REKAPITULASI

RENCANA ANGGARAN BIAYA

NAMA PAKET : PEMBANGUNAN GEDUNG SOSIAL KEAGAMAAN


INSTANSI : KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
SATUAN KERJA : POLITEKNIK NEGERI UJUNG PANDANG
PROV. /KAB. /KOTA : SULAWESI SELATAN / KOTA MAKASSAR
TAHUN ANGGARAN : APBN 2021

JUMLAH HARGA
NO. URAIAN PEKERJAAN
( Rp. )

I. A. PEKERJAAN PERSIAPAN
1. PRELIMINARIES 75,500,000.00

JUMLAH HARGA PERSIAPAN 75,500,000.00


B. PEKERJAAN STRUKTUR
1. ELEVASI -13,50 M S/D +0,80 M 1,385,619,051.42
2. ELEVASI +0,80 M S/D +4,92 M 2,255,504,827.59
3. ELEVASI +4,92 M S/D +TOP FLOOR 1,864,217,225.73

JUMLAH HARGA STRUKTUR 5,505,341,104.75


C. PEKERJAAN ARSITEKTUR
1. PEKERJAAN LANTAI 508,274,844.44
2. PEKERJAAN SPARING PIPA 41,658,765.00
3. PEKERJAAN DINDING 3,547,984.00

JUMLAH HARGA ARSITEKTUR 553,481,593.44


II. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)
1. KESELAMATAN DAN KESEHATAN KERJA 159,650,000.00

JUMLAH HARGA K3 159,650,000.00

JUMLAH TOTAL 6,293,972,698.19


DIBULATKAN 6,294,000,000.00
PPN 10% 629,400,000.00
TOTAL HARGA + PPN 6,923,400,000.00

TERBILANG Enam milyar Sembilan ratus dua puluh Tiga juta Empat Ratus Ribu Rupiah

Penawar,
CV. ADITAMA BANGUN MANDIRI

ANDALAS AUDI
Direktur
RENCANA ANGGARAN BIAYA
NAMA PAKET : PEMBANGUNAN GEDUNG SOSIAL KEAGAMAAN
INSTANSI : KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
SATUAN KERJA : POLITEKNIK NEGERI UJUNG PANDANG
PROV. /KAB. /KOTA : SULAWESI SELATAN / KOTA MAKASSAR
TAHUN ANGGARAN : APBN 2021
JENIS PEKERJAAN : PEKERJAAN PERSIAPAN

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

A. PEKERJAAN PERSIAPAN 75,500,000.00

1 PRELIMINARIES
1 Mobilisasi dan Demobilisasi alat Pancang Ls 1.00 38,000,000.00 38,000,000.00
2 Mobilisasi dan Demobilisasi tenaga kerja Ls 1.00 10,000,000.00 10,000,000.00
3 Rakit dan Bongkar Alat Pancang Ls 1.00 7,500,000.00 7,500,000.00
4 Direksi Keet, Gudang Ls 1.00 20,000,000.00 20,000,000.00
RENCANA ANGGARAN BIAYA
NAMA PAKET : PEMBANGUNAN GEDUNG SOSIAL KEAGAMAAN
INSTANSI : KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
SATUAN KERJA : POLITEKNIK NEGERI UJUNG PANDANG
PROV. /KAB. /KOTA : SULAWESI SELATAN / KOTA MAKASSAR
TAHUN ANGGARAN : APBN 2021
JENIS PEKERJAAN : PEKERJAAN STRUKTUR

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

B. PEKERJAAN STRUKTUR 5,505,341,104.75

1. ELEVASI -13,50 M S/D +0,80 M 1,385,619,051.42

A. Pondasi Tiang Pancang Mini Pile 25 cm x 25 cm; Panjang 6 M 235,704,000.00


a. Pekerjaan Tiang Pancang Segi (Mini Pile) 25 cm x 25 cm, P = 6 m M1 560.00 388,400.00 217,504,000.00
Pemancangan Hydrolic Type Presstressed 25 x 25,
K.500 Segmen Bottom, Midle & Upper
b. Pekerjaan Penyambungan Titik 56.00 200,000.00 11,200,000.00
c. Pembobokan Tiang Pancang dari Kepala ke Poer Plat Titik 56.00 125,000.00 7,000,000.00

