REKAPITULASI BILL OF QUANTITY (BOQ)

Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

JUMLAH HARGA
PEKERJAAN
NO. URAIAN PEKERJAAN
( RUPIAH )

1 2 3

A PEKERJAAN PEMBANGUNAN RESERVOIR (KAP. 150 M3) 579.968.293,39

B PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.200 MM = 504 M 583.783.030,17

C PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.150 MM = 3.480 M 2.522.004.443,36

D PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.100 MM = 5.610 M 2.080.736.396,70

E PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.75 MM = 3.924 M 1.449.106.060,21

F PENGADAAN DAN PEMASANGAN POMPA TENAGA SURYA 1.393.224.525,00

TERBILANG : JUMLAH 8.608.822.748,83

PPN 10% 860.882.274,88


SEMBILAN MILYAR EMPAT RATUS ENAM PULUH SEMBILAN JUTA
TOTAL 9.469.705.023,71
TUJUH RATUS RIBU RUPIAH.
DIBULATKAN 9.469.700.000,00

Makassar, 18 November 2020

PT. KARYA ENAM ENAM KONSTRUKSI

Ir. ELBER MAQBUL AMIN


Kuasa Direktur
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
A PEKERJAAN PEMBANGUNAN RESERVOIR (KAP. 150 M3)

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Reservoir M2 100,00 12.403,44 1.240.344,00
2 Papan Nama Proyek Bh 1,00 607.714,91 607.714,91
3 Pengukuran dan Pemasangan Bouwplank M 12,00 63.222,98 758.675,70
4 Mobilisasi dan Demobilisasi (Tenaga, Bahan dan Peralatan yang dibutuhkan) Ls 1,00 107.800.000,00 107.800.000,00
5 K3 Konstruksi

