REKAPITULASI RENCANA ANGGARAN BIAYA

KEGIATAN BELANJA MODAL GEDUNG DAN BANGUNAN


PEKERJAAN REVITALISASI GEDUNG
LOKASI LAPAS INDRAMAYU
TAHUN ANGGARAN 2018

JUMLAH
NO. URAIAN PEKERJAAN
(RP.)
A LANTAI 1
I PEKERJAAN PERSIAPAN 35.518.537,00
II PEKERJAAN TANAH 25.303.395,00
III PEKERJAAN PASANGAN 660.960.234,91
IV PEKERJAAN ATAP, KUSEN, PINTU DAN JENDELA 128.963.320,17
V PEKERJAAN INSTALASI LISTRIK 11.150.000,00
VI PEKERJAAN PENGECATAN 54.791.175,03
VII PEKERJAAN TANGGA 2 UNIT 32.638.934,29
JUMLAH A 949.325.596,40
B LANTAI 2
I PEKERJAAN PASANGAN 3.038.341.364,52
II PEKERJAAN ATAP, KUSEN, PINTU DAN JENDELA 247.674.152,33
III PEKERJAAN KM/WC DAN INSTALASI AIR 108.535.085,72
IV PEKERJAAN INSTALASI LISTRIK 9.143.000,00
V PEKERJAAN PENGECATAN 163.549.477,97
JUMLAH B 3.567.243.080,54
C LANTAI ATAP
I PEKERJAAN PASANGAN 846.331.074,14
II PEKERJAAN PENGECATAN 45.845.860,94
JUMLAH C 892.176.935,08
D PEMBUATAN POS JAGA ( 2 UNIT )
I PEK. BETONAN DAN PASANGAN 64.566.523,02
II PEKERJAAN ATAP, KUSEN, PINTU DAN JENDELA 3.233.572,66
III PEK. INSTALASI LISTRIK DAN TANGGA 22.275.000,00
IV PEKERJAAN PENGECATAN 3.504.884,85
JUMLAH D 93.579.980,53
JUMLAH (A + B + C + D) 5.502.325.592,55
PPn 10% 550.232.559,26
TOTAL 6.052.558.151,81
DIBULATKAN 6.052.558.000,00
TERBILANG :
ENAM MILYAR LIMA PULUH DUA JUTA LIMA RATUS LIMA PULUH DELAPAN RIBU RUPIAH

INDRAMAYU, AGUSTUS 2017

DIBUAT :
KONSULTAN PERENCANA
CV. TRI MULYA UTAMA

Ir. H. IMAM MULYANA


DIREKTUR
RENCANA ANGGARAN BIAYA (EE)
KEGIATAN BELANJA MODAL GEDUNG DAN BANGUNAN
PEKERJAAN REVITALISASI GEDUNG
LOKASI LAPAS INDRAMAYU
TAHUN ANGGARAN 2018

