 50,000.00 = Rp 28,500.00
Mandor 0.2500 Oh x Rp 58,000.00 = Rp 14,500.00
= Rp 573,800.00
= Rp 5,318,975.00
51
32 : 1m' Kolom penguat beton bertulang (11 x 11) cm
Bahan :
Kayu sengon 0.0020 m3 x Rp 1,782,500.00 = Rp 3,565.00
Paku biasa 2"-5" 0.0100 Kg x Rp 17,000.00 = Rp 170.00
Besi beton (polos/ulir) 3.0000 Kg x Rp 10,500.00 = Rp 31,500.00
Kawat beton 0.4500 Kg x Rp 19,000.00 = Rp 8,550.00
Semen portland 4.0000 Kg x Rp 1,075.00 = Rp 4,300.00
Pasir beton 0.0060 m3 x Rp 160,000.00 = Rp 960.00
Koral beton 0.0090 m3 x Rp 175,000.00 = Rp 1,575.00
= Rp 50,620.00
Tenaga :
Pekerja 0.0600 Oh x Rp 35,000.00 = Rp 2,100.00
Tukang batu 0.0200 Oh x Rp 46,000.00 = Rp 920.00
Tukang kayu 0.0200 Oh x Rp 48,000.00 = Rp 960.00
Tukang besi 0.0200 Oh x Rp 48,000.00 = Rp 960.00
Kepala tukang 0.0060 Oh x Rp 50,000.00 = Rp 300.00
Mandor 0.0030 Oh x Rp 58,000.00 = Rp 174.00
= Rp 5,414.00
= Rp 56,034.00
33 : 1m' Ring balok beton bertulang (10 x 15) cm
Bahan :
Kayu sengon 0.0030 m3 x Rp 1,782,500.00 = Rp 5,347.50
Paku biasa 2"-5" 0.0200 Kg x Rp 17,000.00 = Rp 340.00
Besi beton (polos/ulir) 3.6000 Kg x Rp 10,500.00 = Rp 37,800.00
Kawat beton 0.0500 Kg x Rp 19,000.00 = Rp 950.00
Semen portland 5.5000 Kg x Rp 1,075.00 = Rp 5,912.50
Pasir beton 0.0090 m3 x Rp 160,000.00 = Rp 1,440.00
Koral beton 0.0150 m3 x Rp 175,000.00 = Rp 2,625.00
= Rp 54,415.00
Tenaga :
Pekerja 0.1000 Oh x Rp 35,000.00 = Rp 3,500.00
Tukang batu 0.0330 Oh x Rp 46,000.00 = Rp 1,518.00
Tukang kayu 0.0330 Oh x Rp 48,000.00 = Rp 1,584.00
Tukang besi 0.0330 Oh x Rp 48,000.00 = Rp 1,584.00
Kepala tukang 0.0100 Oh x Rp 50,000.00 = Rp 500.00
Mandor 0.0050 Oh x Rp 58,000.00 = Rp 290.00
= Rp 8,976.00
= Rp 63,391.00
52
= Rp 9,382.00
= Rp 104,262.00
53
H. PEKERJAAN LANGIT-LANGIT
1 : 1m2 Plafon kalsiboard
Bahan :
Plafond kalsiboard 0.3640 Lbr x Rp 75,000.00 = Rp 27,300.00
Paku sekrup 0.1100 Kg x Rp 22,000.00 = Rp 2,420.00
= Rp 29,720.00
Tenaga :
Pekerja 0.1000 Oh x Rp 35,000.00 = Rp 3,500.00
Tukang kayu 0.0500 Oh x Rp 48,000.00 = Rp 2,400.00
Kepala tukang 0.0050 Oh x Rp 53,000.00 = Rp 265.00
Mandor 0.0050 Oh x Rp 58,000.00 = Rp 290.00
= Rp 6,455.00
= Rp 36,175.00
2 : 1m2 Plafon akustik
Bahan :
Plafond akustik 0.7280 Lbr x Rp 90,000.00 = Rp 65,520.00
Paku sekrup 0.1100 Kg x Rp 22,000.00 = Rp 2,420.00
= Rp 67,940.00
Tenaga :
Pekerja 0.1000 Oh x Rp 35,000.00 = Rp 3,500.00
Tukang kayu 0.0500 Oh x Rp 48,000.00 = Rp 2,400.00
Kepala tukang 0.0050 Oh x Rp 53,000.00 = Rp 265.00
Mandor 0.0050 Oh x Rp 58,000.00 = Rp 290.00
= Rp 6,455.00
= Rp 74,395.00
I. PEKERJAAN SANITASI
1 Memasang 1 buah kloset duduk sekelas TOTO
Bahan :
Kloset duduk 1.0000 bh x Rp 2,100,000.00 = Rp 2,100,000.00
Perlengkapan 6.0000% x Rp 2,100,000.00 = Rp 126,000.00
= Rp 2,226,000.00
Tenaga :
Pekerja 3.3000 Oh x Rp 35,000.00 = Rp 115,500.00