B. Pondasi Siklop (Dia. 80 cm) 77,461,529.91


3
a. Galian Tanah M 13.35 78,500.00 1,047,975.00
b. Cor Beton (Lantai Kerja) K-100 M3 1.71 1,007,258.73 1,722,412.43
c. Isian Siklop M3 15.37 1,345,747.42 20,684,137.86
d. Gorong-Gorong Dia. 80 cm, h = 50 cm Bh 68.00 525,000.00 35,700,000.00
e. Besi Beton Ulir Kg 735.36 17,662.50 12,988,296.00
f. Besi Beton Polos Kg 301.13 17,662.50 5,318,708.63

C. Poer P01 (130 cm x 130 cm x 40 cm) 123,167,042.00


a. Galian Tanah M3 114.75 78,500.00 9,007,875.00
b. Pasir Urug, t = 10 cm M3 4.04 552,000.00 2,230,080.00
3
c. Cor Beton (Lantai Kerja) K-100, t = 5 cm M 2.02 1,007,258.73 2,034,662.63
d. Bekisting M2 70.72 208,360.50 14,735,254.56
e. Besi Beton Ulir Kg 3,518.62 17,662.50 62,147,625.75
f. Cor Beton K-300 M3 22.98 1,345,747.42 30,925,275.73
g. Urugan Tanah Kembali M3 79.73 26,166.67 2,086,268.33

D. Poer P02 (150 cm x 150 cm x 50 cm) 150,081,465.10


a. Galian Tanah M3 133.52 78,500.00 10,481,320.00
b. Pasir Urug, t = 10 cm M3 5.95 552,000.00 3,284,400.00
c. Cor Beton (Lantai Kerja) K-100, t = 5 cm M3 2.98 1,007,258.73 3,001,631.02
d. Bekisting M2 84.00 208,360.50 17,502,282.00
e. Besi Beton Ulir Kg 4,025.60 17,662.50 71,102,160.00
f. Cor Beton K-300 M3 31.50 1,345,747.42 42,391,043.75
g. Urugan Tanah Kembali M3 88.61 26,166.67 2,318,628.33

E. Pedestal Kolom 162,436,223.41

1. Pedestal Kolom K1, ukuran (40 cm x 40 cm) 78,958,204.41


a. Bekisting M2 86.40 255,150.50 22,045,003.20
b. Besi Beton Ulir Kg 2,203.31 17,662.50 38,915,962.88
c. Besi Beton Polos Kg 360.65 17,662.50 6,369,980.63
d. Cor Beton K-300 M3 8.64 1,345,747.42 11,627,257.71

2. Pedestal Kolom K2, ukuran (30 cm x 40 cm) 83,478,019.00


a. Bekisting M2 80.64 255,150.50 20,575,336.32
b. Besi Beton Ulir Kg 2,154.35 17,662.50 38,051,206.88
c. Besi Beton Polos Kg 880.53 17,662.50 15,552,361.13
d. Cor Beton K-300 M3 6.91 1,345,747.42 9,299,114.68
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

F. Sloef 312,192,700.00

1. Sloef Type S1, ukuran (30 cm x 50 cm) 145,694,455.73


2
a. Bekisting M 187.12 208,360.50 38,988,416.76
b. Besi Beton Ulir Kg 2,341.11 17,662.50 41,349,855.38
c. Besi Beton Polos Kg 1,561.56 17,662.50 27,581,053.50
d. Cor Beton K-300 M3 28.07 1,345,747.42 37,775,130.10