a Penyiapan RKK Ls 1,00 2.000.000,00 2.000.000,00


b Sosialisasi, promosi dan pelatihan Ls 1,00 3.000.000,00 3.000.000,00
c Alat Pelindung Kerja dan Alat Pelindung Diri
- Topi Pelindung (Safet Helmet) Bh 15,00 50.000,00 750.000,00
- Pelindung Pernafasan (Masker) Bh 30,00 8.500,00 255.000,00
- Sarung Tangan (Safety Gloves) Pcs 30,00 5.000,00 150.000,00
- Sepatu Keselamatan (Safety Boat) Pcs 15,00 150.000,00 2.250.000,00
- Rompi Keselamatan (Savety Vast) Bh 15,00 40.000,00 600.000,00
d Asuransi dan Perizinan Ls 1,00 5.000.000,00 5.000.000,00
e Personel Keselamatan Konstruksi Ls 1,00 4.000.000,00 4.000.000,00
f Fasilitas, sarana dan prasarana kesehatan Ls 1,00 5.000.000,00 5.000.000,00
g Rambu - Rambu yang diperlukan Ls 1,00 3.000.000,00 3.000.000,00
h Kegiatan dan peralatan terkait dengan Pengendalian RKK Ls 1,00 5.000.000,00 5.000.000,00
SUB JUMLAH PEKERJAAN PERSIAPAN 141.411.734,61
II PEKERJAAN TANAH
1 Galian Tanah Bangunan Reservoir M3 20,37 183.617,28 3.740.283,99
2 Urugan Kembali Bekas Galian M3 5,09 66.074,40 336.318,70
3 Konsultasi dengan ahli terkait keselamatan konstruksi OJ 1,00 1.000.000,00 1.000.000,00
SUB JUMLAH PEKERJAAN TANAH 5.076.602,69
III PEKERJAAN PASANGAN, BETON DAN PLESTERAN RESERVOIR
1 Urugan Pasir Bawah Lantai M3 3,39 408.998,88 1.386.506,20
2 Lantai Kerja (Beton Tumbuk camp.135 t=5 cm) M3 4,75 1.128.788,25 5.361.744,19
3 Pasangan Pondasi Batu Kali ad.14 M3 13,65 1.121.078,36 15.302.719,65
4 Cor Rabat Keliling M3 1,95 1.128.788,25 2.201.137,09
5 Cor Plat Lantai
- Beton K.225 M3 16,97 1.410.916,35 23.943.250,41
- Besi (menggunakan besi polos) Kg 1.615,72 20.866,06 33.713.703,03
- Bekisting M2 8,30 510.528,36 4.237.385,39
6 Cor Plat Dinding + Sekat
- Beton K.225 M3 19,69 1.410.916,35 27.780.942,87
- Besi (menggunakan besi polos) Kg 2.714,34 20.866,06 56.637.568,81
- Bekisting M2 196,88 510.528,36 100.512.823,66
7 Cor Plat Penutup
- Beton K.175 M3 7,37 1.338.401,66 9.864.020,23
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
- Besi (menggunakan besi polos) Kg 1.019,69 20.866,06 21.276.908,03
- Bekisting M2 65,20 510.528,36 33.286.449,12
8 Plesteran Dinding Luar Dalam, Lantai dan Plat Penutup ad.12 M2 268,18 82.226,61 22.051.532,27
9 Acian Dinding Luar, Dalam dan Lantai M2 206,77 48.378,10 10.003.139,61
10 Pengecatan Dinding Bagian Luar (2 kali secara merata) M2 134,09 37.411,50 5.016.508,48
SUB JUMLAH PEKERJAAN TANAH 372.576.339,05
IV PEKERJAAN PASANGAN, BETON DAN PLESTERAN RUANG KONTROL
1 Pasangan Pondasi Batu Kali ad.14 M3 1,75 1.121.078,36 1.961.887,13
2 Cor Lantai (K175) M3 0,30 1.338.401,66 401.520,50
3 Cor Sloof
- Beton K.175 M3 0,15 1.338.401,66 200.760,25
- Besi (menggunakan besi polos) Kg 36,34 20.866,06 758.272,45
- Bekisting M2 2,50 510.528,36 1.276.320,90
4 Cor Kolom
- Beton K.175 M3 0,13 1.338.401,66 173.992,22
- Besi (menggunakan besi polos) Kg 36,62 20.866,06 764.114,95
- Bekisting M2 2,52 424.278,36 1.069.181,47
5 Cor Ring Balok
- Beton K.175 M3 0,06 1.338.401,66 80.304,10
- Besi (menggunakan besi polos) Kg 30,58 20.866,06 638.083,97
- Bekisting M2 0,80 432.404,40 345.923,52
6 Cor Plat Penutup
- Beton K.175 M3 0,47 1.338.401,66 629.048,78
- Besi (menggunakan besi polos) Kg 65,25 20.866,06 1.361.510,11
- Bekisting M2 4,93 510.528,36 2.516.904,82
7 Pasangan Dinding Bata ad.14 M2 11,44 293.067,88 3.352.696,58
8 Plesteran Dinding dan Lantai ad.14 M2 28,87 82.226,61 2.373.882,23
9 Acian Dinding Bagian Dalam dan Luar M2 22,87 48.378,10 1.106.407,13
10 Pengecatan Dinding Luar Dalam dan Penutup (2 kali) M2 25,87 37.411,50 967.835,59
SUB JUMLAH PEKERJAAN TANAH 19.978.646,72
V PEKERJAAN PENGADAAN/PEMASANGAN PIPA DAN ACCESSORIES
1 Pipa Outlet GIP Klas Medium dia. 150 mm M 12,00 541.282,61 6.495.391,31
2 Pipa Inlet GIP Klas Medium dia. 100 mm M 12,00 355.752,27 4.269.027,24
3 Pipa Overflow GIP Klas Medium dia. 100 mm M 6,00 355.752,27 2.134.513,62
4 Pipa Kuras GIP Klas Medium dia. 100 mm M 6,00 355.752,27 2.134.513,62
5 Gate Valve Flange dia.150 mm Bh 1,00 4.228.363,13 4.228.363,13
6 Gate Valve Flange dia.100 mm Bh 2,00 3.699.098,63 7.398.197,25
7 Bend Flange dia.150x45 Bh 2,00 363.581,70 727.163,40
8 Bend Flange dia.100x90 Bh 2,00 339.419,63 678.839,25
9 Flange Las dia.150 mm Bh 5,00 268.083,98 1.340.419,88
10 Flange Las dia.100 mm Bh 4,00 186.393,15 745.572,60
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
11 Tee Flange dia.150x100 Bh 1,00 363.581,70 363.581,70
12 Karet Paking dia.150 mm Bh 5,00 65.582,78 327.913,88
13 Karet Paking dia.100 mm Bh 2,00 60.980,48 121.960,95
14 Mur+Baut dia.5/8, P=7 cm Bh 44,00 9.918,75 436.425,00
15 Ring dia.5/8 Bh 88,00 3.967,50 349.140,00
SUB JUMLAH PEKERJAAN TANAH 31.751.022,82
VI PEKERJAAN LAIN-LAIN
1 Kusen Pintu Besi Hollow uk.50x50 mm Unit 1,00 937.500,00 937.500,00
2 Pasang Pintu Plat Baja 2,3 mm + Rangka Hollow uk.40x40 mm Unit 1,00 1.312.500,00 1.312.500,00
3 Pasang Batu Angin uk.20x20 cm Bh 18,00 18.750,00 337.500,00
4 Gembok Bh 3,00 26.250,00 78.750,00
5 Biaya Pengelasan Flange dia.150 mm Titik 5,00 146.797,50 733.987,50
6 Biaya Pengelasan Flange dia.100 mm Titik 4,00 130.927,50 523.710,00
7 Manhole 60x60 cm Unit 2,00 562.500,00 1.125.000,00
8 Tangga Turun Naik Pipa GIP dia.40 mm Unit 2,00 1.312.500,00 2.625.000,00
9 Pipa Vent dia.50 mm Unit 4,00 375.000,00 1.500.000,00
SUB JUMLAH PEKERJAAN TANAH 9.173.947,50
JUMLAH PEKERJAAN PEMBANGUNAN RESERVOIR (KAP. 150 M3) 579.968.293,39
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
B PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.200 MM = 504 M