Tukang batu 1.1000 Oh x Rp 46,000.00 = Rp 50,600.00
Kepala tukang 0.0010 Oh x Rp 50,000.00 = Rp 50.00
Mandor 0.1600 Oh x Rp 58,000.00 = Rp 9,280.00
= Rp 175,430.00
= Rp 2,401,430.00
54
3 Memasang 1 bh wastafel TOTO
Bahan :
washbak 1.0000 bh x Rp 950,000.00 = Rp 950,000.00
Perlengkapan 12% x Rp 950,000.00 = Rp 114,000.00
Semen portland 6.0000 Kg x Rp 1,000.00 = Rp 6,000.00
Pasir pasang 0.0100 m3 x Rp 230,000.00 = Rp 2,300.00
= Rp 1,072,300.00
Tenaga :
Pekerja 1.2000 Oh x Rp 35,000.00 = Rp 42,000.00
Tukang batu 1.4500 Oh x Rp 46,000.00 = Rp 66,700.00
Kepala tukang 0.1500 Oh x Rp 50,000.00 = Rp 7,500.00
Mandor 0.1000 Oh x Rp 58,000.00 = Rp 5,800.00
= Rp 122,000.00
= Rp 1,194,300.00
55
3 : 1m2 Pasang folding door
Bahan :
Folding door 1.0000 m2 x Rp 488,750.00 = Rp 488,750.00
= Rp 488,750.00
Tenaga :
Pekerja 1.0500 Oh x Rp 35,000.00 = Rp 36,750.00
Tukang besi 1.0500 Oh x Rp 48,000.00 = Rp 50,400.00
Kepala tukang 0.1050 Oh x Rp 53,000.00 = Rp 5,565.00
Mandor 0.0052 Oh x Rp 58,000.00 = Rp 301.60
= Rp 93,016.60
= Rp 581,766.60
4 : 1 m' Pasang kusen allumunium coklat 4"
Bahan :
Kusen allumunium 1.0500 m' x Rp 90,000.00 = Rp 94,500.00
Asesoris 0.1000 x Rp 94,500.00 = Rp 9,450.00
= Rp 103,950.00
Tenaga :
Pekerja 0.1500 Oh x Rp 35,000.00 = Rp 5,250.00
Tukang besi 0.2500 Oh x Rp 48,000.00 = Rp 12,000.00
Kepala tukang 0.0250 Oh x Rp 53,000.00 = Rp 1,325.00
Mandor 0.0750 Oh x Rp 58,000.00 = Rp 4,350.00
= Rp 22,925.00
= Rp 126,875.00
56
K. PEKERJAAN KUNCI DAN KACA
1 : 1 bh Pasang kunci tanam
Bahan :
Kunci tanam 2 x putar 1.0000 bh x Rp 175,000.00 = Rp 175,000.00
= Rp 175,000.00
Tenaga :
Pekerja 0.0100 Oh x Rp 35,000.00 = Rp 350.00
Tukang kayu 0.5000 Oh x Rp 48,000.00 = Rp 24,000.00
Kepala tukang 0.0100 Oh x Rp 53,000.00 = Rp 530.00
Mandor 0.0050 Oh x Rp 58,000.00 = Rp 290.00
= Rp 25,170.00
= Rp 200,170.00
57
6 : 1 bh Pasang grendel
Bahan :
Grendel 1.0000 bh x Rp 11,500.00 = Rp 11,500.00
= Rp 11,500.00
Tenaga :
Pekerja 0.0100 Oh x Rp 35,000.00 = Rp 350.00
Tukang kayu 0.1000 Oh x Rp 48,000.00 = Rp 4,800.00
Kepala tukang 0.0100 Oh x Rp 53,000.00 = Rp 530.00
Mandor 0.0005 Oh x Rp 58,000.00 = Rp 29.00
= Rp 5,709.00
= Rp 17,209.00
11 : 1 m2 Pasang kaca es 5 mm
Bahan :
kaca es 1.1000 m2 x Rp 88,000.00 = Rp 96,800.00
= Rp 96,800.00
Tenaga :
Pekerja 0.0150 Oh x Rp 35,000.00 = Rp 525.00
Tukang kayu 0.1500 Oh x Rp 48,000.00 = Rp 7,200.00
Kepala tukang 0.0150 Oh x Rp 53,000.00 = Rp 795.00
Mandor 0.00075 Oh x Rp 58,000.00 = Rp 43.50
= Rp 8,563.50
= Rp 105,363.50
58
12 : 1 m2 Pasang kaca partisi kaca bening 8 mm rangka allumunium
Bahan :
Kaca bening 1.0000 m2 x Rp 168,918.40 = Rp 168,918.40
Kusen Allumunium 1.2500 m' x Rp 126,875.00 = Rp 158,593.75
= Rp 327,512.15
59
