RENCANA ANGGARAN BIAYA

REKAPITULASI TOTAL
PEMBANGUNAN GEDUNG ASRAMA MAHASISWA
UNIVERSITAS PADJADJARAN ASAL KABUPATEN BANDUNG

Jumlah Total
No. Uraian Pekerjaan Harga
( Rp )
A. PEKERJAAN PERSIAPAN 61.378.100,00
I. PEKERJAAN PERSIAPAN HARGA LUMSUM 24.050.000,00
II. PEKERJAAN PERSIAPAN HARGA SATUAN 37.328.100,00
B. PEKERJAAN STRUKTUR 1.591.440.057,83
I. PEKERJAAN GALIAN DAN URUGAN 101.886.675,36
II. PEKERJAAN PONDASI, SLOOF, DAN KOLOM 1.231.950.382,47
III. PEKERJAAN ATAP 257.603.000,00

C. PEKERJAAN ARSITEKTUR 2.242.676.247,50


I. PEKERJAAN DINDING DAN PLESTERAN 989.071.867,50
II. PEK.KUSEN PINTU/JENDELA DAN ASESORIES 326.800.695,00
III. PEKERJAAN PLAFOND 173.865.500,00
IV. PEKERJAAN LANTAI 384.775.210,00
V. PEKERJAAN PENGECATAN DAN LABURAN 274.725.325,00
VI. PEKERJAAN SANITARY 41.723.200,00
VII. PEKERJAAN LAIN - LAIN 51.714.450,00

D. PEKERJAAN MEKANIKAL, ELEKTRIKAL, PLUMBING 395.333.908

I. PEKERJAAN MEKANIKAL DAN PLUMBING 220.732.908,00

II. PEKERJAAN ELEKTRIKAL 174.601.000,00

JUMLAH TOTAL 4.290.828.313,33

PPN (10%) 429.082.831,33

JUMLAH TOTAL 4.719.911.144,66

DIBULATKAN 4.719.911.000,00
Terbilang :
Empat milyar ltujuh ratus sembilan belas juta sembilan ratus sebelas ribu rupiah = = = =