I PEKERJAAN PERSIAPAN
1 Pembersihan Seluruh Jalur Pipa M2 126,00 12.403,44 1.562.833,44
SUB JUMLAH PEKERJAAN PERSIAPAN 1.562.833,44
II PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.200 MM = 504 M
1 Pengadaan Pipa
a Pipa GIP Kls Medium dia.200 mm M 504,00 686.408,25 345.949.758,00
2 Pengadaan Accessories
a Flange Las dia.200 mm 10 K Bh 168,00 355.527,68 59.728.649,40
b Karet Paking dia.200 mm Bh 84,00 73.636,80 6.185.491,20
c Baut uk.5/8 Bh 1.008,00 9.918,75 9.998.100,00
d Ring Bh 2.016,00 3.967,50 7.998.480,00
e Bend Flange dia.200 mmx90 Bh 4,00 448.724,25 1.794.897,00
f Bend Flange dia.200 mmx45 Bh 6,00 448.724,25 2.692.345,50
g Reducer Flange dia.200x150 mm Bh 1,00 588.555,00 588.555,00
SUB JUMLAH PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.200 MM = 504 M 434.936.276,10
III PEKERJAAN PEMASANGAN PIPA GIP DIA.200 MM DAN ACCESSORIES
Pemasangan pipa lengkap dengan accessories termasuk penggalian tanah, urugan kembali, perbaikan akibat
galian, penyeberangan pipa pada jalan/sungai, pengecatan serta perbaikan kembali kebocoran sesuai gambar
spesifikasi teknis
1 Galian Tanah Keras M3 161,28 121.113,22 19.533.139,48
2 Urugan Tanah Kembali M3 141,12 66.074,40 9.324.419,33
3 Pemasangan Pipa GIP Kls Medium dia.200 mm M 504,00 169.845,98 85.602.375,94
SUB JUMLAH PEKERJAAN PEMASANGAN PIPA GIP DIA.200 MM DAN ACCESSORIES 114.459.934,74
IV PEKERJAAN LAIN-LAIN
1 Pengecoran Trasbok Pipa, camp.1 Pc 2 Psr 3 Kr M3 0,96 1.211.808,22 1.163.335,89
2 Biaya Pengelasan Flange dia.200 mm Titik 168,00 188.456,25 31.660.650,00
SUB JUMLAH PEKERJAAN LAIN-LAIN 32.823.985,89
JUMLAH PEKERJAAN PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.200 MM = 504 M 583.783.030,17
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
C PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.150 MM = 3.480 M