Kepala tukang 0.0350 Oh x Rp 50,000.00 = Rp 1,750.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 41,290.00
= Rp 294,273.50
60
6 : 1 m2 Pasang lantai keramik jeruk 30 x 30 cm
Bahan :
Ubin keramik jeruk 30 x 30 cm 1.0000 m2 x Rp 200,000.00 = Rp 200,000.00
Semen portland 11.3800 Kg x Rp 1,075.00 = Rp 12,233.50
Pasir pasang 0.0420 m3 x Rp 125,000.00 = Rp 5,250.00
Semen warna 1.5000 Kg x Rp 7,000.00 = Rp 10,500.00
= Rp 227,983.50
Tenaga :
Pekerja 0.6200 Oh x Rp 35,000.00 = Rp 21,700.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Kepala tukang 0.0350 Oh x Rp 50,000.00 = Rp 1,750.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 41,290.00
= Rp 269,273.50
7 : 1 m2 Pasang lantai keramik motif 20 x 20 cm
Bahan :
Ubin keramik motif 20/20 1.0000 m2 x Rp 230,000.00 = Rp 230,000.00
Semen portland 11.3800 Kg x Rp 1,075.00 = Rp 12,233.50
Pasir pasang 0.0420 m3 x Rp 125,000.00 = Rp 5,250.00
Semen warna 1.5000 Kg x Rp 7,000.00 = Rp 10,500.00
= Rp 257,983.50
Tenaga :
Pekerja 0.6200 Oh x Rp 35,000.00 = Rp 21,700.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Kepala tukang 0.0350 Oh x Rp 50,000.00 = Rp 1,750.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 41,290.00
= Rp 299,273.50
8 : 1 m2 Pasang lantai keramik jeruk 20 x 20 cm
Bahan :
Ubin keramik jeruk 20/20 1.0000 m2 x Rp 195,000.00 = Rp 195,000.00
Semen portland 11.3800 Kg x Rp 1,075.00 = Rp 12,233.50
Pasir pasang 0.0420 m3 x Rp 125,000.00 = Rp 5,250.00
Semen warna 1.5000 Kg x Rp 7,000.00 = Rp 10,500.00
= Rp 222,983.50
Tenaga :
Pekerja 0.6200 Oh x Rp 35,000.00 = Rp 21,700.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Kepala tukang 0.0350 Oh x Rp 50,000.00 = Rp 1,750.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 41,290.00
= Rp 264,273.50
9 : 1 m2 Pasang keramik dinding motif 20 x 25
Bahan :
Keramik dinding 1.0000 m2 x Rp 235,000.00 = Rp 235,000.00
Semen portland 9.3000 Kg x Rp 1,075.00 = Rp 9,997.50
Pasir pasang 0.0180 m3 x Rp 125,000.00 = Rp 2,250.00
Semen warna 1.5000 Kg x Rp 7,000.00 = Rp 10,500.00
= Rp 257,747.50
Tenaga :
Pekerja 0.6000 Oh x Rp 35,000.00 = Rp 21,000.00
Tukang batu 0.1000 Oh x Rp 46,000.00 = Rp 4,600.00
Kepala tukang 0.0450 Oh x Rp 50,000.00 = Rp 2,250.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 29,590.00
= Rp 287,337.50
10 : 1 m2 Pasang granit dark green
Bahan :
Granit dark green 1.0000 m2 x Rp 819,000.00 = Rp 819,000.00
Semen portland 14.1500 Kg x Rp 1,075.00 = Rp 15,211.25
Pasir pasang 0.0390 m3 x Rp 125,000.00 = Rp 4,875.00
Semen warna 2.0000 Kg x Rp 7,000.00 = Rp 14,000.00
= Rp 853,086.25
Tenaga :
Pekerja 0.6200 Oh x Rp 35,000.00 = Rp 21,700.00
Tukang batu 0.3500 Oh x Rp 46,000.00 = Rp 16,100.00
Kepala tukang 0.0350 Oh x Rp 50,000.00 = Rp 1,750.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 41,290.00
= Rp 894,376.25
61