KODE HARGA SAT. JUMLAH


NO. URAIAN PEKERJAAN VOLUME
ANALISA (RP.) (RP.)
1 2 3 4 5 6=3x5
1 BANGUNAN UTAMA
A LANTAI 1
I PEKERJAAN PERSIAPAN
1 Administrasi, dokumentasi dan test lab. 1,00 Ls - 7.000.000,00 7.000.000,00
2 Pek. Pengukuran dan Pas. Bouwplank 147,00 M1 A.1a 56.295,00 8.275.365,00
3 Papan nama proyek digital printing 1,00 M2 A.11a.Rob 243.172,00 243.172,00
4 Pek. Mob Demobilisasi / Over layen material 1,00 Ls - 5.000.000,00 5.000.000,00
5 Pek. Bongkaran atap 1,00 Ls - 10.000.000,00 10.000.000,00
6 Pas. Jaring pengaman 1,00 Ls - 5.000.000,00 5.000.000,00
Jumlah ……………… 35.518.537,00
II PEKERJAAN TANAH
1 Pek. Galian tanah pondasi setapak 261,40 M3 B.3 56.475,00 14.762.565,00
2 Pek. Urugan kembali bekas galian 210,60 M3 B.9 33.750,00 7.107.750,00
3 Pek. Urugan pasir bawah pondasi t. 10 cm 16,80 M3 B.11 204.350,00 3.433.080,00
Jumlah ……………… 25.303.395,00
III PEKERJAAN PASANGAN
1 Pek. Kerucuk bambu Ampel dia. 8 cm P. 100 cm 1.053,00 Bh A.9 4.908,00 5.168.124,00
2 Pek. Batu belah 1 Pc : 5 Ps, bawah pondasi setapak 33,70 M3 C.6 708.680,00 23.882.516,00
3 Pek. Cor beton ready mix K. 225 pondasi setapak (120x120) cm 50,50 M3 G.4e 1.110.675,00 56.089.087,50
4 Pek. Cor beton site mix K. 225 sloof 20/30 cm 7,92 M3 G.4b 988.750,00 7.830.900,00
5 Pek. Cor beton ready mix K. 225 kolom 30/30 cm 42,12 M3 G.4e 1.110.675,00 46.781.631,00
6 Pek. Besi beton terpasang BJTD. 24 13.152,30 Kg G.25a 14.287,10 187.908.225,33
7 Pek. Begisting dengan Multiplek t. 9 mm 858,40 M2 G.4p 121.982,75 104.709.992,60
8 Pek. Bata merah 1/2 bata 1 Pc : 5 Ps 163,50 M2 D.12 106.607,00 17.430.244,50
9 Pek. Plesteran 1 Pc : 5 Ps 327,00 M2 E.3 59.326,80 19.399.863,60
10 Pek. Acian 327,00 M2 E.4 25.430,00 8.315.610,00
11 Pas. Steger / alat bantu 272,50 M2 A.11 285.725,00 77.860.062,50
12 Pek. Keramik (40 x 40) cm (selasar) 168,00 M2 M.5e 179.267,00 30.116.856,00
13 Pek. Septictank 2.5 x 1.5 x 1.5 + Rembesan 10,00 Bh J.36b 3.812.637,39 38.126.373,88
14 Pek. Pas. Grevel 1/2 d.30 cm 141,00 M1 J38 264.828,00 37.340.748,00
Jumlah ……………… 660.960.234,91
IV PEKERJAAN ATAP, KUSEN, PINTU DAN JENDELA
1 Pek. Plafond GRC rangka hollow 1.168,50 M2 I.20e 110.366,56 128.963.320,17
Jumlah ……………… 128.963.320,17
V PEKERJAAN INSTALASI LISTRIK
1 Instalasi titik lampu komplit 50,00 Titik - 150.000,00 7.500.000,00
2 Pas. Lampu LED 9 watt setara Philips 50,00 Bh - 73.000,00 3.650.000,00
Jumlah ……………… 11.150.000,00
VI PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dan kolom 802,20 M2 N.14 27.802,90 22.303.486,38
2 Pek. Pengecatan plafond 1.168,50 M2 N.14 27.802,90 32.487.688,65
Jumlah ……………… 54.791.175,03
VII PEKERJAAN TANGGA 2 UNIT
1 Pek. Kerucuk bambu Ampel dia. 8 cm P. 100 cm 16,00 Bh A.9 4.908,00 78.528,00