2. Sloef Type S2, ukuran (25 cm x 40 cm) 156,122,864.13


2
a. Bekisting M 270.13 208,360.50 56,284,421.87
b. Besi Beton Ulir Kg - 17,662.50 -
c. Besi Beton Polos Kg 3,079.55 17,662.50 54,392,551.88
d. Cor Beton K-300 M3 33.77 1,345,747.42 45,445,890.39

3. Sloef Type S3, ukuran (15 cm x 20 cm) 10,375,380.13


2
a. Bekisting M 17.83 208,360.50 3,715,067.72
b. Besi Beton Ulir Kg - 17,662.50 -
c. Besi Beton Polos Kg 274.99 17,662.50 4,857,010.88
3
d. Cor Beton K-300 M 1.34 1,345,747.42 1,803,301.54

G. Pekerjaan Pondasi Batu Gunung dan Timbunan Tanah 324,576,091.00


a. Galian Tanah M3 231.53 78,500.00 18,175,105.00
b. Pas. Batu Kosong M3 81.77 409,425.00 33,478,682.25
c. Pas. Batu Gunung Camp. 1 SP : 4 PP M3 238.87 712,425.00 170,176,959.75
3
d. Timbunan Tanah M 852.80 120,480.00 102,745,344.00

2. ELEVASI +0,80 M S/D +4,92 M 2,255,504,827.59

A. Kolom 280,783,917.47

1. Kolom K1, ukuran (40 cm x 40 cm) 148,458,497.74


a. Bekisting M2 197.76 255,150.50 50,458,562.88
b. Besi Beton Ulir Kg 3,260.90 17,662.50 57,595,646.25
c. Besi Beton Polos Kg 780.49 17,662.50 13,785,404.63
3
d. Cor Beton K-300 M 19.78 1,345,747.42 26,618,883.98

2. Kolom K2, ukuran (30 cm x 40 cm) 132,325,419.73


a. Bekisting M2 184.58 255,150.50 47,095,679.29
b. Besi Beton Ulir Kg 2,898.58 17,662.50 51,196,169.25
c. Besi Beton Polos Kg 721.52 17,662.50 12,743,847.00
d. Cor Beton K-300 M3 15.82 1,345,747.42 21,289,724.19

3. Kolom Praktis, ukuran (11 cm x 11 cm) -


a. Panjang Kolom Praktis M1 - - -

B. Balok 898,481,619.40

1. Balok B1, ukuran (35 cm x 60 cm) 259,555,706.40


a. Bekisting M2 295.00 359,561.20 106,070,554.00
b. Besi Beton Ulir Kg 4,073.94 17,662.50 71,955,965.25
c. Besi Beton Polos Kg 1,570.54 17,662.50 27,739,662.75
d. Cor Beton K-300 M3 39.97 1,345,747.42 53,789,524.40

2. Balok B2, ukuran (30 cm x 50 cm) 380,692,167.10


a. Bekisting M2 459.76 359,561.20 165,311,857.31
b. Besi Beton Ulir Kg 5,854.64 17,662.50 103,407,579.00
c. Besi Beton Polos Kg 2,297.57 17,662.50 40,580,830.13
d. Cor Beton K-300 M3 53.05 1,345,747.42 71,391,900.66
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

3. Balok BA.1, ukuran (25 cm x 40 cm) 205,011,254.39


a. Bekisting M2 249.73 359,561.20 89,793,218.48
b. Besi Beton Ulir Kg 2,980.44 17,662.50 52,642,021.50
c. Besi Beton Polos Kg 1,731.02 17,662.50 30,574,140.75
3
d. Cor Beton K-300 M 23.78 1,345,747.42 32,001,873.66

4. Balok BA.2, ukuran (20 cm x 30 cm) 47,484,037.48


a. Bekisting M2 64.05 359,561.20 23,029,894.86
b. Besi Beton Ulir Kg 537.71 17,662.50 9,497,302.88
c. Besi Beton Polos Kg 481.09 17,662.50 8,497,252.13
3
d. Cor Beton K-300 M 4.80 1,345,747.42 6,459,587.62