11 : 1 m' Pasang step nozing tangga
Bahan :
Step nozing tangga 0.0300 m2 x Rp 540,500.00 = Rp 16,215.00
Semen portland 9.3000 Kg x Rp 1,075.00 = Rp 9,997.50
Pasir pasang 0.0180 m3 x Rp 125,000.00 = Rp 2,250.00
Semen warna 1.5000 Kg x Rp 7,000.00 = Rp 10,500.00
= Rp 38,962.50
Tenaga :
Pekerja 0.6000 Oh x Rp 35,000.00 = Rp 21,000.00
Tukang batu 0.1000 Oh x Rp 46,000.00 = Rp 4,600.00
Kepala tukang 0.0450 Oh x Rp 50,000.00 = Rp 2,250.00
Mandor 0.0300 Oh x Rp 58,000.00 = Rp 1,740.00
= Rp 29,590.00
= Rp 68,552.50
12 : 1 m2 Pasang lantai parquet jati
Bahan :
Parquit jati 1.0500 m2 x Rp 166,770.00 = Rp 175,108.50
Lem vinyl 0.6000 Kg x Rp 35,650.00 = Rp 21,390.00
= Rp 196,498.50
Tenaga :
Pekerja 0.6500 Oh x Rp 35,000.00 = Rp 22,750.00
Tukang kayu 0.3500 Oh x Rp 48,000.00 = Rp 16,800.00
Kepala tukang 0.0350 Oh x Rp 53,000.00 = Rp 1,855.00
Mandor 0.0325 Oh x Rp 58,000.00 = Rp 1,885.00
= Rp 43,290.00
= Rp 239,788.50
M. PEKERJAAN PENGECATAN
1 : 1 m2 Pengecatan kayu bidang kayu baru
Bahan :
Cat meni 0.2000 Kg x Rp 20,000.00 = Rp 4,000.00
Plamir 0.1500 Kg x Rp 25,000.00 = Rp 3,750.00
Cat dasar 0.1700 Kg x Rp 80,000.00 = Rp 13,600.00
Cat penutup 0.2600 Kg x Rp 80,000.00 = Rp 20,800.00
= Rp 42,150.00
Tenaga :
Pekerja 0.0700 Oh x Rp 35,000.00 = Rp 2,450.00
Tukang cat 0.0090 Oh x Rp 46,000.00 = Rp 414.00
Kepala tukang 0.0060 Oh x Rp 50,000.00 = Rp 300.00
Mandor 0.0025 Oh x Rp 58,000.00 = Rp 145.00
= Rp 3,309.00
= Rp 45,459.00
2 : 1 m2 Pengecatan tembok baru
Bahan :
Plamir 0.1000 Kg x Rp 25,000.00 = Rp 2,500.00
Cat dasar 0.1000 Kg x Rp 70,000.00 = Rp 7,000.00
Cat penutup 2x 0.2600 Kg x Rp 70,000.00 = Rp 18,200.00
= Rp 27,700.00
Tenaga :
Pekerja 0.0200 Oh x Rp 35,000.00 = Rp 700.00
Tukang cat 0.0630 Oh x Rp 46,000.00 = Rp 2,898.00
Kepala tukang 0.0063 Oh x Rp 50,000.00 = Rp 315.00
Mandor 0.0025 Oh x Rp 58,000.00 = Rp 145.00
= Rp 4,058.00
= Rp 31,758.00
62
3 : 1 m2 Politur
Bahan :
Politur 0.1500 ltr x Rp 55,000.00 = Rp 8,250.00
Politur jadi 0.3720 ltr x Rp 40,000.00 = Rp 14,880.00
Amplas 2.0000 lbr x Rp 4,000.00 = Rp 8,000.00
= Rp 31,130.00
Tenaga :
Tukang cat 0.0600 Oh x Rp 46,000.00 = Rp 2,760.00
Kepala tukang 0.0160 Oh x Rp 50,000.00 = Rp 800.00
Mandor 0.0025 Oh x Rp 58,000.00 = Rp 145.00
= Rp 3,705.00
= Rp 34,835.00
63
Politur teakwood 1.0300 m2 x Rp 34,835.00 = Rp 35,880.05
Door closer 1.0000 bh x Rp 250,000.00 = Rp 250,000.00
Handel 2.0000 bh x Rp 30,000.00 = Rp 60,000.00
Engsel 3.0000 bh x Rp 17,188.50 = Rp 51,565.50
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
= Rp 2,214,640.23
64
7 : 1 unit Pintu PVC (PC7, PC8, PC9, PC10)
Kusen alumunium 5.1200 m' x Rp 126,875.00 = Rp 649,600.00
Pintu PVC 1.0000 unit x Rp 350,000.00 = Rp 350,000.00
= Rp 999,600.00
b. Hotel
1 : 1 unit Pintu allumunium (P1)
Kusen alumunium 5.7000 m' x Rp 126,875.00 = Rp 723,187.50