2 Pas. Stoot werk 24,66 M2 A.11c 221.515,00 5.462.559,90
3 Pek. Galian tanah pondasi setapak 0,72 M3 B.1 45.875,00 33.030,00
4 Pek. Urugan kembali galian tanah 0,24 M3 B.9 33.750,00 8.100,00
5 Pek. Pondasi batu belah 1 Pc : 5 Ps 1,76 M3 C.6 708.680,00 1.250.111,52
6 Pek. Cor beton site mix K. 225 pondasi setapak (60 x 60) cm 0,33 M3 G.4b 988.750,00 324.310,00
7 Pek. Cor beton site mix K. 225 balok 15/30 cm 1,14 M3 G.4b 988.750,00 1.127.175,00
8 Pek. Cor beton site mix K. 225 balok 20/30 cm 0,50 M3 G.4b 988.750,00 492.397,50
9 Pek. Cor beton site mix K. 225 plat tangga t. 12 cm 2,28 M3 G.4b 988.750,00 2.250.395,00
10 Pek. Cor beton site mix K. 225 plat bordes t. 12 cm 0,07 M3 G.4b 988.750,00 67.235,00
11 Pek. Besi beton terpasang BJTD. 24 598,64 Kg G.25a 14.287,10 8.552.829,54
12 Pek. Begisting dengan Multiplek t. 9 mm 35,00 M2 G.4p 121.982,75 4.269.396,25
13 Pek. Lantai Keramik (40 x 40) cm 27,74 M2 M.5e 179.267,00 4.972.866,58
14 Pek. Pemasangan besi Railling stainless steel dia. 2,5" 15,00 M1 - 250.000,00 3.750.000,00
Jumlah ……………… 32.638.934,29
KODE HARGA SAT. JUMLAH
NO. URAIAN PEKERJAAN VOLUME
ANALISA (RP.) (RP.)
1 2 3 4 5 6=3x5
B LANTAI 2
I PEKERJAAN PASANGAN
1 Pek. Urugan pasir t. 5 cm 58,42 M3 B.11.2 206.001,50 12.034.607,63
2 Pek. Cor beton ready mix K. 225 kolom 30/30 cm 42,12 M3 G.4e.2 1.126.352,00 47.441.946,24
3 Pek. Cor beton ready mix K. 225 balok 20/40 cm 56,24 M3 G.4e.2 1.126.352,00 63.346.036,48
4 Pek. Cor beton ready mix K. 225 balok anak 20/25 17,15 M3 G.4e.2 1.126.352,00 19.316.936,80
5 Pek. Cor beton site mix K. 225 ringbalk 15/20 2,64 M3 G.4b.2 1.000.705,00 2.641.861,20
6 Pek. Cor beton site mix K. 225 balok latay 15/20 3,20 M3 G.4b.2 1.000.705,00 3.202.256,00
7 Pek. Cor beton site mix K. 225 balok gantung 15/25 6,60 M3 G.4p.2 1.000.705,00 6.604.653,00
8 Pek. Cor beton ready mix K. 225 pengecoran dinding 15 cm 309,30 M3 G.4e.2 1.126.352,00 348.380.673,60
9 Pek. Cor beton ready mix K. 225 plat dak t. 12 cm 140,22 M3 G.4e.2 1.126.352,00 157.937.077,44
10 Pek. Besi beton terpasang BJTD. 24 20.393,50 Kg G.25a.2 17.500,00 356.886.250,00
11 Pek. Besi wiremesh lantai dak M 10 2.337,00 M2 H.2e.2 125.000,00 292.125.000,00
12 Pek. Besi wiremesh dinding 4.124,00 M2 H.5e.2 125.000,00 515.500.000,00
13 Pek. Begisting dengan Multiplek t. 9 mm 5.556,88 M2 G.4p.2 126.009,75 700.221.059,58
14 Pek. Pas Bondek Plat Dak t. 7 mm 1.168,50 M2 G.25a.2 150.000,00 175.275.000,00
15 Pas. Steger / alat bantu 148,92 M2 A.11.2 309.204,00 46.046.659,68
16 Pas. Stoot werk 230,60 M2 A.11c.2 230.338,50 53.116.058,10
17 Pek. Bata merah 1/2 bata 1 Pc : 5 Ps 130,20 M2 D.12.2 109.026,00 14.195.185,20