5. Balok Bordes Tangga, ukuran (20 cm x 30 cm) 5,738,454.03


2
a. Bekisting M 7.52 359,561.20 2,703,900.22
b. Besi Beton Ulir Kg 70.08 17,662.50 1,237,788.00
c. Besi Beton Polos Kg 59.06 17,662.50 1,043,147.25
d. Cor Beton K-300 M3 0.56 1,345,747.42 753,618.56

6. Balok RB1, ukuran (10 cm x 15 cm) -


1
a. Panjang Balok Praktis M - - -

C. Pekerjaan Tangga 53,919,532.45


a. Bekisting M2 62.90 441,564.50 27,774,407.05
b. Besi Beton Polos Kg 901.20 17,662.50 15,917,445.00
3
c. Cor Beton K-300 M 7.60 1,345,747.42 10,227,680.40

D. Pekerjaan Plat Beton 1,022,319,758.27


a. Bekisting Boundeck M2 1,395.98 236,170.00 329,688,596.60
b. Pemasangan Stegger/Scafolding M2 1,395.98 125,000.00 174,497,500.00
c. Pembesian (Wiremesh) M10 Kg 12,044.14 22,743.00 273,919,876.02
d. Angkur Wiremesh Besi Beton Polos Kg 1,062.94 17,662.50 18,774,177.75
e. Cor Beton K-300 M3 167.52 1,345,747.42 225,439,607.90

3. ELEVASI +4,92 M S/D +TOP FLOOR 1,864,217,225.73

A. Kolom 141,381,015.84

1. Kolom K1, ukuran (40 cm x 40 cm) 43,291,690.19


a. Bekisting M2 57.60 255,150.50 14,696,668.80
b. Besi Beton Ulir Kg 950.76 17,662.50 16,792,798.50
c. Besi Beton Polos Kg 229.34 17,662.50 4,050,717.75
d. Cor Beton K-300 M3 5.76 1,345,747.42 7,751,505.14

2. Kolom K2, ukuran (30 cm x 40 cm) 98,089,325.64


a. Bekisting M2 50.40 255,150.50 12,859,585.20
b. Besi Beton Ulir Kg 2,898.58 17,662.50 51,196,169.25
c. Besi Beton Polos Kg 721.52 17,662.50 12,743,847.00
d. Cor Beton K-300 M3 15.82 1,345,747.42 21,289,724.19

B. Balok 144,095,696.45

1. Balok B1, ukuran (35 cm x 60 cm) 144,095,696.45


a. Bekisting M2 166.53 359,561.20 59,877,726.64
b. Besi Beton Ulir Kg 2,162.06 17,662.50 38,187,384.75
c. Besi Beton Polos Kg 887.22 17,662.50 15,670,523.25
d. Cor Beton K-300 M3 22.56 1,345,747.42 30,360,061.81
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

C. Rangka Atap Baja dan Penutup Atap 1,578,740,513.45

1. Pekerjaan Kuda-Kuda dan Rangka 991,799,161.25


a. Baja Siku 21.70.70.7 Kg 11,425.86 30,670.00 350,431,126.20
b. Baja Siku 21.50.50.5 Kg 6,380.40 30,670.00 195,686,868.00
c. Baut HTB M19 Bh 480.00 30,000.00 14,400,000.00
d. Baut HTB M16 Bh 4,176.00 20,000.00 83,520,000.00
e. End Plat, t = 10 mm Kg 904.32 30,670.00 27,735,494.40
f. Rib Plat, t = 8 mm Kg 1,290.16 30,670.00 39,569,207.20
g. Pipa SCH 40. 16" Kg 270.60 30,670.00 8,299,302.00
h. Gording Canal 125.50.20.2,3 mm Kg 5,971.80 30,670.00 183,155,106.00
i. Pengecatan Permukaan Baja (Cat Zincromate) M2 1,547.66 57,507.50 89,002,057.45