Pintu alumunium 2.8000 m2 x Rp 468,016.60 = Rp 1,310,446.48
65
Kaca motif 5 mm 1.8000 m2 x Rp 124,063.50 = Rp 223,314.30
Door closer 2.0000 bh x Rp 250,000.00 = Rp 500,000.00
Handel 4.0000 bh x Rp 30,000.00 = Rp 120,000.00
Engsel 6.0000 bh x Rp 17,188.50 = Rp 103,131.00
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
= Rp 3,180,249.28
66
2 : 1 unit Pintu allumunium (P2)
Kusen alumunium 5.7000 m' x Rp 126,875.00 = Rp 723,187.50
Pintu alumunium 2.8000 m2 x Rp 468,016.60 = Rp 1,310,446.48
Kaca bening 5 mm 1.8000 m2 x Rp 91,063.50 = Rp 163,914.30
Door closer 2.0000 bh x Rp 250,000.00 = Rp 500,000.00
Handel 4.0000 bh x Rp 30,000.00 = Rp 120,000.00
Engsel 6.0000 bh x Rp 17,188.50 = Rp 103,131.00
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
= Rp 3,120,849.28
67
10 : 1 unit Pintu allumunium (PJ2, PJ3)
Kusen alumunium 17.7000 m' x Rp 126,875.00 = Rp 2,245,687.50
Pintu alumunium 1.6000 m2 x Rp 468,016.60 = Rp 748,826.56
Jendela alumunum 1.4000 m2 x Rp 443,016.60 = Rp 620,223.24
Kaca bening 5 mm 2.7700 m2 x Rp 91,063.50 = Rp 252,245.90
Door closer 1.0000 bh x Rp 250,000.00 = Rp 250,000.00
Handel 2.0000 bh x Rp 30,000.00 = Rp 60,000.00
Engsel pintu 3.0000 bh x Rp 17,188.50 = Rp 51,565.50
Engsel jendela 4.0000 bh x Rp 14,334.00 = Rp 57,336.00
kait angin 4.0000 bh x Rp 25,813.50 = Rp 103,254.00
Grendel 2.0000 bh x Rp 17,209.00 = Rp 34,418.00
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
= Rp 4,623,726.70
68
4 : 1 unit Pintu allumunium (P8)
Kusen alumunium 5.1200 m' x Rp 126,875.00 = Rp 649,600.00
Pintu alumunium 1.8900 m2 x Rp 468,016.60 = Rp 884,551.37
Kaca es 5 mm 0.4000 m2 x Rp 105,363.50 = Rp 42,145.40
Teakwood 4 mm 0.1389 lb x Rp 160,000.00 = Rp 22,222.22
Politur teakwood 0.8000 m2 x Rp 34,835.00 = Rp 27,868.00
Door closer 2.0000 bh x Rp 250,000.00 = Rp 500,000.00
Handel 4.0000 bh x Rp 30,000.00 = Rp 120,000.00
Engsel 6.0000 bh x Rp 17,188.50 = Rp 103,131.00
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
= Rp 2,549,687.99
7 : 1 unit Bouven
Kusen alumunium 2.0000 m' x Rp 126,875.00 = Rp 253,750.00
Jendela alumunium 0.2400 m2 x Rp 443,016.60 = Rp 106,323.98
Kaca es 5 mm 0.1500 m2 x Rp 105,363.50 = Rp 15,804.53
Engsel 2.0000 bh x Rp 14,334.00 = Rp 28,668.00
Kait angin 1.0000 bh x Rp 25,813.50 = Rp 25,813.50
grendel 1.0000 bh x Rp 17,209.00 = Rp 17,209.00
= Rp 447,569.01
d. Support Building
1 : 1 unit Pintu panil kayu kamfer
Kusen kayu kamper 0.0549 m3 x Rp 126,875.00 = Rp 6,960.87
Pintu panil kayu kamper 1.6000 m2 x Rp 468,016.60 = Rp 748,826.56
Engsel pintu 3.0000 bh x Rp 17,188.50 = Rp 51,565.50
Kunci 1.0000 bh x Rp 200,170.00 = Rp 200,170.00
Grendel 1.0000 bh x Rp 17,209.00 = Rp 17,209.00
Kait angin 2.0000 bh x Rp 25,813.50 = Rp 51,627.00
= Rp 1,076,358.93
69