I PEKERJAAN PERSIAPAN
1 Pembersihan Seluruh Jalur Pipa M2 870,00 12.403,44 10.790.992,80
SUB JUMLAH PEKERJAAN PERSIAPAN 10.790.992,80
II PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.150 MM = 3.480 M
a Pengadaan Pipa
1 Pipa GIP Kls Medium dia.150 mm M 3.480,00 376.775,25 1.311.177.870,00
b Pengadaan Accessories
1 Flange Las dia.150 mm 10 K Bh 1.160,00 268.083,98 310.977.411,00
2 Karet Paking dia.150 mm Bh 580,00 65.582,78 38.038.009,50
3 Baut uk.5/8 Bh 4.640,00 9.918,75 46.023.000,00
4 Ring Bh 9.280,00 3.967,50 36.818.400,00
5 Bend Flange dia.150 mmx90 Bh 6,00 363.581,70 2.181.490,20
6 Bend Flange dia.150 mmx45 Bh 10,00 363.581,70 3.635.817,00
7 Bend Flange dia.150 mmx22,5 Bh 10,00 363.581,70 3.635.817,00
8 Tee GIP dia.150x150 mm Bh 1,00 388.894,35 388.894,35
9 Gate Valve dia.150 mm Bh 1,00 4.228.363,13 4.228.363,13
10 Gibault Joint GIP dia.150 mm Bh 3,00 523.511,63 1.570.534,88
11 Air Releife dia.20 mm Bh 2,00 286.493,18 572.986,35
12 Clamp Sadle GIP dia.150x20 mm Bh 2,00 207.103,50 414.207,00
13 Reducer Flange dia.150x100 mm Bh 2,00 425.712,75 851.425,50
SUB JUMLAH PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.150 MM = 3.480 M 1.760.514.225,90
III PEKERJAAN PEMASANGAN PIPA GIP DIA.150 MM DAN ACCESSORIES
Pemasangan pipa lengkap dengan accessories termasuk penggalian tanah, urugan kembali, perbaikan akibat
galian, penyeberangan pipa pada jalan/sungai, pengecatan serta perbaikan kembali kebocoran sesuai gambar
spesifikasi teknis

1 Galian Tanah Keras M3 469,80 121.113,22 56.898.988,88


2 Urugan Tanah Kembali M3 435,00 66.074,40 28.742.364,00
3 Pemasangan Pipa GIP Kls Medium dia.150 mm M 3.480,00 146.797,50 510.855.300,00
SUB JUMLAH PEKERJAAN PEMASANGAN PIPA GIP DIA.200 MM DAN ACCESSORIES 596.496.652,88
IV PEKERJAAN LAIN-LAIN
1 Pengecoran Trasbok Pipa, camp.1 Pc 2 Psr 3 Kr M3 1,92 1.211.808,22 2.326.671,79
2 Biaya Pengelasan Flange dia.150 mm Titik 1.160,00 130.927,50 151.875.900,00
SUB JUMLAH PEKERJAAN LAIN-LAIN 154.202.571,79
JUMLAH PEKERJAAN PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.200 MM = 504 M 2.522.004.443,36
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
D PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.100 MM = 5.610 M

I PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.100 MM


a Pengadaan Pipa
1 Pipa GIP Kls Medium dia.100 mm M 5.610,00 235.161,00 1.319.253.210,00
b Pengadaan Accessories
1 Socket dia.100 mm Bh 935,00 116.207,64 108.654.143,40
2 Bend Socket dia.100 mmx90 Bh 6,00 176.037,98 1.056.227,85
3 Bend Socket dia.100 mmx45 Bh 8,00 176.037,98 1.408.303,80
4 Tee Socket dia.100 mmx100 mm Bh 4,00 218.609,25 874.437,00
5 Tee Socket dia.100 mmx75 mm Bh 8,00 194.447,18 1.555.577,40
6 Gibault Joint GIP dia.100 mm Bh 6,00 317.558,70 1.905.352,20
7 Water Moer GIP dia.100 mm Bh 6,00 184.092,00 1.104.552,00
8 Gate Valve Flange dia.100 mm Bh 4,00 3.699.098,63 14.796.394,50
9 Flange dia.100 mm Bh 8,00 186.393,15 1.491.145,20
10 Nepple GIP dia.100 mm Bh 4,00 60.980,48 243.921,90
11 Clamp Sadle GIP dia.100x20 mm Bh 4,00 159.929,93 639.719,70
12 Air Releife dia.20 mm Bh 4,00 286.493,18 1.145.972,70
13 Reducer Flange dia.100x75 mm Bh 3,00 182.941,43 548.824,28
14 Baut uk.5/8 Bh 64,00 9.918,75 634.800,00
15 Ring Bh 128,00 3.967,50 507.840,00
16 Karet Paking dia.100 mm Bh 6,00 60.980,48 365.882,85
17 Stree Box dia.100 mm Bh 3,00 187.859,10 563.577,30
SUB JUMLAH PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.100 MM 1.454.677.781,93
II PEKERJAAN PEMASANGAN PIPA GIP DIA.100 MM DAN ACCESSORIES
Pemasangan pipa lengkap dengan accessories termasuk penggalian tanah, urugan kembali, perbaikan akibat
galian, penyeberangan pipa pada jalan/sungai, pengecatan serta perbaikan kembali kebocoran sesuai gambar
spesifikasi teknis

1 Galian Tanah Keras M3 797,85 121.113,22 96.630.179,39


2 Urugan Tanah Kembali M3 701,25 66.074,40 46.334.673,00
3 Pemasangan Pipa GIP Kls Medium dia.100 mm M 5.610,00 85.317,12 478.629.043,20
SUB JUMLAH PEKERJAAN PEMASANGAN PIPA GIP DIA.100 MM DAN ACCESSORIES 621.593.895,59
III PEKERJAAN LAIN-LAIN
1 Pengecoran Stree Box, camp.1 Pc 2 Psr 3 Kr M3 2,82 1.211.808,22 3.417.299,19
2 Biaya Pengelasan Flange dia.100 mm Titik 8,00 130.927,50 1.047.420,00
SUB JUMLAH PEKERJAAN LAIN-LAIN 4.464.719,19
JUMLAH PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.100 MM = 5.610 M 2.080.736.396,70
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
E PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.75 MM = 3.924 M

I PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.75 MM


a Pengadaan Pipa
1 Pipa GIP Kls Medium dia.75 mm M 3.924,00 235.161,00 922.771.764,00
b Pengadaan Accessories
1 Socket dia.75 mm Bh 654,00 103.551,75 67.722.844,50
2 Bend Socket dia.75 mmx90 Bh 6,00 176.037,98 1.056.227,85
3 Bend Socket dia.75 mmx45 Bh 8,00 176.037,98 1.408.303,80
4 Tee GIP dia.75x75 mm Bh 4,00 218.609,25 874.437,00
5 Tee GIP dia.75x50 mm Bh 6,00 194.447,18 1.166.683,05
6 Gibault Joint GIP dia.75 mm Bh 5,00 317.558,70 1.587.793,50
7 Water Moer GIP dia.75 mm Bh 4,00 184.092,00 736.368,00
8 Gate Valve Flange dia.75 mm Bh 4,00 3.699.098,63 14.796.394,50
9 Nepple GIP dia.75 mm Bh 6,00 186.393,15 1.118.358,90
10 Reducer dia.75x50 mm Bh 5,00 60.980,48 304.902,38
11 Karet Paking dia.75 mm Bh 8,00 159.929,93 1.279.439,40
12 Baut uk.5/8 Bh 48,00 286.493,18 13.751.672,40
13 Ring Bh 96,00 182.941,43 17.562.376,80
14 Clamp Sadle dia.75x20 mm Bh 3,00 9.918,75 29.756,25
15 Stree Box dia.75 mm Bh 4,00 3.967,50 15.870,00
16 Dop GIP dia.75 mm Bh 2,00 60.980,48 121.960,95
17 Air Valve dia.20 mm Bh 3,00 187.859,10 563.577,30
SUB JUMLAH PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.75 MM 1.046.137.566,08
II PEKERJAAN PEMASANGAN PIPA GIP DIA.75 MM DAN ACCESSORIES
Pemasangan pipa lengkap dengan accessories termasuk penggalian tanah, urugan kembali, perbaikan akibat
galian, penyeberangan pipa pada jalan/sungai, pengecatan serta perbaikan kembali kebocoran sesuai gambar
spesifikasi teknis