2. Penutup Atap 586,941,352.20


2
a. Pemasangan Aluminium Foil Bubble 4 mm M 1,179.25 151,500.00 178,656,375.00
2
b. Atap Zyngcalume, t = 0,40 mm warna M 1,179.25 233,000.00 274,765,250.00
c. Pemasangan Nok Atap Zyngcalume M1 162.88 171,120.00 27,872,025.60
d. Pemasangan Listplank Woodplank 4 m x 30 cm x 8 mm M1 115.81 221,463.62 25,647,701.60
e. Ornamen Makara (Galvalum 0,4 Dico Gold) + Acc Ls 1.00 80,000,000.00 80,000,000.00
RENCANA ANGGARAN BIAYA
NAMA PAKET : PEMBANGUNAN GEDUNG SOSIAL KEAGAMAAN
INSTANSI : KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
SATUAN KERJA : POLITEKNIK NEGERI UJUNG PANDANG
PROV. /KAB. /KOTA : SULAWESI SELATAN / KOTA MAKASSAR
TAHUN ANGGARAN : APBN 2021
JENIS PEKERJAAN : PEKERJAAN ARSITEKTUR

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )

C. PEKERJAAN ARSITEKTUR 553,481,593.44

1. PEKERJAAN LANTAI 553,481,593.44

A. Pekerjaan Lantai 508,274,844.44


1. Pasir Alas, t = 5 cm M3 127.90 552,000.00 70,600,800.00
2. Rabat Beton K-100 M3 63.95 1,007,258.73 64,414,195.79
3. Keramik Lantai 60 x 60 (Homogeneus) M2 860.61 433,715.44 373,259,848.64

B. Pekerjaan Sparing Pipa 41,658,765.00


1. Pipa Air Hujan 4" M1 120.00 271,646.50 32,597,580.00
2. Pipa Air Kotor 3" M1 30.00 208,646.50 6,259,395.00
3. Pipa Air Buangan 2,5" M1 30.00 93,393.00 2,801,790.00

C. Pekerjaan Dinding 3,547,984.00


1. Pas. Dinding Bata Ringan M2 8.80 189,020.00 1,663,376.00
2. Plesteran M2 8.80 129,065.00 1,135,772.00
3. Acian M2 8.80 85,095.00 748,836.00
ANALISIS PERHITUNGAN BIAYA SMK3 KONSTRUKSI
NAMA PAKET : PEMBANGUNAN GEDUNG SOSIAL KEAGAMAAN
INSTANSI : KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
SATUAN KERJA : POLITEKNIK NEGERI UJUNG PANDANG
PROV. /KAB. /KOTA : SULAWESI SELATAN / KOTA MAKASSAR
TAHUN ANGGARAN : APBN 2021
JENIS PEKERJAAN : PENYELENGGARAAN KEAMANAN DAN KESEHATAN KERJA SERTA KESELAMATAN KONSTRUKSI
SATUAN PEMBAYARAN : LUMP SUM

HARGA SATUAN JUMLAH HARGA


NO. URAIAN SATUAN KOEFISIEN
( Rp. ) ( Rp. )

A. Penyiapan RK3K, terdiri atas :


1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Set 1.00 2,500,000.00 2,500,000.00
dan Formulir
2 Pembuatan Kartu Identitas Pekerja (KIP) Lb 80.00 50,000.00 4,000,000.00

Jumlah A 6,500,000.00
B. Sosialisasi dan Promosi K3, terdiri atas :
1 Induksi K3 (Sefety Induction) Org 1.00 2,500,000.00 2,500,000.00
2 Pengarahan K3 (Safety Briefing) :
Pertemuan Keselamatan (Safety Talk dan/atau Org 1.00 2,500,000.00 2,500,000.00
Tool Box Meeting) setiap hari
3 Peralatan K3 ; Org 1.00 2,500,000.00 2,500,000.00
4 Simulasi K3 ; Org 1.00 2,500,000.00 2,500,000.00
5 Spanduk (Benner) Lb 2.00 1,500,000.00 3,000,000.00
6 Poster ; Lb 6.00 2,000,000.00 12,000,000.00
7 Papan Informasi K3; Buah 12.00 500,000.00 6,000,000.00