18 Pek. Plesteran 1 Pc : 5 Ps 260,40 M2 E.3.2 63.120,80 16.436.656,32
19 Pek. Acian 260,40 M2 E.4 25.430,00 6.621.972,00
20 Pek. Lantai Keramik (40 x 40) cm 1.081,55 M2 M.5e.2 185.855,00 201.011.475,25
Jumlah ……………… 3.038.341.364,52
II PEKERJAAN ATAP, KUSEN, PINTU DAN JENDELA
1 Pek. Plafond GRC rangka hollow 1.329,00 M2 I.20e.2 110.366,56 146.677.152,33
2 Pek. Pintu Besi + Kusen Besi 77,12 M2 ls 850.000,00 65.552.000,00
3 Pek. Daun jendela besi 26,90 M2 ls 850.000,00 22.865.000,00
4 Pek. Tralis Besi 14,80 M2 ls 850.000,00 12.580.000,00
Jumlah ……………… 247.674.152,33
III PEKERJAAN KM/WC DAN INSTALASI AIR
1 Pas. Kloset jongkok setara INA 29,00 Bh J.3.2 259.354,00 7.521.266,00
2 Pas. Pipa PVC dia. 1/2" 130,00 M1 J.25.2 18.777,10 2.441.023,00
3 Pas. Pipa PVC dia. 3" 240,00 M1 J.31.2 79.792,62 19.150.227,60
4 Pas. Pipa PVC dia. 4" 150,00 M1 J.32.2 110.792,62 16.618.892,25
5 Pas. Kran air Kw. 1 29,00 Bh J.35.2 128.552,50 3.728.022,50
6 Pas. Floor drain stainless steel 29,00 Bh J.36.2 158.229,65 4.588.659,85
7 Pek. Dinding keramik warna km/wc (20 x 25) cm 219,24 M2 M.68.2 185.918,00 40.760.662,32
8 Pek. Lantai keramik warna km/wc (20 x 20) cm anti slip 87,00 M2 M.68a.2 135.440,60 11.783.332,20
9 Pas. Tempat sabun putih 29,00 Bh - 67.000,00 1.943.000,00
Jumlah ……………… 108.535.085,72
IV PEKERJAAN INSTALASI LISTRIK
1 Instalasi titik lampu komplit 41,00 Titik - 150.000,00 6.150.000,00
2 Pas. Lampu LED 9 watt setara Philips 41,00 Bh - 73.000,00 2.993.000,00
Jumlah ……………… 9.143.000,00
V PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dan kolom 4.599,20 M2 N.14.2 28.356,10 130.415.375,12
2 Pek. Pengecatan plafond 1.168,50 M2 N.14.2 28.356,10 33.134.102,85
Jumlah ……………… 163.549.477,97
C LANTAI ATAP
I PEKERJAAN PASANGAN
1 Pek. Cor beton ready mix K. 225 dak lantai atap t. 12 cm 165,36 M3 G.4e.2 1.126.352,00 186.253.566,72
2 Pek. Cor beton ready mix K. 225 balok 20/25 17,15 M3 G.4e.2 1.126.352,00 19.316.936,80
3 Pek. Pas Bondek Plat Dak t. 7 mm 1.329,00 M2 - 150.500,00 200.014.500,00
4 Pek. Cor beton ready mix K. 225 listplank beton t. 8 cm 12,56 M3 G.4e.2 1.126.352,00 14.146.981,12
5 Pek. Besi beton terpasang BJTD. 24 1.537,10 Kg G.25a.2 14.445,00 22.203.409,50
6 Pek. Besi wiremesh 2.658,00 M2 - 125.000,00 332.250.000,00
7 Pek. Begisting dengan Multiplek t. 9 mm 370,40 M2 G.4p.2 126.009,75 46.674.011,40
8 Pas. Steger / alat bantu 35,00 M2 A.11.2 309.204,00 10.822.140,00
9 Pas. Stoot werk 63,60 M2 A.11c.2 230.338,50 14.649.528,60
Jumlah ……………… 846.331.074,14
II PEKERJAAN PENGECATAN
1 Pek. Pengecatan listplank beton 370,40 M2 N.14.2 28.356,10 10.503.099,44
2 Pek. Pengecatan lapisan water proof lantai dak atap 1.329,00 M2 N.14.2 26.593,50 35.342.761,50
Jumlah ……………… 45.845.860,94