1 Galian Tanah Keras M3 529,74 121.113,22 64.158.515,04


2 Urugan Tanah Kembali M3 490,50 66.074,40 32.409.493,20
3 Pemasangan Pipa GIP Kls Medium dia.75 mm M 3.924,00 78.083,71 306.400.485,89
SUB JUMLAH PEKERJAAN PEMASANGAN PIPA GIP DIA.75 MM DAN ACCESSORIES 402.968.494,13
JUMLAH PEKERJAAN PENGADAAN PEMASANGAN PIPA GIP KELAS MEDIUM DIA.75 MM = 3.924 M 1.449.106.060,21
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Jaringan Perpipaan SPAM Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Lokasi : Kawasan Perbatasan Oirata Cs. Kab. Maluku Barat Daya
Sumber Dana : APBN
Tahun Anggaran : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
( RUPIAH ) ( RUPIAH )

1 2 3 4 5 7
F PENGADAAN DAN PEMASANGAN POMPA TENAGA SURYA

I PENGADAAN POMPA TENAGA SURYA


- Kapasitas
- Head
- Peak Capacity

1 Pengadaan Submersible Multistage Pump Set 1,00 156.404.250,00 156.404.250,00


2 Pengadaan Solar Module 270 WP lengkap dengan accessories Pcs 108,00 8.549.925,00 923.391.900,00
- Solar Module cristaline minimum 29.160 Wp
- Terminal Socket dan Terminal Box
3 Pengadaan Kabel Array ke Control Box lengkap dengan socket & plug Set 1,00 543.750,00 543.750,00
4 Pengadaan Kabel Intermodule array ke array, lengkap dengan socket & plug Set 1,00 3.915.000,00 3.915.000,00
5 Pengadaan Combine Junction Box (AC/DC) Set 1,00 42.880.125,00 42.880.125,00
6 Pengadaan Solar Inveter Outdoor IP.66 AC-DC minimum 18.500 watt Set 1,00 83.433.000,00 83.433.000,00
7 Pengadaan Sensor dry running Set 1,00 6.220.500,00 6.220.500,00
8 Pengadaan Sine Wave 200-500 38A IP20 Set 1,00 43.217.250,00 43.217.250,00
SUB JUMLAH PEKERJAAN PENGADAAN PIPA GIP DAN ACCESSORIES KLS MEDIUM DIA.75 MM 1.260.005.775,00
II INSTALLATION, TESTING, COMMISSIONING & TRAINING OPERATOR
1 Pengadaan 1 unit support solar module Set 1,00 78.300.000,00 78.300.000,00
2 Pengadaan Drop Cable power 4c x 10mm, c/w resin & termination kabel M 100,00 163.125,00 16.312.500,00
3 Pengadaan cable 2C x 1,5 mm M 100,00 27.187,50 2.718.750,00
4 Pengadaan Accessories Mekanikal dia. 4 Set 1,00 8.700.000,00 8.700.000,00
5 Pengadaan Flow sleeve dia.8 Set 1,00 16.312.500,00 16.312.500,00
6 Supervisi, Testing, commisioning by principle/ASP dan training operator Lot 1,00 10.875.000,00 10.875.000,00
SUB JUMLAH INSTALLATION, TESTING, COMMISSIONING & TRAINING OPERATOR 133.218.750,00
III PEKERJAAN PAGAR BRC PENGAMAN KELILING MODUL SURYA
1 Pemasangan Pondasi ad.14 M3 13,00 1.121.078,36 14.574.018,71
2 Plesteran Pondasi ad.14 M2 116,20 82.226,61 9.554.732,08
3 Pengadaan Pemasangan Pagar BRC uk.2,4 m x 1,75 m besi 8 mm lengkap Lbr 56,00 1.202.250,00 67.326.000,00
4 Pengadaan Pemasangan Pintu BRC uk.1 m x 1,75 m besi 8 mm lengkap Unit 1,00 1.687.500,00 1.687.500,00
SUB JUMLAH PEKERJAAN PAGAR BRC PENGAMAN KELILING MODUL SURYA 93.142.250,79
JUMLAH PEKERJAAN PENGADAAN DAN PEMASANGAN POMPA TENAGA SURYA 1.393.224.525,00