Jumlah B 31,000,000.00
C. Alat Pelindung Diri (APD), terdiri atas :
1 Topi Pelindung (Safety Helmet) Buah 35.00 50,000.00 1,750,000.00
2 Pelindung Mata (Goggles, Spectacles) Psg 35.00 40,000.00 1,400,000.00
3 Tameng Muka (Face Shield) Buah 35.00 30,000.00 1,050,000.00
4 Pelindung Telinga (Ear Plug, Ear Muff) Psg 5.00 10,000.00 50,000.00
5 Pelindung Pernapasan dan Mulut (Masker) Buah 35.00 10,000.00 350,000.00
6 Sarung Tangan (Safety Glose) Psg 35.00 10,000.00 350,000.00
7 Sepatu Keselamatan (Safety Shoes) Psg 35.00 100,000.00 3,500,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness) Buah 5.00 250,000.00 1,250,000.00
9 Rompi Keselamatan (Safety Vast) Buah 35.00 20,000.00 700,000.00
10 Pelindung Jatuh (Fall Arrster) Buah 5.00 1,000,000.00 5,000,000.00

Jumlah C 15,400,000.00
D. Asuransi dan Perijinan, terdiri atas :
1 BPJS Ketenagakerjaan dan Kesehatan Kerja Ls 1.00 25,000,000.00 25,000,000.00

Jumlah D 25,000,000.00
E. Personel K3 Konstruksi, terdiri atas :
1 Ahli K3 OB 1.00 15,000,000.00 15,000,000.00
2 Petugas P3K OB 1.00 10,000,000.00 10,000,000.00
3 Petugas Pengatur Lalu Lintas (Flaqman) OB 1.00 7,500,000.00 7,500,000.00
4 Petugas Medis OB 1.00 7,500,000.00 7,500,000.00

Jumlah E 40,000,000.00
F. Fasilitas Sarana Kesehatan
1 Peralatan P3K (Kotak P3K,Tandu,Obat Luka, Perban, Dll) Ls 1.00 25,000,000.00 25,000,000.00

Jumlah F 25,000,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
( Rp. ) ( Rp. )

G. Rambu-Rambu, terdiri atas :


1 Rambu Petunjuk Buah 4.00 500,000.00 2,000,000.00
2 Rambu Larangan Buah 4.00 500,000.00 2,000,000.00
3 Rambu Peringatan Buah 4.00 500,000.00 2,000,000.00
4 Rambu Kewajiban Buah 2.00 500,000.00 1,000,000.00
5 Rambu Informasi Buah 4.00 500,000.00 2,000,000.00
6 Rambu Pekerjaan Sementara Buah 6.00 500,000.00 3,000,000.00
7 Tongkat Pengatur Lalu Lintas Buah 1.00 50,000.00 50,000.00
8 Kerucut Lalu Lintas (Traffic Cone) Buah 2.00 100,000.00 200,000.00
9 Lampu Putar (Rotary Lamp) Buah 2.00 100,000.00 200,000.00
10 Lampu Selang Lalu Lintas Ls 1.00 500,000.00 500,000.00

Jumlah G 12,950,000.00
H. Lain-lain Terkait Dengan Pengendalian Resiko K3
1 Biaya Konsultasi Ls - - -

Jumlah H -
I. Lain-lain Terkait Dengan Pengendalian Resiko K3
1 Alat Pemadam Api Ringan (APAR) Buah 2.00 300,000.00 600,000.00
2 Bendera K3 Buah 1.00 100,000.00 100,000.00
3 Lampu Darurat Buah 2.00 300,000.00 600,000.00
4 Pelaporan dan Penyelidikan Insiden Ls 1.00 2,500,000.00 2,500,000.00

Jumlah I 3,800,000.00

J. Jumlah Harga K3K (A + B + C + D + E + F + G + H + I) 159,650,000.00